YNH Property (YNH Property Berhad)
YNH Property Berhad is a Perak-based developer listed on Bursa Malaysia's Main Market, with 59 housing projects in the KPKT register under two YNH companies: 52 completed, 2 under construction (both classed Sick), 1 not yet started and 4 with permits cancelled; none is Abandoned. The company says it began township development in Sitiawan in 1982.
- 59 projects in the KPKT register
- 52 completed
- 2 under construction (of which 2 Sick)
- 1 not yet started
- 4 with the permit cancelled
Has YNH Property handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 59 housing projects under 2 YNH Property companies in 3 states: 52 completed, 2 under construction (of which 2 Sick), 1 not yet started, 4 with the permit cancelled.
Of the 52 completed projects, 14 have both a handover deadline and a completion date in the register: 9 handed over or certified complete after that deadline (2 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 5 received the completion certificate before the deadline (handover date not recorded).
2 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 52
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN AMAN MUHIBBAH 4KPKT 4131-141 | ManjungPerak | 12 | 3 Aug 20251st sale agreement 3 Aug 2023 | CFO 24 Dec 2025 Handover 24 Dec 2025 | 143 days after |
| TAMAN AMAN MUHIBBAH 4KPKT 4131-142 | ManjungPerak | 6 | 6 Dec 20251st sale agreement 6 Dec 2023 | CFO 23 Dec 2025 Handover 24 Dec 2025 | 18 days after |
| TAMAN BINTANG 1KPKT 4131-138 | ManjungPerak | 40 | 14 Aug 20201st sale agreement 14 Aug 2018 | CCC 20 Oct 2021 | 432 days after † |
| THE OOAK, SERVICED APARTMENTS, KIARA 163KPKT 19269-1 | Kuala LumpurWP Kuala Lumpur | 336 | 14 Sep 2021Extended 6 months from 14 Mar 20211st sale agreement 14 Mar 2018 | CCC 16 Aug 2021 | CCC before deadline; handover not recorded |
| TAMAN BUNGA RAYAKPKT 4131-137 | ManjungPerak | 13 | 3 Aug 20201st sale agreement 3 Aug 2018 | CFO 6 May 2021 | 276 days after † |
| TAMAN MANJUNG POINT SEKSYEN 2KPKT 4131-135 | ManjungPerak | 105 | 14 Mar 20191st sale agreement 14 Mar 2017 | CFO 5 Sep 2019 | 175 days after |
| SFERA RESIDENSIKPKT 4131-132 | PetalingSelangor | 519 | 28 Oct 20171st sale agreement 28 Oct 2014 | CFO 3 Apr 2019 | 522 days after |
| TAMAN SEJATIKPKT 4131-134 | ManjungPerak | 100 | 11 May 20181st sale agreement 11 May 2016 | CCC 2 Jul 2018 | 52 days after |
| TAMAN INDAH RAYAKPKT 4131-136 | ManjungPerak | 6 | 30 Mar 20191st sale agreement 30 Mar 2017 | CCC 25 Jun 2018 | CCC before deadline; handover not recorded |
| TAMAN SEJATI 3KPKT 4131-101 | ManjungPerak | 22 | 29 Jun 20171st sale agreement 29 Jun 2015 | CCC 9 Mar 2017 | CCC before deadline; handover not recorded |
| TAMAN DESA MANJUNGKPKT 4131-129 | ManjungPerak | 201 | 17 Nov 20161st sale agreement 17 Nov 2014 | CCC 17 Aug 2016 | CCC before deadline; handover not recorded |
| TAMAN DESA MANJUNG POINT 2KPKT 4131-54 | ManjungPerak | 203 | 4 Oct 20151st sale agreement 4 Oct 2013 | CCC 10 Jul 2015 | CCC before deadline; handover not recorded |
