Mah Sing (Mah Sing Group Berhad)
Mah Sing Group Berhad is a Bursa Malaysia Main Market-listed property developer with 141 housing projects in the KPKT register: 97 completed, 40 under construction, 3 not yet started and 1 with the permit cancelled, under 31 Mah Sing companies in Kuala Lumpur, Selangor, Johor and Penang, none classed Sick or Abandoned. Listed in 1992, it has developed property since 1994.
- 141 projects in the KPKT register
- 97 completed
- 40 under construction
- 3 not yet started
- 1 with the permit cancelled
- None Sick or Abandoned
Has Mah Sing handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 141 housing projects under 31 Mah Sing companies in 4 states: 97 completed, 40 under construction, 3 not yet started, 1 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 97 completed projects, 77 have both a handover deadline and a completion date in the register: 21 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 40 handed over or certified complete after that deadline (5 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 16 received the completion certificate before the deadline (handover date not recorded).
55 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 97
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| M SENYUMIAKPKT 11727-6 | SepangSelangor | 150 | 12 Oct 2026Extended 12 months from 12 Oct 20251st sale agreement 12 Oct 2023 | CCC 16 Oct 2026 Handover 20 Oct 2026 | 8 days after |
| MERIDIN EAST ALLAMANDAKPKT 14297-20 | Johor BahruJohor | 101 | 2 Sep 2026Extended 6 months from 2 Mar 20261st sale agreement 2 Mar 2024 | CCC 20 Aug 2026 Handover 26 Aug 2026 | 7 days before |
| PANORAKPKT 11998-5 | GombakSelangor | 149 | 13 Jun 20261st sale agreement 13 Jun 2023 | CCC 23 Jun 2026 Handover 24 Jun 2026 | 11 days after |
| MERIDIN EASTKPKT 14297-19 | Johor BahruJohor | 187 | 6 Jun 2026Extended 6 months from 6 Dec 20251st sale agreement 6 Dec 2023 | CCC 13 May 2026 Handover 19 May 2026 | 18 days before |
| RESIDENSI M ASTRAKPKT 10168-4M Astra @ Setapak · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,426 | 18 Jun 2027Extended 18 months from 18 Dec 20251st sale agreement 18 Dec 2022 | CCC 20 Apr 2026 Handover 21 Apr 2026 | 423 days before |
| M SENYUMIAKPKT 11727-5 | SepangSelangor | 160 | 17 Apr 2026Extended 12 months from 17 Apr 20251st sale agreement 17 Apr 2023 | CCC 8 Apr 2026 Handover 9 Apr 2026 | 8 days before |
| M SENYUMIAKPKT 11727-4 | SepangSelangor | 139 | 14 Jan 2026Extended 12 months from 14 Jan 20251st sale agreement 14 Jan 2023 | CCC 23 Jan 2026 Handover 23 Jan 2026 | 9 days after |
| MERIDIN EAST FASA 2GKPKT 14297-21 | Johor BahruJohor | 170 | 27 Jan 20261st sale agreement 27 Jan 2024 | CCC 5 Dec 2025 Handover 5 Dec 2025 | 53 days before |
| MERIDIN EAST FASA 2GKPKT 14297-18 | Johor BahruJohor | 157 | 18 Nov 20251st sale agreement 18 Nov 2023 | CCC 31 Oct 2025 Handover 3 Nov 2025 | 15 days before |
| PANORAKPKT 11998-4 | GombakSelangor | 247 | 9 Sep 20251st sale agreement 9 Sep 2022 | CCC 25 Aug 2025 Handover 2 Sep 2025 | 7 days before |
| M SENYUMIAKPKT 11727-3 | SepangSelangor | 270 | 16 Aug 2025Extended 12 months from 16 Aug 20241st sale agreement 16 Aug 2022 | CCC 11 Aug 2025 Handover 11 Aug 2025 | 5 days before |
| MERIDIN EAST FASA 1CKPKT 14297-15 | Johor BahruJohor | 155 | 10 Jun 20251st sale agreement 10 Jun 2023 | CCC 6 Jun 2025 Handover 10 Jun 2025 | On the deadline |
Handed over or certified complete after the deadline — 12 most recent of 40
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| M SENYUMIAKPKT 11727-6 | SepangSelangor | 150 | 12 Oct 2026Extended 12 months from 12 Oct 20251st sale agreement 12 Oct 2023 | CCC 16 Oct 2026 Handover 20 Oct 2026 | 8 days after |
| PANORAKPKT 11998-5 | GombakSelangor | 149 | 13 Jun 20261st sale agreement 13 Jun 2023 | CCC 23 Jun 2026 Handover 24 Jun 2026 | 11 days after |
| M SENYUMIAKPKT 11727-4 | SepangSelangor | 139 | 14 Jan 2026Extended 12 months from 14 Jan 20251st sale agreement 14 Jan 2023 | CCC 23 Jan 2026 Handover 23 Jan 2026 | 9 days after |
| MERIDIN EAST FASA 1CKPKT 14297-14 | Johor BahruJohor | 128 | 20 May 20251st sale agreement 20 May 2023 | CCC 6 Jun 2025 Handover 9 Jun 2025 | 20 days after |
| MERIDIN EAST PARCEL 2FKPKT 14297-13 | Johor BahruJohor | 195 | 18 Mar 20251st sale agreement 18 Mar 2023 | CCC 16 May 2025 Handover 20 May 2025 | 63 days after |
| MERIDIN EAST PARCEL 2FKPKT 14297-12 | Johor BahruJohor | 179 | 4 Mar 20251st sale agreement 4 Mar 2023 | CCC 4 Apr 2025 Handover 7 Apr 2025 | 34 days after |
| FLORA QUESTAKPKT 13425-6 | SepangSelangor | 477 | 1 Jan 2022Extended 6 months from 1 Jul 20211st sale agreement 1 Jul 2018 | CCC 13 Jul 2022 | 193 days after † |
| M VERTICAKPKT 19318-1 | Kuala LumpurWP Kuala Lumpur | 1,493 | 19 Aug 2021Extended 6 months from 19 Feb 20211st sale agreement 19 Feb 2018 | CCC 30 Jun 2022 | 315 days after † |
| M CENTURAKPKT 19228-1 | Kuala LumpurWP Kuala Lumpur | 1,413 | 30 May 2021Extended 6 months from 30 Nov 20201st sale agreement 30 Nov 2017 | CCC 9 Dec 2021 | 193 days after † |
| ELITE PARK DEVELOPMENT SDN BHDKPKT 13138-3 | GombakSelangor | 244 | 3 Oct 20181st sale agreement 3 Oct 2015 | CCC 6 Oct 2021 | 1,099 days after |
| MERIDIN EASTKPKT 14297-3 | Johor BahruJohor | 378 | 10 Feb 2020Extended 6 months from 10 Aug 20191st sale agreement 10 Aug 2017 | CCC 5 Aug 2021 | 542 days after |
| M ARUNAKPKT 19392-1 | GombakSelangor | 196 | 1 Apr 2021Extended 10 months from 1 Jun 20201st sale agreement 1 Jun 2018 | CCC 23 Apr 2021 | 22 days after † |
