Matrix Concepts (Matrix Concepts Holdings Berhad)
Matrix Concepts Holdings Berhad is a Seremban-based property developer listed on Bursa Malaysia's Main Market, with 170 housing projects in the KPKT register under nine group companies: 133 completed, 31 under construction, 2 not yet started and 4 with the permit cancelled, none classed Sick or Abandoned. 138 of the projects are in Negeri Sembilan; the rest are in Johor and Kuala Lumpur.
- 170 projects in the KPKT register
- 133 completed
- 31 under construction
- 2 not yet started
- 4 with the permit cancelled
- None Sick or Abandoned
Has Matrix Concepts handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 170 housing projects under 9 Matrix Concepts companies in 3 states: 133 completed, 31 under construction, 2 not yet started, 4 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 133 completed projects, 104 have both a handover deadline and a completion date in the register: 52 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 14 handed over or certified complete after that deadline (4 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 38 received the completion certificate before the deadline (handover date not recorded).
10 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 133
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| LAMAN SENDAYAN 2 PRECINCT 2CKPKT 19342-23 | SerembanNegeri Sembilan | 216 | 12 Apr 20271st sale agreement 12 Apr 2025 | CCC 29 Sep 2026 Handover 8 Oct 2026 | 186 days before |
| BUKIT EKA PRECINCT 10KPKT 7164-49 | SerembanNegeri Sembilan | 237 | 14 Aug 20261st sale agreement 14 Aug 2024 | CCC 11 Jun 2026 Handover 23 Jun 2026 | 52 days before |
| IMPIANA BAYU 3B1 - P2KPKT 7164-47 | KluangJohor | 98 | 15 May 20261st sale agreement 15 May 2024 | CCC 28 Apr 2026 Handover 4 May 2026 | 11 days before |
| BUKIT EKA PRECINCT 8AKPKT 7164-48Ferra I & II @ Eka Heights · on PropertySifu | SerembanNegeri Sembilan | 368 | 30 Jul 20261st sale agreement 30 Jul 2024 | CCC 18 Mar 2026 Handover 1 Apr 2026 | 120 days before |
| BAYU SUTERA (PRECINCT 4B-2)KPKT 10613-63 | Port DicksonNegeri Sembilan | 40 | 26 May 20271st sale agreement 26 May 2025 | CCC 13 Feb 2026 Handover 6 Mar 2026 | 446 days before |
| BAYU SUTERA (PRECINCT 4B-1)KPKT 10613-60 | Port DicksonNegeri Sembilan | 148 | 18 Nov 20261st sale agreement 18 Nov 2024 | CCC 28 Jan 2026 Handover 12 Feb 2026 | 279 days before |
| BAYU SUTERA (PRECINCT 4A-3)KPKT 10613-56Elonia II & III @ Bayu Sutera · on PropertySifu | Port DicksonNegeri Sembilan | 128 | 6 Mar 20261st sale agreement 6 Mar 2024 | CCC 24 Dec 2025 Handover 5 Jan 2026 | 60 days before |
| BUKIT EKA PRECINCT 4KPKT 7164-50Meora @ Eka Heights · on PropertySifu | SerembanNegeri Sembilan | 262 | 2 Oct 20261st sale agreement 2 Oct 2024 | CCC 21 Oct 2025 Handover 5 Nov 2025 | 331 days before |
| HIJAYU 2 (RESORT VILLA 2)KPKT 10613-59 | SerembanNegeri Sembilan | 20 | 28 Jun 20261st sale agreement 28 Jun 2024 | CCC 27 Aug 2025 Handover 24 Oct 2025 | 247 days before |
| BUKIT EKA PRECINCT 3AKPKT 30517-2 | SerembanNegeri Sembilan | 275 | 28 Dec 20251st sale agreement 28 Dec 2023 | CCC 21 Oct 2025 Handover 24 Oct 2025 | 65 days before |
| IRAMA SENDAYAN 2DKPKT 30156-5 | SerembanNegeri Sembilan | 144 | 7 Feb 20261st sale agreement 7 Feb 2024 | CCC 17 Oct 2025 Handover 23 Oct 2025 | 107 days before |
| BUKIT EKA PRECINCT 3BKPKT 30517-1 | SerembanNegeri Sembilan | 155 | 6 Oct 20251st sale agreement 6 Oct 2023 | CCC 4 Sep 2025 Handover 10 Sep 2025 | 26 days before |
Handed over or certified complete after the deadline — 12 most recent of 14
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BAYU SUTERA (PRECINCT 2A)KPKT 10613-46 | Port DicksonNegeri Sembilan | 255 | 24 Nov 20231st sale agreement 24 Nov 2021 | CCC 29 Nov 2023 Handover 4 Dec 2023 | 10 days after |
| TIARA SENDAYAN (PRECINCT 13B1)KPKT 19342-14 | SerembanNegeri Sembilan | 143 | 23 Nov 20231st sale agreement 23 Nov 2021 | CCC 22 Nov 2023 Handover 27 Nov 2023 | 4 days after |
| TIARA SENDAYAN (PRECINCT 13)KPKT 19342-12 | SerembanNegeri Sembilan | 280 | 21 Oct 20231st sale agreement 21 Oct 2021 | CCC 18 Oct 2023 Handover 24 Oct 2023 | 3 days after |
| LAMAN SENDAYAN (PRESINT 1B)KPKT 10613-45 | SerembanNegeri Sembilan | 266 | 23 Jul 20231st sale agreement 23 Jul 2021 | CCC 20 Jul 2023 Handover 24 Jul 2023 | 1 day after |
| BANDAR SERI IMPIAN - IMPIANA DAMAI 2AKPKT 7164-44 | KluangJohor | 68 | 19 Apr 2023Extended 5 months from 19 Nov 20221st sale agreement 19 Nov 2020 | CCC 18 Apr 2023 Handover 18 Apr 2023 / 25 Apr 2023 | 6 days after |
| BANDAR SERI IMPIAN-IMPIANA BAYU 3B2KPKT 7164-42 | KluangJohor | 221 | 14 Apr 2022Extended 6 months from 14 Oct 20211st sale agreement 14 Oct 2019 | CCC 18 Jan 2023 Handover 19 May 2022 / 18 Jan 2023 / 13 Feb 2023 | 35–305 days after † |
| IMPIANA BAYU 3AKPKT 7164-40 | KluangJohor | 83 | 10 Sep 20211st sale agreement 10 Sep 2019 | CCC 28 Apr 2022 Handover 9 May 2022 | 241 days after † |
| ARA SENDAYAN 2AKPKT 7164-36 | SerembanNegeri Sembilan | 244 | 16 Oct 20201st sale agreement 16 Oct 2018 | CCC 30 Mar 2021 | 165 days after † |
| TIARA SENDAYAN (PRECINCT 2)KPKT 19342-2 | SerembanNegeri Sembilan | 504 | 17 Jul 20201st sale agreement 17 Jul 2018 | CCC 29 Jul 2020 | 12 days after † |
| RESIDENSI SIGCKPKT 7164-25 | SerembanNegeri Sembilan | 125 | 3 Aug 20181st sale agreement 3 Aug 2016 | CCC 16 Aug 2018 | 13 days after |
