Maxim (Maxim Global Berhad)
Maxim Global Berhad is a Bursa Malaysia Main Market-listed developer of affordable and mid-range homes with nine housing projects in the KPKT register under seven group companies: five completed and four under construction, one of which, The Atas, is classed Late (Lewat); none is Sick or Abandoned. All nine have KPKT-approved deadline extensions.
- 9 projects in the KPKT register
- 5 completed
- 4 under construction
- None Sick or Abandoned
Has Maxim handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 9 housing projects under 7 Maxim companies in 2 states: 5 completed, 4 under construction. 0 classed Sick (Sakit), 0 Abandoned (Terbengkalai), 1 Late (Lewat).
Of the 5 completed projects, 5 have both a handover deadline and a completion date in the register: 3 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 2 received the completion certificate before the deadline (handover date not recorded).
9 projects had the delivery period extended with KPKT approval.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI MAXIM RISENKPKT 30037-1Maxim Risen · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,236 | 1 Feb 2027Extended 18 months from 1 Aug 20251st sale agreement 1 Aug 2022 | CCC 2 Sep 2026 Handover 15 Sep 2026 | 139 days before |
| RESIDENSI MAXKPKT 20169-1 | Kuala LumpurWP Kuala Lumpur | 818 | 1 Jun 2026Extended 18 months from 1 Dec 20241st sale agreement 1 Dec 2021 | CCC 12 Sep 2025 Handover 29 Sep 2025 | 245 days before |
| RESIDENSI METRO KEPONGKPKT 14656-2 | Kuala LumpurWP Kuala Lumpur | 1,520 | 21 May 2023Extended 6 months from 21 Nov 20221st sale agreement 21 Nov 2019 | CCC 16 Mar 2023 Handover 17 Apr 2023 | 34 days before |
| RESIDENSI THE ADDRESS IIKPKT 19088-2 | Kuala LumpurWP Kuala Lumpur | 202 | 23 Sep 2023Extended 29 months from 23 Apr 20211st sale agreement 23 Apr 2018 | CCC 7 Mar 2023 | CCC before deadline; handover not recorded |
| THE ADDRESSKPKT 19088-1 | Kuala LumpurWP Kuala Lumpur | 376 | 13 Mar 2023Extended 29 months from 13 Oct 20201st sale agreement 13 Oct 2017 | CCC 30 Aug 2022 | CCC before deadline; handover not recorded |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI MAX IIKPKT 30267-1 | Kuala LumpurWP Kuala Lumpur | 604 | SmoothOn schedule | 30 Jan 2028Extended 16 months from 30 Sep 20261st sale agreement 30 Sep 2023 | 88% |
| RESIDENSI THE ATASKPKT 19088-3The Atas · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 624 | DelayLate | 11 Sep 2028Extended 16 months from 11 May 20271st sale agreement 11 May 2024 | 33–38% |
| RESIDENSI MAXIM PELANGIKPKT 31074-1 | Johor BahruJohor | 2,743 | SmoothOn schedule | 26 Sep 2030Extended 22 months from 26 Nov 20281st sale agreement 26 Nov 2025 | 20% |
| RESIDENSI MAXIM D'PARCKPKT 31046-1Maxim D'Parc · on PropertySifu | WP Kuala Lumpur | 1,116 | SmoothOn schedule | 4 Nov 2030Extended 18 months from 4 May 20291st sale agreement 4 May 2026 | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Maxim at a glance
| Listed | Bursa Malaysia Main Market · MAXIM (4022) · listed 22 December 1970, then as Pacific Chemicals Berhad[1][2][3] |
|---|---|
| Started | Incorporated on 4 December 1968 as Pacific Chemicals Berhad; later Tadmax Resources Berhad; Maxim Global Berhad since 3 November 2020[2] |
| Head office | Kelana Jaya, Petaling Jaya, Selangor[1] |
| Leadership | Tan Sri Datuk Seri Gan Seong Liam — Executive Chairman[4][6][7] Gan Kuok Chyuan — Managing Director[4] |
| Companies in the KPKT register | BUILTAMONT DEVELOPMENT SDN. BHD. (55%) KPKT 30037[1] BUTIRJAYA MAXIM DEVELOPMENT SDN. BHD. KPKT 20169[1] KAISAR MAXIM SDN. BHD. KPKT 19088[1] MAXIM PELANGI SDN. BHD. (51%) KPKT 31074[1] MIZUMI MAXIM SDN. BHD. KPKT 31046[1] PROMINENT MAXIM SDN. BHD. (51%) KPKT 30267[1] WAWASAN METRO BINA SDN. BHD. KPKT 14656[1] |
| Website | maximglobal.com.my |
| Gan Seong Liam in property development since | 1985[1] |
| Focus | Affordable and mid-range homes[5] |
| First project in the south | Residensi Maxim Pelangi, Taman Pelangi, Johor Bahru: launched November 2025[1] |
| Land bought in 2025 | About 47.35 acres in Johor and Pahang, outside its existing core regions[1] |
Maxim projects on sale on PropertySifu
Maxim D'Parc
- RESIDENSI MAXIM RISEN — 0.9 km, 2026
- RESIDENSI THE ADDRESS II — 6.9 km, 2023
- THE ADDRESS — 7.5 km, 2022
Maxim Risen
- RESIDENSI THE ADDRESS II — 4.7 km, 2023
- THE ADDRESS — 5.5 km, 2022
The Atas
- THE ADDRESS — 0.4 km, 2022
- RESIDENSI THE ADDRESS II — 1.2 km, 2023
- RESIDENSI MAXIM RISEN — 7.2 km, 2026
Who is Maxim? The company behind the projects
Maxim Global Berhad was incorporated on 4 December 1968 as Pacific Chemicals Berhad and listed on the Main Board of the Kuala Lumpur Stock Exchange on 22 December 1970 [2]. It later became Tadmax Resources Berhad and took its present name on 3 November 2020 [2]. Its main business today is developing affordable and mid-range homes [5]; the head office is in Kelana Jaya, Petaling Jaya [1].