Show all 40
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| M SENYUMIAKPKT 11727-6 | SepangSelangor | 150 | 12 Oct 2026Extended 12 months from 12 Oct 20251st sale agreement 12 Oct 2023 | CCC 16 Oct 2026 Handover 20 Oct 2026 | 8 days after |
| PANORAKPKT 11998-5 | GombakSelangor | 149 | 13 Jun 20261st sale agreement 13 Jun 2023 | CCC 23 Jun 2026 Handover 24 Jun 2026 | 11 days after |
| M SENYUMIAKPKT 11727-4 | SepangSelangor | 139 | 14 Jan 2026Extended 12 months from 14 Jan 20251st sale agreement 14 Jan 2023 | CCC 23 Jan 2026 Handover 23 Jan 2026 | 9 days after |
| MERIDIN EAST FASA 1CKPKT 14297-14 | Johor BahruJohor | 128 | 20 May 20251st sale agreement 20 May 2023 | CCC 6 Jun 2025 Handover 9 Jun 2025 | 20 days after |
| MERIDIN EAST PARCEL 2FKPKT 14297-13 | Johor BahruJohor | 195 | 18 Mar 20251st sale agreement 18 Mar 2023 | CCC 16 May 2025 Handover 20 May 2025 | 63 days after |
| MERIDIN EAST PARCEL 2FKPKT 14297-12 | Johor BahruJohor | 179 | 4 Mar 20251st sale agreement 4 Mar 2023 | CCC 4 Apr 2025 Handover 7 Apr 2025 | 34 days after |
| FLORA QUESTAKPKT 13425-6 | SepangSelangor | 477 | 1 Jan 2022Extended 6 months from 1 Jul 20211st sale agreement 1 Jul 2018 | CCC 13 Jul 2022 | 193 days after † |
| M VERTICAKPKT 19318-1 | Kuala LumpurWP Kuala Lumpur | 1,493 | 19 Aug 2021Extended 6 months from 19 Feb 20211st sale agreement 19 Feb 2018 | CCC 30 Jun 2022 | 315 days after † |
| M CENTURAKPKT 19228-1 | Kuala LumpurWP Kuala Lumpur | 1,413 | 30 May 2021Extended 6 months from 30 Nov 20201st sale agreement 30 Nov 2017 | CCC 9 Dec 2021 | 193 days after † |
| ELITE PARK DEVELOPMENT SDN BHDKPKT 13138-3 | GombakSelangor | 244 | 3 Oct 20181st sale agreement 3 Oct 2015 | CCC 6 Oct 2021 | 1,099 days after |
| MERIDIN EASTKPKT 14297-3 | Johor BahruJohor | 378 | 10 Feb 2020Extended 6 months from 10 Aug 20191st sale agreement 10 Aug 2017 | CCC 5 Aug 2021 | 542 days after |
| M ARUNAKPKT 19392-1 | GombakSelangor | 196 | 1 Apr 2021Extended 10 months from 1 Jun 20201st sale agreement 1 Jun 2018 | CCC 23 Apr 2021 | 22 days after † |
| FERINGGHI RESIDENCE 2KPKT 12324-2 | Daerah Timor LautPulau Pinang | 478 | 13 Aug 20191st sale agreement 13 Aug 2016 | CCC 25 Nov 2020 | 470 days after |
| RESIDENSI SERI WAHYUKPKT 13545-4 | Kuala LumpurWP Kuala Lumpur | 660 | 31 Mar 20201st sale agreement 31 Mar 2017 | CCC 1 Sep 2020 | 154 days after † |
| LAKEVILLE RESIDENCEKPKT 13545-3 | Kuala LumpurWP Kuala Lumpur | 654 | 21 Nov 2019Extended 12 months from 21 Nov 20181st sale agreement 21 Nov 2015 | CCC 29 Jun 2020 | 221 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-4 | SepangSelangor | 813 | 9 Jun 20191st sale agreement 9 Jun 2016 | CCC 3 Mar 2020 | 268 days after |
| MERIDIN BAYVUE SERVICED APARTMENTKPKT 10279-4 | Johor BahruJohor | 1,176 | 30 Jun 20171st sale agreement 30 Jun 2014 | CCC 12 Feb 2020 | 957 days after |
| DSARA SENTRALKPKT 9600-5 | PetalingSelangor | 444 | 17 Nov 20181st sale agreement 17 Nov 2015 | CCC 10 Jan 2019 | 54 days after |
| SIERRA PERDANAKPKT 10279-2 | Johor BahruJohor | 808 | 25 Jun 20081st sale agreement 25 Jun 2006 | CCC 22 Oct 2018 | 3,771 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-2 | SepangSelangor | 1,660 | 12 Jan 20171st sale agreement 12 Jan 2014 | CCC 6 Jun 2018 | 510 days after |
| LAKEVILLE RESIDENCEKPKT 13545-1 | Kuala LumpurWP Kuala Lumpur | 622 | 23 Jun 20171st sale agreement 23 Jun 2014 | CCC 12 Apr 2018 | 293 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-1 | SepangSelangor | 1,532 | 20 Mar 20171st sale agreement 20 Mar 2014 | CCC 28 Mar 2018 | 373 days after |
| SOUTHBAY CITYKPKT 12029-1 | Daerah Barat DayaPulau Pinang | 362 | 27 Apr 20151st sale agreement 27 Apr 2012 | CCC 11 Dec 2017 | 959 days after |
| M RESIDENSI 2KPKT 13262-1 | GombakSelangor | 388 | 4 Feb 20171st sale agreement 4 Feb 2014 | CCC 22 Nov 2017 | 291 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-3 | SepangSelangor | 196 | 6 Jun 20171st sale agreement 6 Jun 2014 | CCC 22 Nov 2017 | 169 days after |
| MERIDIN SUITES RESIDENCEKPKT 13078-1 | Johor BahruJohor | 756 | 29 Jun 20161st sale agreement 29 Jun 2013 | CCC 11 May 2017 | 316 days after |
| SIERRA PERDANAKPKT 10279-3 | Johor BahruJohor | 894 | 23 Nov 20111st sale agreement 23 Nov 2009 | CCC 27 Mar 2017 | 1,951 days after |
| ICON CITYKPKT 11896-1 | PetalingSelangor | 582 | 9 Mar 20141st sale agreement 9 Mar 2012 | CCC 22 Feb 2017 | 1,081 days after |
| CANALKPKT 11998-3 | GombakSelangor | 64 | 14 Jan 20171st sale agreement 14 Jan 2015 | CCC 20 Jan 2017 | 6 days after |
| M CITYKPKT 11727-1 | Kuala LumpurWP Kuala Lumpur | 1,539 | 14 Nov 20141st sale agreement 14 Nov 2011 | CCC 19 Jan 2017 | 797 days after |
| M RESIDENCE 2KPKT 13138-1 | GombakSelangor | 455 | 20 Aug 20161st sale agreement 20 Aug 2013 | CCC 16 Dec 2016 | 118 days after |
| GARDEN PLAZAKPKT 11202-2 | SepangSelangor | 1,149 | 8 Sep 20141st sale agreement 8 Sep 2011 | CCC 2 Nov 2015 | 420 days after |
| M RESIDENCE, RAWANGKPKT 11998-2 | GombakSelangor | 400 | 16 Jan 20151st sale agreement 16 Jan 2013 | CCC 5 Oct 2015 | 262 days after |
| FERRINGHI RESIDENCEKPKT 12324-1 | Daerah Timor LautPulau Pinang | 200 | 22 Nov 20141st sale agreement 22 Nov 2012 | CCC 28 Jul 2015 | 248 days after |
| LEGENDA@SOUTHBAYKPKT 11348-1 | Daerah Barat DayaPulau Pinang | 76 | 10 Nov 20131st sale agreement 10 Nov 2010 | CCC 15 May 2015 | 551 days after |
