IJM Land (IJM Land Berhad)
IJM Land, the property arm of Bursa Malaysia-listed IJM Corporation Berhad, has 243 housing projects in the KPKT register under the 23 companies counted here, including a 50% joint venture and a joint-development partner: 214 completed, 25 under construction, 1 not yet started and 3 with cancelled sales permits. None is classed Sick or Abandoned; two are classed Late (Lewat).
- 243 projects in the KPKT register
- 214 completed
- 25 under construction
- 1 not yet started
- 3 with the permit cancelled
- None Sick or Abandoned
Has IJM Land handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 243 housing projects under 23 IJM Land companies in 5 states: 214 completed, 25 under construction, 1 not yet started, 3 with the permit cancelled. 0 classed Sick (Sakit), 0 Abandoned (Terbengkalai), 2 Late (Lewat).
Of the 214 completed projects, 128 have both a handover deadline and a completion date in the register: 33 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 23 handed over or certified complete after that deadline (2 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 72 received the completion certificate before the deadline (handover date not recorded).
44 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 214
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| AYRA TERRACESKPKT 30653-1 | Seberang Perai SelatanPulau Pinang | 100 | 25 Sep 20261st sale agreement 25 Sep 2024 | CCC 7 Oct 2026 Handover 8 Oct 2026 | 13 days after |
| AUSTIN DUTAKPKT 8326-24 | Johor BahruJohor | 58 | 23 Nov 20261st sale agreement 23 Nov 2024 | CCC 20 Aug 2026 Handover 20 Aug 2026 | 95 days before |
| AUSTIN DUTAKPKT 8326-22 | Johor BahruJohor | 130 | 31 May 20261st sale agreement 31 May 2024 | CCC 1 Jul 2026 Handover 2 Jul 2026 | 32 days after |
| S2 HEIGHTS NOVAKPKT 9567-29 | SerembanNegeri Sembilan | 70 | 13 Jul 20261st sale agreement 13 Jul 2024 | CCC 5 Jun 2026 Handover 23 Jun 2026 | 20 days before |
| SIERRA HIJAUAN FASA 2EKPKT 10296-6 | GombakSelangor | 25 | 10 Mar 20261st sale agreement 10 Mar 2023 | CCC 18 Sep 2025 Handover 3 Mar 2026 | 7 days before |
| THE TERRACES CONDOMINIUMKPKT 6212-4 | Daerah Timor LautPulau Pinang | 410 | 16 Jul 2025Extended 17 months from 16 Feb 20241st sale agreement 16 Feb 2021 | CCC 4 Feb 2026 Handover 25 Feb 2026 | 224 days after |
| SIERRA HIJAUANKPKT 10296-7 | GombakSelangor | 78 | 10 Mar 20261st sale agreement 10 Mar 2023 | CCC 18 Sep 2025 Handover 9 Feb 2026 | 29 days before |
| VIO BANJ'RANKPKT 9567-28 | SerembanNegeri Sembilan | 40 | 3 Mar 20261st sale agreement 3 Mar 2024 | CCC 30 Dec 2025 Handover 21 Jan 2026 | 41 days before |
| AUSTIN DUTAKPKT 8326-20 | Johor BahruJohor | 135 | 25 Nov 20251st sale agreement 25 Nov 2023 | CCC 14 Nov 2025 Handover 14 Nov 2025 | 11 days before |
| SUTERA @ S2 HEIGHTS AMANKPKT 9567-27 | SerembanNegeri Sembilan | 204 | 27 Dec 20251st sale agreement 27 Dec 2023 | CCC 7 Nov 2025 Handover 14 Nov 2025 | 43 days before |
| SIERRA HIJAUANKPKT 10296-8 | GombakSelangor | 20 | 21 Jul 20261st sale agreement 21 Jul 2023 | CCC 18 Sep 2025 | CCC before deadline; handover not recorded |
| SIERRA HIJAUANKPKT 10296-9 | GombakSelangor | 17 | 25 Aug 20261st sale agreement 25 Aug 2023 | CCC 18 Sep 2025 | CCC before deadline; handover not recorded |