Handed over or certified complete after the deadline (9)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN AMAN MUHIBBAH 4KPKT 4131-141 | ManjungPerak | 12 | 3 Aug 20251st sale agreement 3 Aug 2023 | CFO 24 Dec 2025 Handover 24 Dec 2025 | 143 days after |
| TAMAN AMAN MUHIBBAH 4KPKT 4131-142 | ManjungPerak | 6 | 6 Dec 20251st sale agreement 6 Dec 2023 | CFO 23 Dec 2025 Handover 24 Dec 2025 | 18 days after |
| TAMAN BINTANG 1KPKT 4131-138 | ManjungPerak | 40 | 14 Aug 20201st sale agreement 14 Aug 2018 | CCC 20 Oct 2021 | 432 days after † |
| TAMAN BUNGA RAYAKPKT 4131-137 | ManjungPerak | 13 | 3 Aug 20201st sale agreement 3 Aug 2018 | CFO 6 May 2021 | 276 days after † |
| TAMAN MANJUNG POINT SEKSYEN 2KPKT 4131-135 | ManjungPerak | 105 | 14 Mar 20191st sale agreement 14 Mar 2017 | CFO 5 Sep 2019 | 175 days after |
| SFERA RESIDENSIKPKT 4131-132 | PetalingSelangor | 519 | 28 Oct 20171st sale agreement 28 Oct 2014 | CFO 3 Apr 2019 | 522 days after |
| TAMAN SEJATIKPKT 4131-134 | ManjungPerak | 100 | 11 May 20181st sale agreement 11 May 2016 | CCC 2 Jul 2018 | 52 days after |
| TAMAN DESA MANJUNG POINT 2KPKT 4131-80 | ManjungPerak | 230 | 8 Feb 20151st sale agreement 8 Feb 2013 | CCC 10 Jul 2015 | 152 days after |
| 188 SUITESKPKT 4131-123 | Kuala LumpurWP Kuala Lumpur | 446 | 16 Jan 20141st sale agreement 16 Jan 2011 | CCC 11 Nov 2014 | 299 days after |
Show all 52 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN AMAN MUHIBBAH 4KPKT 4131-141 | ManjungPerak | 12 | 3 Aug 20251st sale agreement 3 Aug 2023 | CFO 24 Dec 2025 Handover 24 Dec 2025 | 143 days after |
| TAMAN AMAN MUHIBBAH 4KPKT 4131-142 | ManjungPerak | 6 | 6 Dec 20251st sale agreement 6 Dec 2023 | CFO 23 Dec 2025 Handover 24 Dec 2025 | 18 days after |
| TAMAN BINTANG 1KPKT 4131-138 | ManjungPerak | 40 | 14 Aug 20201st sale agreement 14 Aug 2018 | CCC 20 Oct 2021 | 432 days after † |
| THE OOAK, SERVICED APARTMENTS, KIARA 163KPKT 19269-1 | Kuala LumpurWP Kuala Lumpur | 336 | 14 Sep 2021Extended 6 months from 14 Mar 20211st sale agreement 14 Mar 2018 | CCC 16 Aug 2021 | CCC before deadline; handover not recorded |
| TAMAN BUNGA RAYAKPKT 4131-137 | ManjungPerak | 13 | 3 Aug 20201st sale agreement 3 Aug 2018 | CFO 6 May 2021 | 276 days after † |
| TAMAN MANJUNG POINT SEKSYEN 2KPKT 4131-135 | ManjungPerak | 105 | 14 Mar 20191st sale agreement 14 Mar 2017 | CFO 5 Sep 2019 | 175 days after |
| SFERA RESIDENSIKPKT 4131-132 | PetalingSelangor | 519 | 28 Oct 20171st sale agreement 28 Oct 2014 | CFO 3 Apr 2019 | 522 days after |
| TAMAN SEJATIKPKT 4131-134 | ManjungPerak | 100 | 11 May 20181st sale agreement 11 May 2016 | CCC 2 Jul 2018 | 52 days after |
| TAMAN INDAH RAYAKPKT 4131-136 | ManjungPerak | 6 | 30 Mar 20191st sale agreement 30 Mar 2017 | CCC 25 Jun 2018 | CCC before deadline; handover not recorded |
| TAMAN SEJATI 3KPKT 4131-101 | ManjungPerak | 22 | 29 Jun 20171st sale agreement 29 Jun 2015 | CCC 9 Mar 2017 | CCC before deadline; handover not recorded |
| TAMAN DESA MANJUNGKPKT 4131-129 | ManjungPerak | 201 | 17 Nov 20161st sale agreement 17 Nov 2014 | CCC 17 Aug 2016 | CCC before deadline; handover not recorded |
