Country Garden (Country Garden Holdings Company Limited)
Country Garden Holdings, a Chinese developer listed in Hong Kong since 2007, has 14 housing projects in Malaysia's KPKT register under four project companies we could link to it: 11 completed, 1 under construction and 2 with the permit cancelled; none is classed Sick or Abandoned. They are in Danga Bay (Johor Bahru), Diamond City (Semenyih) and Lake City (Kepong).
- 14 projects in the KPKT register
- 11 completed
- 1 under construction
- 2 with the permit cancelled
- None Sick or Abandoned
Has Country Garden handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 14 housing projects under 4 Country Garden companies in 3 states: 11 completed, 1 under construction, 2 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 11 completed projects, 11 have both a handover deadline and a completion date in the register: 2 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 5 handed over or certified complete after that deadline; 4 received the completion certificate before the deadline (handover date not recorded).
5 projects had the delivery period extended with KPKT approval.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| DIAMOND RESIDENCE B5KPKT 13170-6 | Hulu LangatSelangor | 201 | 16 Oct 20251st sale agreement 16 Oct 2022 | CCC 24 Jun 2025 Handover 30 Jun 2025 | 108 days before |
| RESIDENSI BARONKPKT 20110-1Lake City @ KL North · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,077 | 21 Sep 2025Extended 12 months from 21 Sep 20241st sale agreement 21 Sep 2021 | CCC 14 May 2025 | CCC before deadline; handover not recorded |
| ARADIA RESIDENCEKPKT 19739-1 | Kuala LumpurWP Kuala Lumpur | 1,003 | 5 Sep 2024Extended 23 months from 5 Oct 20221st sale agreement 5 Oct 2019 | CCC 26 Feb 2024 Handover 13 Mar 2024 | 176 days before |
| ACACIAKPKT 13170-5 | Hulu LangatSelangor | 216 | 14 Nov 2022Extended 11 months from 14 Dec 20211st sale agreement 14 Dec 2018 | CCC 26 Sep 2022 | CCC before deadline; handover not recorded |
| LAURELKPKT 13170-4 | Hulu LangatSelangor | 72 | 2 May 2021Extended 6 months from 2 Nov 20201st sale agreement 2 Nov 2017 | CCC 29 Jul 2020 | CCC before deadline; handover not recorded |
| DIAMOND CITYKPKT 13170-2 | Hulu LangatSelangor | 395 | 30 Jun 20191st sale agreement 30 Jun 2016 | CCC 23 Nov 2018 | CCC before deadline; handover not recorded |
| COUNTRY GARDEN DANGA BAYKPKT 13130-4 | Johor BahruJohor | 2,198 | 15 Sep 20161st sale agreement 15 Sep 2013 | CCC 15 Nov 2017 | 426 days after |
| COUNTRY GARDEN DANGA BAYKPKT 13130-3 | Johor BahruJohor | 2,352 | 21 Jan 20161st sale agreement 21 Jan 2013 | CCC 23 Oct 2017 | 641 days after |
| COUNTRY GARDEN DANGA BAYKPKT 13130-1 | Johor BahruJohor | 1,904 | 8 Aug 2017Extended 12 months from 8 Aug 20161st sale agreement 8 Aug 2013 | CCC 5 Sep 2017 | 28 days after |
| COUNTRY GARDEN DANGA BAYKPKT 13130-2KPKT records this tower's first sale agreement as 26 September 1994, before Country Garden bought the Danga Bay land in December 2012 and planned its first Malaysian launch for August 2013 [s4]; the deadline and the gap shown are calculated from the date in the register.[4] | Johor BahruJohor | 2,159 | 26 Sep 19971st sale agreement 26 Sep 1994 | CCC 5 Sep 2017 | 7,284 days after |
| MAYLAND VENUE SDN. BHD.KPKT 13170-1 | Hulu LangatSelangor | 400 | 29 Nov 20161st sale agreement 29 Nov 2013 | CCC 29 Jun 2017 | 212 days after |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| SAPPHIRE RESIDENCEKPKT 13170-7Sapphire Residence @ Diamond City · on PropertySifu | Hulu LangatSelangor | 449 | SmoothOn schedule | 13 Oct 20281st sale agreement 13 Oct 2025 | 28–40% |
Permit cancelled or other KPKT status (2)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| COUNTRY GARDEN DANGA BAYKPKT 13130-5 | Johor BahruJohor | 202 | Permit cancelledPermit cancelled | — | 0% |
| MAYLAND VENUE SDN. BHD.KPKT 13170-3 | Hulu LangatSelangor | 81 | Permit cancelledPermit cancelled | — | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Country Garden at a glance
| Listed | Stock Exchange of Hong Kong · stock code 2007 · listed in 2007 (parent company Country Garden Holdings Company Limited)[1] |
|---|---|
| Started | Established in 1992[1] |
| Head office | Shunde District, Foshan, Guangdong, China (principal place of business)[1] |
| Leadership | Yang Huiyan — Chairman (since 1 March 2023)[1] Cheng Guangyu — President (since 4 December 2025)[1] |
| Companies in the KPKT register | COUNTRY GARDEN DANGA BAY SDN. BHD. KPKT 13130[3][4] MAYLAND VENUE SDN. BHD. (55%) KPKT 13170[2][6][8] LAKE CITY KL NORTH SDN. BHD. KPKT 19739[9][11] LAKE CITY DEVELOPMENT SDN. BHD. KPKT 20110[10][9] |