| HIJAYU 3KPKT 10613-24 | SerembanNegeri Sembilan | 394 | 3 Feb 20181st sale agreement 3 Feb 2016 | CCC 25 Jun 2018 | 142 days after |
| BANDAR SERI IMPIAN : IMPIANA BAYU 2KPKT 7164-24 | KluangJohor | 423 | 3 Jun 20171st sale agreement 3 Jun 2015 | CCC 3 Jan 2018 | 214 days after |
Show all 14
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BAYU SUTERA (PRECINCT 2A)KPKT 10613-46 | Port DicksonNegeri Sembilan | 255 | 24 Nov 20231st sale agreement 24 Nov 2021 | CCC 29 Nov 2023 Handover 4 Dec 2023 | 10 days after |
| TIARA SENDAYAN (PRECINCT 13B1)KPKT 19342-14 | SerembanNegeri Sembilan | 143 | 23 Nov 20231st sale agreement 23 Nov 2021 | CCC 22 Nov 2023 Handover 27 Nov 2023 | 4 days after |
| TIARA SENDAYAN (PRECINCT 13)KPKT 19342-12 | SerembanNegeri Sembilan | 280 | 21 Oct 20231st sale agreement 21 Oct 2021 | CCC 18 Oct 2023 Handover 24 Oct 2023 | 3 days after |
| LAMAN SENDAYAN (PRESINT 1B)KPKT 10613-45 | SerembanNegeri Sembilan | 266 | 23 Jul 20231st sale agreement 23 Jul 2021 | CCC 20 Jul 2023 Handover 24 Jul 2023 | 1 day after |
| BANDAR SERI IMPIAN - IMPIANA DAMAI 2AKPKT 7164-44 | KluangJohor | 68 | 19 Apr 2023Extended 5 months from 19 Nov 20221st sale agreement 19 Nov 2020 | CCC 18 Apr 2023 Handover 18 Apr 2023 / 25 Apr 2023 | 6 days after |
| BANDAR SERI IMPIAN-IMPIANA BAYU 3B2KPKT 7164-42 | KluangJohor | 221 | 14 Apr 2022Extended 6 months from 14 Oct 20211st sale agreement 14 Oct 2019 | CCC 18 Jan 2023 Handover 19 May 2022 / 18 Jan 2023 / 13 Feb 2023 | 35–305 days after † |
| IMPIANA BAYU 3AKPKT 7164-40 | KluangJohor | 83 | 10 Sep 20211st sale agreement 10 Sep 2019 | CCC 28 Apr 2022 Handover 9 May 2022 | 241 days after † |
| ARA SENDAYAN 2AKPKT 7164-36 | SerembanNegeri Sembilan | 244 | 16 Oct 20201st sale agreement 16 Oct 2018 | CCC 30 Mar 2021 | 165 days after † |
| TIARA SENDAYAN (PRECINCT 2)KPKT 19342-2 | SerembanNegeri Sembilan | 504 | 17 Jul 20201st sale agreement 17 Jul 2018 | CCC 29 Jul 2020 | 12 days after † |
| RESIDENSI SIGCKPKT 7164-25 | SerembanNegeri Sembilan | 125 | 3 Aug 20181st sale agreement 3 Aug 2016 | CCC 16 Aug 2018 | 13 days after |
| HIJAYU 3KPKT 10613-24 | SerembanNegeri Sembilan | 394 | 3 Feb 20181st sale agreement 3 Feb 2016 | CCC 25 Jun 2018 | 142 days after |
| BANDAR SERI IMPIAN : IMPIANA BAYU 2KPKT 7164-24 | KluangJohor | 423 | 3 Jun 20171st sale agreement 3 Jun 2015 | CCC 3 Jan 2018 | 214 days after |
| TAMAN SERI IMPIAN - IMPIANA BAYU 1KPKT 7164-22 | KluangJohor | 603 | 31 Jul 20151st sale agreement 31 Jul 2013 | CCC 4 Nov 2015 | 96 days after |
| HIJAYU 3DKPKT 10613-15 | SerembanNegeri Sembilan | 534 | 21 Dec 20141st sale agreement 21 Dec 2012 | CCC 4 Feb 2015 | 45 days after |
Show all 133 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| LAMAN SENDAYAN 2 PRECINCT 2CKPKT 19342-23 | SerembanNegeri Sembilan | 216 | 12 Apr 20271st sale agreement 12 Apr 2025 | CCC 29 Sep 2026 Handover 8 Oct 2026 | 186 days before |
| BUKIT EKA PRECINCT 10KPKT 7164-49 | SerembanNegeri Sembilan | 237 | 14 Aug 20261st sale agreement 14 Aug 2024 | CCC 11 Jun 2026 Handover 23 Jun 2026 | 52 days before |
| IMPIANA BAYU 3B1 - P2KPKT 7164-47 | KluangJohor | 98 | 15 May 20261st sale agreement 15 May 2024 | CCC 28 Apr 2026 Handover 4 May 2026 | 11 days before |
| BUKIT EKA PRECINCT 8AKPKT 7164-48Ferra I & II @ Eka Heights · on PropertySifu | SerembanNegeri Sembilan | 368 | 30 Jul 20261st sale agreement 30 Jul 2024 | CCC 18 Mar 2026 Handover 1 Apr 2026 | 120 days before |
| BAYU SUTERA (PRECINCT 4B-2)KPKT 10613-63 | Port DicksonNegeri Sembilan | 40 | 26 May 20271st sale agreement 26 May 2025 | CCC 13 Feb 2026 Handover 6 Mar 2026 | 446 days before |
| BAYU SUTERA (PRECINCT 4B-1)KPKT 10613-60 | Port DicksonNegeri Sembilan | 148 | 18 Nov 20261st sale agreement 18 Nov 2024 | CCC 28 Jan 2026 Handover 12 Feb 2026 | 279 days before |
| BAYU SUTERA (PRECINCT 4A-3)KPKT 10613-56Elonia II & III @ Bayu Sutera · on PropertySifu | Port DicksonNegeri Sembilan | 128 | 6 Mar 20261st sale agreement 6 Mar 2024 | CCC 24 Dec 2025 Handover 5 Jan 2026 | 60 days before |
| BUKIT EKA PRECINCT 4KPKT 7164-50Meora @ Eka Heights · on PropertySifu | SerembanNegeri Sembilan | 262 | 2 Oct 20261st sale agreement 2 Oct 2024 | CCC 21 Oct 2025 Handover 5 Nov 2025 | 331 days before |
| HIJAYU 2 (RESORT VILLA 2)KPKT 10613-59 | SerembanNegeri Sembilan | 20 | 28 Jun 20261st sale agreement 28 Jun 2024 | CCC 27 Aug 2025 Handover 24 Oct 2025 | 247 days before |
| BUKIT EKA PRECINCT 3AKPKT 30517-2 | SerembanNegeri Sembilan | 275 | 28 Dec 20251st sale agreement 28 Dec 2023 | CCC 21 Oct 2025 Handover 24 Oct 2025 | 65 days before |
| IRAMA SENDAYAN 2DKPKT 30156-5 | SerembanNegeri Sembilan | 144 | 7 Feb 20261st sale agreement 7 Feb 2024 | CCC 17 Oct 2025 Handover 23 Oct 2025 | 107 days before |
| BUKIT EKA PRECINCT 3BKPKT 30517-1 | SerembanNegeri Sembilan | 155 | 6 Oct 20251st sale agreement 6 Oct 2023 | CCC 4 Sep 2025 Handover 10 Sep 2025 | 26 days before |
| BAYU SUTERA (PRECINCT 3A)KPKT 10613-58Izara I & II @ Bayu Sutera · on PropertySifu | Port DicksonNegeri Sembilan | 171 | 12 Jan 20261st sale agreement 12 Jan 2024 | CCC 21 Aug 2025 Handover 25 Aug 2025 | 140 days before |
| HIJAYU 2 (RESORT VILLA)KPKT 10613-52 | SerembanNegeri Sembilan | 14 | 21 Jul 20251st sale agreement 21 Jul 2023 | CCC 25 Apr 2025 Handover 3 Jun 2025 | 48 days before |