| TAMAN DESA MANJUNG POINT 2KPKT 4131-54 | ManjungPerak | 203 | 4 Oct 20151st sale agreement 4 Oct 2013 | CCC 10 Jul 2015 | CCC before deadline; handover not recorded |
| TAMAN DESA MANJUNG POINT 2KPKT 4131-80 | ManjungPerak | 230 | 8 Feb 20151st sale agreement 8 Feb 2013 | CCC 10 Jul 2015 | 152 days after |
| 188 SUITESKPKT 4131-123 | Kuala LumpurWP Kuala Lumpur | 446 | 16 Jan 20141st sale agreement 16 Jan 2011 | CCC 11 Nov 2014 | 299 days after |
| TAMAN PUNDUT RAYAKPKT 4131-126 | ManjungPerak | 75 | — | CCC 14 Feb 2014 | — |
| TAMAN SERI MELURKPKT 4131-127 | ManjungPerak | 30 | — | CCC 23 Jan 2014 | — |
| KAR SIN BERHADKPKT 4131-124 | ManjungPerak | 167 | — | CFO 30 Aug 2013 | — |
| TAMAN SERI MELURKPKT 4131-118 | ManjungPerak | 76 | — | CCC 10 Apr 2012 | — |
| KAR SIN BERHADKPKT 4131-121 | ManjungPerak | 30 | — | CCC 9 Nov 2011 | — |
| TAMAN NAHKODAKPKT 4131-114 | ManjungPerak | 88 | — | CCC 5 Oct 2011 | — |
| TAMAN SEJATI 2KPKT 4131-106 | ManjungPerak | 36 | — | CFO 26 Jan 2011 | — |
| TAMAN SENTOSA 3KPKT 4131-119 | ManjungPerak | 17 | — | CCC 24 Dec 2010 | — |
| TAMAN MANJUNG POINT SEKSYEN 4KPKT 4131-117 | ManjungPerak | 217 | — | CCC 10 Aug 2010 | — |
| TAMAN PINGGIRAN PERMAIKPKT 4131-97 | Larut & MatangPerak | 26 | — | CFO 20 May 2010 | — |
| TAMAN PEGAWAIKPKT 4131-115 | ManjungPerak | 40 | — | CCC 4 May 2010 | — |
| TAMAN EMASKPKT 4131-116 | ManjungPerak | 33 | — | CCC 27 Apr 2010 | — |
| CERIAAN KIARAKPKT 4131-104 | Kuala LumpurWP Kuala Lumpur | 238 | — | CFO 4 Mar 2010 | — |
| TAMAN ORKID 2KPKT 4131-113 | ManjungPerak | 34 | — | CCC 5 Feb 2010 | — |
| TAMAN SEJATIKPKT 4131-109 | ManjungPerak | 98 | — | CFO 4 Feb 2010 | — |
| TAMAN SEJATIKPKT 4131-120 | ManjungPerak | 23 | — | CFO 4 Feb 2010 | — |
| TAMAN SINGA BARUKPKT 4131-112 | ManjungPerak | 126 | — | CFO 8 Jan 2010 | — |
| TAMAN MUTIARAKPKT 4131-111 | ManjungPerak | 14 | — | CCC 22 Oct 2009 | — |
| TAMAN BIRU 2KPKT 4131-107 | ManjungPerak | 60 | — | CFO 29 Sep 2009 | — |
| TAMAN HARMONIKPKT 4131-110 | ManjungPerak | 20 | — | CFO 8 Sep 2009 | — |
| TAMAN BAHTERAKPKT 4131-96 | ManjungPerak | 23 | — | CFO 26 May 2009 | — |
| TAMAN HIJAU IIKPKT 4131-100 | ManjungPerak | 24 | — | CFO 26 Feb 2009 | — |
| TAMAN MANJUNG BARUKPKT 4131-102 | ManjungPerak | 102 | — | CFO 23 Feb 2009 | — |
| TAMAN MANJUNG BARUKPKT 4131-103 | ManjungPerak | 84 | — | CFO 23 Feb 2009 | — |
| TAMAN SAMUDERAKPKT 4131-98 | ManjungPerak | 52 | — | CFO 3 Feb 2009 | — |
| TAMAN MANJUNG POINT SEKSYEN 2KPKT 4131-108 | ManjungPerak | 50 | — | CFO 14 Feb 2008 | — |
| TAMAN SEJATI 2KPKT 4131-99 | ManjungPerak | 23 | — | CFO 19 Jun 2007 | — |
| TAMAN MANJUNG POINT SEKSYEN 2KPKT 4131-88 | ManjungPerak | 289 | — | CFO 7 Jun 2007 | — |
| TAMAN JASMINKPKT 4131-93 | ManjungPerak | 31 | — | CFO 18 May 2007 | — |
| TAMAN MANJUNG POINT SEKSYEN 2KPKT 4131-89 | ManjungPerak | 370 | — | CFO 7 Mar 2007 | — |
| TAMAN HARMONIKPKT 4131-94 | ManjungPerak | 28 | — | CFO 7 Mar 2007 | — |
| TAMAN MEGAH 3KPKT 4131-92 | ManjungPerak | 21 | — | CFO 31 Dec 2006 | — |
| TAMAN MUTIARAKPKT 4131-87 | ManjungPerak | 12 | — | CFO 2 May 2006 | — |
| TAMAN SAMUDERAKPKT 4131-84 | ManjungPerak | 22 | — | CFO 25 Apr 2006 | — |
