Mitrajaya (Mitrajaya Holdings Berhad)
Mitrajaya Holdings Berhad is a Bursa Malaysia-listed construction and property group with 15 housing projects in the KPKT register under six Mitrajaya companies: 11 completed, 3 under construction and 1 not yet started, none classed Sick or Abandoned. It began in 1985 as a contractor and has developed property since 1999, starting with Puchong Prima.
- 15 projects in the KPKT register
- 11 completed
- 3 under construction
- 1 not yet started
- None Sick or Abandoned
Has Mitrajaya handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 15 housing projects under 6 Mitrajaya companies in 3 states: 11 completed, 3 under construction, 1 not yet started. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 11 completed projects, 6 have both a handover deadline and a completion date in the register: 3 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 2 handed over or certified complete after that deadline; 1 received the completion certificate before the deadline (handover date not recorded).
2 projects had the delivery period extended with KPKT approval.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| AMBER 3 @ BUKIT SENTOSAKPKT 10505-5 | Hulu SelangorSelangor | 67 | 25 Aug 20261st sale agreement 25 Aug 2024 | CCC 11 Mar 2026 Handover 12 Mar 2026 | 166 days before |
| AMBER 2 @ BUKIT SENTOSAKPKT 10505-4 | Hulu SelangorSelangor | 79 | 19 Mar 20261st sale agreement 19 Mar 2024 | CCC 25 Sep 2025 Handover 25 Sep 2025 | 175 days before |
| AMBER 1 @ BUKIT SENTOSAKPKT 10505-3 | Hulu SelangorSelangor | 67 | 9 Jan 20251st sale agreement 9 Jan 2023 | CCC 21 Aug 2024 Handover 27 Aug 2024 | 135 days before |
| WANGSA MAJUKPKT 11382-3Marketed as Wangsa 9 Residency: 565 condominium units in three blocks. KPKT records the CCC and handover of the two 36-storey blocks (169 units each) on 20 Mar 2019, and of the 46-storey block (227 units) on 29 Mar and 3 Apr 2023; the comparison with the deadline uses the last block.[3] | Kuala LumpurWP Kuala Lumpur | 565 | 9 Feb 2020Extended 29 months from 9 Sep 20171st sale agreement 9 Sep 2014 | CCC 29 Mar 2023 Handover 20 Mar 2019 / 3 Apr 2023 | 1,149 days after |
| PANGSAPURI SERI AKASIAKPKT 10505-2 | PetalingSelangor | 408 | 20 Mar 20201st sale agreement 20 Mar 2017 | CCC 5 Mar 2020 | CCC before deadline; handover not recorded |
| 6 TINGKAT DUPLEX DI TAMAN PUCHONG PRIMAKPKT 11382-2280 Park Homes · on PropertySifu | PetalingSelangor | 280 | 17 Oct 20151st sale agreement 17 Oct 2012 | CCC 31 Mar 2016 | 166 days after |
| TAMAN PUCHONG PRIMAKPKT 11382-1 | PetalingSelangor | 212 | — | CCC 1 Oct 2013 | — |
| TAMAN PUCHONG PRIMAKPKT 10505-1 | PetalingSelangor | 243 | — | CFO 25 Aug 2011 | — |
| KIARA 9KPKT 10572-1 | Kuala LumpurWP Kuala Lumpur | 210 | — | CFO 13 Jul 2011 | — |
| DESA IDAMANKPKT 7713-7 | PetalingSelangor | 540 | — | CFO 8 Jun 2010 | — |
| PUCHONG PRIMA FASA 4AKPKT 7713-6 | PetalingSelangor | 846 | — | CFO 30 Nov 2007 | — |
Under construction (3) and not yet started (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| AMBER 4 @ BUKIT SENTOSAKPKT 10505-6 | Hulu SelangorSelangor | 43 | SmoothOn schedule | 10 May 20271st sale agreement 10 May 2025 | 88–95% |
