Thriven (Thriven Global Berhad)
Thriven Global Berhad, formerly Mulpha Land Berhad, is a Bursa Malaysia-listed property company with 23 housing projects in the KPKT register under four Thriven companies, all 23 completed and none classed Sick or Abandoned. Seventeen are in Kulim, Kedah, where Thriven develops the Desa Aman township; the rest are in Penang and Kuala Lumpur, including eNESTa Kepong.
- 23 projects in the KPKT register
- 23 completed
- None Sick or Abandoned
Has Thriven handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 23 housing projects under 4 Thriven companies in 3 states: 23 completed. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 23 completed projects, 21 have both a handover deadline and a completion date in the register: 6 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 3 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 12 received the completion certificate before the deadline (handover date not recorded).
1 project had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| ENESTA AVENUE - CANARYKPKT 7190-17 | KulimKedah | 28 | 29 Aug 20251st sale agreement 29 Aug 2023 | CCC 26 Feb 2025 Handover 27 Feb 2025 | 183 days before |
| ENESTA AVENUE - CANARYKPKT 7190-15 | KulimKedah | 24 | 30 Dec 20241st sale agreement 30 Dec 2022 | CCC 10 Sep 2024 Handover 10 Sep 2024 | 111 days before |
| ENESTA AVENUE - STARLINGKPKT 7190-16 | KulimKedah | 45 | 2 Feb 20251st sale agreement 2 Feb 2023 | CCC 10 Sep 2024 Handover 10 Sep 2024 | 145 days before |
| ENESTA AVENUE - STARLINGKPKT 7190-12 | KulimKedah | 76 | 17 May 20241st sale agreement 17 May 2022 | CCC 4 Apr 2024 Handover 8 Apr 2024 | 39 days before |
| ENESTA AVENUE - STARLINGKPKT 7190-13 | KulimKedah | 64 | 17 May 20241st sale agreement 17 May 2022 | CCC 4 Apr 2024 Handover 8 Apr 2024 | 39 days before |
| ENESTA AVENUE - CANARYKPKT 7190-14 | KulimKedah | 24 | 17 May 20241st sale agreement 17 May 2022 | CCC 4 Apr 2024 Handover 8 Apr 2024 | 39 days before |
| SUITE ENESTA KEPONGKPKT 14713-2 | Kuala LumpurWP Kuala Lumpur | 258 | 8 Feb 2023Extended 30 months from 8 Aug 20201st sale agreement 8 Aug 2017 | CCC 8 Sep 2022 | CCC before deadline; handover not recorded |
| PANGSAPURI ENESTA DESA AMANKPKT 7190-10 | KulimKedah | 148 | 28 Nov 20211st sale agreement 28 Nov 2018 | CCC 12 May 2021 | CCC before deadline; handover not recorded |
| PANGSAPURI ENESTA DESA AMANKPKT 7190-11 | KulimKedah | 148 | 27 Feb 20221st sale agreement 27 Feb 2019 | CCC 12 May 2021 | CCC before deadline; handover not recorded |
| RESIDENSI ENESTA KEPONGKPKT 14713-1eNESTa Kepong · on PropertySifuResidensi Enesta Kepong is the 42-storey RUMAWIP block of 254 affordable homes behind eNESTa Kepong; the 35-storey eNESTa Kepong tower with 258 serviced apartments is registered separately as SUITE ENESTA KEPONG (14713-2).[6] | Kuala LumpurWP Kuala Lumpur | 254 | 30 Jun 20201st sale agreement 30 Jun 2017 | CCC 12 Oct 2020 | 104 days after † |
| DA BUSINESS PARK FASA 1KPKT 7190-6 | KulimKedah | 18 | 19 Mar 20201st sale agreement 19 Mar 2018 | CCC 28 Nov 2019 | CCC before deadline; handover not recorded |
| INDAHYUKPKT 7190-8 | KulimKedah | 40 | 18 Mar 20191st sale agreement 18 Mar 2017 | CCC 15 Nov 2019 | 242 days after |
Handed over or certified complete after the deadline (3)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI ENESTA KEPONGKPKT 14713-1eNESTa Kepong · on PropertySifuResidensi Enesta Kepong is the 42-storey RUMAWIP block of 254 affordable homes behind eNESTa Kepong; the 35-storey eNESTa Kepong tower with 258 serviced apartments is registered separately as SUITE ENESTA KEPONG (14713-2).[6] | Kuala LumpurWP Kuala Lumpur | 254 | 30 Jun 20201st sale agreement 30 Jun 2017 | CCC 12 Oct 2020 | 104 days after † |