Handed over or certified complete after the deadline — 12 most recent of 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| AYRA TERRACESKPKT 30653-1 | Seberang Perai SelatanPulau Pinang | 100 | 25 Sep 20261st sale agreement 25 Sep 2024 | CCC 7 Oct 2026 Handover 8 Oct 2026 | 13 days after |
| AUSTIN DUTAKPKT 8326-22 | Johor BahruJohor | 130 | 31 May 20261st sale agreement 31 May 2024 | CCC 1 Jul 2026 Handover 2 Jul 2026 | 32 days after |
| THE TERRACES CONDOMINIUMKPKT 6212-4 | Daerah Timor LautPulau Pinang | 410 | 16 Jul 2025Extended 17 months from 16 Feb 20241st sale agreement 16 Feb 2021 | CCC 4 Feb 2026 Handover 25 Feb 2026 | 224 days after |
| ROBIN (FASA 14B)KPKT 12392-21 | Kuala LangatSelangor | 180 | 24 Nov 20231st sale agreement 24 Nov 2021 | CCC 7 Dec 2023 Handover 7 Dec 2023 | 13 days after |
| ROBIN (FASA 14A)KPKT 12392-22 | Kuala LangatSelangor | 128 | 23 Nov 20231st sale agreement 23 Nov 2021 | CCC 7 Dec 2023 Handover 7 Dec 2023 | 14 days after |
| TAMAN ALAM SURIAKPKT 8104-23 | Kuala SelangorSelangor | 119 | 27 Apr 20201st sale agreement 27 Apr 2018 | CCC 11 Aug 2020 | 106 days after † |
| CYPRESS POTENTIAL SDN. BHD.KPKT 13695-2 | Kota TinggiJohor | 95 | 14 May 20201st sale agreement 14 May 2018 | CCC 5 Aug 2020 | 83 days after † |
| BANDAR RIMBAYU SDN BHD (FASA 10 B)KPKT 12392-12 | Kuala LangatSelangor | 98 | 9 Sep 20191st sale agreement 9 Sep 2017 | CCC 25 Sep 2019 | 16 days after |
| SIERRA HIJAUANKPKT 10296-3 | GombakSelangor | 40 | 8 Jan 20191st sale agreement 8 Jan 2016 | CCC 10 Sep 2019 | 245 days after |
| TREHAUS SEMI D VILLAKPKT 6212-2 | Daerah Timor LautPulau Pinang | 26 | 11 Sep 20171st sale agreement 11 Sep 2015 | CCC 8 Mar 2019 | 543 days after |
| SAUJANA DUTAKPKT 9567-14 | SerembanNegeri Sembilan | 76 | 17 Oct 20161st sale agreement 17 Oct 2014 | CCC 29 Mar 2018 | 528 days after |
| AUSTIN DUTAKPKT 8326-8 | Johor BahruJohor | 183 | 29 Jun 20171st sale agreement 29 Jun 2015 | CCC 28 Aug 2017 | 60 days after |
Show all 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| AYRA TERRACESKPKT 30653-1 | Seberang Perai SelatanPulau Pinang | 100 | 25 Sep 20261st sale agreement 25 Sep 2024 | CCC 7 Oct 2026 Handover 8 Oct 2026 | 13 days after |
| AUSTIN DUTAKPKT 8326-22 | Johor BahruJohor | 130 | 31 May 20261st sale agreement 31 May 2024 | CCC 1 Jul 2026 Handover 2 Jul 2026 | 32 days after |
| THE TERRACES CONDOMINIUMKPKT 6212-4 | Daerah Timor LautPulau Pinang | 410 | 16 Jul 2025Extended 17 months from 16 Feb 20241st sale agreement 16 Feb 2021 | CCC 4 Feb 2026 Handover 25 Feb 2026 | 224 days after |
| ROBIN (FASA 14B)KPKT 12392-21 | Kuala LangatSelangor | 180 | 24 Nov 20231st sale agreement 24 Nov 2021 | CCC 7 Dec 2023 Handover 7 Dec 2023 | 13 days after |
| ROBIN (FASA 14A)KPKT 12392-22 | Kuala LangatSelangor | 128 | 23 Nov 20231st sale agreement 23 Nov 2021 | CCC 7 Dec 2023 Handover 7 Dec 2023 | 14 days after |
| TAMAN ALAM SURIAKPKT 8104-23 | Kuala SelangorSelangor | 119 | 27 Apr 20201st sale agreement 27 Apr 2018 | CCC 11 Aug 2020 | 106 days after † |
| CYPRESS POTENTIAL SDN. BHD.KPKT 13695-2 | Kota TinggiJohor | 95 | 14 May 20201st sale agreement 14 May 2018 | CCC 5 Aug 2020 | 83 days after † |
| BANDAR RIMBAYU SDN BHD (FASA 10 B)KPKT 12392-12 | Kuala LangatSelangor | 98 | 9 Sep 20191st sale agreement 9 Sep 2017 | CCC 25 Sep 2019 | 16 days after |