| AMBER 5 @ BUKIT SENTOSAKPKT 10505-7 | Hulu SelangorSelangor | 49 | SmoothOn schedule | 27 Jun 20281st sale agreement 27 Jun 2026 | 93% |
| AMORA RESIDENSI @ WARISAN 9KPKT 30615-1 | SepangSelangor | 594 | SmoothOn schedule | 27 Apr 2029Extended 12 months from 27 Apr 20281st sale agreement 27 Apr 2025 | 22–52% |
| RUMAH KEDAI - TAMAN RENGIT JAYAKPKT 4751-2 | Kota TinggiJohor | 24 | Not startedNot started | — | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Mitrajaya at a glance
| Listed | Bursa Malaysia Main Market · MITRA (9571) · listed on the KLSE Second Board on 8 December 1994, Main Board from 29 May 1998[1][2] |
|---|---|
| Started | 1985, as the construction company Pembinaan Mitrajaya Sdn Bhd, set up by Tan Eng Piow[2][1] |
| Head office | Taman Puchong Prima, Puchong, Selangor[1] |
| Leadership | Tan Eng Piow — Executive Chairman (since 12 June 2024) and Group Managing Director (since 9 September 1994)[1] |
| Companies in the KPKT register | MITRAJAYA HOMES SDN. BHD. KPKT 11382[1] MITRAJAYA WARISAN SDN. BHD. (60%) KPKT 30615[1] PRIMAHARTA DEVELOPMENT SDN. BHD. KPKT 7713[1] LEO VISTA SDN. BHD. KPKT 10505[1] KINA-BIJAK SDN. BHD. KPKT 10572[1] KEMAJUAN SEKIM BARU SDN. BHD. KPKT 4751[1] |
| Website | mitrajaya.com.my |
| Property since | 1999, with the 250-acre Puchong Prima township in Puchong, Selangor[3] |
| Construction arm | Pembinaan Mitrajaya Sdn Bhd, set up in 1985 as an infrastructure contractor[1] |
| Planned project (company figure) | Transit-oriented development about 150 m from Puchong Prima LRT station: 3,691 serviced apartments including affordable units, estimated GDV RM1.5 billion; development order approved in February 2026 (Annual Report 2025)[1] |
| Outside Malaysia | Blue Valley Golf and Country Estate, South Africa: contractor there from 1998, full owner of the estate company Mitrajaya Development SA since 2001[1] |
Mitrajaya projects on sale on PropertySifu
Who is Mitrajaya? The company behind the projects
Mitrajaya began in 1985, when Tan Eng Piow set up the construction company Pembinaan Mitrajaya Sdn Bhd [2]; the group describes it as an infrastructure contractor that grew into a building-construction specialist [1]. The holding company, Mitrajaya Holdings Berhad, was listed on the Second Board of the Kuala Lumpur Stock Exchange on 8 December 1994 and moved to the Main Board on 29 May 1998 [2]; it trades on Bursa Malaysia's Main Market as MITRA (9571) [1]. Tan Eng Piow has been group managing director since 9 September 1994 and executive chairman since 12 June 2024, and the group is based in Puchong Prima, Selangor [1].
Mitrajaya moved into property development in 1999 with the 250-acre Puchong Prima township in Puchong [3]. KPKT registers six completed Puchong Prima projects under three group companies — Primaharta Development, Leo Vista and Mitrajaya Homes — with CCC or CFO dates from 2007 to 2020. They include 280 Park Homes, registered as 6 TINGKAT DUPLEX DI TAMAN PUCHONG PRIMA: 280 duplex apartments in 11 blocks [3]. In Kuala Lumpur, Kina-Bijak Sdn Bhd developed KIARA 9 in Mont Kiara (210 units, CFO in 2011), and Mitrajaya Homes developed Wangsa 9 Residency in Wangsa Maju, 565 condominium units in three blocks [3].