| IRAMA SENDAYAN 2CKPKT 30156-3 | SerembanNegeri Sembilan | 283 | 1 Aug 20251st sale agreement 1 Aug 2023 | CCC 21 May 2025 Handover 23 May 2025 | 70 days before |
| IRAMA SENDAYAN 2BKPKT 30156-4 | SerembanNegeri Sembilan | 89 | 11 Sep 20251st sale agreement 11 Sep 2023 | CCC 26 Mar 2025 Handover 28 Mar 2025 | 167 days before |
| BAYU SUTERA (PRECINCT 3B)KPKT 10613-57Izara I & II @ Bayu Sutera · on PropertySifu | Port DicksonNegeri Sembilan | 200 | 28 Jul 20251st sale agreement 28 Jul 2023 | CCC 25 Mar 2025 Handover 27 Mar 2025 | 123 days before |
| BAYU SUTERA (PRECINCT 4A-2)KPKT 10613-55Elonia II & III @ Bayu Sutera · on PropertySifu | Port DicksonNegeri Sembilan | 70 | 5 Apr 20251st sale agreement 5 Apr 2023 | CCC 27 Feb 2025 Handover 3 Mar 2025 | 33 days before |
| IMPIANA DAMAI 2KPKT 7164-46 | KluangJohor | 67 | 15 Feb 20251st sale agreement 15 Feb 2023 | CCC 7 Feb 2025 Handover 13 Feb 2025 | 2 days before |
| TIARA SENDAYAN (PRECINCT 14C3-B)KPKT 19342-22 | SerembanNegeri Sembilan | 130 | 9 Jun 20251st sale agreement 9 Jun 2023 | CCC 7 Feb 2025 Handover 12 Feb 2025 | 117 days before |
| TIARA SENDAYAN (PRECINCT 14C3-A)KPKT 19342-21 | SerembanNegeri Sembilan | 206 | 12 May 20251st sale agreement 12 May 2023 | CCC 9 Jan 2025 Handover 15 Jan 2025 | 117 days before |
| IMPIANA BAYU 3B1KPKT 7164-45 | KluangJohor | 54 | 30 Jan 20251st sale agreement 30 Jan 2023 | CCC 17 Dec 2024 Handover 19 Dec 2024 | 42 days before |
| IRAMA SENDAYAN 2AKPKT 30156-2 | SerembanNegeri Sembilan | 213 | 17 Mar 20251st sale agreement 17 Mar 2023 | CCC 12 Dec 2024 Handover 16 Dec 2024 | 91 days before |
| RESORT RESIDENCE 2BKPKT 10613-54 | SerembanNegeri Sembilan | 84 | 23 Nov 20241st sale agreement 23 Nov 2022 | CCC 14 Nov 2024 Handover 18 Nov 2024 | 5 days before |
| TIARA SENDAYAN (PRECINCT 14C2)KPKT 19342-18 | SerembanNegeri Sembilan | 153 | 28 Feb 20251st sale agreement 28 Feb 2023 | CCC 4 Oct 2024 Handover 9 Oct 2024 | 142 days before |
| IRAMA SENDAYAN 1KPKT 30156-1 | SerembanNegeri Sembilan | 192 | 26 Oct 20241st sale agreement 26 Oct 2022 | CCC 26 Sep 2024 Handover 1 Oct 2024 | 25 days before |
| BAYU SUTERA (PRECINCT 4A-1)KPKT 10613-53 | Port DicksonNegeri Sembilan | 227 | 21 Oct 20241st sale agreement 21 Oct 2022 | CCC 9 Sep 2024 Handover 12 Sep 2024 | 39 days before |
| TIARA SENDAYAN (PRECINCT 14C1)KPKT 19342-17 | SerembanNegeri Sembilan | 82 | 23 Feb 20251st sale agreement 23 Feb 2023 | CCC 27 Aug 2024 Handover 29 Aug 2024 | 178 days before |
| RESORT RESIDENCE 2AKPKT 10613-50 | SerembanNegeri Sembilan | 126 | 1 Sep 20241st sale agreement 1 Sep 2022 | CCC 22 Aug 2024 Handover 26 Aug 2024 | 6 days before |
| TIARA SENDAYAN (PRECINCT 14B)KPKT 19342-16 | SerembanNegeri Sembilan | 71 | 22 Aug 20241st sale agreement 22 Aug 2022 | CCC 12 Jun 2024 Handover 14 Jun 2024 | 69 days before |
| TIARA SENDAYAN (PRECINCT 14B2)KPKT 19342-20 | SerembanNegeri Sembilan | 11 | 24 Mar 20251st sale agreement 24 Mar 2023 | CCC 12 Jun 2024 Handover 14 Jun 2024 | 283 days before |
| NUSARI AMAN 3KPKT 10613-49 | SerembanNegeri Sembilan | 219 | 1 Jul 20241st sale agreement 1 Jul 2022 | CCC 23 May 2024 Handover 28 May 2024 | 34 days before |
| BAYU SUTERA (PRECINCT 1A)KPKT 10613-51 | Port DicksonNegeri Sembilan | 193 | 29 Sep 20241st sale agreement 29 Sep 2022 | CCC 22 Apr 2024 Handover 24 Apr 2024 | 158 days before |
| LAMAN SENDAYAN (PRESINT 3)KPKT 10613-43 | SerembanNegeri Sembilan | 250 | 2 Aug 20261st sale agreement 2 Aug 2023 | CCC 5 Jan 2024 Handover 15 Apr 2024 | 839 days before |
| TIARA SENDAYAN (PRECINCT 14A)KPKT 19342-15 | SerembanNegeri Sembilan | 80 | 1 Jul 20241st sale agreement 1 Jul 2022 | CCC 3 Apr 2024 Handover 15 Apr 2024 | 77 days before |
| TIARA SENDAYAN (PRECINCT 14A2)KPKT 19342-19 | SerembanNegeri Sembilan | 8 | 28 Mar 20251st sale agreement 28 Mar 2023 | CCC 3 Apr 2024 Handover 15 Apr 2024 | 347 days before |
| RESORT RESIDENCE 1BKPKT 10613-47 | SerembanNegeri Sembilan | 183 | 22 Dec 20231st sale agreement 22 Dec 2021 | CCC 18 Dec 2023 Handover 20 Dec 2023 | 2 days before |
| BAYU SUTERA (PRECINCT 2A)KPKT 10613-46 | Port DicksonNegeri Sembilan | 255 | 24 Nov 20231st sale agreement 24 Nov 2021 | CCC 29 Nov 2023 Handover 4 Dec 2023 | 10 days after |
| BAYU SUTERA (PRECINCT 1B)KPKT 10613-48 | Port DicksonNegeri Sembilan | 190 | 31 Dec 20231st sale agreement 31 Dec 2021 | CCC 29 Nov 2023 Handover 4 Dec 2023 | 27 days before |
| TIARA SENDAYAN (PRECINCT 13B2)KPKT 19342-13 | SerembanNegeri Sembilan | 53 | 24 Jan 20241st sale agreement 24 Jan 2022 | CCC 22 Nov 2023 Handover 27 Nov 2023 | 58 days before |
| TIARA SENDAYAN (PRECINCT 13B1)KPKT 19342-14 | SerembanNegeri Sembilan | 143 | 23 Nov 20231st sale agreement 23 Nov 2021 | CCC 22 Nov 2023 Handover 27 Nov 2023 | 4 days after |
| TIARA SENDAYAN (PRECINCT 13)KPKT 19342-12 | SerembanNegeri Sembilan | 280 | 21 Oct 20231st sale agreement 21 Oct 2021 | CCC 18 Oct 2023 Handover 24 Oct 2023 | 3 days after |
| LAMAN SENDAYAN (PRESINT 1A)KPKT 10613-44 | SerembanNegeri Sembilan | 274 | 21 Sep 2023Extended 5 months from 21 Apr 20231st sale agreement 21 Apr 2021 | CCC 14 Sep 2023 Handover 19 Sep 2023 | 2 days before |
| BAYU SUTERA (PRECINCT 2B)KPKT 10613-42 | Port DicksonNegeri Sembilan | 325 | 15 Sep 20231st sale agreement 15 Sep 2021 | CCC 30 Aug 2023 Handover 21 Jun 2023 / 4 Sep 2023 | 11 days before |