| ICON RESIDENCEKPKT 11606-1 | Kuala LumpurWP Kuala Lumpur | 290 | 15 May 20141st sale agreement 15 May 2011 | CCC 5 May 2015 | 355 days after |
| MAH SING PROPERTIES SDN BHDKPKT 5911-29 | Johor BahruJohor | 460 | 18 Feb 20151st sale agreement 18 Feb 2012 | CFO 24 Mar 2015 | 34 days after |
| CLOVER @ GARDEN RESIDENCEKPKT 11202-3 | SepangSelangor | 231 | 18 Nov 20141st sale agreement 18 Nov 2011 | CCC 24 Dec 2014 | 36 days after |
| AMAN PERDANAKPKT 9600-3 | KlangSelangor | 600 | 9 Sep 20101st sale agreement 9 Sep 2007 | CFO 7 Oct 2014 | 1,489 days after |
| M RESIDENCE, RAWANGKPKT 11998-1 | GombakSelangor | 447 | 30 Mar 20141st sale agreement 30 Mar 2012 | CCC 14 Aug 2014 | 137 days after |
Show all 97 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| M SENYUMIAKPKT 11727-6 | SepangSelangor | 150 | 12 Oct 2026Extended 12 months from 12 Oct 20251st sale agreement 12 Oct 2023 | CCC 16 Oct 2026 Handover 20 Oct 2026 | 8 days after |
| MERIDIN EAST ALLAMANDAKPKT 14297-20 | Johor BahruJohor | 101 | 2 Sep 2026Extended 6 months from 2 Mar 20261st sale agreement 2 Mar 2024 | CCC 20 Aug 2026 Handover 26 Aug 2026 | 7 days before |
| PANORAKPKT 11998-5 | GombakSelangor | 149 | 13 Jun 20261st sale agreement 13 Jun 2023 | CCC 23 Jun 2026 Handover 24 Jun 2026 | 11 days after |
| MERIDIN EASTKPKT 14297-19 | Johor BahruJohor | 187 | 6 Jun 2026Extended 6 months from 6 Dec 20251st sale agreement 6 Dec 2023 | CCC 13 May 2026 Handover 19 May 2026 | 18 days before |
| RESIDENSI M ASTRAKPKT 10168-4M Astra @ Setapak · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,426 | 18 Jun 2027Extended 18 months from 18 Dec 20251st sale agreement 18 Dec 2022 | CCC 20 Apr 2026 Handover 21 Apr 2026 | 423 days before |
| M SENYUMIAKPKT 11727-5 | SepangSelangor | 160 | 17 Apr 2026Extended 12 months from 17 Apr 20251st sale agreement 17 Apr 2023 | CCC 8 Apr 2026 Handover 9 Apr 2026 | 8 days before |
| M SENYUMIAKPKT 11727-4 | SepangSelangor | 139 | 14 Jan 2026Extended 12 months from 14 Jan 20251st sale agreement 14 Jan 2023 | CCC 23 Jan 2026 Handover 23 Jan 2026 | 9 days after |
| MERIDIN EAST FASA 2GKPKT 14297-21 | Johor BahruJohor | 170 | 27 Jan 20261st sale agreement 27 Jan 2024 | CCC 5 Dec 2025 Handover 5 Dec 2025 | 53 days before |
| MERIDIN EAST FASA 2GKPKT 14297-18 | Johor BahruJohor | 157 | 18 Nov 20251st sale agreement 18 Nov 2023 | CCC 31 Oct 2025 Handover 3 Nov 2025 | 15 days before |
| PANORAKPKT 11998-4 | GombakSelangor | 247 | 9 Sep 20251st sale agreement 9 Sep 2022 | CCC 25 Aug 2025 Handover 2 Sep 2025 | 7 days before |
| M SENYUMIAKPKT 11727-3 | SepangSelangor | 270 | 16 Aug 2025Extended 12 months from 16 Aug 20241st sale agreement 16 Aug 2022 | CCC 11 Aug 2025 Handover 11 Aug 2025 | 5 days before |
| MERIDIN EAST FASA 1CKPKT 14297-15 | Johor BahruJohor | 155 | 10 Jun 20251st sale agreement 10 Jun 2023 | CCC 6 Jun 2025 Handover 10 Jun 2025 | On the deadline |
| MERIDIN EAST FASA 1CKPKT 14297-14 | Johor BahruJohor | 128 | 20 May 20251st sale agreement 20 May 2023 | CCC 6 Jun 2025 Handover 9 Jun 2025 | 20 days after |
| MERIDIN EAST PARCEL 2FKPKT 14297-13 | Johor BahruJohor | 195 | 18 Mar 20251st sale agreement 18 Mar 2023 | CCC 16 May 2025 Handover 20 May 2025 | 63 days after |
| MERIDIN EAST PARCEL 2FKPKT 14297-12 | Johor BahruJohor | 179 | 4 Mar 20251st sale agreement 4 Mar 2023 | CCC 4 Apr 2025 Handover 7 Apr 2025 | 34 days after |
| RESIDENSI M ARISA PELANGIKPKT 19228-2M Arisa · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,598 | 28 Jun 2025Extended 29 months from 28 Jan 20231st sale agreement 28 Jan 2020 | CCC 26 Mar 2025 | CCC before deadline; handover not recorded |
| M SENYUMIAKPKT 11727-2 | SepangSelangor | 262 | 9 May 2025Extended 12 months from 9 May 20241st sale agreement 9 May 2022 | CCC 13 Dec 2024 Handover 20 Dec 2024 | 140 days before |
| RESIDENSI M LUNAKPKT 11348-2M Luna · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,672 | 9 Feb 2025Extended 23 months from 9 Mar 20231st sale agreement 9 Mar 2020 | CCC 28 Nov 2024 Handover 3 Dec 2024 | 68 days before |
| TAMAN SENDAYU RAWANGKPKT 19392-3 | GombakSelangor | 240 | 30 Dec 20241st sale agreement 30 Dec 2021 | CCC 5 Nov 2024 Handover 22 Nov 2024 | 38 days before |
| MERIDIN EASTKPKT 14297-11 | Johor BahruJohor | 108 | 23 Aug 20241st sale agreement 23 Aug 2022 | CCC 5 Aug 2024 Handover 8 Aug 2024 | 15 days before |
| MERIDIN EASTKPKT 14297-10 | Johor BahruJohor | 210 | 25 May 20241st sale agreement 25 May 2022 | CCC 15 Apr 2024 Handover 23 Apr 2024 | 32 days before |
| M OSCARKPKT 5911-31M Oscar · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 910 | 5 Sep 2024Extended 23 months from 5 Oct 20221st sale agreement 5 Oct 2019 | CCC 26 Mar 2024 Handover 4 Apr 2024 | 154 days before |
| SENSORY RESIDENCEKPKT 13425-7 | SepangSelangor | 488 | 12 Nov 20241st sale agreement 12 Nov 2021 | CCC 10 Jan 2024 Handover 29 Feb 2024 | 257 days before |
| MERIDIN EASTKPKT 14297-9 | Johor BahruJohor | 155 | 1 Nov 20231st sale agreement 1 Nov 2021 | CCC 26 Oct 2023 Handover 31 Oct 2023 | 1 day before |
| RESIDENSI M ADORA WANGSAKPKT 11606-2 | Kuala LumpurWP Kuala Lumpur | 677 | 13 Jul 2024Extended 12 months from 13 Jul 20231st sale agreement 13 Jul 2020 | CCC 29 Sep 2023 Handover 6 Oct 2023 | 281 days before |
| M ARUNAKPKT 19392-4 | GombakSelangor | 177 | 1 Oct 20231st sale agreement 1 Oct 2021 | CCC 14 Sep 2023 Handover 15 Sep 2023 | 16 days before |
