Iwajib Group is a private developer based in Sungai Besi, Kuala Lumpur, with six housing projects in the KPKT register under five companies we matched to the projects on its website: five completed and one under construction, IX Suria Residences in Kajang (Hulu Langat), none classed Sick or Abandoned. It says it was established in 2008.
- 6 projects in the KPKT register
- 5 completed
- 1 under construction
- None Sick or Abandoned
Has Iwajib Group handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 6 housing projects under 5 Iwajib Group companies in 2 states: 5 completed, 1 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 5 completed projects, 3 have both a handover deadline and a completion date in the register: 1 handed over on or before the deadline; 2 handed over or certified complete after that deadline.
No project has a KPKT-approved extension of the delivery period.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN SEMENYIH IDAMANKPKT 14279-2 | Hulu LangatSelangor | 113 | 14 Nov 20221st sale agreement 14 Nov 2019 | CCC 13 Jun 2022 Handover 27 Jun 2022 | 140 days before |
| RESIDENSI SHAMELINKPKT 14180-1 | Kuala LumpurWP Kuala Lumpur | 318 | 2 Jun 20191st sale agreement 2 Jun 2016 | CCC 17 Feb 2020 | 260 days after |
| TAMAN SEMENYIH IDAMANKPKT 14279-1 | Hulu LangatSelangor | 137 | 5 May 20191st sale agreement 5 May 2016 | CCC 9 Aug 2019 | 96 days after |
| TAMAN CHERAS IDAMANKPKT 11862-1 | Hulu LangatSelangor | 133 | — | CCC 13 Feb 2014 | — |
| TAMAN CHERAS IDAMANKPKT 11182-1 | Hulu LangatSelangor | 40 | — | CCC 4 Apr 2012 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI SURIA IDAMANKPKT 30587-1IX Suria Residences · on PropertySifu | Hulu LangatSelangor | 380 | SmoothOn schedule | 2 Oct 20271st sale agreement 2 Oct 2024 | 65% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Iwajib Group at a glance
| Listed | Not listed — the Iwajib developer companies are private limited companies (Sdn Bhd) |
|---|---|
| Started | 2008, according to the company[2] |
| Head office | Sungai Besi, Kuala Lumpur[1] |
| Leadership | Datuk Chew Yin Keen — Director[4] Datin Adeline Quak Soo Bee — Chief Executive Officer[4] |
| Companies in the KPKT register | IWAJIB ESTATE SDN. BHD. KPKT 30587[3] IWAJIB PROPERTY SDN. BHD. KPKT 14279[1][2] IDAMAN WAJIB SDN. BHD. KPKT 11182[2][1] HARTANAH WAJIB SDN. BHD. KPKT 11862[2] HKS DEVELOPMENT SDN. BHD. KPKT 14180[2] |
| Website | iwajib.com.my |
| Where it builds | Kajang and Semenyih in Hulu Langat, Selangor; Shamelin in Kuala Lumpur[1][2] |
| OnePark, Semenyih | 250 homes, completed in two phases: 137 in 2019 and 113 in 2022[2] |
| IX SURIA Residences | Kajang: 380 freehold homes in two 18-storey blocks on 4.75 acres; developer Iwajib Estate Sdn Bhd, licence 30587[3] |
Iwajib Group projects on sale on PropertySifu
Who is Iwajib Group? The company behind the projects
Iwajib Group says it was established in 2008 [2], with its office in Sungai Besi, Kuala Lumpur [1]. Its leadership page names Datuk Chew Yin Keen as director and Datin Adeline Quak Soo Bee as chief executive officer [4]. No stock-exchange listing was found; its projects are developed through private companies.
The company's milestones start with Taman Cheras Idaman 2: 40 double-storey terrace homes in 2012 and a further 133 units in 2014 [2]. KPKT registers them as TAMAN CHERAS IDAMAN under Idaman Wajib Sdn Bhd (11182-1, CCC 4 April 2012) and Hartanah Wajib Sdn Bhd (11862-1, CCC 13 February 2014). OnePark in Semenyih, 250 homes delivered in 2019 and 2022 [1][2], is registered as TAMAN SEMENYIH IDAMAN under Iwajib Property Sdn Bhd (14279-1 and 14279-2). The Sky Residence @ Shamelin, which the company calls its first high-rise development, with a CCC dated 17 February 2020 [2], is registered as RESIDENSI SHAMELIN under HKS Development Sdn Bhd (14180-1).
IX SURIA Residences in Kajang is developed by Iwajib Estate Sdn Bhd, which the project website describes as a member of Iwajib Group, under developer licence 30587; it has 380 freehold homes in two 18-storey blocks on 4.75 acres [3]. The company reported that both towers reached full structural height in July 2026 [2].
Frequently asked questions
Is Iwajib a listed company?
No stock-exchange listing was found. Each Iwajib project is developed through its own private company; IX SURIA Residences, for example, is developed by Iwajib Estate Sdn Bhd under developer licence 30587 [3].
What does KPKT show for IX Suria Residences?
KPKT registers it as RESIDENSI SURIA IDAMAN (30587-1, 380 units in two blocks of 204 and 176). The first sale agreement is dated 2 October 2024 and the handover deadline is 2 October 2027, with no extension recorded. It is on schedule (Lancar), with reported progress of 65% for both blocks.
Was OnePark handed over on time?
Phase 1 (14279-1, 137 houses): first sale agreement 5 May 2016, deadline 5 May 2019; the CCC is dated 9 August 2019, 96 days after the deadline, and the handover date is not recorded. Phase 2 (14279-2, 113 houses): CCC on 13 June 2022 and handover on 27 June 2022, 140 days before the 14 November 2022 deadline. Neither phase has an approved extension.
Was The Sky Residence @ Shamelin completed on time?
KPKT registers it as RESIDENSI SHAMELIN (14180-1, 318 serviced apartments, 36 storeys) under HKS Development Sdn Bhd. The first sale agreement is dated 2 June 2016 and the deadline 2 June 2019, with no extension; the CCC is dated 17 February 2020, 260 days after the deadline, and the handover date is not recorded.
Does Iwajib have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the six projects under these five companies as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). Five are completed; IX Suria Residences is under construction and on schedule (Lancar).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Iwajib Group — home page (projects, office) · Iwajib Group · accessed 28 Oct 2026
https://www.iwajib.com.my/ - [2] Our Story — milestones and figures · Iwajib Group · accessed 28 Oct 2026
https://www.iwajib.com.my/our-story/ - [3] IX SURIA Residences — developer and licence details · Iwajib Estate Sdn Bhd · accessed 28 Oct 2026
https://www.iwajib.com.my/ix-suria-residences/ - [4] Leadership · Iwajib Group · accessed 28 Oct 2026
https://www.iwajib.com.my/leadership/