Sick & Abandoned Housing Projects in Negeri Sembilan (2026)

Official KPKT status (TEDUH) · updated 2026-09-07
20 Sick 3 Abandoned 7 Late 30 total
As at 2026-09-07, KPKT records 20 Sick, 3 Abandoned and 7 Late housing projects in Negeri Sembilan — all 30 listed in full below. Statuses are quoted directly from the KPKT TEDUH register, unamended. Check the project or developer name before you buy. Seremban district accounts for 10 of the state's 23 sick-or-abandoned projects — and that district includes Nilai and the S2/Rimbun Kasia corridors where most KL commuter-belt launches sit.

What do these statuses mean?

Sick
“Sick” (registry term: Sakit) — a project delayed by more than 30% against its expected progress schedule, or whose Sale & Purchase Agreement period has expired.
Abandoned
“Abandoned” (registry term: Terbengkalai) — an incomplete project with no significant site activity for 6 consecutive months; or a winding-up petition filed (S.218 Companies Act); or the company under a Receiver & Manager; or the developer admitting inability in writing — and confirmed by the Minister under S.11(1)(c) of Act 118.
Late
“Late” (registry term: Lewat) — TEDUH status for a project behind schedule that has not yet met the sick-project definition.

Definitions: National Housing Department — Sick Projects · Abandoned Projects

Which districts in Negeri Sembilan are most affected?

DistrictSick / Abandoned projects
Seremban10
Port Dickson3
Kuala Pilah3
Jempol3
Rembau2
Tampin1

Full list (30 projects)

ProjectDistrictDeveloperKPKT statusSold / Total unitsPermit valid until
TAMAN PINGGIRAN FELDA GEMASTampinRESOLUTE FORTUNE SDN. BHD.Abandoned3352009-12-23
Linear Legend Sdn BhdSerembanLINEAR LEGEND SDN. BHD.Abandoned5 / 52014-07-07
TAMAN REMBAU BAYURembauJBS SURIA BUMI SDN. BHD.Abandoned27 / 272023-02-07
BUKIT ARA PERDANASerembanBELLANOVA SDN. BHD.Sick304 / 3042015-06-18
DWI@RIMBUN KASIASerembanMEADOWFIELD SDN. BHD.
Group: IREKA (ireka.com.my)
Sick286 / 3822026-01-27
TAMAN KERSANIKuala PilahSANI-MAP DEVELOPMENT SDN. BHD.Sick173 / 3222026-11-08
QUEENSBURY @ MAHKOTA HILLS FASA 8A2 & 8A3 PARCEL 2SerembanKIA ACE DEVELOPMENT SDN. BHD.
Group: UMLAND (umland.com.my)
Sick258 / 2752026-10-20
TAMAN KEMUNINGJempolBESTARAYA DEVELOPMENT SDN. BHD.Sick67 / 1032027-04-02
TAMAN TERATAIJempolAMBER GLO DEVELOPMENT SDN. BHD.Sick49 / 1012026-12-28
CADANGAN PEMAJUAN 123 UNIT RUMAH TERES 2 TINGKAT DIATAS LOT 465, 469 & 470JempolKIARA KONSUL SDN. BHD.Sick46 / 582020-06-27
TAMAN KOTA LAGENDARembauBERIBU LAGENDA SDN. BHD.Sick10 / 492027-02-28
TAMAN HARMONI 2Kuala PilahILHAM PROPERTY RESOURCES SDN. BHD.Sick32 / 322022-08-17
TAMAN LINGGI IMPIANPort DicksonTERAS SEJAHTERA SDN. BHD.Sick16 / 362027-06-22
PEARL 2SerembanTHP ENSTEK DEVELOPMENT SDN. BHD.
Group: TH-PROPERTIES (th-properties.com)
Sick24 / 322027-04-01
FELORASerembanTHP HARTANAH SDN. BHD.
Group: TH-PROPERTIES (th-properties.com)
Sick21 / 312027-04-03
SIKAMAT RESIDENCESerembanSIKAMAT DEVELOPMENT SDN. BHD.Sick12 / 122020-05-07
TAMAN LINGGI IMPIANPort DicksonTERAS SEJAHTERA SDN. BHD.Sick25 / 282026-11-05
TAMAN BAIDURISerembanBIDARA CAMAR SDN. BHD.Sick4 / 262026-04-28
TAMAN SERI NEGERISerembanBIDARA CAMAR SDN. BHD.Sick18 / 222026-05-29
TAMAN KERANJIPort DicksonMASSUFEI SDN. BHD.Sick4 / 192027-04-14
TAMAN SERI GENTAMKuala PilahCAPAIAN YAKIN SDN. BHD.Sick4 / 192024-03-30
MANTAP BUMIMAS SDN BHDSerembanMANTAP BUMIMAS SDN. BHD.Sick8 / 132026-09-21
TAMAN RESAKJelebuKEMASCON BUILDERS SDN. BHD.Sick2 / 122027-02-27
TAMAN PD RESTUPort DicksonGREENWAY REALTY SDN. BHD.
Group: PC (pc.jaring.my)
Late70 / 1092027-05-05
TAMAN LILYJempolGAYA IDAMAN SDN. BHD.Late51 / 772026-10-15
BUKIT SURIA RUMAH KLUSTERBSS DEVELOPMENT SDN. BHD.
Group: MCHB (mchb.com.my)
Late53 / 562026-11-24
TAMAN SETIA INDAHSerembanPARADIGM CONNECTION SDN. BHD.Late23 / 262027-06-10
TAMAN DESA PENARIKANJempolMONT VICTORIA DEVELOPMENT SDN. BHD.Late1 / 172026-11-19
TAMAN DESA PENARIKANJempolMONT VICTORIA DEVELOPMENT SDN. BHD.Late1 / 102026-11-20
TAMAN MUTIARA ZAITUNSerembanSILAUAN MINDA (M) SDN. BHD.Late1 / 92026-12-29
Unit data refreshes on TEDUH's per-state review cycle; the “sold” figure is KPKT's latest record, not necessarily today's.