| M VERTICAKPKT 19318-2 | Kuala LumpurWP Kuala Lumpur | 2,191 | 24 May 2024Extended 30 months from 24 Nov 20211st sale agreement 24 Nov 2018 | CCC 3 Apr 2023 | CCC before deadline; handover not recorded |
| M ARUNAKPKT 19392-2 | GombakSelangor | 192 | 12 Apr 2023Extended 5 months from 12 Nov 20221st sale agreement 12 Nov 2020 | CCC 21 Dec 2022 Handover 22 Dec 2022 | 111 days before |
| MERIDIN EASTKPKT 14297-8 | Johor BahruJohor | 94 | 5 May 2023Extended 5 months from 5 Dec 20221st sale agreement 5 Dec 2020 | CCC 15 Dec 2022 Handover 22 Dec 2022 | 134 days before |
| FLORA QUESTAKPKT 13425-6 | SepangSelangor | 477 | 1 Jan 2022Extended 6 months from 1 Jul 20211st sale agreement 1 Jul 2018 | CCC 13 Jul 2022 | 193 days after † |
| M VERTICAKPKT 19318-1 | Kuala LumpurWP Kuala Lumpur | 1,493 | 19 Aug 2021Extended 6 months from 19 Feb 20211st sale agreement 19 Feb 2018 | CCC 30 Jun 2022 | 315 days after † |
| MERIDIN EAST - ACACIAKPKT 14297-7 | Johor BahruJohor | 93 | 26 Nov 2022Extended 11 months from 26 Dec 20211st sale agreement 26 Dec 2019 | CCC 19 May 2022 | CCC before deadline; handover not recorded |
| M VISTA @ SOUTHBAY CITYKPKT 12029-2 | Daerah Barat DayaPulau Pinang | 237 | 3 May 2022Extended 18 months from 3 Nov 20201st sale agreement 3 Nov 2017 | CCC 31 Dec 2021 | CCC before deadline; handover not recorded |
| M CENTURAKPKT 19228-1 | Kuala LumpurWP Kuala Lumpur | 1,413 | 30 May 2021Extended 6 months from 30 Nov 20201st sale agreement 30 Nov 2017 | CCC 9 Dec 2021 | 193 days after † |
| ELITE PARK DEVELOPMENT SDN BHDKPKT 13138-3 | GombakSelangor | 244 | 3 Oct 20181st sale agreement 3 Oct 2015 | CCC 6 Oct 2021 | 1,099 days after |
| MERIDIN EASTKPKT 14297-3 | Johor BahruJohor | 378 | 10 Feb 2020Extended 6 months from 10 Aug 20191st sale agreement 10 Aug 2017 | CCC 5 Aug 2021 | 542 days after |
| M ARUNAKPKT 19392-1 | GombakSelangor | 196 | 1 Apr 2021Extended 10 months from 1 Jun 20201st sale agreement 1 Jun 2018 | CCC 23 Apr 2021 | 22 days after † |
| MERIDIN EAST SDN. BHD.KPKT 14297-6 | Johor BahruJohor | 236 | 17 Jun 2021Extended 6 months from 17 Dec 20201st sale agreement 17 Dec 2018 | CCC 2 Mar 2021 | CCC before deadline; handover not recorded |
| RUMAH MAMPU MILIK JOHORKPKT 14297-5 | Johor BahruJohor | 264 | 20 Jul 20221st sale agreement 20 Jul 2019 | CCC 22 Feb 2021 | CCC before deadline; handover not recorded |
| FERINGGHI RESIDENCE 2KPKT 12324-2 | Daerah Timor LautPulau Pinang | 478 | 13 Aug 20191st sale agreement 13 Aug 2016 | CCC 25 Nov 2020 | 470 days after |
| RESIDENSI SERI WAHYUKPKT 13545-4 | Kuala LumpurWP Kuala Lumpur | 660 | 31 Mar 20201st sale agreement 31 Mar 2017 | CCC 1 Sep 2020 | 154 days after † |
| LAKEVILLE RESIDENCEKPKT 13545-3 | Kuala LumpurWP Kuala Lumpur | 654 | 21 Nov 2019Extended 12 months from 21 Nov 20181st sale agreement 21 Nov 2015 | CCC 29 Jun 2020 | 221 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-4 | SepangSelangor | 813 | 9 Jun 20191st sale agreement 9 Jun 2016 | CCC 3 Mar 2020 | 268 days after |
| MERIDIN BAYVUE SERVICED APARTMENTKPKT 10279-4 | Johor BahruJohor | 1,176 | 30 Jun 20171st sale agreement 30 Jun 2014 | CCC 12 Feb 2020 | 957 days after |
| MERIDIN EASTKPKT 14297-4 | Johor BahruJohor | 90 | 6 Sep 20191st sale agreement 6 Sep 2017 | CCC 25 Mar 2019 | CCC before deadline; handover not recorded |
| DSARA SENTRALKPKT 9600-5 | PetalingSelangor | 444 | 17 Nov 20181st sale agreement 17 Nov 2015 | CCC 10 Jan 2019 | 54 days after |
| SIERRA PERDANAKPKT 10279-2 | Johor BahruJohor | 808 | 25 Jun 20081st sale agreement 25 Jun 2006 | CCC 22 Oct 2018 | 3,771 days after |
| MERIDIN EASTKPKT 14297-2 | Johor BahruJohor | 116 | 6 Aug 20181st sale agreement 6 Aug 2016 | CCC 30 Jul 2018 | CCC before deadline; handover not recorded |
| BANDAR BARU LEMBAH SELATANKPKT 13425-2 | SepangSelangor | 1,660 | 12 Jan 20171st sale agreement 12 Jan 2014 | CCC 6 Jun 2018 | 510 days after |
| DSARA SENTRALKPKT 9600-4 | PetalingSelangor | 494 | 29 Sep 2018Extended 12 months from 29 Sep 20171st sale agreement 29 Sep 2014 | CCC 5 Jun 2018 | CCC before deadline; handover not recorded |
| LAKEVILLE RESIDENCEKPKT 13545-1 | Kuala LumpurWP Kuala Lumpur | 622 | 23 Jun 20171st sale agreement 23 Jun 2014 | CCC 12 Apr 2018 | 293 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-1 | SepangSelangor | 1,532 | 20 Mar 20171st sale agreement 20 Mar 2014 | CCC 28 Mar 2018 | 373 days after |
| MERIDIN EASTKPKT 14297-1 | Johor BahruJohor | 492 | 31 Mar 20181st sale agreement 31 Mar 2016 | CCC 26 Mar 2018 | CCC before deadline; handover not recorded |
| SOUTHBAY CITYKPKT 12029-1 | Daerah Barat DayaPulau Pinang | 362 | 27 Apr 20151st sale agreement 27 Apr 2012 | CCC 11 Dec 2017 | 959 days after |
| M RESIDENSI 2KPKT 13262-1 | GombakSelangor | 388 | 4 Feb 20171st sale agreement 4 Feb 2014 | CCC 22 Nov 2017 | 291 days after |
| BANDAR BARU LEMBAH SELATANKPKT 13425-3 | SepangSelangor | 196 | 6 Jun 20171st sale agreement 6 Jun 2014 | CCC 22 Nov 2017 | 169 days after |
| MERIDIN SUITES RESIDENCEKPKT 13078-1 | Johor BahruJohor | 756 | 29 Jun 20161st sale agreement 29 Jun 2013 | CCC 11 May 2017 | 316 days after |
| SIERRA PERDANAKPKT 10279-3 | Johor BahruJohor | 894 | 23 Nov 20111st sale agreement 23 Nov 2009 | CCC 27 Mar 2017 | 1,951 days after |
| ICON CITYKPKT 11896-1 | PetalingSelangor | 582 | 9 Mar 20141st sale agreement 9 Mar 2012 | CCC 22 Feb 2017 | 1,081 days after |
| CANALKPKT 11998-3 | GombakSelangor | 64 | 14 Jan 20171st sale agreement 14 Jan 2015 | CCC 20 Jan 2017 | 6 days after |