| SIERRA HIJAUANKPKT 10296-3 | GombakSelangor | 40 | 8 Jan 20191st sale agreement 8 Jan 2016 | CCC 10 Sep 2019 | 245 days after |
| TREHAUS SEMI D VILLAKPKT 6212-2 | Daerah Timor LautPulau Pinang | 26 | 11 Sep 20171st sale agreement 11 Sep 2015 | CCC 8 Mar 2019 | 543 days after |
| SAUJANA DUTAKPKT 9567-14 | SerembanNegeri Sembilan | 76 | 17 Oct 20161st sale agreement 17 Oct 2014 | CCC 29 Mar 2018 | 528 days after |
| AUSTIN DUTAKPKT 8326-8 | Johor BahruJohor | 183 | 29 Jun 20171st sale agreement 29 Jun 2015 | CCC 28 Aug 2017 | 60 days after |
| BANDAR PUNCAK ALAMKPKT 8104-17 | Kuala SelangorSelangor | 160 | 16 Jul 20151st sale agreement 16 Jul 2013 | CCC 9 Aug 2017 | 755 days after |
| BANDAR PUNCAK ALAMKPKT 8104-21 | Kuala SelangorSelangor | 116 | 3 Jun 20161st sale agreement 3 Jun 2014 | CCC 12 Apr 2017 | 313 days after |
| THE LIGHT WATERFRONT PENANGKPKT 8140-7 | Daerah Timor LautPulau Pinang | 849 | 12 Oct 20151st sale agreement 12 Oct 2012 | CCC 19 Jan 2017 | 465 days after |
| EPIC PANGSAPURIKPKT 7828-5 | Johor BahruJohor | 528 | 30 Sep 20161st sale agreement 30 Sep 2013 | CCC 12 Oct 2016 | 12 days after |
| PERMATANG SANCTUARYKPKT 6928-9 | Seberang Perai TengahPulau Pinang | 176 | 27 Nov 20141st sale agreement 27 Nov 2012 | CCC 29 Apr 2016 | 519 days after |
| ALAM SURIA (PHASE 5A5-1)KPKT 8104-15 | Kuala SelangorSelangor | 77 | 13 Sep 20151st sale agreement 13 Sep 2013 | CCC 1 Dec 2015 | 79 days after |
| TITIAN TEGAS SDN BHDKPKT 10487-2 | SerembanNegeri Sembilan | 158 | 2 Nov 20151st sale agreement 2 Nov 2013 | CCC 12 Nov 2015 | 10 days after |
| SANCTUARY VILLAKPKT 6928-10 | Seberang Perai TengahPulau Pinang | 136 | 22 Jul 20151st sale agreement 22 Jul 2013 | CCC 8 Oct 2015 | 78 days after |
| SHNG VILLASKPKT 11790-1 | Hulu LangatSelangor | 44 | 28 Mar 20141st sale agreement 28 Mar 2012 | CCC 5 May 2015 | 403 days after |
| ALAM SURIA (PHASE 5A4)KPKT 8104-13 | Kuala SelangorSelangor | 332 | 15 Mar 20141st sale agreement 15 Mar 2012 | CCC 22 Apr 2015 | 403 days after |
| IJM PROPERTIES SDN BHDKPKT 8326-7 | Daerah Timor LautPulau Pinang | 505 | 7 Mar 20151st sale agreement 7 Mar 2012 | CFO 25 Mar 2015 | 18 days after |
Show all 214 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| AYRA TERRACESKPKT 30653-1 | Seberang Perai SelatanPulau Pinang | 100 | 25 Sep 20261st sale agreement 25 Sep 2024 | CCC 7 Oct 2026 Handover 8 Oct 2026 | 13 days after |
| AUSTIN DUTAKPKT 8326-24 | Johor BahruJohor | 58 | 23 Nov 20261st sale agreement 23 Nov 2024 | CCC 20 Aug 2026 Handover 20 Aug 2026 | 95 days before |
| AUSTIN DUTAKPKT 8326-22 | Johor BahruJohor | 130 | 31 May 20261st sale agreement 31 May 2024 | CCC 1 Jul 2026 Handover 2 Jul 2026 | 32 days after |
| S2 HEIGHTS NOVAKPKT 9567-29 | SerembanNegeri Sembilan | 70 | 13 Jul 20261st sale agreement 13 Jul 2024 | CCC 5 Jun 2026 Handover 23 Jun 2026 | 20 days before |
| SIERRA HIJAUAN FASA 2EKPKT 10296-6 | GombakSelangor | 25 | 10 Mar 20261st sale agreement 10 Mar 2023 | CCC 18 Sep 2025 Handover 3 Mar 2026 | 7 days before |
| THE TERRACES CONDOMINIUMKPKT 6212-4 | Daerah Timor LautPulau Pinang | 410 | 16 Jul 2025Extended 17 months from 16 Feb 20241st sale agreement 16 Feb 2021 | CCC 4 Feb 2026 Handover 25 Feb 2026 | 224 days after |
| SIERRA HIJAUANKPKT 10296-7 | GombakSelangor | 78 | 10 Mar 20261st sale agreement 10 Mar 2023 | CCC 18 Sep 2025 Handover 9 Feb 2026 | 29 days before |