| INDAHYUKPKT 7190-8 | KulimKedah | 40 | 18 Mar 20191st sale agreement 18 Mar 2017 | CCC 15 Nov 2019 | 242 days after |
| DESA AMANKPKT 7190-1 | KulimKedah | 1,021 | 8 Jun 20001st sale agreement 8 Jun 1998 | CCC 19 Mar 2014 | 5,032 days after |
Show all 23 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| ENESTA AVENUE - CANARYKPKT 7190-17 | KulimKedah | 28 | 29 Aug 20251st sale agreement 29 Aug 2023 | CCC 26 Feb 2025 Handover 27 Feb 2025 | 183 days before |
| ENESTA AVENUE - CANARYKPKT 7190-15 | KulimKedah | 24 | 30 Dec 20241st sale agreement 30 Dec 2022 | CCC 10 Sep 2024 Handover 10 Sep 2024 | 111 days before |
| ENESTA AVENUE - STARLINGKPKT 7190-16 | KulimKedah | 45 | 2 Feb 20251st sale agreement 2 Feb 2023 | CCC 10 Sep 2024 Handover 10 Sep 2024 | 145 days before |
| ENESTA AVENUE - STARLINGKPKT 7190-12 | KulimKedah | 76 | 17 May 20241st sale agreement 17 May 2022 | CCC 4 Apr 2024 Handover 8 Apr 2024 | 39 days before |
| ENESTA AVENUE - STARLINGKPKT 7190-13 | KulimKedah | 64 | 17 May 20241st sale agreement 17 May 2022 | CCC 4 Apr 2024 Handover 8 Apr 2024 | 39 days before |
| ENESTA AVENUE - CANARYKPKT 7190-14 | KulimKedah | 24 | 17 May 20241st sale agreement 17 May 2022 | CCC 4 Apr 2024 Handover 8 Apr 2024 | 39 days before |
| SUITE ENESTA KEPONGKPKT 14713-2 | Kuala LumpurWP Kuala Lumpur | 258 | 8 Feb 2023Extended 30 months from 8 Aug 20201st sale agreement 8 Aug 2017 | CCC 8 Sep 2022 | CCC before deadline; handover not recorded |
| PANGSAPURI ENESTA DESA AMANKPKT 7190-10 | KulimKedah | 148 | 28 Nov 20211st sale agreement 28 Nov 2018 | CCC 12 May 2021 | CCC before deadline; handover not recorded |
| PANGSAPURI ENESTA DESA AMANKPKT 7190-11 | KulimKedah | 148 | 27 Feb 20221st sale agreement 27 Feb 2019 | CCC 12 May 2021 | CCC before deadline; handover not recorded |
| RESIDENSI ENESTA KEPONGKPKT 14713-1eNESTa Kepong · on PropertySifuResidensi Enesta Kepong is the 42-storey RUMAWIP block of 254 affordable homes behind eNESTa Kepong; the 35-storey eNESTa Kepong tower with 258 serviced apartments is registered separately as SUITE ENESTA KEPONG (14713-2).[6] | Kuala LumpurWP Kuala Lumpur | 254 | 30 Jun 20201st sale agreement 30 Jun 2017 | CCC 12 Oct 2020 | 104 days after † |
| DA BUSINESS PARK FASA 1KPKT 7190-6 | KulimKedah | 18 | 19 Mar 20201st sale agreement 19 Mar 2018 | CCC 28 Nov 2019 | CCC before deadline; handover not recorded |
| INDAHYUKPKT 7190-8 | KulimKedah | 40 | 18 Mar 20191st sale agreement 18 Mar 2017 | CCC 15 Nov 2019 | 242 days after |
| INDAHYUKPKT 7190-9 | KulimKedah | 30 | 11 Oct 20191st sale agreement 11 Oct 2017 | CCC 6 May 2019 | CCC before deadline; handover not recorded |
| SURIAKPKT 7190-7 | KulimKedah | 66 | 20 Mar 20191st sale agreement 20 Mar 2017 | CCC 3 Dec 2018 | CCC before deadline; handover not recorded |
| ANGGUNKPKT 7190-4 | KulimKedah | 6 | 7 Mar 20191st sale agreement 7 Mar 2017 | CCC 28 Nov 2017 | CCC before deadline; handover not recorded |
| KLASIKKPKT 7190-5 | KulimKedah | 37 | 14 Jul 20181st sale agreement 14 Jul 2016 | CCC 27 Nov 2017 | CCC before deadline; handover not recorded |
| PESONAKPKT 7190-3 | KulimKedah | 21 | 25 Mar 20181st sale agreement 25 Mar 2016 | CCC 16 Jun 2017 | CCC before deadline; handover not recorded |
| THE COLONIALKPKT 7190-2 | KulimKedah | 48 | 26 Oct 20161st sale agreement 26 Oct 2014 | CCC 29 Aug 2016 | CCC before deadline; handover not recorded |