| TAMAN CAHAYAKPKT 4131-90 | ManjungPerak | 30 | — | CFO 21 Apr 2006 | — |
| TAMAN BIRUKPKT 4131-85 | ManjungPerak | 60 | — | CFO 14 Feb 2006 | — |
| TAMAN BIRUKPKT 4131-86 | ManjungPerak | 23 | — | CFO 14 Feb 2006 | — |
| TAMAN AMANKPKT 4131-91 | ManjungPerak | 28 | — | CFO 3 Feb 2006 | — |
Under construction (2) and not yet started (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN PANCHOR DAMAIKPKT 4131-140 | ManjungPerak | 92 | SickSick | 9 Aug 20251st sale agreement 9 Aug 2023 | 55–59% |
| SOLASTA DUTAMASKPKT 4131-139Solasta Dutamas · on PropertySifuYNH's 2025 annual report said construction of Towers A and B had reached the typical floors and remained on schedule; the KPKT register classes the project as Sick, with the extended deadline of 13 April 2026 and reported progress of 30%–87%.[1] | Kuala LumpurWP Kuala Lumpur | 1,159 | SickSick | 13 Apr 2026Extended 12 months from 13 Apr 20251st sale agreement 13 Apr 2022 | 30–87% |
| LUMUT RIA KONDOMINIUMKPKT 4131-52 | ManjungPerak | 237 | Not startedNot started | — | 0% |
Permit cancelled or other KPKT status (4)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN ACHEH MUTIARAKPKT 4131-122 | ManjungPerak | 54 | Permit cancelledPermit cancelled | — | 5% |
| TAMAN SAMUDERA BARUKPKT 4131-13 | ManjungPerak | 288 | Permit cancelledPermit cancelled | — | 5% |
| TAMAN PANCHOR DAMAIKPKT 4131-130 | ManjungPerak | 92 | Permit cancelledPermit cancelled | — | 0% |
| TAMAN KAMPAR SAUJANAKPKT 4131-133 | KintaPerak | 126 | Permit cancelledPermit cancelled | — | 5% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
YNH Property at a glance
| Listed | Bursa Malaysia Main Market · YNHPROP (3158)[1] |
|---|---|
| Started | 1982 in Sitiawan, Perak, by the company's account, when the late Dato' Yu Neh Huat began township development there[2] |
| Head office | Seri Manjung, Perak[1] |
| Leadership | Dato' Yu Kuan Huat — Executive Chairman (since 18 December 2024)[1][3] Yu Kai Leun — Group Managing Director (from December 2025)[3] |
| Companies in the KPKT register | KAR SIN BHD. KPKT 4131[1] D'KIARA PLACE SDN. BHD. KPKT 19269[1] |
| Website | ynhb.com.my |
| Started | 1982, township development in Sitiawan, Perak (company account)[2] |
| Land bank (company figure) | About 700 acres of undeveloped land in Seri Manjung, Perak, and a 93-acre freehold site in Genting Highlands (annual report 2025)[1] |
| Where it builds (company account) | Perak, the Klang Valley and Genting Highlands[2] |
YNH Property projects on sale on PropertySifu
Solasta Dutamas
- THE OOAK, SERVICED APARTMENTS, KIARA 163 — 2.3 km, 2021
Who is YNH Property? The company behind the projects
YNH Property traces its start to Sitiawan, Perak, where, according to the company, the late Dato' Yu Neh Huat began township development in 1982 [2]. The listed holding company, YNH Property Berhad, trades on the Main Market of Bursa Malaysia as YNHPROP (stock code 3158), and its head office is in Seri Manjung, Perak [1]. Its main developer company, Kar Sin Berhad, is wholly owned; the serviced apartments at Kiara 163, The OOAK, are registered under D'Kiara Place Sdn Bhd, also wholly owned [1].
