Avaland (Avaland Berhad)
Avaland Berhad, formerly MCT Berhad, is a Bursa Malaysia-listed developer based in Subang Jaya, Selangor, with 28 housing projects in the KPKT register under ten Avaland companies: 18 completed, 9 under construction and 1 with its permit cancelled, none classed Sick, Abandoned or Late. It is controlled by the Philippines' Ayala Land; 27 of the 28 projects are in Selangor.
- 28 projects in the KPKT register
- 18 completed
- 9 under construction
- 1 with the permit cancelled
- None Sick or Abandoned
Has Avaland handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 28 housing projects under 10 Avaland companies in 2 states: 18 completed, 9 under construction, 1 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 18 completed projects, 16 have both a handover deadline and a completion date in the register: 8 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 7 handed over or certified complete after that deadline (2 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 1 received the completion certificate before the deadline (handover date not recorded).
10 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 18
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI AETAS DAMANSARAKPKT 20017-1Aetas Damansara · on PropertySifu | PetalingSelangor | 226 | 16 Dec 2025Extended 24 months from 16 Dec 20231st sale agreement 16 Dec 2020 | CCC 18 Jun 2025 Handover 10 Jul 2025 | 159 days before |
| SKY PARK PROPERTIES SDN. BHD.KPKT 12075-1Avaland's milestones page lists the completion of SkyPark, Cyberjaya in 2017; the KPKT register records the CCC and handover on 7 Jul 2025.[4] | SepangSelangor | 295 | 15 Jan 20161st sale agreement 15 Jan 2013 | CCC 7 Jul 2025 Handover 7 Jul 2025 | 3,461 days after |
| CASA EMBUN @ CYBERSOUTHKPKT 30240-2 | SepangSelangor | 505 | 1 Feb 20271st sale agreement 1 Feb 2024 | CCC 24 Jun 2025 Handover 30 Jun 2025 | 581 days before |
| ALIRA @ TROPICANA METROPARKKPKT 20185-1 | PetalingSelangor | 492 | 27 Nov 2025Extended 12 months from 27 Nov 20241st sale agreement 27 Nov 2021 | CCC 10 Jun 2025 Handover 20 Jun 2025 | 160 days before |
| ALIRA @ TROPICANA METROPARKKPKT 20185-2 | PetalingSelangor | 340 | 15 Jul 2026Extended 12 months from 15 Jul 20251st sale agreement 15 Jul 2022 | CCC 10 Jun 2025 Handover 20 Jun 2025 | 390 days before |
| LAKEFRONT RESIDENCE @ CYBERJAYAKPKT 12047-3 | SepangSelangor | 606 | 24 Sep 20251st sale agreement 24 Sep 2022 | CCC 27 Mar 2025 Handover 16 Jun 2025 | 100 days before |
| CASA EMBUNKPKT 30240-1 | SepangSelangor | 482 | 29 Dec 20251st sale agreement 29 Dec 2022 | CCC 29 Nov 2024 Handover 16 Dec 2024 | 378 days before |
| CASA BAYUKPKT 13953-7 | SepangSelangor | 180 | 2 Feb 2024Extended 5 months from 2 Sep 20231st sale agreement 2 Sep 2020 | CCC 8 Aug 2023 Handover 16 Aug 2023 | 170 days before |
| CASA BAYUKPKT 13953-6 | SepangSelangor | 80 | 14 Nov 2023Extended 6 months from 14 May 20231st sale agreement 14 May 2020 | CCC 29 Mar 2023 Handover 7 Apr 2023 | 221 days before |