| VIO BANJ'RANKPKT 9567-28 | SerembanNegeri Sembilan | 40 | 3 Mar 20261st sale agreement 3 Mar 2024 | CCC 30 Dec 2025 Handover 21 Jan 2026 | 41 days before |
| AUSTIN DUTAKPKT 8326-20 | Johor BahruJohor | 135 | 25 Nov 20251st sale agreement 25 Nov 2023 | CCC 14 Nov 2025 Handover 14 Nov 2025 | 11 days before |
| SUTERA @ S2 HEIGHTS AMANKPKT 9567-27 | SerembanNegeri Sembilan | 204 | 27 Dec 20251st sale agreement 27 Dec 2023 | CCC 7 Nov 2025 Handover 14 Nov 2025 | 43 days before |
| SIERRA HIJAUANKPKT 10296-8 | GombakSelangor | 20 | 21 Jul 20261st sale agreement 21 Jul 2023 | CCC 18 Sep 2025 | CCC before deadline; handover not recorded |
| SIERRA HIJAUANKPKT 10296-9 | GombakSelangor | 17 | 25 Aug 20261st sale agreement 25 Aug 2023 | CCC 18 Sep 2025 | CCC before deadline; handover not recorded |
| AVELAKPKT 12392-27 | Kuala LangatSelangor | 145 | 25 Sep 20251st sale agreement 25 Sep 2023 | CCC 7 Jul 2025 Handover 11 Sep 2025 | 14 days before |
| AVELAKPKT 12392-25 | Kuala LangatSelangor | 136 | 22 Aug 20251st sale agreement 22 Aug 2023 | CCC 7 Jul 2025 Handover 15 Aug 2025 | 7 days before |
| AVELAKPKT 12392-26 | Kuala LangatSelangor | 164 | 25 Aug 20251st sale agreement 25 Aug 2023 | CCC 7 Jul 2025 Handover 15 Aug 2025 | 10 days before |
| SANCTUARY SURIAKPKT 6928-18 | Seberang Perai TengahPulau Pinang | 20 | 29 Dec 20251st sale agreement 29 Dec 2023 | CCC 6 Jun 2025 Handover 12 Jun 2025 | 200 days before |
| AUSTIN DUTAKPKT 8326-19 | Johor BahruJohor | 125 | 8 Jun 20251st sale agreement 8 Jun 2023 | CCC 28 Mar 2025 Handover 11 Apr 2025 | 58 days before |
| SAVVY @ RIANA DUTAMASKPKT 19221-2Savvy @ Riana Dutamas · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 921 | 29 Apr 2025Extended 17 months from 29 Nov 20231st sale agreement 29 Nov 2020 | CCC 3 Oct 2024 Handover 1 Nov 2024 | 179 days before |
| ARENAKPKT 6516-43 | SerembanNegeri Sembilan | 96 | 18 Oct 20241st sale agreement 18 Oct 2022 | CCC 9 Sep 2024 Handover 23 Sep 2024 | 25 days before |
| SIERRA HIJAUANKPKT 10296-5 | GombakSelangor | 80 | 27 Aug 20241st sale agreement 27 Aug 2021 | CCC 11 Mar 2024 Handover 9 Aug 2024 | 18 days before |
| AUSTIN DUTAKPKT 8326-16 | Johor BahruJohor | 110 | 15 Jun 20241st sale agreement 15 Jun 2022 | CCC 4 Jun 2024 Handover 5 Jun 2024 | 10 days before |
| PANGSAPURI DUTA PERINTISKPKT 8104-28 | Kuala SelangorSelangor | 316 | 25 Jan 2025Extended 11 months from 25 Feb 20241st sale agreement 25 Feb 2021 | CCC 27 Mar 2024 | CCC before deadline; handover not recorded |
| SIERRA HIJAUANKPKT 10296-4 | GombakSelangor | 50 | 31 May 20241st sale agreement 31 May 2021 | CCC 11 Mar 2024 | CCC before deadline; handover not recorded |
| ROBIN (FASA 14C)KPKT 12392-24 | Kuala LangatSelangor | 132 | 22 Dec 20231st sale agreement 22 Dec 2021 | CCC 14 Dec 2023 Handover 15 Dec 2023 | 7 days before |
| ROBIN (FASA 14D)KPKT 12392-23 | Kuala LangatSelangor | 175 | 15 Dec 20231st sale agreement 15 Dec 2021 | CCC 14 Dec 2023 Handover 14 Dec 2023 | 1 day before |
| ROBIN (FASA 14B)KPKT 12392-21 | Kuala LangatSelangor | 180 | 24 Nov 20231st sale agreement 24 Nov 2021 | CCC 7 Dec 2023 Handover 7 Dec 2023 | 13 days after |
| ROBIN (FASA 14A)KPKT 12392-22 | Kuala LangatSelangor | 128 | 23 Nov 20231st sale agreement 23 Nov 2021 | CCC 7 Dec 2023 Handover 7 Dec 2023 | 14 days after |