Tan Sri Datuk Seri Gan Seong Liam, who has been in property development since 1985, joined the board in February 2019 and became managing director in August that year [1]. The company's website now lists him as executive chairman and his son Gan Kuok Chyuan as managing director [4]. Maxim Holdings Sdn Bhd — then a private property developer, now a Maxim Global subsidiary — marketed Maxim Citylights in Sentul and Maxim Residences in Alam Damai, Cheras [1]. KPKT registers those two projects under Meridian Maxim Sdn Bhd and Trillion Maxim Sdn Bhd, which the annual report lists as related companies with common directors, not subsidiaries [1], so they are not counted in the table above.
Its projects on PropertySifu are registered under group subsidiaries: Maxim Risen in Taman Desa Aman, Cheras, under Builtamont Development Sdn Bhd, 55% owned; The Atas in Taman Desa under Kaisar Maxim Sdn Bhd, wholly owned; and Maxim D'Parc in Alam Damai, Cheras, under a wholly owned subsidiary with KPKT developer code 31046 [1]. Residensi Maxim Pelangi in Taman Pelangi, Johor Bahru, launched in November 2025, is the group's first project in the southern region, and in 2025 the group bought about 47.35 acres in Johor and Pahang, outside its existing core regions [1].
Frequently asked questions
Is Maxim a listed company?
Yes. Maxim Global Berhad is listed on the Main Market of Bursa Malaysia under the stock name MAXIM [1], stock code 4022 [3]. It was listed on the Main Board of the Kuala Lumpur Stock Exchange on 22 December 1970 as Pacific Chemicals Berhad, was later called Tadmax Resources Berhad, and has been Maxim Global Berhad since 3 November 2020 [2].
How many housing projects has Maxim completed?
In the KPKT register, five of the nine housing projects under seven Maxim Global companies are completed: The Address and Residensi The Address II in Taman Desa (completion certificates dated 30 August 2022 and 7 March 2023; handover dates not recorded), Residensi Metro Kepong (handed over 17 April 2023), Residensi Max (29 September 2025) and Residensi Maxim Risen (15 September 2026). Each of the five was handed over, or certified complete, before the deadline set by its first sale agreement as extended with KPKT approval; all nine projects have such an extension.
Is The Atas classed as late?
Yes. As at 27 October 2026 the KPKT register classes The Atas (19088-3, 624 units) as Late (Lewat). Its first sale agreement was signed on 11 May 2024; the handover deadline of 11 May 2027 was extended with approval by 16 months to 11 September 2028, and reported construction progress is 33–38%.
Has Maxim D'Parc's handover deadline been extended?
Yes, according to KPKT. Maxim D'Parc (31046-1, 1,116 units, first sale agreement 4 May 2026) had a deadline of 4 May 2029, extended with approval by 18 months to 4 November 2030. It is recorded as on schedule (Lancar), with reported progress of 0%.
Was Maxim Risen handed over on time?
KPKT records the first sale agreement on 1 August 2022 and a handover deadline of 1 August 2025, extended with approval by 18 months to 1 February 2027. The completion certificate is dated 2 September 2026 and vacant possession 15 September 2026: 139 days before the extended deadline and 410 days after the original one. The developer is Builtamont Development Sdn Bhd, 55% owned by Maxim Global [1].
Are Maxim Citylights and Maxim Residences counted on this page?
No. They were marketed by Maxim Holdings Sdn Bhd, then a private developer [1], but KPKT registers them under Meridian Maxim Sdn Bhd and Trillion Maxim Sdn Bhd, which Maxim Global's 2025 annual report lists as related companies with common directors rather than subsidiaries [1]. This page counts only projects registered under companies in the listed group.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Maxim Global Berhad Annual Report 2025 · Maxim Global Berhad · 28 Apr 2026 · accessed 28 Oct 2026
https://maximglobal.com.my/wp-content/uploads/2026/04/Maxim-AR2025-28.04.2026-Final.pdf - [2] Company Profile · Maxim Global Berhad · accessed 28 Oct 2026
https://maximglobal.com.my/company-profile/ - [3] Investor Relations (links to Bursa Malaysia announcements for stock code 4022) · Maxim Global Berhad · accessed 28 Oct 2026
https://maximglobal.com.my/investor-relations/ - [4] Profile of Board of Directors · Maxim Global Berhad · accessed 28 Oct 2026
https://maximglobal.com.my/profile-of-board-of-directors/ - [5] Maxim Global Berhad — home page · Maxim Global Berhad · accessed 28 Oct 2026
https://maximglobal.com.my/ - [6] 董事经理提议以每股24仙献购Maxim Global · The Edge Malaysia(中文) · 4 May 2026 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/802223 - [7] Insider Moves: ASM Automation Group Bhd, Maxim Global Bhd, Coastal Contracts Bhd, ITMAX System Bhd, Ge-Shen Corp Bhd · The Edge Malaysia · 18 May 2026 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/804481
Last updated 28 Oct 2026