| SELANGORKU PR1MA & LAKEFRONTHOMES @ CYBERJAYAKPKT 12047-2 | SepangSelangor | 3,243 | 28 Jun 20201st sale agreement 28 Jun 2017 | CCC 18 Apr 2022 Handover 27 Jul 2020 / 27 Jun 2022 | 29–729 days after † |
| CASAWOODKPKT 13953-4 | SepangSelangor | 251 | 4 Sep 20211st sale agreement 4 Sep 2018 | CCC 16 Nov 2020 | CCC before deadline; handover not recorded |
| ECO GREEN CITY SDN. BHD.KPKT 13953-3 | SepangSelangor | 264 | 25 May 20201st sale agreement 25 May 2017 | CCC 4 Sep 2020 | 102 days after † |
Handed over or certified complete after the deadline (7)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| SKY PARK PROPERTIES SDN. BHD.KPKT 12075-1Avaland's milestones page lists the completion of SkyPark, Cyberjaya in 2017; the KPKT register records the CCC and handover on 7 Jul 2025.[4] | SepangSelangor | 295 | 15 Jan 20161st sale agreement 15 Jan 2013 | CCC 7 Jul 2025 Handover 7 Jul 2025 | 3,461 days after |
| SELANGORKU PR1MA & LAKEFRONTHOMES @ CYBERJAYAKPKT 12047-2 | SepangSelangor | 3,243 | 28 Jun 20201st sale agreement 28 Jun 2017 | CCC 18 Apr 2022 Handover 27 Jul 2020 / 27 Jun 2022 | 29–729 days after † |
| ECO GREEN CITY SDN. BHD.KPKT 13953-3 | SepangSelangor | 264 | 25 May 20201st sale agreement 25 May 2017 | CCC 4 Sep 2020 | 102 days after † |
| LAKEFRONT RESIDENCE SDN. BHD.KPKT 12047-1 | SepangSelangor | 1,298 | 8 Oct 20161st sale agreement 8 Oct 2013 | CCC 27 Feb 2020 | 1,237 days after |
| CASA VIEWKPKT 13953-2 | SepangSelangor | 530 | 31 Jul 20171st sale agreement 31 Jul 2015 | CCC 12 Nov 2018 | 469 days after |
| ECO GREENKPKT 13953-1 | SepangSelangor | 418 | 20 May 20171st sale agreement 20 May 2015 | CCC 19 Oct 2018 | 517 days after |
| THE PLACE PROPERTIES SDN BHDKPKT 11617-1 | SepangSelangor | 53 | 1 Jul 20141st sale agreement 1 Jul 2011 | CCC 31 Mar 2015 Handover 31 Mar 2015 | 273 days after |
Show all 18 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI AETAS DAMANSARAKPKT 20017-1Aetas Damansara · on PropertySifu | PetalingSelangor | 226 | 16 Dec 2025Extended 24 months from 16 Dec 20231st sale agreement 16 Dec 2020 | CCC 18 Jun 2025 Handover 10 Jul 2025 | 159 days before |
| SKY PARK PROPERTIES SDN. BHD.KPKT 12075-1Avaland's milestones page lists the completion of SkyPark, Cyberjaya in 2017; the KPKT register records the CCC and handover on 7 Jul 2025.[4] | SepangSelangor | 295 | 15 Jan 20161st sale agreement 15 Jan 2013 | CCC 7 Jul 2025 Handover 7 Jul 2025 | 3,461 days after |
| CASA EMBUN @ CYBERSOUTHKPKT 30240-2 | SepangSelangor | 505 | 1 Feb 20271st sale agreement 1 Feb 2024 | CCC 24 Jun 2025 Handover 30 Jun 2025 | 581 days before |
| ALIRA @ TROPICANA METROPARKKPKT 20185-1 | PetalingSelangor | 492 | 27 Nov 2025Extended 12 months from 27 Nov 20241st sale agreement 27 Nov 2021 | CCC 10 Jun 2025 Handover 20 Jun 2025 | 160 days before |
| ALIRA @ TROPICANA METROPARKKPKT 20185-2 | PetalingSelangor | 340 | 15 Jul 2026Extended 12 months from 15 Jul 20251st sale agreement 15 Jul 2022 | CCC 10 Jun 2025 Handover 20 Jun 2025 | 390 days before |
| LAKEFRONT RESIDENCE @ CYBERJAYAKPKT 12047-3 | SepangSelangor | 606 | 24 Sep 20251st sale agreement 24 Sep 2022 | CCC 27 Mar 2025 Handover 16 Jun 2025 | 100 days before |