| M CITYKPKT 11727-1 | Kuala LumpurWP Kuala Lumpur | 1,539 | 14 Nov 20141st sale agreement 14 Nov 2011 | CCC 19 Jan 2017 | 797 days after |
| M RESIDENCE 2KPKT 13138-1 | GombakSelangor | 455 | 20 Aug 20161st sale agreement 20 Aug 2013 | CCC 16 Dec 2016 | 118 days after |
| M RESIDENCE 2KPKT 13138-2 | GombakSelangor | 296 | 28 Oct 20161st sale agreement 28 Oct 2013 | CCC 25 Oct 2016 | CCC before deadline; handover not recorded |
| GARDEN PLAZAKPKT 11202-2 | SepangSelangor | 1,149 | 8 Sep 20141st sale agreement 8 Sep 2011 | CCC 2 Nov 2015 | 420 days after |
| SRI PULAI PERDANA 2KPKT 5911-28 | Johor BahruJohor | 459 | 29 Oct 20171st sale agreement 29 Oct 2015 | CCC 12 Oct 2015 | CCC before deadline; handover not recorded |
| M RESIDENCE, RAWANGKPKT 11998-2 | GombakSelangor | 400 | 16 Jan 20151st sale agreement 16 Jan 2013 | CCC 5 Oct 2015 | 262 days after |
| SRI PULAI PERDANA 2KPKT 5911-30 | Johor BahruJohor | 62 | 9 Sep 20151st sale agreement 9 Sep 2013 | CCC 30 Aug 2015 | CCC before deadline; handover not recorded |
| FERRINGHI RESIDENCEKPKT 12324-1 | Daerah Timor LautPulau Pinang | 200 | 22 Nov 20141st sale agreement 22 Nov 2012 | CCC 28 Jul 2015 | 248 days after |
| LEGENDA@SOUTHBAYKPKT 11348-1 | Daerah Barat DayaPulau Pinang | 76 | 10 Nov 20131st sale agreement 10 Nov 2010 | CCC 15 May 2015 | 551 days after |
| ICON RESIDENCEKPKT 11606-1 | Kuala LumpurWP Kuala Lumpur | 290 | 15 May 20141st sale agreement 15 May 2011 | CCC 5 May 2015 | 355 days after |
| KINRARA RESIDENCEKPKT 10264-3 | PetalingSelangor | 417 | 30 Mar 20151st sale agreement 30 Mar 2012 | CCC 27 Mar 2015 | CCC before deadline; handover not recorded |
| MAH SING PROPERTIES SDN BHDKPKT 5911-29 | Johor BahruJohor | 460 | 18 Feb 20151st sale agreement 18 Feb 2012 | CFO 24 Mar 2015 | 34 days after |
| CLOVER @ GARDEN RESIDENCEKPKT 11202-3 | SepangSelangor | 231 | 18 Nov 20141st sale agreement 18 Nov 2011 | CCC 24 Dec 2014 | 36 days after |
| AMAN PERDANAKPKT 9600-3 | KlangSelangor | 600 | 9 Sep 20101st sale agreement 9 Sep 2007 | CFO 7 Oct 2014 | 1,489 days after |
| M RESIDENCE, RAWANGKPKT 11998-1 | GombakSelangor | 447 | 30 Mar 20141st sale agreement 30 Mar 2012 | CCC 14 Aug 2014 | 137 days after |
| PERDANA RESIDENCE 2KPKT 10168-3 | GombakSelangor | 108 | 19 Nov 20141st sale agreement 19 Nov 2011 | CCC 4 Jul 2014 | CCC before deadline; handover not recorded |
| M SUITESKPKT 11430-1 | Kuala LumpurWP Kuala Lumpur | 442 | — | CCC 2 Dec 2013 | — |
| GARDEN RESIDENCEKPKT 11202-1 | SepangSelangor | 676 | 28 Mar 20141st sale agreement 28 Mar 2011 | CCC 21 Oct 2013 | CCC before deadline; handover not recorded |
| ONE LEGENDAKPKT 11347-1 | Hulu LangatSelangor | 26 | — | CCC 8 Jan 2013 | — |
| KINRARA RESIDENCEKPKT 10264-2 | PetalingSelangor | 267 | — | CFO 12 Dec 2012 | — |
| PERDANA RESIDENCE 2KPKT 10168-2 | GombakSelangor | 268 | — | CCC 26 Jun 2012 | — |
| AMAN PERDANAKPKT 9600-1 | KlangSelangor | 1,100 | — | CFO 20 Jun 2012 | — |
| DAMAI UTAMAKPKT 11433-1 | PetalingSelangor | 180 | — | CCC 24 Apr 2012 | — |
| AMAN PERDANAKPKT 9600-2 | KlangSelangor | 708 | — | CCC 25 Aug 2011 | — |
| ENRICH PROPERTY DEVELOPMENT SDN BHDKPKT 10945-1 | Daerah Barat DayaPulau Pinang | 284 | — | CCC 6 Jul 2011 | — |
| PANGSAPURI KOS RENDAH DI SOUTHBAYKPKT 10945-2 | Daerah Barat DayaPulau Pinang | 88 | — | CCC 6 Jul 2011 Handover 29 Jul 2011 | — |
| KEMUNING RESIDENCEKPKT 10264-1 | KlangSelangor | 150 | — | CCC 28 Apr 2011 | — |
| AUSTIN PERDANAKPKT 5911-26 | Johor BahruJohor | 185 | — | CFO 9 Sep 2010 | — |
| HIJAUAN RESIDENKPKT 10393-1 | Hulu LangatSelangor | 122 | — | CFO 10 Jun 2009 | — |
| SIERRA PERDANAKPKT 10279-1 | Johor BahruJohor | 84 | — | CFO 23 Mar 2009 | — |
| PERDANA RESIDENCEKPKT 10168-1 | Kuala LangatSelangor | 73 | — | CFO 30 Jun 2008 | — |
| TAMAN SRI PULAI PERDANAKPKT 5911-27 | Johor BahruJohor | 141 | — | CFO 9 Apr 2008 | — |
| SRI PULAI PERDANAKPKT 5911-23 | Johor BahruJohor | 208 | — | CFO 22 Nov 2006 | — |
| AUSTIN PERDANAKPKT 5911-25 | Johor BahruJohor | 845 | — | CFO 4 Oct 2006 | — |
| DAMANSARA LEGENDAKPKT 5911-24 | PetalingSelangor | 116 | — | CFO 9 Jun 2006 | — |
| SRI PULAI PERDANAKPKT 5911-16 | Johor BahruJohor | 278 | — | CFO 26 Apr 2006 | — |
| LAKEVILLE RESIDENCEKPKT 13545-2 | Kuala LumpurWP Kuala Lumpur | 622 | 22 Nov 2018Extended 12 months from 22 Nov 20171st sale agreement 22 Nov 2014 | — | — |
Under construction (40) and not yet started (3) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| HIJAUAN RESIDENKPKT 10393-2 | Hulu LangatSelangor | 108 | SmoothNot started | 12 Apr 20131st sale agreement 12 Apr 2011 | 0–100% |
| BAYU SEKAMATKPKT 10393-3 | Hulu LangatSelangor | 220 | SmoothNot started | 22 Mar 20141st sale agreement 22 Mar 2011 | 0–100% |
| M SENYUMIAKPKT 11727-7 | SepangSelangor | 195 | SmoothOn schedule | 18 Dec 2026Extended 12 months from 18 Dec 20251st sale agreement 18 Dec 2023 | 92–96% |
| DEDAUNKPKT 11998-6 | GombakSelangor | 213 | SmoothOn schedule | 29 Jan 20271st sale agreement 29 Jan 2024 | 96% |
| TAMAN TIARA INDAH (M TIARA)KPKT 10279-5 | Johor BahruJohor | 223 | SmoothOn schedule | 20 Feb 2027Extended 6 months from 20 Aug 20261st sale agreement 20 Aug 2024 | 93–94% |
| ALLAMANDA 3KPKT 14297-22 | Johor BahruJohor | 126 | SmoothOn schedule | 21 Feb 2027Extended 6 months from 21 Aug 20261st sale agreement 21 Aug 2024 | 97% |
| MERIDIN EAST JASMINE 2KPKT 14297-24 | Johor BahruJohor | 168 | SmoothOn schedule | 8 Mar 20271st sale agreement 8 Mar 2025 | 94% |