The newer projects are outside Puchong. Amber, at Bandar Baru Bukit Sentosa in Rawang, has 305 double-storey terraced houses in five phases [1]; KPKT registers them as AMBER 1 to AMBER 5 @ BUKIT SENTOSA under Leo Vista Sdn Bhd, three completed between August 2024 and March 2026 and two under construction. Phase 1 of Amora Residensi @ Warisan 9 in Kota Warisan, Sepang, was launched in January 2025 with 594 serviced apartments in three towers on a 22.2-acre leasehold site [1]; it is registered under Mitrajaya Warisan Sdn Bhd, which the group owns 60% of [1]. In Johor, Kemajuan Sekim Baru Sdn Bhd has a 24-unit shophouse project in Kota Tinggi that has not started.
In its 2025 annual report, the group also describes a planned transit-oriented development next to the Puchong Prima LRT station, with 3,691 serviced apartments and an estimated gross development value of RM1.5 billion [1]; that is a company plan, not a KPKT record. Buildings Mitrajaya constructs for other developers are not counted here, and Pangsapuri Seri Warisan in Kota Warisan was developed by Gema Padu Sdn Bhd, with Mitrajaya Homes as project manager [3], so it is not in the table above either.
Frequently asked questions
Is Mitrajaya a listed company?
Who developed 280 Park Homes, and was it handed over on time?
280 Park Homes was developed by Mitrajaya Homes Sdn Bhd (KPKT developer code 11382), wholly owned by Mitrajaya Holdings [1][3]. KPKT registers it as 6 TINGKAT DUPLEX DI TAMAN PUCHONG PRIMA (11382-2), 280 units: first sale agreement 17 October 2012, handover deadline 17 October 2015, with no approved extension. The CCC is dated 31 March 2016, 166 days after that deadline; the register does not record the handover date.
Does Mitrajaya have any Sick or Abandoned projects?
No. As at 27 October 2026, none of the 15 Mitrajaya projects in the KPKT register is classed Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). The 3 under construction are recorded as on schedule (Lancar); the 1 not yet started is a 24-unit shophouse project in Kota Tinggi, Johor.
Were Mitrajaya's completed projects handed over on time?
KPKT lists 11 completed Mitrajaya projects; 6 have dates that can be compared with a deadline (the extended deadline where an extension was approved). Amber phases 1 to 3 in Rawang were handed over 135 to 175 days before their deadlines, and Pangsapuri Seri Akasia in Puchong Prima received its CCC 15 days before its deadline (handover date not recorded). Two were later: 280 Park Homes, with its CCC 166 days after the deadline, and Wangsa 9 Residency, registered as WANGSA MAJU (565 units in three blocks), whose deadline was extended with approval by 29 months to 9 February 2020. Its two 36-storey blocks (169 units each) were handed over on 20 March 2019, before that extended deadline; the 46-storey block (227 units) received its CCC on 29 March 2023 and was handed over on 3 April 2023, 1,149 days after it. The table above counts the project by its last block. The other 5, completed between 2007 and 2013, have no deadline in the register.
Which company develops Amora Residensi @ Warisan 9, and has its deadline been extended?
Mitrajaya Warisan Sdn Bhd (KPKT developer code 30615), which Mitrajaya Holdings owns 60% of [1]. KPKT registers 594 serviced apartments (30615-1); the first sale agreement was signed on 27 April 2025, and the handover deadline of 27 April 2028 has been extended with approval by 12 months to 27 April 2029. It is recorded as on schedule (Lancar), with reported construction progress of 22–52% across its components.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Mitrajaya Holdings Berhad Annual Report 2025 · Mitrajaya Holdings Berhad · 2026-04 · accessed 28 Oct 2026
https://www.insage.com.my/ir/cmn/downloading.aspx?sFileName=26120000067377&sReportType=AR&sCompanyCode=MITRA - [2] Mitrajaya Holdings Berhad — corporate profile (home page) · Mitrajaya Holdings Berhad · accessed 28 Oct 2026
https://www.mitrajaya.com.my/ - [3] Property · Mitrajaya Holdings Berhad · accessed 28 Oct 2026
https://www.mitrajaya.com.my/property.php
Last updated 28 Oct 2026