The company says it has expanded from Perak into residential and commercial developments in the Klang Valley and Genting Highlands [2]. Its 2025 annual report says about 700 acres of undeveloped land remain in Seri Manjung, where its Manjung Point township is, and mentions a 93-acre freehold site in Genting Highlands [1]. In the KPKT register, 54 of its 59 housing projects are in Perak; the Kuala Lumpur and Selangor projects include 188 Suites, Sfera Residensi, The OOAK and Solasta Dutamas.
Solasta Dutamas in Mont Kiara, Kuala Lumpur, is registered with KPKT under Kar Sin Berhad (4131-139): 1,159 serviced apartments in three blocks. The 2025 annual report said construction of Towers A and B had reached the typical floors and remained on schedule [1]; the KPKT register now classes the project as Sick (Sakit), with the details in the FAQ below.
Executive chairman Dato' Yu Kuan Huat was Kar Sin's managing and founder director before he joined the board in 2003 [1]. After the annual general meeting in December 2025, Yu Kai Leun became group managing director, with Dato' Yu Kuan Huat continuing as executive chairman [3].
Frequently asked questions
Is YNH Property a listed company?
Yes. YNH Property Berhad is listed on the Main Market of Bursa Malaysia under the stock name YNHPROP and stock code 3158 [1].
Which company develops Solasta Dutamas?
KPKT registers Solasta Dutamas (4131-139) under Kar Sin Berhad (KPKT developer code 4131), which YNH Property Berhad's 2025 annual report lists as a wholly-owned subsidiary [1].
Is Solasta Dutamas classed as a Sick project?
Yes. As at 27 October 2026, KPKT classes Solasta Dutamas (4131-139) as Sick (Sakit). The first sale agreement was signed on 13 April 2022; the handover deadline of 13 April 2025 was extended with approval by 12 months to 13 April 2026. The register shows three components: two 33-storey blocks of 329 units each at 30.27% reported progress (one classed Sick, one Late) and a 42-storey block of 501 units at 87.26% (Sick). No CCC or handover date is recorded yet.
Does YNH have any Sick or Abandoned projects?
As at 27 October 2026, two of YNH's 59 housing projects in the KPKT register are classed Sick and none Abandoned. Besides Solasta Dutamas, Taman Panchor Damai (4131-140), 92 terrace houses in Manjung, Perak, is classed Sick: first sale agreement 9 August 2023, handover deadline 9 August 2025 with no extension recorded, and reported progress of 55% and 59% for its two components. An earlier project registered under the same name (4131-130) has its permit cancelled.
How many housing projects has YNH completed, and were they handed over on time?
In the KPKT register, 52 of YNH's 59 housing projects are completed. Of the 14 completed projects with both a handover deadline and a completion date recorded, none was handed over on or before the deadline (the extended deadline where KPKT approved an extension); 9 were handed over or certified complete after it, 2 of them under construction during the 18 March–31 August 2020 movement control period; 5 received the completion certificate before the deadline, with no handover date recorded. The other 38 completed projects do not have both dates in the register.
Was The OOAK at Kiara 163 completed on time?
KPKT registers The OOAK (19269-1, 336 serviced apartments) under D'Kiara Place Sdn Bhd. The first sale agreement was signed on 14 March 2018; the deadline of 14 March 2021 was extended with approval by 6 months to 14 September 2021. The CCC is dated 16 August 2021, 29 days before the extended deadline; the register does not record the handover date. Construction ran through 18 March–31 August 2020, a period that section 35 of Act 829 excludes from handover deadlines.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] YNH Property Berhad Annual Report 2025 · YNH Property Berhad · 30 Oct 2025 · accessed 28 Oct 2026
http://ynhb.listedcompany.com/misc/ar2025.pdf - [2] About YNH Property · YNH Property Berhad · accessed 28 Oct 2026
https://www.ynhb.com.my/about - [3] YNH Property board shake-up: Kuan Chon steps back as son voted out, nephews take top roles · The Edge Malaysia · 17 Dec 2025 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/786335
Last updated 28 Oct 2026