Sick & Abandoned Housing Projects in Melaka (2026)

Official KPKT status (TEDUH) · updated 2026-09-07
14 Sick 1 Abandoned 5 Late 20 total
As at 2026-09-07, KPKT records 14 Sick, 1 Abandoned and 5 Late housing projects in Melaka — all 20 listed in full below. Statuses are quoted directly from the KPKT TEDUH register, unamended. Check the project or developer name before you buy.

What do these statuses mean?

Sick
“Sick” (registry term: Sakit) — a project delayed by more than 30% against its expected progress schedule, or whose Sale & Purchase Agreement period has expired.
Abandoned
“Abandoned” (registry term: Terbengkalai) — an incomplete project with no significant site activity for 6 consecutive months; or a winding-up petition filed (S.218 Companies Act); or the company under a Receiver & Manager; or the developer admitting inability in writing — and confirmed by the Minister under S.11(1)(c) of Act 118.
Late
“Late” (registry term: Lewat) — TEDUH status for a project behind schedule that has not yet met the sick-project definition.

Definitions: National Housing Department — Sick Projects · Abandoned Projects

Which districts in Melaka are most affected?

DistrictSick / Abandoned projects
Melaka Tengah7
Jasin4
Alor Gajah4

Full list (20 projects)

ProjectDistrictDeveloperKPKT statusSold / Total unitsPermit valid until
BABA NYONYA RESORTJasinNOVASARA DEVELOPMENT SDN. BHD.Abandoned4 / 42020-03-24
TAMAN SEBATU JAYAJasinLIMASJAYA SDN. BHD.Sick209 / 2092008-03-26
PORTO DE MELAKAMelaka TengahTINTA ANGGUN ENGINEERING SDN. BHD.Sick82 / 862021-03-03
TAMAN TEHEL INDAHJasinSUARA KIARAMAS SDN. BHD.
Group: TEOBROS DEVELOPMENT SDN. BHD.
Sick151 / 3562027-02-24
TAMAN PAYA RUMPUT GEMILANGMelaka TengahANJURAN CITY SDN. BHD.
Group: SHANGHEIGHT (shangheight.com.my)
Sick195 / 2392026-08-27
SATORI SERVICED RESIDENCESMelaka TengahPROLIFIC PROPERTIES SDN. BHD.Sick33 / 412023-01-03
EVORA RESORTMelaka TengahI COAST SDN. BHD.Sick95 / 952016-07-27
TAMAN REMBIA DAMAIAlor GajahITG PROJECTS SDN. BHD.Sick31 / 632027-06-24
TAMAN SRI AMAN LAGENDAAlor GajahKL CITY DEVELOPMENT SDN. BHD.Sick47 / 472022-03-25
TAMAN MACHAP BARUAlor GajahTAMAH RESOURCES SDN. BHD.
Group: FRANKHOUSE (frankhouse.com.my)
Sick10 / 102016-04-04
TAMAN GADEK PERMAIAlor GajahEUROSMILE SDN. BHD.Sick4 / 252026-02-05
BATU GAJAHJasinA&N PROJECTS SDN. BHD.
Group: MOH SENG DEVELOPMENT SDN. BHD.
Sick12 / 222026-09-27
TAMAN PAYA RUMPUT BERLIANMelaka TengahTIONG YUEN DEVELOPMENT SENDIRIAN BERHADSick6 / 212027-03-05
TAMAN SEMABOK JAYA 2Melaka TengahPEMBANGUNAN PAKATAN MAJU SDN. BHD.Sick17 / 202026-06-30
TAMAN PADANG TEMU PERMAIMelaka TengahPEMAJU BUMI CEMERLANG SDN. BHD.Sick5 / 132027-04-25
TAMAN REMBIA INDAHAlor GajahSWISS RELIANCE SDN. BHD.
Group: PBREALTY (pbrealty.com.my)
Late365 / 3912027-08-13
TAMAN PAYA DALAM FLORAMelaka TengahMERAK MESRA DEVELOPMENT SDN. BHD.
Group: THIAN REALTY SDN. BHD.
Late36 / 472027-07-19
TAMAN TAMBUN PERWIRAAlor GajahGALAXY GRACE SDN. BHD.Late23 / 412026-10-09
TAMAN BALIK BUKIT PERMAIMelaka TengahKERIS IMPIAN DEVELOPMENT SDN. BHD.Late12 / 282026-12-21
TAMAN KOMPANG RIAAlor GajahMERCHANT CAPITAL SDN. BHD.Late11 / 242026-09-22
Unit data refreshes on TEDUH's per-state review cycle; the “sold” figure is KPKT's latest record, not necessarily today's.

Your project is on the list? Next steps

  1. Confirm the current status — find the project in the table above or directly at teduh.kpkt.gov.my; statuses change as TEDUH updates.
  2. Know your rights — our guides: project turned Sick/Late: buyer rights and abandoned project: steps for buyers (official JPN channels, the bank confirmation letter, the Tribunal).
  3. Before buying another unit — check the developer group delivery records and how to check a developer's track record before paying a deposit.

Frequently asked questions

How many distressed housing projects are in Melaka?

As at 2026-09-07: 14 Sick, 1 Abandoned, 5 Late (official KPKT TEDUH record).

Does this list include projects that have been rehabilitated?

No. It shows the current TEDUH status; a project that recovers and receives its CCC drops off the list at the next update.

Can units in a sick project still be sold?

Yes — sick status does not stop sales. That is exactly why it pays to check this list and confirm the APDL status with the developer and your financier before signing anything.

How do I check my own project's status?

Search the project name in the table above, or check directly at teduh.kpkt.gov.my. This list is compiled from that same official register, just easier to search.

Status changed? Get monthly updates
Data source: TEDUH, Ministry of Housing and Local Government (KPKT) — teduh.kpkt.gov.my, data as at 2026-09-07. Used under the Government Open Data Terms of Use 1.0. Analysis by Affirm Plus Research. Project statuses are quoted exactly as recorded by KPKT, unamended.
PropertySifu does not represent any project on these distressed lists. Sabah/Sarawak/WP Labuan are not covered by TEDUH (East Malaysian housing development falls under state legislation).