| SANCTUARY TERRACEKPKT 6928-17 | Seberang Perai TengahPulau Pinang | 95 | 14 Nov 20231st sale agreement 14 Nov 2021 | CCC 17 Oct 2023 Handover 20 Oct 2023 | 25 days before |
| RIMBUN AMANKPKT 9567-25 | SerembanNegeri Sembilan | 120 | 26 Oct 20231st sale agreement 26 Oct 2021 | CCC 10 Aug 2023 Handover 4 Oct 2023 | 22 days before |
| RIMBUN AMANKPKT 9567-24 | SerembanNegeri Sembilan | 184 | 24 Aug 20231st sale agreement 24 Aug 2021 | CCC 10 Aug 2023 Handover 11 Aug 2023 / 14 Aug 2023 | 10 days before |
| STARLING (FASA 12D)KPKT 12392-20 | Kuala LangatSelangor | 183 | 22 Jun 2023Extended 5 months from 22 Jan 20231st sale agreement 22 Jan 2021 | CCC 9 Jun 2023 Handover 19 Jun 2023 | 3 days before |
| RIMBUN KIARAKPKT 6516-42 | SerembanNegeri Sembilan | 145 | 31 May 20231st sale agreement 31 May 2021 | CCC 23 May 2023 Handover 30 May 2023 | 1 day before |
| RIMBUN KIARAKPKT 6516-41 | SerembanNegeri Sembilan | 110 | 27 Sep 2023Extended 5 months from 27 Apr 20231st sale agreement 27 Apr 2021 | CCC 23 May 2023 | CCC before deadline; handover not recorded |
| STARLING (FASA 12C)KPKT 12392-19 | Kuala LangatSelangor | 224 | 16 Mar 2023Extended 5 months from 16 Oct 20221st sale agreement 16 Oct 2020 | CCC 16 Mar 2023 Handover 16 Mar 2023 | On the deadline |
| RB LAND SDN. BHD.KPKT 6516-40 | SerembanNegeri Sembilan | 129 | 9 Mar 2023Extended 5 months from 9 Oct 20221st sale agreement 9 Oct 2020 | CCC 1 Mar 2023 Handover 9 Mar 2023 | On the deadline |
| RIMBUN IMPIAN FASA 2KPKT 9567-23 | SerembanNegeri Sembilan | 144 | 28 Mar 2023Extended 5 months from 28 Oct 20221st sale agreement 28 Oct 2020 | CCC 19 Jan 2023 Handover 31 Jan 2023 | 56 days before |
| STARLING (FASA 12B)KPKT 12392-17 | Kuala LangatSelangor | 148 | 11 Jan 2023Extended 5 months from 11 Aug 20221st sale agreement 11 Aug 2020 | CCC 9 Jan 2023 Handover 9 Jan 2023 | 2 days before |
| STARLING (FASA 12A)KPKT 12392-18 | Kuala LangatSelangor | 125 | 24 Nov 2022Extended 5 months from 24 Jun 20221st sale agreement 24 Jun 2020 | CCC 17 Nov 2022 Handover 22 Nov 2022 | 2 days before |
| RIMBUN IMPIANKPKT 9567-22 | SerembanNegeri Sembilan | 201 | 12 Nov 2022Extended 11 months from 12 Dec 20211st sale agreement 12 Dec 2019 | CCC 30 Sep 2022 Handover 30 Sep 2022 | 43 days before |
| TAMAN ALAM SURIAKPKT 8104-27 | Kuala SelangorSelangor | 127 | 14 Apr 2023Extended 11 months from 14 May 20221st sale agreement 14 May 2020 | CCC 28 Jul 2022 Handover 12 Aug 2022 | 245 days before |
| BANDAR RIMBAYU SDN BHD (FASA 8A1)KPKT 12392-13 | Kuala LangatSelangor | 180 | 1 Jul 2022Extended 11 months from 31 Jul 20211st sale agreement 31 Jul 2018 | CCC 24 Nov 2021 Handover 15 Jun 2022 | 16 days before |
| SURIAKPKT 13695-3 | Kota TinggiJohor | 84 | 30 Mar 2022Extended 6 months from 30 Sep 20211st sale agreement 30 Sep 2019 | CCC 10 Mar 2022 Handover 11 Mar 2022 | 19 days before |
| AUSTIN DUTAKPKT 8326-15 | Johor BahruJohor | 140 | 12 Aug 2022Extended 11 months from 12 Sep 20211st sale agreement 12 Sep 2019 | CCC 22 Feb 2022 Handover 23 Feb 2022 | 170 days before |
| SANCTUARY VILLAGEKPKT 6928-15 | Seberang Perai TengahPulau Pinang | 8 | 21 Jun 20231st sale agreement 21 Jun 2021 | CCC 12 Dec 2021 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 11)KPKT 12392-15 | Kuala LangatSelangor | 111 | 2 Mar 2022Extended 6 months from 30 Aug 20211st sale agreement 30 Aug 2019 | CCC 26 Nov 2021 | CCC before deadline; handover not recorded |