| CASA EMBUNKPKT 30240-1 | SepangSelangor | 482 | 29 Dec 20251st sale agreement 29 Dec 2022 | CCC 29 Nov 2024 Handover 16 Dec 2024 | 378 days before |
| CASA BAYUKPKT 13953-7 | SepangSelangor | 180 | 2 Feb 2024Extended 5 months from 2 Sep 20231st sale agreement 2 Sep 2020 | CCC 8 Aug 2023 Handover 16 Aug 2023 | 170 days before |
| CASA BAYUKPKT 13953-6 | SepangSelangor | 80 | 14 Nov 2023Extended 6 months from 14 May 20231st sale agreement 14 May 2020 | CCC 29 Mar 2023 Handover 7 Apr 2023 | 221 days before |
| SELANGORKU PR1MA & LAKEFRONTHOMES @ CYBERJAYAKPKT 12047-2 | SepangSelangor | 3,243 | 28 Jun 20201st sale agreement 28 Jun 2017 | CCC 18 Apr 2022 Handover 27 Jul 2020 / 27 Jun 2022 | 29–729 days after † |
| CASAWOODKPKT 13953-4 | SepangSelangor | 251 | 4 Sep 20211st sale agreement 4 Sep 2018 | CCC 16 Nov 2020 | CCC before deadline; handover not recorded |
| ECO GREEN CITY SDN. BHD.KPKT 13953-3 | SepangSelangor | 264 | 25 May 20201st sale agreement 25 May 2017 | CCC 4 Sep 2020 | 102 days after † |
| LAKEFRONT RESIDENCE SDN. BHD.KPKT 12047-1 | SepangSelangor | 1,298 | 8 Oct 20161st sale agreement 8 Oct 2013 | CCC 27 Feb 2020 | 1,237 days after |
| CASA VIEWKPKT 13953-2 | SepangSelangor | 530 | 31 Jul 20171st sale agreement 31 Jul 2015 | CCC 12 Nov 2018 | 469 days after |
| ECO GREENKPKT 13953-1 | SepangSelangor | 418 | 20 May 20171st sale agreement 20 May 2015 | CCC 19 Oct 2018 | 517 days after |
| THE PLACE PROPERTIES SDN BHDKPKT 11617-1 | SepangSelangor | 53 | 1 Jul 20141st sale agreement 1 Jul 2011 | CCC 31 Mar 2015 Handover 31 Mar 2015 | 273 days after |
| USJ ONE AVENUEKPKT 9490-2 | PetalingSelangor | 146 | — | CFO 5 Jun 2009 | — |
| USJ ONE AVENUEKPKT 9490-1 | PetalingSelangor | 448 | — | CFO 6 Feb 2008 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI ALORAKPKT 30162-1Alora Residence · on PropertySifu | PetalingSelangor | 492 | SmoothOn schedule | 1 Sep 2027Extended 12 months from 1 Sep 20261st sale agreement 1 Sep 2023 | 74% |
| RESIDENSI AMIKAKPKT 20185-3Amika Residences · on PropertySifu | PetalingSelangor | 468 | SmoothOn schedule | 21 Mar 2028Extended 12 months from 21 Mar 20271st sale agreement 21 Mar 2024 | 72–75% |
| RESIDENSI ALORAKPKT 30162-2 | PetalingSelangor | 278 | SmoothOn schedule | 21 May 20281st sale agreement 21 May 2025 | 78% |
| AVALON CYBERSOUTHKPKT 30240-3Avalon Cybersouth · on PropertySifu | SepangSelangor | 166 | SmoothOn schedule | 8 Jul 20281st sale agreement 8 Jul 2025 | 58–67% |
| RESIDENSI AETAS SEPUTEHKPKT 30624-1Aetas Seputeh · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 126 | SmoothOn schedule | 12 Aug 2028Extended 14 months from 12 Jun 20271st sale agreement 12 Jun 2024 | 36–40% |
| RESIDENSI ANJAKPKT 9490-3 | Hulu LangatSelangor | 504 | SmoothOn schedule | 20 Aug 2028Extended 14 months from 20 Jun 20271st sale agreement 20 Jun 2024 | 40% |
| LAKEFRONT RESIDENCEKPKT 12047-4Sanderling Lakefront 1 & 2 · on PropertySifu | SepangSelangor | 606 | SmoothOn schedule | 6 Nov 2028Extended 12 months from 6 Nov 20271st sale agreement 6 Nov 2024 | 25–31% |
