I already bought — now the project is Sick / Late. What are my rights?

Your SPA and loan remain in force. Key rights: LAD after the delivery date, Tribunal claims up to RM50k, and a JPN confirmation letter for loan restructuring.
By the PropertySifu Editorial · Updated August 2026 · 5 min read read
The straight answer

Your SPA and your loan remain in force — do not stop paying instalments on your own initiative.

Your key rights: LAD damages once the delivery date in your SPA passes, the Homebuyer Claims Tribunal for claims up to RM50,000, and a problem-project confirmation letter from JPN you can use to negotiate loan restructuring with your bank.

Bank instalments — do I keep paying?

Your housing loan is a separate contract with the bank; the developer's delay does not cancel it. Stopping payments unilaterally can damage your credit record. The step KPKT records: buyers in Sick-status projects can request a problem-project confirmation letter from the National Housing Department and present it to their bank to negotiate instalment restructuring.

LAD: late-delivery damages

The statutory SPA (Schedule G/H, Act 118) sets late-delivery damages calculated on the purchase price at the rate in the agreement. It starts only after the delivery date in your SPA passes — Sick status before that date does not yet qualify. Keep every document and receipt.

Where to report and claim

  1. The developer, in writing — request the revised schedule and progress records.
  2. The National Housing Department's e-aduan — project status complaints, officially recorded.
  3. The Homebuyer Claims Tribunal — claims up to RM50,000, no lawyer needed.
  4. Claims above the tribunal limit — through the courts; get a lawyer's advice.

When does it count as abandoned?

When there is no significant site activity for 6 consecutive months (or the developer is wound up / admits inability), confirmed by the Minister under S.11(1)(c) of Act 118. The process differs after that — see steps for buyers in abandoned projects.

What this article is — and is not

Facts and official channels only, not legal advice. Every case differs — for court action or loan restructuring, consult your lawyer and your bank.

Frequently asked questions

Can I cancel my purchase because the project is sick?

Sick status by itself is not an automatic ground for cancellation. Termination rights depend on your SPA terms and specific circumstances — get a lawyer's advice before acting.

How long before I can claim LAD?

LAD starts the moment the delivery date in your SPA passes without handover. Before that date, site delays do not yet qualify.