| TAMAN ALAM SURIAKPKT 8104-26 | Kuala SelangorSelangor | 82 | 26 Dec 2021Extended 6 months from 26 Jun 20211st sale agreement 26 Jun 2019 | CCC 19 Nov 2021 | CCC before deadline; handover not recorded |
| AUSTIN DUTAKPKT 8326-14 | Johor BahruJohor | 123 | 11 Apr 2022Extended 10 months from 11 Jun 20211st sale agreement 11 Jun 2019 | CCC 1 Nov 2021 | CCC before deadline; handover not recorded |
| 3 RESIDENCEKPKT 8140-9 | Daerah Timor LautPulau Pinang | 478 | 24 Mar 2023Extended 18 months from 24 Sep 20211st sale agreement 24 Sep 2018 | CCC 25 Oct 2021 | CCC before deadline; handover not recorded |
| SANCTUARY VILLAGEKPKT 6928-16 | Seberang Perai TengahPulau Pinang | 32 | 22 Aug 20221st sale agreement 22 Aug 2020 | CCC 18 Oct 2021 | CCC before deadline; handover not recorded |
| RIANA DUTAMASKPKT 19221-1 | Kuala LumpurWP Kuala Lumpur | 1,018 | 22 Oct 2022Extended 22 months from 22 Dec 20201st sale agreement 22 Dec 2017 | CCC 30 Aug 2021 | CCC before deadline; handover not recorded |
| AUSTIN DUTAKPKT 8326-13 | Johor BahruJohor | 100 | 20 Sep 2021Extended 6 months from 20 Mar 20211st sale agreement 20 Mar 2019 | CCC 31 May 2021 | CCC before deadline; handover not recorded |
| TAMAN ALAM SURIAKPKT 8104-24 | Kuala SelangorSelangor | 170 | 14 Jan 2022Extended 10 months from 14 Mar 20211st sale agreement 14 Mar 2019 | CCC 24 May 2021 | CCC before deadline; handover not recorded |
| SAFIRA APARTMENTKPKT 6516-38 | SerembanNegeri Sembilan | 242 | 27 Feb 2022Extended 6 months from 27 Aug 20211st sale agreement 27 Aug 2018 | CCC 10 May 2021 | CCC before deadline; handover not recorded |
| SWANS (FASA 11)KPKT 12392-14 | Kuala LangatSelangor | 84 | 1 Sep 2021Extended 6 months from 1 Mar 20211st sale agreement 1 Mar 2019 | CCC 30 Apr 2021 | CCC before deadline; handover not recorded |
| RIMBUN ALAM, SEREMBAN 2 HEIGHTSKPKT 9567-21 | SerembanNegeri Sembilan | 102 | 8 Nov 2021Extended 6 months from 8 May 20211st sale agreement 8 May 2019 | CCC 19 Mar 2021 | CCC before deadline; handover not recorded |
| ARA IMPIANKPKT 6516-39 | SerembanNegeri Sembilan | 119 | 10 Jul 2021Extended 6 months from 10 Jan 20211st sale agreement 10 Jan 2019 | CCC 17 Dec 2020 | CCC before deadline; handover not recorded |
| TAMAN ALAM SURIAKPKT 8104-25 | Kuala SelangorSelangor | 96 | 28 May 2021Extended 6 months from 28 Nov 20201st sale agreement 28 Nov 2018 | CCC 3 Dec 2020 | CCC before deadline; handover not recorded |
| RESIDENSI SURIA PANTAIKPKT 13619-3 | Kuala LumpurWP Kuala Lumpur | 896 | —Extended 12 months (date not registered) | CCC 14 Aug 2020 | — |
| TAMAN ALAM SURIAKPKT 8104-23 | Kuala SelangorSelangor | 119 | 27 Apr 20201st sale agreement 27 Apr 2018 | CCC 11 Aug 2020 | 106 days after † |
| CYPRESS POTENTIAL SDN. BHD.KPKT 13695-2 | Kota TinggiJohor | 95 | 14 May 20201st sale agreement 14 May 2018 | CCC 5 Aug 2020 | 83 days after † |
| KONDOMINIUM RIANA SELATANKPKT 6928-12 | Kuala LumpurWP Kuala Lumpur | 536 | 2 Mar 2022Extended 18 months from 30 Aug 20201st sale agreement 30 Aug 2017 | CCC 29 Jul 2020 | CCC before deadline; handover not recorded |