| Website | countrygarden.com.cn |
| Malaysian projects on this page | Danga Bay (Johor Bahru), Diamond City (Semenyih, Selangor) and Lake City (Kepong, Kuala Lumpur)[4][5][11] |
| First Malaysian project | Country Garden Danga Bay, Johor Bahru, described in 2013 as its first project on its own outside China[4] |
| Diamond City shareholding | Country Garden 55%, Land & General Berhad 45% (reported in 2023); developer Mayland Venue Sdn Bhd[6][7][2] |
| Lake City partner | Developed with Perdana ParkCity Sdn Bhd (work began in 2019); the project website says it is managed and marketed by Country Garden Group[11][9] |
Country Garden projects on sale on PropertySifu
Sapphire Residence @ Diamond City
- LAUREL — 0.4 km, 2020
- DIAMOND CITY — 0.6 km, 2018
- ACACIA — 0.8 km, 2022
Who is Country Garden? The company behind the projects
Country Garden was established in 1992 and listed on the Stock Exchange of Hong Kong in 2007 [1]. The listed parent, Country Garden Holdings Company Limited, is incorporated in the Cayman Islands and has its principal place of business in Shunde, Foshan, in China's Guangdong province; its chairman is Yang Huiyan, in the role since 1 March 2023, and Cheng Guangyu became president on 4 December 2025 [1]. This page counts only the Malaysian project companies listed above.
Its first Malaysian project, Country Garden Danga Bay in Johor Bahru, was described in 2013 as the company's first project on its own outside China; it is developed by Country Garden Danga Bay Sdn Bhd on land bought in December 2012 [4], a company that Country Garden's annual reports up to 2021 list as wholly owned [3]. KPKT registers five projects under it: four serviced-apartment towers with 8,613 units, certified complete between September and November 2017, and a fifth with the permit cancelled. The annual reports also list Country Garden Pacificview Sdn Bhd, 58% owned in 2021 [3], which The Edge described in 2015 as the developer of Forest City in Johor [13]; we could not match that company to a KPKT registration with a document, so Forest City is not counted in the table above.
Diamond City in Semenyih, Selangor, began as a 55:45 joint venture between Country Garden and the Mayland Group, reported in 2014 as a 102-hectare freehold development split into Plot A and Plot B [5]. Country Garden's 2016 annual report lists its developer, Mayland Venue Sdn Bhd, as 55% owned by the group [2]. In 2023 the New Straits Times reported that Land & General Berhad owns 45% of Diamond City and Country Garden the other 55%; L&G's largest shareholder, with 34.7%, is Mayland Parkview Sdn Bhd of the Mayland Group [6]. L&G's 2026 annual report records a 45% stake in Country Garden Properties (Malaysia) Sdn Bhd and lists Diamond City (Plot B) as a joint venture [7], and the project website calls it a development by Country Garden and Land & General Berhad [8]. Sapphire Residence, the phase on PropertySifu, is registered under Mayland Venue.
In Kuala Lumpur, Country Garden and Perdana ParkCity Sdn Bhd began work in 2019 on Lake City, an 80-acre development in Kepong [11], to be built through a joint-venture company [12]. The project website, copyrighted by Lake City KL North Sdn Bhd, says it is managed and marketed by Country Garden Group [9]. KPKT registers the first phase, Aradia Residence (1,003 units), under Lake City KL North Sdn Bhd, and Baron Residence (1,077 units), the project on PropertySifu, under Lake City Development Sdn Bhd. The partners' shareholdings in Lake City have not been published.
Frequently asked questions
Is Country Garden a listed company?
Yes. Its parent, Country Garden Holdings Company Limited, has been listed on the Stock Exchange of Hong Kong since 2007 under stock code 2007 [1]. Its Malaysian projects are developed through private Malaysian companies (Sdn Bhd); Country Garden's annual reports list Country Garden Danga Bay Sdn Bhd as wholly owned and Mayland Venue Sdn Bhd as 55% owned [3][2].
Which company develops Sapphire Residence @ Diamond City?
Mayland Venue Sdn Bhd (KPKT developer code 13170), which Country Garden's 2016 annual report lists as 55% owned by the group [2]. Despite its name, it is the Diamond City joint-venture company: the New Straits Times reported in 2023 that Land & General Berhad holds 45% of Diamond City and Country Garden 55% [6], and the project website names Country Garden and Land & General Berhad as its developers [8].
Has Sapphire Residence's handover deadline been extended?