| TIARA SENDAYAN (PRESINT 7)KPKT 19342-8 | SerembanNegeri Sembilan | 254 | 18 Aug 2023Extended 5 months from 18 Mar 20231st sale agreement 18 Mar 2021 | CCC 16 Aug 2023 Handover 16 Aug 2023 | 2 days before |
| LAMAN SENDAYAN (PRESINT 1B)KPKT 10613-45 | SerembanNegeri Sembilan | 266 | 23 Jul 20231st sale agreement 23 Jul 2021 | CCC 20 Jul 2023 Handover 24 Jul 2023 | 1 day after |
| NUSARI BAYU 2KPKT 10613-41 | SerembanNegeri Sembilan | 192 | 19 Jun 2023Extended 5 months from 19 Jan 20231st sale agreement 19 Jan 2021 | CCC 15 Jun 2023 Handover 19 Jun 2023 | On the deadline |
| TIARA SENDAYAN (PRESINT 9A2)KPKT 19342-10 | SerembanNegeri Sembilan | 32 | 9 Aug 20231st sale agreement 9 Aug 2021 | CCC 1 Jun 2023 Handover 8 Jun 2023 | 62 days before |
| TIARA SENDAYAN (PRECINT 9A1)KPKT 19342-11 | SerembanNegeri Sembilan | 11 | 23 Sep 20231st sale agreement 23 Sep 2021 | CCC 1 Jun 2023 Handover 8 Jun 2023 | 107 days before |
| TIARA SENDAYAN (PRESINT 9B)KPKT 19342-9 | SerembanNegeri Sembilan | 47 | 17 Aug 20231st sale agreement 17 Aug 2021 | CCC 1 Jun 2023 Handover 8 Jun 2023 | 70 days before |
| BANDAR SERI IMPIAN - IMPIANA DAMAI 2AKPKT 7164-44 | KluangJohor | 68 | 19 Apr 2023Extended 5 months from 19 Nov 20221st sale agreement 19 Nov 2020 | CCC 18 Apr 2023 Handover 18 Apr 2023 / 25 Apr 2023 | 6 days after |
| BANDAR SERI IMPIAN-IMPIANA BAYU 3B2KPKT 7164-42 | KluangJohor | 221 | 14 Apr 2022Extended 6 months from 14 Oct 20211st sale agreement 14 Oct 2019 | CCC 18 Jan 2023 Handover 19 May 2022 / 18 Jan 2023 / 13 Feb 2023 | 35–305 days after † |
| TIARA SENDAYAN (PRESINT 6)KPKT 19342-7 | SerembanNegeri Sembilan | 278 | 22 Mar 2023Extended 5 months from 22 Oct 20221st sale agreement 22 Oct 2020 | CCC 1 Feb 2023 | CCC before deadline; handover not recorded |
| RESIDENSI CHAMBERSKPKT 9363-2 | Kuala LumpurWP Kuala Lumpur | 509 | 1 Jul 2023Extended 23 months from 1 Aug 20211st sale agreement 1 Aug 2018 | CCC 19 Dec 2022 Handover 22 Dec 2022 | 191 days before |
| LAMAN SENDAYAN (PRESINT 2)KPKT 10613-40 | SerembanNegeri Sembilan | 380 | 28 Mar 2023Extended 5 months from 28 Oct 20221st sale agreement 28 Oct 2020 | CCC 28 Oct 2022 Handover 31 Oct 2022 | 148 days before |
| LAMAN SENDAYAN (PRESINT 4)KPKT 10613-39 | SerembanNegeri Sembilan | 306 | 21 Jan 2023Extended 5 months from 21 Aug 20221st sale agreement 21 Aug 2020 | CCC 22 Jun 2022 Handover 23 Jun 2022 | 212 days before |
| IMPIANA BAYU 3AKPKT 7164-40 | KluangJohor | 83 | 10 Sep 20211st sale agreement 10 Sep 2019 | CCC 28 Apr 2022 Handover 9 May 2022 | 241 days after † |
| RESORT RESIDENCE 1KPKT 10613-38 | SerembanNegeri Sembilan | 183 | 23 Apr 20221st sale agreement 23 Apr 2020 | CCC 9 Mar 2022 Handover 15 Mar 2022 | 39 days before |
| TIARA SENDAYAN (PRECINCT 8)KPKT 19342-6 | SerembanNegeri Sembilan | 240 | 23 Apr 20221st sale agreement 23 Apr 2020 | CCC 9 Mar 2022 Handover 15 Mar 2022 | 39 days before |
| ARA SENDAYAN 2KPKT 7164-43 | SerembanNegeri Sembilan | 44 | 2 Mar 20221st sale agreement 2 Mar 2020 | CCC 2 Mar 2022 Handover 2 Mar 2022 | On the deadline |
| HIJAYU AMAN (P2)KPKT 10613-37 | SerembanNegeri Sembilan | 109 | 11 Feb 20221st sale agreement 11 Feb 2020 | CCC 9 Aug 2021 | CCC before deadline; handover not recorded |
| TIARA SENDAYAN (PRECINCT 5)KPKT 19342-5 | SerembanNegeri Sembilan | 243 | 19 Sep 20211st sale agreement 19 Sep 2019 | CCC 9 Jul 2021 | CCC before deadline; handover not recorded |
| HIJAYU 2 - RESORT HOMES (SL)KPKT 10613-35 | SerembanNegeri Sembilan | 175 | 18 Sep 20211st sale agreement 18 Sep 2019 | CCC 5 May 2021 | CCC before deadline; handover not recorded |
| HIJAYU AMAN (P1)KPKT 10613-36 | SerembanNegeri Sembilan | 251 | 18 Jun 20211st sale agreement 18 Jun 2019 | CCC 9 Apr 2021 | CCC before deadline; handover not recorded |
| TIARA SENDAYAN (PRECINCT 3)KPKT 19342-4 | SerembanNegeri Sembilan | 428 | 14 Jun 20211st sale agreement 14 Jun 2019 | CCC 9 Apr 2021 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 2AKPKT 7164-36 | SerembanNegeri Sembilan | 244 | 16 Oct 20201st sale agreement 16 Oct 2018 | CCC 30 Mar 2021 | 165 days after † |
| TIARA SENDAYAN (PRECINCT 4)KPKT 19342-3 | SerembanNegeri Sembilan | 363 | 17 Jan 20211st sale agreement 17 Jan 2019 | CCC 24 Nov 2020 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 3A1KPKT 7164-37 | SerembanNegeri Sembilan | 85 | 29 Jan 20211st sale agreement 29 Jan 2019 | CCC 13 Nov 2020 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 3A2 (2)KPKT 7164-38 | SerembanNegeri Sembilan | 45 | 28 Jun 20211st sale agreement 28 Jun 2019 | CCC 13 Nov 2020 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 3A2 (1)KPKT 7164-39 | SerembanNegeri Sembilan | 12 | 29 Jul 20211st sale agreement 29 Jul 2019 | CCC 13 Nov 2020 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 3A2 (3)KPKT 7164-41 | SerembanNegeri Sembilan | 12 | 17 Jan 20211st sale agreement 17 Jan 2019 | CCC 13 Nov 2020 | CCC before deadline; handover not recorded |
| RESIDENSI SIGC - PHASE 1BKPKT 7164-35 | SerembanNegeri Sembilan | 78 | 7 Jan 20211st sale agreement 7 Jan 2019 | CCC 11 Aug 2020 | CCC before deadline; handover not recorded |
| TIARA SENDAYAN (PRECINCT 2)KPKT 19342-2 | SerembanNegeri Sembilan | 504 | 17 Jul 20201st sale agreement 17 Jul 2018 | CCC 29 Jul 2020 | 12 days after † |
| ARA SENDAYAN 3BKPKT 7164-34 | SerembanNegeri Sembilan | 168 | 12 Jun 20201st sale agreement 12 Jun 2018 | CCC 12 May 2020 | CCC before deadline; handover not recorded |