| AUSTIN DUTAKPKT 8326-12 | Johor BahruJohor | 84 | 20 Aug 20201st sale agreement 20 Aug 2018 | CCC 20 May 2020 | CCC before deadline; handover not recorded |
| WATERSIDE RESIDENCEKPKT 8140-8 | Daerah Timor LautPulau Pinang | 256 | 23 Jun 2021Extended 18 months from 23 Dec 20191st sale agreement 23 Dec 2016 | CCC 20 Feb 2020 | CCC before deadline; handover not recorded |
| SEREMBAN TWO HOLDINGS SDN BHDKPKT 9567-20 | SerembanNegeri Sembilan | 105 | 26 Feb 20201st sale agreement 26 Feb 2018 | CCC 4 Dec 2019 | CCC before deadline; handover not recorded |
| SANCTUARY RIDGEKPKT 6928-14 | Seberang Perai TengahPulau Pinang | 208 | 3 Feb 20201st sale agreement 3 Feb 2018 | CCC 18 Nov 2019 | CCC before deadline; handover not recorded |
| AUSTIN DUTAKPKT 8326-11 | Johor BahruJohor | 83 | 30 May 20201st sale agreement 30 May 2018 | CCC 1 Oct 2019 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 10 B)KPKT 12392-12 | Kuala LangatSelangor | 98 | 9 Sep 20191st sale agreement 9 Sep 2017 | CCC 25 Sep 2019 | 16 days after |
| SIERRA HIJAUANKPKT 10296-3 | GombakSelangor | 40 | 8 Jan 20191st sale agreement 8 Jan 2016 | CCC 10 Sep 2019 | 245 days after |
| AUSTIN DUTAKPKT 8326-10 | Johor BahruJohor | 182 | 28 Nov 20191st sale agreement 28 Nov 2017 | CCC 26 Aug 2019 | CCC before deadline; handover not recorded |
| PANTAI SENTRALKPKT 13619-2 | Kuala LumpurWP Kuala Lumpur | 243 | 29 Jun 2019Extended 12 months from 29 Jun 20181st sale agreement 29 Jun 2015 | CCC 26 Jun 2019 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 10 A1)KPKT 12392-10 | Kuala LangatSelangor | 118 | 8 Jun 20191st sale agreement 8 Jun 2017 | CCC 31 May 2019 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 10 A2)KPKT 12392-11 | Kuala LangatSelangor | 130 | 21 Jul 20191st sale agreement 21 Jul 2017 | CCC 31 May 2019 | CCC before deadline; handover not recorded |
| RIMBUN HARMONIKPKT 9567-19 | SerembanNegeri Sembilan | 228 | 17 Jul 20191st sale agreement 17 Jul 2017 | CCC 30 May 2019 | CCC before deadline; handover not recorded |
| PANGSAPURI DANAU PERINTISKPKT 8104-22 | Kuala SelangorSelangor | 252 | 19 Sep 20191st sale agreement 19 Sep 2016 | CCC 7 May 2019 | CCC before deadline; handover not recorded |
| AUSTIN DUTAKPKT 8326-9 | Johor BahruJohor | 132 | 31 May 20191st sale agreement 31 May 2017 | CCC 25 Mar 2019 | CCC before deadline; handover not recorded |
| PANTAI SENTRAL PARKKPKT 13619-1 | Kuala LumpurWP Kuala Lumpur | 211 | 10 Mar 2019Extended 12 months from 10 Mar 20181st sale agreement 10 Mar 2015 | CCC 8 Mar 2019 | CCC before deadline; handover not recorded |
| TREHAUS SEMI D VILLAKPKT 6212-2 | Daerah Timor LautPulau Pinang | 26 | 11 Sep 20171st sale agreement 11 Sep 2015 | CCC 8 Mar 2019 | 543 days after |
| SEREMBAN TWO HOLDINGS SDN BHDKPKT 9567-18 | SerembanNegeri Sembilan | 187 | 9 Mar 20191st sale agreement 9 Mar 2017 | CCC 13 Feb 2019 | CCC before deadline; handover not recorded |
| KALISTA 2 ( BLOCK A)KPKT 6516-37 | SerembanNegeri Sembilan | 208 | 31 May 20191st sale agreement 31 May 2016 | CCC 22 Jan 2019 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 7B2)KPKT 12392-9 | Kuala LangatSelangor | 155 | 23 Nov 20181st sale agreement 23 Nov 2016 | CCC 2 Nov 2018 | CCC before deadline; handover not recorded |
| TITIAN TEGAS SDN BHDKPKT 10487-4 | SerembanNegeri Sembilan | 117 | 2 Jan 20191st sale agreement 2 Jan 2017 | CCC 29 Oct 2018 | CCC before deadline; handover not recorded |