Not according to KPKT. Sapphire Residence (KPKT 13170-7, 449 terrace houses, town houses and detached houses) had its first sale agreement on 13 October 2025 and a handover deadline of 13 October 2028, with no extension recorded. KPKT lists it as on schedule (Lancar), with reported construction progress of 28–40%.
Has Lake City @ KL North been completed?
Yes, both phases registered with KPKT. Baron Residence (20110-1, 1,077 units), the project on PropertySifu, had its first sale agreement on 21 September 2021 and a deadline of 21 September 2024, extended with approval by 12 months to 21 September 2025; its CCC is dated 14 May 2025, 130 days before the extended deadline, and the handover date is not recorded. Aradia Residence (19739-1, 1,003 units) had a deadline of 5 October 2022, extended by 23 months to 5 September 2024; its CCC is dated 26 February 2024 and vacant possession 13 March 2024, 176 days before the extended deadline.
Were the Country Garden Danga Bay towers handed over on time?
KPKT records completion certificates after the deadline for all four completed towers; the register does not record their handover dates. 13130-1 (1,904 units): deadline 8 August 2016, extended with approval by 12 months to 8 August 2017; CCC 5 September 2017, 28 days after the extended deadline. 13130-3 (2,352 units): deadline 21 January 2016; CCC 23 October 2017, 641 days after. 13130-4 (2,198 units): deadline 15 September 2016; CCC 15 November 2017, 426 days after. For 13130-2 (2,159 units, CCC 5 September 2017), the register gives a first sale agreement date of 26 September 1994, before Country Garden bought the land in December 2012 [4], so the deadline shown for it is calculated from that recorded date.
Does Country Garden have any Sick or Abandoned projects in Malaysia?
No. As at 27 October 2026, none of the 14 projects under the four companies on this page is classed Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). Two have the permit cancelled: a 202-unit serviced-apartment project at Danga Bay (13130-5) and an 81-unit landed project at Diamond City (13170-3).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Country Garden Holdings Company Limited Annual Report 2025 · Country Garden Holdings Company Limited via HKEXnews · 27 Apr 2026 · accessed 28 Oct 2026
https://www1.hkexnews.hk/listedco/listconews/sehk/2026/0427/2026042701933.pdf - [2] Country Garden Holdings Company Limited Annual Report 2016 (note 47, principal subsidiaries; overseas project details) · Country Garden Holdings Company Limited via HKEXnews · 5 Apr 2017 · accessed 28 Oct 2026
https://www1.hkexnews.hk/listedco/listconews/sehk/2017/0405/ltn201704051278.pdf - [3] Country Garden Holdings Company Limited Annual Report 2021 (principal subsidiaries) · Country Garden Holdings Company Limited via HKEXnews · 22 Apr 2022 · accessed 28 Oct 2026
https://www1.hkexnews.hk/listedco/listconews/sehk/2022/0422/2022042200635.pdf - [4] Country Garden to strengthen presence in Malaysia · The Edge Malaysia · 5 Aug 2013 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/country-garden-strengthen-presence-malaysia - [5] China developer upbeat on property sales here · New Straits Times · 17 Jun 2014 · accessed 28 Oct 2026
https://www.nst.com.my/amp/business/properties/2014/06/3378/China%20developer%20%20%20upbeat%20on%20property%20sales%20here - [6] Diamond City project self-sustaining · New Straits Times · 25 Sep 2023 · accessed 28 Oct 2026
https://nst.com.my/amp/business/corporate/2023/09/959310/diamond-city-project-self-sustaining - [7] Land & General Berhad Annual Report 2026 (note 5, investments in associates; key project highlights) · Land & General Berhad · 31 Jul 2026 · accessed 28 Oct 2026
https://www.insage.com.my/ir/cmn/loadpdf.aspx?sFileName=26212000068735&sReportType=AR&sCompanyCode=LG - [8] Country Garden Diamond City — official project website · Mayland Venue Sdn Bhd · accessed 28 Oct 2026
https://tour.cgdiamondcity.com.my/ - [9] Lake City KL North — official project website · Lake City KL North Sdn Bhd · accessed 28 Oct 2026
https://lakecity.com.my/ - [10] Baron Residence — Lake City KL North official website · Lake City KL North Sdn Bhd · accessed 28 Oct 2026
https://lakecity.com.my/baron-residence/ - [11] Lake City to redefine integrated residential development · StarProperty (The Star) · 5 Sep 2019 · accessed 28 Oct 2026
https://www.starproperty.my/news/lake-city-to-redefine-integrated-residential-development/115059 - [12] Lake City's Phase 1 draws good response · New Straits Times · 26 Sep 2019 · accessed 28 Oct 2026
https://www.nst.com.my/amp/property/2019/09/524678/lake-citys-phase-1-draws-good-response - [13] Forest City resumes but GDV shrinks 25% to RM450b · The Edge Financial Daily · 20 Mar 2015 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/forest-city-resumes-gdv-shrinks-25-rm450b - [14] 置地通用:与碧桂园的士毛月合资项目可自给自足 · The Edge Malaysia(中文) · accessed 28 Oct 2026
https://theedgemalaysia.com/node/683152