| MERIDIN EAST PARCEL 4A5KPKT 14297-25 | Johor BahruJohor | 111 | SmoothOn schedule | 8 Mar 20271st sale agreement 8 Mar 2025 | 96% |
| RESIDENSI IRIS SELANGORKUKPKT 11727-8 | SepangSelangor | 178 | SmoothOn schedule | 17 Mar 20271st sale agreement 17 Mar 2024 | 98% |
| SKIM PERUMAHAN MAMPU MILIK TAMAN BESTARI PERDANA 2KPKT 14297-16 | Johor BahruJohor | 140 | SmoothOn schedule | 31 Mar 20271st sale agreement 31 Mar 2024 | 97% |
| SKIM PERUMAHAN MAMPU MILIK TAMAN BESTARI PERDANA 2KPKT 14297-17 | Johor BahruJohor | 176 | SmoothOn schedule | 31 Mar 20271st sale agreement 31 Mar 2024 | 97% |
| MERIDIN EAST PARCEL 4A4KPKT 14297-23 | Johor BahruJohor | 156 | SmoothOn schedule | 5 May 2027Extended 6 months from 5 Nov 20261st sale agreement 5 Nov 2024 | 96% |
Show all 43 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| HIJAUAN RESIDENKPKT 10393-2 | Hulu LangatSelangor | 108 | SmoothNot started | 12 Apr 20131st sale agreement 12 Apr 2011 | 0–100% |
| BAYU SEKAMATKPKT 10393-3 | Hulu LangatSelangor | 220 | SmoothNot started | 22 Mar 20141st sale agreement 22 Mar 2011 | 0–100% |
| M SENYUMIAKPKT 11727-7 | SepangSelangor | 195 | SmoothOn schedule | 18 Dec 2026Extended 12 months from 18 Dec 20251st sale agreement 18 Dec 2023 | 92–96% |
| DEDAUNKPKT 11998-6 | GombakSelangor | 213 | SmoothOn schedule | 29 Jan 20271st sale agreement 29 Jan 2024 | 96% |
| TAMAN TIARA INDAH (M TIARA)KPKT 10279-5 | Johor BahruJohor | 223 | SmoothOn schedule | 20 Feb 2027Extended 6 months from 20 Aug 20261st sale agreement 20 Aug 2024 | 93–94% |
| ALLAMANDA 3KPKT 14297-22 | Johor BahruJohor | 126 | SmoothOn schedule | 21 Feb 2027Extended 6 months from 21 Aug 20261st sale agreement 21 Aug 2024 | 97% |
| MERIDIN EAST JASMINE 2KPKT 14297-24 | Johor BahruJohor | 168 | SmoothOn schedule | 8 Mar 20271st sale agreement 8 Mar 2025 | 94% |
| MERIDIN EAST PARCEL 4A5KPKT 14297-25 | Johor BahruJohor | 111 | SmoothOn schedule | 8 Mar 20271st sale agreement 8 Mar 2025 | 96% |
| RESIDENSI IRIS SELANGORKUKPKT 11727-8 | SepangSelangor | 178 | SmoothOn schedule | 17 Mar 20271st sale agreement 17 Mar 2024 | 98% |
| SKIM PERUMAHAN MAMPU MILIK TAMAN BESTARI PERDANA 2KPKT 14297-16 | Johor BahruJohor | 140 | SmoothOn schedule | 31 Mar 20271st sale agreement 31 Mar 2024 | 97% |
| SKIM PERUMAHAN MAMPU MILIK TAMAN BESTARI PERDANA 2KPKT 14297-17 | Johor BahruJohor | 176 | SmoothOn schedule | 31 Mar 20271st sale agreement 31 Mar 2024 | 97% |
| MERIDIN EAST PARCEL 4A4KPKT 14297-23 | Johor BahruJohor | 156 | SmoothOn schedule | 5 May 2027Extended 6 months from 5 Nov 20261st sale agreement 5 Nov 2024 | 96% |
| TAMAN TIARA INDAHKPKT 10279-8 | Johor BahruJohor | 163 | SmoothOn schedule | 24 May 20271st sale agreement 24 May 2025 | 74–82% |
| TAMAN TIARA INDAHKPKT 10279-6 | Johor BahruJohor | 252 | SmoothOn schedule | 12 Jun 2027Extended 6 months from 12 Dec 20261st sale agreement 12 Dec 2024 | 81% |
| TAMAN TIARA INDAHKPKT 10279-7 | Johor BahruJohor | 116 | SmoothOn schedule | 7 Sep 2027Extended 6 months from 7 Mar 20271st sale agreement 7 Mar 2025 | 84% |
| RESIDENSI ANGGUNKPKT 30440-1 | Johor BahruJohor | 421 | SmoothOn schedule | 13 Oct 2027Extended 12 months from 13 Oct 20261st sale agreement 13 Oct 2023 | 92% |
| RESIDENSI ANGGUNKPKT 30440-2 | Johor BahruJohor | 619 | SmoothOn schedule | 21 Dec 2027Extended 12 months from 21 Dec 20261st sale agreement 21 Dec 2023 | 92% |
| RESIDENSI M NOVAKPKT 11202-4M Nova · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,248 | SmoothOn schedule | 17 Feb 2028Extended 18 months from 17 Aug 20261st sale agreement 17 Aug 2023 | 92% |
| RESIDENSI M ZENYAKPKT 11430-2M Zenya · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 619 | SmoothOn schedule | 6 Apr 2028Extended 12 months from 6 Apr 20271st sale agreement 6 Apr 2024 | 72% |
| M LEGASIKPKT 30897-1M Legasi Semenyih · on PropertySifu | Hulu LangatSelangor | 330 | SmoothOn schedule | 10 Apr 2028Extended 12 months from 10 Apr 20271st sale agreement 10 Apr 2025 | 50–70% |
| MERIDIN EAST PARCEL 4A6KPKT 14297-28 | Johor BahruJohor | 124 | SmoothOn schedule | 7 May 2028Extended 6 months from 7 Nov 20271st sale agreement 7 Nov 2025 | 47% |
| MERIDIN EAST PARCEL 1AKPKT 14297-29 | Johor | 111 | SmoothOn schedule | 15 May 20281st sale agreement 15 May 2026 | 55% |
| RESIDENSI ANGGUNKPKT 30440-3 | Johor BahruJohor | 486 | SmoothOn schedule | 1 Jun 2028Extended 12 months from 1 Jun 20271st sale agreement 1 Jun 2024 | 81% |
| M SINARKPKT 13425-8M Sinar · on PropertySifu | SepangSelangor | 500 | SmoothOn schedule | 4 Jun 2028Extended 12 months from 4 Jun 20271st sale agreement 4 Jun 2024 | 64–70% |
| RESIDENSI M TERRAKPKT 30805-1M Terra · on PropertySifu | PetalingSelangor | 999 | SmoothOn schedule | 27 Jul 2028Extended 12 months from 27 Jul 20271st sale agreement 27 Jul 2024 | 43–44% |
| M LEGASIKPKT 30897-2M Legasi Semenyih · on PropertySifu | Hulu LangatSelangor | 256 | SmoothOn schedule | 10 Sep 2028Extended 12 months from 10 Sep 20271st sale agreement 10 Sep 2025 | 20–47% |
| PANGSAPURI CENDANAKPKT 13138-4 | GombakSelangor | 244 | SmoothOn schedule | 6 Oct 20281st sale agreement 6 Oct 2025 | 59% |
| RESIDENSI M AZURAKPKT 30834-1M Azura · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,140 | SmoothOn schedule | 14 Nov 2028Extended 12 months from 14 Nov 20271st sale agreement 14 Nov 2024 | 24% |
| RESIDENSI M NOVAKPKT 11202-5 | Kuala LumpurWP Kuala Lumpur | 832 | SmoothOn schedule | 25 Nov 2028Extended 12 months from 25 Nov 20271st sale agreement 25 Nov 2024 | 88% |