Your project is on the list? Next steps

  1. Confirm the current status — find the project in the table above or directly at teduh.kpkt.gov.my; statuses change as TEDUH updates.
  2. Know your rights — our guides: project turned Sick/Late: buyer rights and abandoned project: steps for buyers (official JPN channels, the bank confirmation letter, the Tribunal).
  3. Before buying another unit — check the developer group delivery records and how to check a developer's track record before paying a deposit.

Frequently asked questions

How many distressed housing projects are in Negeri Sembilan?

As at 2026-09-07: 20 Sick, 3 Abandoned, 7 Late (official KPKT TEDUH record).

Does this list include projects that have been rehabilitated?

No. It shows the current TEDUH status; a project that recovers and receives its CCC drops off the list at the next update.

Can units in a sick project still be sold?

Yes — sick status does not stop sales. That is exactly why it pays to check this list and confirm the APDL status with the developer and your financier before signing anything.

How do I check my own project's status?

Search the project name in the table above, or check directly at teduh.kpkt.gov.my. This list is compiled from that same official register, just easier to search.

Why does Negeri Sembilan have more Sakit projects than bigger states like Kedah?

The register (as at 29 Aug 2026) shows Negeri Sembilan with 20 Sakit projects against Kedah's 13, despite tracking fewer projects (1,325 vs 1,691). The register records status, not causes — what it tells a buyer is simply that the sick rate here is worth respecting, not ignoring.

Is it safe to buy a new launch in Seremban or Nilai?

The register says most projects deliver: 1,120 of 1,325 tracked Negeri Sembilan projects are recorded as completed, with about 2% sick, abandoned or delayed (as at 29 Aug 2026). The per-project check is still not optional — verify the status and the developer group's record before paying.

Status changed? Get monthly updates
Data source: TEDUH, Ministry of Housing and Local Government (KPKT) — teduh.kpkt.gov.my, data as at 2026-09-07. Used under the Government Open Data Terms of Use 1.0. Analysis by Affirm Plus Research. Project statuses are quoted exactly as recorded by KPKT, unamended.
PropertySifu does not represent any project on these distressed lists. Sabah/Sarawak/WP Labuan are not covered by TEDUH (East Malaysian housing development falls under state legislation).