| AVALON CYBERSOUTHKPKT 30240-4Avalon Cybersouth · on PropertySifu | SepangSelangor | 177 | SmoothOn schedule | 14 Dec 20281st sale agreement 14 Dec 2025 | 20–25% |
| RESIDENSI ANJAKPKT 9490-4 | Hulu LangatSelangor | 396 | SmoothOn schedule | — | 22% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RAFFLESIAKPKT 13953-5 | SepangSelangor | 486 | Permit cancelledPermit cancelled | — | 5% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Avaland at a glance
| Listed | Bursa Malaysia Main Market · AVALAND (5182) · listed since 6 April 2015; known as MCT Berhad until July 2023[1][2] |
|---|---|
| Started | The company says its journey began in 1999; the listed company, Avaland Berhad, has been on Bursa Malaysia since 2015[5][1] |
| Head office | One City, USJ 25, Subang Jaya, Selangor[1] |
| Leadership | Tan Sri Dato' Sri Abi Musa Asa'ari bin Mohamed Nor — Independent Non-Executive Chairman[1] Apollo Bello Tanco — Executive Director and Chief Executive Officer (since 1 January 2024)[1] |
| Companies in the KPKT register | ONE RESIDENCE SDN. BHD. KPKT 20017[1] ARDENT RESIDENCE SDN. BHD. KPKT 30624[1] USJ CITYPOINT SDN. BHD. KPKT 30162[1] NEXT DELTA SDN. BHD. KPKT 20185[1] ECOLAKE RESIDENCE SDN. BHD. KPKT 30240[1] LAKEFRONT RESIDENCE SDN. BHD. KPKT 12047[1] ECO GREEN CITY SDN. BHD. KPKT 13953[1] USJ ONE AVENUE SDN. BHD. KPKT 9490[1] SKY PARK PROPERTIES SDN. BHD. KPKT 12075[1] THE PLACE PROPERTIES SDN. BHD. KPKT 11617[1] |
| Website | avaland.com.my |
| Controlling shareholder | Ayala Land, Inc. (Philippines), deemed to hold 66.25% through Regent Wise Investments Limited, at 31 March 2026[1] |
| Land bank (company figure) | 187.1 acres at 31 December 2025: 62.8 acres in ongoing projects and 124.3 acres for future projects, with an estimated GDV of RM11.5 billion[1] |
| Units handed over (company figure) | More than 9,000, according to the company's website (viewed October 2026)[5] |
| First township | Cybersouth in Dengkil, Selangor, launched in 2015; the company describes it as a 400-acre community[4][5] |
Avaland projects on sale on PropertySifu
Aetas Damansara
- ALIRA @ TROPICANA METROPARK — 7.2 km, 2025
- ALIRA @ TROPICANA METROPARK — 7.2 km, 2025
Alora Residence
- ALIRA @ TROPICANA METROPARK — 5.2 km, 2025
- ALIRA @ TROPICANA METROPARK — 5.3 km, 2025
Avalon Cybersouth
- CASA EMBUN @ CYBERSOUTH — 0.3 km, 2025
- CASA EMBUN — 0.3 km, 2024
- CASAWOOD — 0.5 km, 2020
Sanderling Lakefront 1 & 2
- SELANGORKU PR1MA & LAKEFRONTHOMES @ CYBERJAYA — 0.5 km, 2022
- SKY PARK PROPERTIES SDN. BHD. — 3.2 km, 2025
- THE PLACE PROPERTIES SDN BHD — 3.2 km, 2015
Who is Avaland? The company behind the projects
Avaland Berhad has been listed on Bursa Malaysia since 6 April 2015 and trades on the Main Market under the stock name AVALAND, code 5182 [1]. It was known as MCT Berhad until it began trading under the Avaland name on 11 July 2023 [2]. The company's website says its journey began in 1999 [5]. Its head office is at One City, USJ 25, Subang Jaya, Selangor [1].