| FORTUNEKPKT 6491-3 | Seberang Perai UtaraPulau Pinang | 20 | 6 Jan 20161st sale agreement 6 Jan 2014 | CCC 13 Oct 2015 | CCC before deadline; handover not recorded |
| TAMAN BUKIT PUNCHORKPKT 6491-1 | Seberang Perai SelatanPulau Pinang | 559 | 3 May 20161st sale agreement 3 May 2013 | CCC 23 Sep 2014 | CCC before deadline; handover not recorded |
| DESA AMANKPKT 7190-1 | KulimKedah | 1,021 | 8 Jun 20001st sale agreement 8 Jun 1998 | CCC 19 Mar 2014 | 5,032 days after |
| TAMAN SERI BAYUKPKT 6491-2 | Seberang Perai SelatanPulau Pinang | 394 | — | CFO 7 Jun 2013 | — |
| ENCLAVE BANGSARKPKT 11079-1 | Kuala LumpurWP Kuala Lumpur | 7 | — | CCC 28 Dec 2012 | — |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Thriven at a glance
| Listed | Bursa Malaysia Main Market · THRIVEN (7889) · named Thriven Global Berhad since 1 July 2015 (formerly Mulpha Land Berhad)[1] |
|---|---|
| Head office | Petaling Jaya, Selangor; northern office in Butterworth, Penang[2] |
| Leadership | Datuk Fakhri Yassin bin Mahiaddin — Executive Chairman[2] Ghazie Yeoh bin Abdullah — Group Managing Director[2] |
| Companies in the KPKT register | GOLDEN CIGNET SDN. BHD. KPKT 7190[4][2] BUKIT PUNCHOR DEVELOPMENT SDN. BHD. KPKT 6491[5][2] THRIVEN AMONA SDN. BHD. KPKT 14713[3][6][2] MULPHA LAND BHD KPKT 11079[1] |
| Website | thriven.com.my |
| Former names | Mega Pascal Bhd, renamed Mulpha Land Bhd on 5 August 2005; renamed Thriven Global Berhad on 1 July 2015[1] |
| Desa Aman township, Kulim (2015 report) | 144.4 acres, of which 128 acres were still to be developed in 2015[3] |
| eNESTa Kepong joint venture | With Amona Group; Thriven was the majority shareholder (2015 report). The joint-venture company, Thriven Amona Sdn Bhd, is now listed by Thriven as its subsidiary Thriven Development Sdn Bhd[3][2] |
| Where its KPKT projects are | Kedah (Kulim), Penang (Seberang Perai) and Kuala Lumpur (Kepong, Bangsar)[3][6][7] |
Thriven projects on sale on PropertySifu
Who is Thriven? The company behind the projects
Thriven Global Berhad is listed on Bursa Malaysia's Main Market in the property sector, stock code 7889 [1]. Bursa's records show two changes of name: from Mega Pascal Bhd to Mulpha Land Bhd on 5 August 2005, and from Mulpha Land Berhad to Thriven Global Berhad on 1 July 2015 [1]; in 2015 the company said it had previously been a subsidiary of Mulpha International [3]. Its executive chairman is Datuk Fakhri Yassin bin Mahiaddin and its group managing director is Ghazie Yeoh bin Abdullah [2]. The head office is in Petaling Jaya, Selangor, with a northern office and sales gallery in Butterworth, Penang, under its subsidiary Bukit Punchor Development Sdn Bhd [2].
Most of its KPKT records are in the north. A 2015 report described Desa Aman in Kulim, Kedah, and Taman Bukit Punchor in Penang as Thriven townships, with 128 of Desa Aman's 144.4 acres then still to be developed [3]. The Kulim land belongs to Golden Cignet Sdn Bhd, a Thriven subsidiary [4][2]; KPKT registers 17 projects under that company in Kulim — terraced, semi-detached and shop houses and two apartment blocks — from DESA AMAN (1,021 terraced houses, first sale agreement in 1998, CCC in 2014) to the ENESTA AVENUE phases handed over in 2024 and 2025. Bukit Punchor Development, also a subsidiary [5][2], has three completed projects in Seberang Perai; in 2022 it agreed to buy 4,700 square metres of freehold land in Butterworth, approved for serviced apartments, for RM21 million [5].