| HIJAYU 2 - RESORT HOMES (SL2&SL3)KPKT 10613-32 | SerembanNegeri Sembilan | 232 | 3 Apr 20201st sale agreement 3 Apr 2018 | CCC 13 Mar 2020 | CCC before deadline; handover not recorded |
| TIARA SENDAYAN (PRECINCT 1)KPKT 19342-1 | SerembanNegeri Sembilan | 404 | 12 Apr 20201st sale agreement 12 Apr 2018 | CCC 13 Mar 2020 | CCC before deadline; handover not recorded |
| BANDAR SERI IMPIAN-IMPIANA CASA 3AKPKT 7164-31 | KluangJohor | 138 | 16 Jan 20201st sale agreement 16 Jan 2018 | CCC 31 Dec 2019 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 4KPKT 7164-33 | SerembanNegeri Sembilan | 193 | 30 Jan 20201st sale agreement 30 Jan 2018 | CCC 20 Dec 2019 | CCC before deadline; handover not recorded |
| HIJAYU 2 - RESORT HOMES (SD2A)KPKT 10613-31 | SerembanNegeri Sembilan | 52 | 10 Jan 20201st sale agreement 10 Jan 2018 | CCC 7 Nov 2019 | CCC before deadline; handover not recorded |
| HIJAYU 2 -RESORT HOMES (SD2B)KPKT 10613-34 | SerembanNegeri Sembilan | 10 | 16 Jan 20211st sale agreement 16 Jan 2019 | CCC 7 Nov 2019 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 1BKPKT 7164-32 | SerembanNegeri Sembilan | 195 | 2 Nov 20191st sale agreement 2 Nov 2017 | CCC 11 Sep 2019 | CCC before deadline; handover not recorded |
| BANDAR SERI IMPIAN - IMPIANA DAMAIKPKT 7164-28 | KluangJohor | 198 | 7 Jun 20191st sale agreement 7 Jun 2017 | CCC 2 Jun 2019 | CCC before deadline; handover not recorded |
| BANDAR SERI IMPIAN-IMPIANA CASA 3BKPKT 7164-30 | KluangJohor | 173 | 15 Jun 20191st sale agreement 15 Jun 2017 | CCC 2 Jun 2019 | CCC before deadline; handover not recorded |
| ARA SENDAYAN 1AKPKT 7164-29 | SerembanNegeri Sembilan | 269 | 26 May 20191st sale agreement 26 May 2017 | CCC 15 May 2019 | CCC before deadline; handover not recorded |
| HIJAYU 2 - RESORT HOMES (SL1)KPKT 10613-30 | SerembanNegeri Sembilan | 129 | 15 Jun 20191st sale agreement 15 Jun 2017 | CCC 29 Mar 2019 | CCC before deadline; handover not recorded |
| SURIAMAN 2KPKT 10613-29 | SerembanNegeri Sembilan | 253 | 28 Mar 20191st sale agreement 28 Mar 2017 | CCC 25 Feb 2019 | CCC before deadline; handover not recorded |
| SURIAMAN 2AKPKT 10613-28 | SerembanNegeri Sembilan | 267 | 20 Oct 20181st sale agreement 20 Oct 2016 | CCC 10 Oct 2018 | CCC before deadline; handover not recorded |
| RESIDENSI SIGCKPKT 7164-25 | SerembanNegeri Sembilan | 125 | 3 Aug 20181st sale agreement 3 Aug 2016 | CCC 16 Aug 2018 | 13 days after |
| HIJAYU 3KPKT 10613-24 | SerembanNegeri Sembilan | 394 | 3 Feb 20181st sale agreement 3 Feb 2016 | CCC 25 Jun 2018 | 142 days after |
| SURIAMAN 1KPKT 10613-27 | SerembanNegeri Sembilan | 124 | 19 Aug 20181st sale agreement 19 Aug 2016 | CCC 18 Jun 2018 | CCC before deadline; handover not recorded |
| SURIAMAN 2BKPKT 10613-26 | SerembanNegeri Sembilan | 232 | 19 Jul 20181st sale agreement 19 Jul 2016 | CCC 12 Jun 2018 | CCC before deadline; handover not recorded |
| BANDAR SERI IMPIAN-IMPIANA 2KPKT 7164-26 | KluangJohor | 52 | 11 Jan 20191st sale agreement 11 Jan 2017 | CCC 7 Jun 2018 | CCC before deadline; handover not recorded |
| BANDAR SERI IMPIAN : IMPIANA INDAHKPKT 7164-27 | KluangJohor | 124 | 16 Jan 20191st sale agreement 16 Jan 2017 | CCC 7 Jun 2018 | CCC before deadline; handover not recorded |
| BANDAR SERI IMPIAN : IMPIANA BAYU 2KPKT 7164-24 | KluangJohor | 423 | 3 Jun 20171st sale agreement 3 Jun 2015 | CCC 3 Jan 2018 | 214 days after |
| SURIAMAN 3KPKT 10613-23 | SerembanNegeri Sembilan | 385 | 19 Oct 20171st sale agreement 19 Oct 2015 | CCC 27 Sep 2017 | CCC before deadline; handover not recorded |
| HIJAYU 3BKPKT 10613-22 | SerembanNegeri Sembilan | 333 | 2 Jul 20171st sale agreement 2 Jul 2015 | CCC 13 Feb 2017 | CCC before deadline; handover not recorded |
| HIJAYU 2 - RESORT HOMESKPKT 10613-21 | SerembanNegeri Sembilan | 64 | 23 Jun 20171st sale agreement 23 Jun 2015 | CCC 22 Dec 2016 | CCC before deadline; handover not recorded |
| HIJAYU 3AKPKT 10613-20 | SerembanNegeri Sembilan | 565 | 3 Jul 20161st sale agreement 3 Jul 2014 | CCC 29 Jun 2016 | CCC before deadline; handover not recorded |
| IMPIANA HEIGHTS @ TAMAN SERI IMPIANKPKT 7164-23 | KluangJohor | 82 | 23 Sep 20161st sale agreement 23 Sep 2014 | CCC 29 Jun 2016 | CCC before deadline; handover not recorded |
| TAMAN SERI IMPIAN - IMPIANA BAYU 1KPKT 7164-22 | KluangJohor | 603 | 31 Jul 20151st sale agreement 31 Jul 2013 | CCC 4 Nov 2015 | 96 days after |
| HIJAYU 1A-1KPKT 10613-19 | SerembanNegeri Sembilan | 367 | 6 Feb 20161st sale agreement 6 Feb 2014 | CCC 22 Oct 2015 | CCC before deadline; handover not recorded |
| HIJAYU 1A-2KPKT 10613-18 | SerembanNegeri Sembilan | 299 | 27 Aug 20151st sale agreement 27 Aug 2013 | CCC 29 Apr 2015 | CCC before deadline; handover not recorded |
| HIJAYU 3DKPKT 10613-15 | SerembanNegeri Sembilan | 534 | 21 Dec 20141st sale agreement 21 Dec 2012 | CCC 4 Feb 2015 | 45 days after |
| HIJAYU 1BKPKT 10613-16 | SerembanNegeri Sembilan | 229 | 25 Sep 20141st sale agreement 25 Sep 2012 | CCC 22 Aug 2014 | CCC before deadline; handover not recorded |
| NUSARI AMANKPKT 10613-13 | SerembanNegeri Sembilan | 285 | — | CCC 18 Apr 2014 | — |
| TAMAN SERI IMPIAN - IMPIANA CASA 2KPKT 7164-21 | KluangJohor | 288 | — | CCC 13 Apr 2014 | — |
| TAMAN DESA PD2BKPKT 7164-20 | Port DicksonNegeri Sembilan | 56 | — | CCC 9 Jan 2014 | — |
| NUSARI AMAN 2KPKT 10613-12 | SerembanNegeri Sembilan | 472 | — | CCC 8 Jan 2014 | — |