| RESIDENSI SURIA MADANIKPKT 5911-32 | Kuala LumpurWP Kuala Lumpur | 800 | SmoothOn schedule | 25 Feb 2029Extended 12 months from 25 Feb 20281st sale agreement 25 Feb 2025 | 20% |
| SKIM PERUMAHAN MAMPU MILIK BESTARI PERDANA 2KPKT 14297-26 | Johor BahruJohor | 192 | SmoothOn schedule | 6 Mar 20291st sale agreement 6 Mar 2026 | 93–94% |
| SKIM PERUMAHAN MAMPU MILIK BESTARI PERDANA 2KPKT 14297-27 | Johor BahruJohor | 200 | SmoothOn schedule | 6 Mar 20291st sale agreement 6 Mar 2026 | 93–94% |
| M LEGASIKPKT 30897-3M Legasi Semenyih · on PropertySifu | Hulu LangatSelangor | 231 | SmoothOn schedule | 8 Apr 2029Extended 12 months from 8 Apr 20281st sale agreement 8 Apr 2026 | 20% |
| M ZENNIKPKT 12029-3 | Pulau Pinang | 494 | SmoothOn schedule | 29 Sep 2029Extended 12 months from 29 Sep 20281st sale agreement 29 Sep 2025 | 5% |
| RESIDENSI METROPOLITAN KEPONGKPKT 11430-3 | Kuala LumpurWP Kuala Lumpur | 702 | SmoothOn schedule | 5 Nov 2029Extended 12 months from 5 Nov 20281st sale agreement 5 Nov 2025 | 20% |
| RESIDENSI M ASPIRAKPKT 5911-33M Aspira · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,618 | SmoothOn schedule | 20 Nov 2029Extended 22 months from 20 Jan 20281st sale agreement 20 Jan 2025 | 21–22% |
| RESIDENSI ANGGUN MEWAHKPKT 9600-6 | Johor BahruJohor | 843 | SmoothOn schedule | 25 Jul 2030Extended 22 months from 25 Sep 20281st sale agreement 25 Sep 2025 | 20% |
| RESIDENSI M AURORAKPKT 13262-2M Aurora · on PropertySifu | WP Kuala Lumpur | 1,544 | SmoothOn schedule | 28 Sep 2030Extended 18 months from 28 Mar 20291st sale agreement 28 Mar 2026 | 5% |
| M AMAYAKPKT 12029-4 | Pulau Pinang | 833 | SmoothOn schedule | 23 Dec 2030Extended 18 months from 23 Jun 20291st sale agreement 23 Jun 2026 | 2% |
| RESIDENSI ANGGUN MEWAHKPKT 9600-7 | Johor BahruJohor | 890 | SmoothOn schedule | 25 Feb 2031Extended 24 months from 25 Feb 20291st sale agreement 25 Feb 2026 | 14% |
| RESIDENSI M MIRAKPKT 11606-3 | Kuala LumpurWP Kuala Lumpur | 633 | SmoothNot started | —Extended 12 months (date not registered) | 0% |
| MERIDIN EAST PARCEL 1AKPKT 14297-30 | Johor | 111 | SmoothOn schedule | — | 50% |
| M SINARKPKT 13425-9 | SepangSelangor | 499 | SmoothOn schedule | —Extended 12 months (date not registered) | 20% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| BANDAR BARU LEMBAH SELATANKPKT 13425-5 | SepangSelangor | 813 | Permit cancelledPermit cancelled | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Mah Sing at a glance
| Listed | Bursa Malaysia Main Market · MAHSING (8583) · listed on the KLSE Second Board in 1992, on the Main Board since 2004[1] |
|---|---|
| Started | Mah Sing Group Berhad registered in 1991; its founder started the plastics manufacturing business in 1979[1] |
| Head office | Wisma Mah Sing, Jalan Sungai Besi, Kuala Lumpur[1] |
| Leadership | Tan Sri Dato' Sri Leong Hoy Kum — Founder and Group Managing Director[1][3] Dato' Voon Tin Yow — Group Chief Executive Officer and Executive Director[1] Admiral (R) Tan Sri Dato' Seri Abu Bakar bin Abdul Jamal — Chairman, Independent Non-Executive Director[1] |
| Companies in the KPKT register | COSMOWEALTH HOUSING DEVELOPMENT SDN. BHD. (78%) KPKT 19228[1] DSARA SENTRAL SDN. BHD. KPKT 9600[1] ELITE PARK DEVELOPMENT SDN. BHD. KPKT 13138[1] ENCHANTING HEIGHTS SDN. BHD. KPKT 13545[1] ENRICH PROPERTY DEVELOPMENT SDN. BHD. KPKT 10945[1] GRAND PRESTIGE DEVELOPMENT SDN. BHD. KPKT 11433[1] ICON CITY DEVELOPMENT SDN. BHD. KPKT 11896[1] LOYAL SIERRA DEVELOPMENT SDN. BHD. KPKT 10393[1] M AZURA SDN. BHD. KPKT 30834[1] M HANA SDN. BHD. KPKT 10264[1] M VERTICA SDN. BHD. KPKT 19318[1] M ZENYA SDN. BHD. KPKT 11430[1] MAH SING PROPERTIES SDN. BHD. KPKT 5911[1] MAJOR LAND DEVELOPMENT SDN. BHD. KPKT 13262[1] MAXIM HEIGHTS SDN. BHD. KPKT 11606[1] MEDITERRANEAN VIEW DEVELOPMENT SDN. BHD. KPKT 19392[1] MERIDIN EAST SDN. BHD. KPKT 14297[1] MESTIKA BISTARI SDN. BHD. KPKT 30897[1] MS LAKECITY SDN. BHD. KPKT 30440[1] MYVILLA DEVELOPMENT SDN. BHD. KPKT 11202[1] NOVA CENTURY DEVELOPMENT SDN. BHD. KPKT 10168[1] NOVA LEGEND DEVELOPMENT SDN. BHD. KPKT 11347[1] OASIS GARDEN DEVELOPMENT SDN. BHD. KPKT 11727[1] SEMAI MERANTI SDN. BHD. KPKT 11998[1] SOUTHVILLE CITY SDN. BHD. KPKT 13425[1] SUPREME SPRINGS SDN. BHD. KPKT 30805[1] TROPIKA ISTIMEWA DEVELOPMENT SDN. BHD. KPKT 13078[1] UPTREND HOUSING DEVELOPMENT SDN. BHD. KPKT 12324[1] VENICE VIEW DEVELOPMENT SDN. BHD. KPKT 10279[1] VIENNA HOME SDN. BHD. KPKT 11348[1] VIENNA VIEW DEVELOPMENT SDN. BHD. KPKT 12029[1] |
| Website | mahsing.com.my |
| Property since | 1994, with four projects; the first was link homes in Ulu Yam[1] |
| Homes delivered in 2025 (company figure) | 4,802 homes[1] |
| Land bank | 2,707 acres at 31 December 2025; remaining gross development value and unbilled sales RM33.70 billion[1] |
| Where it builds (company figure) | More than 60 projects across Greater Kuala Lumpur, the Klang Valley, Johor, Penang and Sabah[1] |
| Largest township | Meridin East, Iskandar Malaysia, Johor: 1,313 acres, launched in 2016[1] |
Mah Sing projects on sale on PropertySifu
M Arisa
- RESIDENSI SERI WAHYU — 2.5 km, 2020
- LAKEVILLE RESIDENCE — 2.6 km, 2020
- LAKEVILLE RESIDENCE — 2.6 km, —
M Aspira
- M OSCAR — 2.2 km, 2024
- M VERTICA — 4.3 km, 2023
- M VERTICA — 4.3 km, 2022
M Astra @ Setapak
- RESIDENSI M ADORA WANGSA — 2.7 km, 2023
- RESIDENSI M ARISA PELANGI — 3.5 km, 2025
- M CENTURA — 3.6 km, 2021
M Azura
- RESIDENSI M ASTRA — 1.6 km, 2026