The Philippine property group Ayala Land took control in 2018: its indirect stake reached 72.31% when a mandatory general offer closed in February that year [3]. At 31 March 2026 Ayala Land was deemed to hold 66.25% through its Hong Kong-incorporated unit, Regent Wise Investments Limited [1]. The chairman is Tan Sri Dato' Sri Abi Musa Asa'ari bin Mohamed Nor. Apollo Bello Tanco, who spent 29 years with the Ayala Land group, has been executive director and chief executive officer since 1 January 2024 [1].
Avaland develops each project through its own company, all wholly owned through Avaland Holdings Berhad [1]. In the KPKT register, Aetas Damansara is registered under One Residence Sdn Bhd, Aetas Seputeh under Ardent Residence Sdn Bhd, Alora Residence under USJ Citypoint Sdn Bhd, Amika Residences under Next Delta Sdn Bhd, Avalon Cybersouth under Ecolake Residence Sdn Bhd and Sanderling Lakefront under LakeFront Residence Sdn Bhd.
The company says it held 187.1 acres of land at 31 December 2025 — 62.8 acres in ongoing projects and 124.3 acres for future projects — with an estimated gross development value of RM11.5 billion [1]. Its first township, Cybersouth in Dengkil, was launched in 2015 [4]. These are company-wide figures; the KPKT register covers only projects licensed as housing.
Frequently asked questions
Is Avaland a listed company?
Who controls Avaland?
Ayala Land, Inc. of the Philippines. At 31 March 2026 it was deemed to hold 66.25% of Avaland through Regent Wise Investments Limited, Avaland's immediate holding company [1].
Does Avaland have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 28 projects under the ten Avaland companies as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). One of them, 13953-5 (486 units, Eco Green City Sdn Bhd), is recorded with its permit cancelled (Permit Telah Dibatalkan).
Which companies develop Avaland's projects on PropertySifu?
Aetas Damansara — One Residence Sdn Bhd (KPKT developer code 20017); Aetas Seputeh — Ardent Residence Sdn Bhd (30624); Alora Residence — USJ Citypoint Sdn Bhd (30162); Amika Residences — Next Delta Sdn Bhd (20185); Avalon Cybersouth — Ecolake Residence Sdn Bhd (30240); Sanderling Lakefront — LakeFront Residence Sdn Bhd (12047). All are wholly owned through Avaland Holdings Berhad, according to Avaland's 2025 annual report [1].
Have the handover deadlines of Avaland's projects on PropertySifu been extended?
Of the Avaland projects on PropertySifu still under construction, four have approved extensions in the KPKT register: Aetas Seputeh (30624-1), from 12 June 2027 by 14 months to 12 August 2028; Amika Residences (20185-3), from 21 March 2027 by 12 months to 21 March 2028; Alora Residence phase 1 (30162-1), from 1 September 2026 by 12 months to 1 September 2027; and Sanderling Lakefront (12047-4), from 6 November 2027 by 12 months to 6 November 2028. Avalon Cybersouth's two phases (30240-3 and 30240-4) have no extension, with deadlines of 8 July 2028 and 14 December 2028. All are recorded as on schedule (Lancar).
Was Aetas Damansara handed over on time?
KPKT records the first sale agreement on 16 December 2020 and a handover deadline of 16 December 2023, extended with approval by 24 months to 16 December 2025. The CCC is dated 18 June 2025 and vacant possession 10 July 2025, 159 days before the extended deadline.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Avaland Berhad Annual Report 2025 · Avaland Berhad · 30 Apr 2026 · accessed 28 Oct 2026
https://www.insage.com.my/ir/cmn/loadpdf.aspx?sFileName=26120000067266&sReportType=AR&sCompanyCode=AVALAND - [2] MCT to be Avaland from July 11; YKGI will be known as Asteel Group from July 12 · The Edge Malaysia · 10 Jul 2023 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/674252 - [3] Ayala Land owns 72.3% of MCT as general offer closes · The Edge Financial Daily · 2018-02 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/ayala-land-owns-723-mct-general-offer-closes - [4] Our Milestones · Avaland Berhad · accessed 28 Oct 2026
https://www.avaland.com.my/milestones - [5] Avaland — home page (company figures) · Avaland Berhad · accessed 28 Oct 2026
https://www.avaland.com.my/
Last updated 28 Oct 2026