| TAMAN SERI IMPIAN - IMPIANA CASA 1KPKT 7164-18 | KluangJohor | 465 | — | CCC 1 Jul 2013 | — |
| NUSARI AMAN 1BKPKT 10613-9 | SerembanNegeri Sembilan | 515 | — | CCC 3 May 2013 | — |
| NUSARI BAYU 3KPKT 10613-11 | SerembanNegeri Sembilan | 219 | — | CCC 6 Feb 2013 | — |
| IMPIANA VILLA @ TAMAN SERI IMPIANKPKT 7164-15 | KluangJohor | 161 | — | CCC 21 Nov 2012 | — |
| NUSARI BAYU 3KPKT 10613-7 | SerembanNegeri Sembilan | 261 | — | CCC 1 Aug 2012 | — |
| ATIYA @ NUSARI BAYUKPKT 10613-4 | SerembanNegeri Sembilan | 54 | — | CCC 28 Dec 2011 | — |
| NUSARI AMAN 2AKPKT 10613-6 | SerembanNegeri Sembilan | 241 | — | CCC 28 Dec 2011 | — |
| NUSARI AMANKPKT 10613-8 | SerembanNegeri Sembilan | 20 | — | CCC 28 Dec 2011 | — |
| TAMAN SERI IMPIAN 3 : IMPIANA GARDEN - MODENAKPKT 7164-16 | KluangJohor | 160 | — | CCC 3 Nov 2011 | — |
| TAMAN SERI IMPIAN : IMPIANA GARDEN - MODENA 2KPKT 7164-19 | KluangJohor | 34 | — | CCC 3 Nov 2011 | — |
| NUSARI AMAN 1AKPKT 10613-5 | SerembanNegeri Sembilan | 236 | — | CCC 7 Oct 2011 | — |
| IDAMAN BAYUKPKT 10613-3 | SerembanNegeri Sembilan | 178 | — | CCC 22 Aug 2011 | — |
| TAMAN DESA PD 2KPKT 7164-13 | Port DicksonNegeri Sembilan | 483 | — | CCC 22 Jun 2011 | — |
| NUSARI BAYU 2KPKT 10613-2 | Negeri Sembilan | 359 | — | CCC 18 Jan 2011 | — |
| TAMAN SERI IMPIAN 3 - IMPIANA GARDENKPKT 7164-14 | KluangJohor | 403 | — | CCC 26 Aug 2010 | — |
| TAMAN SERI IMPIAN 2BKPKT 7164-11 | KluangJohor | 791 | — | CFO 10 Feb 2010 | — |
| NUSARI BAYUKPKT 10613-1 | SerembanNegeri Sembilan | 1,159 | — | CCC 27 Jan 2010 | — |
| TAMAN PULAI PERDANAKPKT 7164-12 | SerembanNegeri Sembilan | 199 | — | CCC 20 Oct 2009 | — |
| TAMAN ANGGERIK TENGGARA-PHASE 1BKPKT 9497-2 | Kota TinggiJohor | 359 | — | CFO 14 Oct 2009 | — |
| TAMAN BUKIT SENDAYANKPKT 7664-9 | SerembanNegeri Sembilan | 675 | — | CFO 30 May 2008 | — |
| MATAHARI INDAHKPKT 7664-11 | SerembanNegeri Sembilan | 407 | — | CFO 5 Feb 2008 | — |
| TAMAN AROWANA INDAHKPKT 7664-10 | SerembanNegeri Sembilan | 383 | — | CFO 5 Nov 2007 | — |
| TAMAN DESA PDKPKT 7164-8 | Port DicksonNegeri Sembilan | 735 | — | CFO 25 Nov 2006 | — |
| BUKIT EKA PRECINCT 8BKPKT 7164-51Ferra I & II @ Eka Heights · on PropertySifu | SerembanNegeri Sembilan | 196 | 22 Nov 20261st sale agreement 22 Nov 2024 | — | — |
| TAMAN SERI IMPIAN - 1KPKT 7164-9 | KluangJohor | 627 | — | — | — |
Under construction (31) and not yet started (2) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| IMPIANA DAMAI 2B - P1KPKT 7164-52 | KluangJohor | 78 | SmoothOn schedule | 17 Dec 20261st sale agreement 17 Dec 2024 | 95% |
| BUKIT SURIA RUMAH KLUSTERKPKT 10613-61 | SerembanNegeri Sembilan | 56 | SmoothOn schedule | 22 Dec 20261st sale agreement 22 Dec 2024 | 98% |
| BUKIT SURIA RUMAH TERES (LH-P1)KPKT 10613-62 | Negeri Sembilan | 76 | SmoothOn schedule | 21 Jan 20271st sale agreement 21 Jan 2025 | 98% |
| LAMAN SENDAYAN 2 PRECINCT 2BKPKT 19342-24 | SerembanNegeri Sembilan | 100 | SmoothOn schedule | 12 Apr 20271st sale agreement 12 Apr 2025 | 84% |
| BUKIT SURIA RUMAH BERKEMBAR (CH-P1)KPKT 10613-66 | SerembanNegeri Sembilan | 14 | SmoothOn schedule | 16 May 20271st sale agreement 16 May 2025 | 98% |
| BAYU SUTERA (PRECINCT 4B-3)KPKT 10613-64 | Port DicksonNegeri Sembilan | 96 | SmoothOn schedule | 23 Jul 20271st sale agreement 23 Jul 2025 | 88% |
| LAMAN SENDAYAN 2 PRECINCT 2AKPKT 19342-25 | SerembanNegeri Sembilan | 161 | SmoothOn schedule | 28 Jul 20271st sale agreement 28 Jul 2025 | 40–59% |
| BUKIT SURIA RUMAH TERES (LH-P2)KPKT 10613-65 | SerembanNegeri Sembilan | 107 | SmoothOn schedule | 18 Aug 20271st sale agreement 18 Aug 2025 | 55–65% |
| IMPIANA HEIGHTS 3KPKT 7164-57 | KluangJohor | 31 | SmoothOn schedule | 20 Aug 20271st sale agreement 20 Aug 2025 | 66–71% |
| BUKIT EKA PRECINCT 2AKPKT 7164-58 | Negeri Sembilan | 206 | SmoothOn schedule | 22 Aug 20271st sale agreement 22 Aug 2025 | 56% |
| BUKIT SURIA RUMAH BERKEMBAR (SD-P1)KPKT 10613-67 | Negeri Sembilan | 32 | SmoothOn schedule | 29 Aug 20271st sale agreement 29 Aug 2025 | 48–60% |
| RESIDENSI BAYUKPKT 30392-1Levia Residence · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 778 | SmoothOn schedule | 3 Oct 2027Extended 12 months from 3 Oct 20261st sale agreement 3 Oct 2023 | 91% |
Show all 33 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| IMPIANA DAMAI 2B - P1KPKT 7164-52 | KluangJohor | 78 | SmoothOn schedule | 17 Dec 20261st sale agreement 17 Dec 2024 | 95% |
| BUKIT SURIA RUMAH KLUSTERKPKT 10613-61 | SerembanNegeri Sembilan | 56 | SmoothOn schedule | 22 Dec 20261st sale agreement 22 Dec 2024 | 98% |
| BUKIT SURIA RUMAH TERES (LH-P1)KPKT 10613-62 | Negeri Sembilan | 76 | SmoothOn schedule | 21 Jan 20271st sale agreement 21 Jan 2025 | 98% |
| LAMAN SENDAYAN 2 PRECINCT 2BKPKT 19342-24 | SerembanNegeri Sembilan | 100 | SmoothOn schedule | 12 Apr 20271st sale agreement 12 Apr 2025 | 84% |
| BUKIT SURIA RUMAH BERKEMBAR (CH-P1)KPKT 10613-66 | SerembanNegeri Sembilan | 14 | SmoothOn schedule | 16 May 20271st sale agreement 16 May 2025 | 98% |
| BAYU SUTERA (PRECINCT 4B-3)KPKT 10613-64 | Port DicksonNegeri Sembilan | 96 | SmoothOn schedule | 23 Jul 20271st sale agreement 23 Jul 2025 | 88% |
| LAMAN SENDAYAN 2 PRECINCT 2AKPKT 19342-25 | SerembanNegeri Sembilan | 161 | SmoothOn schedule | 28 Jul 20271st sale agreement 28 Jul 2025 | 40–59% |