- RESIDENSI M ADORA WANGSA — 2.3 km, 2023
- M CITY — 3.5 km, 2017
M Luna
- LAKEVILLE RESIDENCE — 2.8 km, 2020
- LAKEVILLE RESIDENCE — 2.8 km, —
- LAKEVILLE RESIDENCE — 2.8 km, 2018
M Nova
- RESIDENSI M LUNA — 1.2 km, 2024
- RESIDENSI SERI WAHYU — 2.7 km, 2020
- LAKEVILLE RESIDENCE — 2.7 km, 2020
M Sinar
- SENSORY RESIDENCE — 0.4 km, 2024
- FLORA QUESTA — 0.4 km, 2022
- BANDAR BARU LEMBAH SELATAN — 0.4 km, 2017
M Zenya
- RESIDENSI M LUNA — 1.1 km, 2024
- LAKEVILLE RESIDENCE — 2.6 km, 2020
- LAKEVILLE RESIDENCE — 2.6 km, —
Who is Mah Sing? The company behind the projects
Mah Sing's founder, Tan Sri Dato' Sri Leong Hoy Kum, started its plastics manufacturing business in 1979 and listed Mah Sing Group Berhad on the Second Board of the Kuala Lumpur Stock Exchange in 1992 [1]. The group moved into property development in 1994 with four projects, the first of them link homes in Ulu Yam; it launched its first township, Sri Pulai Perdana in Skudai, Johor, in 2000, and moved to the Main Board in 2004 [1]. Its head office is Wisma Mah Sing on Jalan Sungai Besi, Kuala Lumpur [1].
The company says it has more than 60 projects across Greater Kuala Lumpur, the Klang Valley, Johor, Penang and Sabah, and that it delivered 4,802 homes in 2025 [1]. At 31 December 2025 it had 2,707 acres of remaining land bank and RM33.70 billion of remaining gross development value and unbilled sales [1]. Its largest township by area, the 1,313-acre Meridin East in Iskandar Malaysia, was launched in 2016 [1]. These are group-wide figures: the KPKT register counts each licensed phase as a separate housing project, and none of the Mah Sing projects in it is in Sabah.
The M-series projects listed on PropertySifu are registered with KPKT under Mah Sing subsidiaries. Cosmowealth Housing Development Sdn Bhd, the developer of M Arisa, is 78% owned by Mah Sing; the developers of the others are wholly owned [1]. Maxim Heights Sdn Bhd, registered as the developer of Icon Residence and M Adora, is also a wholly owned Mah Sing subsidiary [1] and is not part of Maxim Global Berhad, a different listed developer.
Leong is founder and group managing director, Dato' Voon Tin Yow is group chief executive officer, and the chairman is Admiral (R) Tan Sri Dato' Seri Abu Bakar bin Abdul Jamal [1].
Frequently asked questions
Is Mah Sing a listed company?
How many housing projects has Mah Sing completed?
In the KPKT register, 97 of the 141 housing projects under 31 Mah Sing companies are completed. Of the 77 completed projects that have both a deadline and a completion date in the register, 21 were handed over on or before the deadline set by the first sale agreement (including any extension KPKT approved), 40 were handed over or certified complete after that deadline — 5 of these were under construction during the 18 March–31 August 2020 movement control period — and 16 received the completion certificate before the deadline, with no handover date recorded. The company says it delivered 4,802 homes in 2025 [1].
Does Mah Sing have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 141 Mah Sing projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). 40 projects are under construction and on schedule (Lancar), and one, 13425-5, has the status Permit Telah Dibatalkan (permit cancelled). Of the 3 not yet started (Belum Mula), two — 10393-2 and 10393-3 — have first sale agreements dated 2011.
Which Mah Sing companies develop the M-series projects on PropertySifu?
According to KPKT: M Aspira and M Oscar — Mah Sing Properties Sdn Bhd; M Arisa — Cosmowealth Housing Development Sdn Bhd; M Astra — Nova Century Development Sdn Bhd; M Aurora — Major Land Development Sdn Bhd; M Azura — M Azura Sdn Bhd; M Legasi — Mestika Bistari Sdn Bhd; M Luna — Vienna Home Sdn Bhd; M Nova — Myvilla Development Sdn Bhd; M Sinar — Southville City Sdn Bhd; M Terra — Supreme Springs Sdn Bhd; M Zenya — M Zenya Sdn Bhd. Mah Sing owns 78% of Cosmowealth and all of the others, according to its 2025 annual report [1].
Has M Nova's handover deadline been extended?
Yes, according to KPKT. The first M Nova registration (11202-4, 1,248 units, first sale agreement 17 August 2023) had a deadline of 17 August 2026, extended with approval by 18 months to 17 February 2028; its reported progress is 92.5%. A second registration (11202-5, 832 units, first sale agreement 25 November 2024) had a deadline of 25 November 2027, extended by 12 months to 25 November 2028; its reported progress is 87.5%. Both are recorded as on schedule (Lancar).
Is Maxim Heights Sdn Bhd part of Mah Sing or of Maxim Global?
Mah Sing. Its 2025 annual report lists Maxim Heights Sdn Bhd as a wholly owned subsidiary [1]. KPKT registers Icon Residence, M Adora and M Mira (not yet started) under it. It is not part of Maxim Global Berhad, the developer of Maxim Risen and Maxim D'Parc.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Mah Sing Group Berhad Integrated Annual Report 2025 · Mah Sing Group Berhad · 30 Apr 2026 · accessed 28 Oct 2026
https://www.mahsing.com.my/web/wp-content/uploads/FA_15149-Mah-Sing-IR-2025_Full-Set_LR.pdf - [2] Sin Chew Business Excellence Awards 2025 — sponsors (关于马星集团 Mah Sing Group Berhad) · Sin Chew Daily 星洲日报 · accessed 28 Oct 2026
https://sinchewbusinessawards2025.sinchew.com.my/sponsor.php - [3] 马星集团与吉隆坡甲洞联手 开发22.6亿柔新经济特区工业园 · The Edge Malaysia(中文) · accessed 28 Oct 2026
https://theedgemalaysia.com/node/786563
Last updated 28 Oct 2026