In Kuala Lumpur, eNESTa Kepong was a joint venture between Amona Group and Thriven, with Thriven as the majority shareholder [3]. A 2017 report described the 2.04-acre leasehold site at Jalan Kepong and Pintasan Segambut as holding a 35-storey tower of 258 serviced apartments and 23 retail lots, plus Residensi Enesta Kepong, a 42-storey block of 254 affordable homes under the RUMAWIP scheme [6]. KPKT registers both under Thriven Amona Sdn Bhd: RESIDENSI ENESTA KEPONG (254 units, CCC on 12 October 2020) and SUITE ENESTA KEPONG (258 serviced apartments, CCC on 8 September 2022). Thriven now lists that company among its subsidiaries as Thriven Development Sdn Bhd, formerly Thriven Amona Sdn Bhd [2].
The oldest Kuala Lumpur record is ENCLAVE BANGSAR, seven bungalows registered under Mulpha Land Bhd — Thriven's former name — with a CCC dated 28 December 2012; Thriven lists Bangsar Enclave among its completed projects [7]. The KPKT register covers only projects licensed as housing, so Thriven's commercial and other buildings are not in the table above.
Frequently asked questions
Is Thriven a listed company?
Yes. Thriven Global Berhad is listed on Bursa Malaysia's Main Market in the property sector under stock code 7889. It was called Mulpha Land Berhad until 1 July 2015, and Mega Pascal Bhd before 5 August 2005 [1].
Who developed eNESTa Kepong?
Thriven Amona Sdn Bhd (KPKT developer code 14713), a joint venture of Thriven and Amona Group in which Thriven was the majority shareholder, as reported in 2015 [3]. Thriven now lists it among its subsidiaries as Thriven Development Sdn Bhd [2]. KPKT registers two projects under it: RESIDENSI ENESTA KEPONG (14713-1, 254 units) and SUITE ENESTA KEPONG (14713-2, 258 serviced apartments).
Was eNESTa Kepong completed on time?
KPKT records RESIDENSI ENESTA KEPONG (14713-1) with a first sale agreement on 30 June 2017 and a handover deadline of 30 June 2020, with no approved extension; its CCC is dated 12 October 2020, 104 days after that deadline. It was under construction during 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether the deadline already reflects it. SUITE ENESTA KEPONG (14713-2) had a first sale agreement on 8 August 2017 and a deadline of 8 August 2020, extended with approval by 30 months to 8 February 2023; its CCC is dated 8 September 2022, 153 days before the extended deadline. The register records no handover date for either.
Does Thriven have any Sick or Abandoned projects?
No. As at 27 October 2026, all 23 Thriven projects in the KPKT register are completed; none is classed Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat).
Were Thriven's projects handed over on time?
Of the 23 completed projects, 21 have dates that can be compared with a deadline (the extended deadline where an extension was approved). Six ENESTA AVENUE phases in Kulim were handed over in 2024 and 2025, 39 to 183 days before their deadlines. Twelve received their CCC before the deadline, with no handover date recorded. Three received their CCC after the deadline: DESA AMAN in Kulim (7190-1, 1,021 terraced houses; first sale agreement 8 June 1998, deadline 8 June 2000, with all components certified by 19 March 2014, 5,032 days after), INDAHYU (7190-8, 40 semi-detached houses, 242 days after) and RESIDENSI ENESTA KEPONG (14713-1, 104 days after). The other 2, completed in 2012 and 2013, have no deadline in the register.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] THRIVEN GLOBAL BERHAD (7889): Company Profile · Bursa Malaysia · accessed 28 Oct 2026
https://www.bursamalaysia.com/trade/trading_resources/listing_directory/company-profile?stock_code=7889 - [2] Board of Directors (with list of subsidiary companies) · Thriven Global Berhad · accessed 28 Oct 2026
https://www.thriven.com.my/board-of-directors - [3] Don't stop me now: Thriven Global Bhd to launch RM1.8 bil of projects in "distressed market" · The Edge Malaysia (City & Country) · 26 Nov 2015 · accessed 28 Oct 2026
https://api.edgeprop.my/content/dont-stop-me-now-thriven-global-bhd-launch-rm18-bil-projects-distressed-market - [4] Thriven Global obtains RM15m credit facility to finance working capital needs · The Edge Malaysia · 3 Sep 2019 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/thriven-global-obtains-rm15m-credit-facility-finance-working-capital-needs - [5] Thriven to acquire land earmarked for apartments in Butterworth · The Edge Malaysia · 22 Sep 2022 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/thriven-acquire-land-earmarked-apartments-butterworth - [6] eNESTa Kepong attracts with MRT access and pricing · The Edge Malaysia (EdgeProp) · 1 May 2017 · accessed 28 Oct 2026
https://www.edgeprop.my/content/1123933/enesta-kepong-attracts-mrt-access-and-pricing - [7] Property Development · Thriven Global Berhad · accessed 28 Oct 2026
https://www.thriven.com.my/property-development
Last updated 28 Oct 2026