| BUKIT SURIA RUMAH TERES (LH-P2)KPKT 10613-65 | SerembanNegeri Sembilan | 107 | SmoothOn schedule | 18 Aug 20271st sale agreement 18 Aug 2025 | 55–65% |
| IMPIANA HEIGHTS 3KPKT 7164-57 | KluangJohor | 31 | SmoothOn schedule | 20 Aug 20271st sale agreement 20 Aug 2025 | 66–71% |
| BUKIT EKA PRECINCT 2AKPKT 7164-58 | Negeri Sembilan | 206 | SmoothOn schedule | 22 Aug 20271st sale agreement 22 Aug 2025 | 56% |
| BUKIT SURIA RUMAH BERKEMBAR (SD-P1)KPKT 10613-67 | Negeri Sembilan | 32 | SmoothOn schedule | 29 Aug 20271st sale agreement 29 Aug 2025 | 48–60% |
| RESIDENSI BAYUKPKT 30392-1Levia Residence · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 778 | SmoothOn schedule | 3 Oct 2027Extended 12 months from 3 Oct 20261st sale agreement 3 Oct 2023 | 91% |
| IMPIANA DAMAI 2B - P2KPKT 7164-56 | KluangJohor | 76 | SmoothOn schedule | 19 Nov 20271st sale agreement 19 Nov 2025 | 40–53% |
| IMPIANA BAYU 3B1 P3KPKT 7164-59 | KluangJohor | 43 | SmoothOn schedule | 21 Nov 20271st sale agreement 21 Nov 2025 | 64–69% |
| BUKIT SURIA RUMAH KLUSTER (CH-P2)KPKT 10613-68 | SerembanNegeri Sembilan | 56 | SmoothOn schedule | 1 Dec 20271st sale agreement 1 Dec 2025 | 65% |
| BUKIT EKA PRECINCT 9AKPKT 7164-53 | SerembanNegeri Sembilan | 160 | SmoothOn schedule | 8 Dec 20271st sale agreement 8 Dec 2025 | 40–46% |
| BUKIT SURIA RUMAH TERES (LH-P3)KPKT 10613-69 | SerembanNegeri Sembilan | 73 | SmoothOn schedule | 30 Dec 20271st sale agreement 30 Dec 2025 | 40–44% |
| LAMAN SENDAYAN 3 (PRESINT 3C-5)KPKT 19342-27 | SerembanNegeri Sembilan | 182 | SmoothOn schedule | 27 Mar 20281st sale agreement 27 Mar 2026 | 52% |
| LAMAN SENDAYAN 3 (PRESINT 3B)KPKT 19342-26 | SerembanNegeri Sembilan | 108 | SmoothOn schedule | 6 Apr 20281st sale agreement 6 Apr 2026 | 33% |
| BUKIT SURIA RUMAH TERES (LH-P4)KPKT 10613-70 | Negeri Sembilan | 98 | SmoothOn schedule | 8 May 20281st sale agreement 8 May 2026 | 12–38% |
| LAMAN SENDAYAN 2 (PRECINCT 2D)KPKT 19342-28 | Negeri Sembilan | 174 | SmoothOn schedule | 15 May 20281st sale agreement 15 May 2026 | 47–50% |
| BUKIT EKA PRECINCT 9BKPKT 7164-54 | SerembanNegeri Sembilan | 169 | SmoothOn schedule | 22 May 20281st sale agreement 22 May 2026 | 30–32% |
| BUKIT SURIA RUMAH KLUSTER (CH-P3)KPKT 10613-71 | Negeri Sembilan | 28 | SmoothOn schedule | 25 May 20281st sale agreement 25 May 2026 | 52% |
| LAMAN SENDAYAN 3 (PRESINT 3A-2)KPKT 19342-29 | SerembanNegeri Sembilan | 124 | SmoothOn schedule | 30 Jun 20281st sale agreement 30 Jun 2026 | 24% |
| BAYU SUTERA 2 (PRESINT 4)KPKT 19342-31 | Negeri Sembilan | 195 | SmoothOn schedule | 12 Jul 20281st sale agreement 12 Jul 2026 | 5% |
| BUKIT SURIA RUMAH BERKEMBAR (SD-P2)KPKT 10613-72 | Negeri Sembilan | 40 | SmoothOn schedule | 17 Jul 20281st sale agreement 17 Jul 2026 | 5–15% |
| LAMAN SENDAYAN 3 (PRESINT 3A-3)KPKT 19342-32 | Negeri Sembilan | 177 | SmoothOn schedule | 15 Aug 20281st sale agreement 15 Aug 2026 | 5% |
| BUKIT EKA PRECINCT 2BKPKT 7164-60 | SerembanNegeri Sembilan | 159 | SmoothOn schedule | 28 Sep 20281st sale agreement 28 Sep 2026 | 15% |
| LAMAN SENDAYAN 2 (PRECINCT 2A - FASA 2)KPKT 19342-30 | Negeri Sembilan | 181 | SmoothOn schedule | — | 5% |
| LAMAN SENDAYAN 3 (PRESINT 3A-1)KPKT 19342-33 | Negeri Sembilan | 108 | SmoothOn schedule | — | 5% |
| BAYU SUTERA 2 (PRESINT 5)KPKT 19342-34 | Negeri Sembilan | 98 | SmoothNot started | — | 0% |
| TAMAN SERI IMPIAN - 2AKPKT 7164-10 | KluangJohor | 973 | SmoothOn schedule | — | 17–90% |
| TAMAN SERI IMPIAN - JENIS A (ASTER)KPKT 7164-17 | KluangJohor | 130 | SmoothNot started | — | 0% |
Permit cancelled or other KPKT status (4)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| HIJAYU AMANKPKT 10613-25 | SerembanNegeri Sembilan | 360 | Permit cancelledPermit cancelled | — | 5% |
| HIJAYU AMAN (PPA1M)KPKT 10613-33 | SerembanNegeri Sembilan | 360 | Permit cancelledPermit cancelled | — | 5% |
| RMMK@TAMAN BUKIT SENDAYANKPKT 7664-12 | SerembanNegeri Sembilan | 60 | Permit cancelledPermit cancelled | — | 0% |
| IMPIANA HEIGHTS 2KPKT 7164-55 | KluangJohor | 13 | Permit cancelledPermit cancelled | — | 15% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Matrix Concepts at a glance
| Listed | Bursa Malaysia Main Market · MATRIX (5236) · listed 28 May 2013[1] |
|---|---|
| Started | Established in 1996[1] |
| Head office | Wisma Matrix, Seremban, Negeri Sembilan[1] |
| Leadership | Lee Tian Hock — Founder and Group Executive Deputy Chairman[2][1] Kelvin Lee Chin Chuan — Group Managing Director[2] Dato' Haji Mohamad Haslah bin Mohamad Amin — Chairman, Non-Independent Non-Executive Director (2025 annual report)[1] |
| Companies in the KPKT register | BSS DEVELOPMENT SDN. BHD. KPKT 10613[1] MATRIX CONCEPTS SDN. BHD. KPKT 7164[1] MATRIX CONCEPTS (NS) SDN. BHD. KPKT 19342[1] MGE DEVELOPMENT SDN. BHD. KPKT 30156[1] MATRIX CONCEPTS (CENTRAL) SDN. BHD. KPKT 9363[1] MATRIX IBS SDN. BHD. KPKT 30517[1] MATRIX CONCEPTS (CHERAS) SDN. BHD. KPKT 30392[1] MATRIX CONCEPTS (SOUTHERN) SDN. BHD. KPKT 9497[1] MASUDA CORPORATION SDN. BHD. KPKT 7664[1] |
| Website | mchb.com.my |
| Flagship township | Bandar Sri Sendayan, Negeri Sembilan[1] |
| Land bank (company figure) | 4,000.8 acres at 31 March 2026, estimated gross development value RM21.8 billion, in Sendayan, Bandar Seri Impian, the Klang Valley and the MVV development[3] |
| Businesses | Property development, construction, education, hospitality and healthcare[1] |
| Outside Malaysia | Ventures in Indonesia and Australia[1] |
Matrix Concepts projects on sale on PropertySifu
Elonia II & III @ Bayu Sutera
- RESORT RESIDENCE 1B — 0.3 km, 2023
- RESORT RESIDENCE 2B — 0.4 km, 2024
- RESORT RESIDENCE 2A — 0.4 km, 2024
Ferra I & II @ Eka Heights
- RESORT RESIDENCE 1 — 0.1 km, 2022
- RESORT RESIDENCE 1B — 0.3 km, 2023
- RESORT RESIDENCE 2B — 0.4 km, 2024
Izara I & II @ Bayu Sutera
- HIJAYU 2 (RESORT VILLA 2) — 0.3 km, 2025
- HIJAYU 2 (RESORT VILLA) — 0.3 km, 2025
- HIJAYU 2 - RESORT HOMES — 0.3 km, 2016
Meora @ Eka Heights
- RESORT RESIDENCE 1 — 0.1 km, 2022
- RESORT RESIDENCE 1B — 0.3 km, 2023
- RESORT RESIDENCE 2B — 0.4 km, 2024
Who is Matrix Concepts? The company behind the projects
Matrix Concepts was established in 1996 and has been listed on the Main Market of Bursa Malaysia since 28 May 2013 [1]. Its head office is Wisma Matrix in Seremban, Negeri Sembilan [1]. The founder, Lee Tian Hock, is group executive deputy chairman, and Kelvin Lee Chin Chuan is group managing director [2].
Its flagship is the Bandar Sri Sendayan township in Negeri Sembilan [1]; KPKT also registers its Bandar Seri Impian and Taman Seri Impian projects in Kluang, Johor. The company says that at 31 March 2026 it had 4,000.8 acres of remaining land bank, with an estimated gross development value of RM21.8 billion, in Sendayan, Bandar Seri Impian, the Klang Valley and the Malaysia Vision Valley (MVV) development [3]. Besides property it runs construction, education, hospitality and healthcare businesses, and it has ventures in Indonesia and Australia [1]. These are group-wide descriptions; the KPKT register counts each licensed phase as a separate housing project.
The Matrix projects listed on PropertySifu are registered with KPKT under wholly owned subsidiaries [1]: the Bayu Sutera precincts (Port Dickson district) under BSS Development Sdn Bhd, the Bukit Eka precincts (Seremban district) under Matrix Concepts Sdn Bhd, and Levia Residence in Cheras, Kuala Lumpur, registered as Residensi Bayu under Matrix Concepts (Cheras) Sdn Bhd, which the group holds through Matrix Concepts (Central) Sdn Bhd [1].
Frequently asked questions
Is Matrix Concepts a listed company?
Yes. Matrix Concepts Holdings Berhad has been listed on the Main Market of Bursa Malaysia since 28 May 2013, under the stock name MATRIX and stock code 5236 [1].
How many housing projects has Matrix Concepts completed?
In the KPKT register, 133 of the 170 housing projects under nine Matrix Concepts companies are completed. Of the 104 completed projects that have both a deadline and a completion date in the register, 52 were handed over on or before the deadline set by the first sale agreement (including any extension KPKT approved), 14 were handed over or certified complete after that deadline — 4 of these were under construction during the 18 March–31 August 2020 movement control period — and 38 received the completion certificate before the deadline, with no handover date recorded.
Does Matrix Concepts have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 170 Matrix Concepts projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). 31 projects are under construction and on schedule (Lancar), and 4 have the status Permit Telah Dibatalkan (permit cancelled).
Which company develops Levia Residence?
Matrix Concepts (Cheras) Sdn Bhd (KPKT developer code 30392). Matrix Concepts' 2025 annual report lists it as a wholly owned subsidiary of Matrix Concepts (Central) Sdn Bhd, which the listed company owns in full [1]. KPKT registers the project as Residensi Bayu (30392-1).
Has Levia Residence's handover deadline been extended?
Yes, according to KPKT. The project (30392-1, 778 units, first sale agreement 3 October 2023) had a deadline of 3 October 2026, extended with approval by 12 months to 3 October 2027. It is recorded as on schedule (Lancar), with reported progress of 91%.
Were the Bayu Sutera and Eka Heights phases on PropertySifu handed over on time?
The KPKT records matched to them show handover before the deadline, with no extension: Izara (Bayu Sutera precincts 3B and 3A) on 27 March 2025 and 25 August 2025, 123 and 140 days early; Elonia (precincts 4A-2 and 4A-3) on 3 March 2025 and 5 January 2026, 33 and 60 days early; Meora (Bukit Eka precinct 4) on 5 November 2025, 331 days early; and Ferra (Bukit Eka precinct 8A) on 1 April 2026, 120 days early. Ferra's precinct 8B is listed as completed, but the register does not show its completion or handover dates.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Matrix Concepts Holdings Berhad Integrated Annual Report 2025 (FY ended 31 March 2025) · Matrix Concepts Holdings Berhad · accessed 28 Oct 2026
https://www.insage.com.my/interactiveAR/MATRIX/interactiveAR2025/ - [2] Matrix Concepts registers RM416.7mil in new property sales in 1Q · The Star · 24 Aug 2026 · accessed 28 Oct 2026
https://www.thestar.com.my/business/business-news/2026/08/24/matrix-concepts-registers-rm4167mil-in-new-property-sales-in-1q - [3] Matrix Concepts' FY2026 revenue rises 19.4% to RM1.37 bil, launches RM1.99 bil of projects · EdgeProp.my (The Edge Media Group) · 27 Jul 2026 · accessed 28 Oct 2026
https://www.edgeprop.my/content/1916900/matrix-concepts’-fy2026-revenue-rises-194-rm137-bil-launches-rm199-bil-projects
Last updated 28 Oct 2026