| KALISTA 2KPKT 6516-36 | SerembanNegeri Sembilan | 314 | 2 Sep 20181st sale agreement 2 Sep 2015 | CCC 6 Aug 2018 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 7B1)KPKT 12392-8 | Kuala LangatSelangor | 224 | 15 Jun 20181st sale agreement 15 Jun 2016 | CCC 12 Jun 2018 | CCC before deadline; handover not recorded |
| RIMBUN IRAMA, SEREMBAN 2 HEIGHTSKPKT 9567-17 | SerembanNegeri Sembilan | 183 | 21 Jun 20181st sale agreement 21 Jun 2016 | CCC 6 Apr 2018 | CCC before deadline; handover not recorded |
| SAUJANA DUTAKPKT 9567-14 | SerembanNegeri Sembilan | 76 | 17 Oct 20161st sale agreement 17 Oct 2014 | CCC 29 Mar 2018 | 528 days after |
| BANDAR RIMBAYU SDN BHD (FASA 7A1)KPKT 12392-6 | Kuala LangatSelangor | 132 | 1 Mar 20181st sale agreement 29 Feb 2016 | CCC 30 Jan 2018 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 7A2)KPKT 12392-7 | Kuala LangatSelangor | 114 | 7 Mar 20181st sale agreement 7 Mar 2016 | CCC 30 Jan 2018 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 5)KPKT 12392-5 | Kuala LangatSelangor | 231 | 26 Feb 20181st sale agreement 26 Feb 2015 | CCC 13 Nov 2017 | CCC before deadline; handover not recorded |
| AUSTIN DUTAKPKT 8326-8 | Johor BahruJohor | 183 | 29 Jun 20171st sale agreement 29 Jun 2015 | CCC 28 Aug 2017 | 60 days after |
| RIMBUN VISTAKPKT 9567-16 | SerembanNegeri Sembilan | 202 | 30 Sep 20171st sale agreement 30 Sep 2015 | CCC 11 Aug 2017 | CCC before deadline; handover not recorded |
| BANDAR PUNCAK ALAMKPKT 8104-17 | Kuala SelangorSelangor | 160 | 16 Jul 20151st sale agreement 16 Jul 2013 | CCC 9 Aug 2017 | 755 days after |
| SANCTUARY RESIDENCEKPKT 6928-13 | Seberang Perai TengahPulau Pinang | 218 | 23 Sep 20171st sale agreement 23 Sep 2015 | CCC 27 Jul 2017 | CCC before deadline; handover not recorded |
| BANDAR PUNCAK ALAMKPKT 8104-21 | Kuala SelangorSelangor | 116 | 3 Jun 20161st sale agreement 3 Jun 2014 | CCC 12 Apr 2017 | 313 days after |
| THE LIGHT WATERFRONT PENANGKPKT 8140-7 | Daerah Timor LautPulau Pinang | 849 | 12 Oct 20151st sale agreement 12 Oct 2012 | CCC 19 Jan 2017 | 465 days after |
| CYPRESS POTENTIAL SDN. BHD.KPKT 13695-1 | Kota TinggiJohor | 40 | 31 Dec 20161st sale agreement 31 Dec 2014 | CFO 22 Dec 2016 | CCC before deadline; handover not recorded |
| EPIC PANGSAPURIKPKT 7828-5 | Johor BahruJohor | 528 | 30 Sep 20161st sale agreement 30 Sep 2013 | CCC 12 Oct 2016 | 12 days after |
| SAMIRA 2 & SUMMERSET 2KPKT 9567-15 | SerembanNegeri Sembilan | 45 | 10 Dec 20161st sale agreement 10 Dec 2014 | CCC 25 Aug 2016 | CCC before deadline; handover not recorded |
| BANDAR PUNCAK ALAMKPKT 8104-20 | Kuala SelangorSelangor | 236 | 25 Aug 20161st sale agreement 25 Aug 2014 | CCC 19 Aug 2016 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU SDN BHD (FASA 4)KPKT 12392-4 | Kuala LangatSelangor | 110 | 27 Oct 20161st sale agreement 27 Oct 2014 | CCC 8 Aug 2016 | CCC before deadline; handover not recorded |
| SEREMBAN 2KPKT 6516-35 | SerembanNegeri Sembilan | 208 | 1 Jan 20171st sale agreement 1 Jan 2014 | CCC 21 Jun 2016 | CCC before deadline; handover not recorded |
| PERMATANG SANCTUARYKPKT 6928-9 | Seberang Perai TengahPulau Pinang | 176 | 27 Nov 20141st sale agreement 27 Nov 2012 | CCC 29 Apr 2016 | 519 days after |
| BANDAR RIMBAYU (FASA 3)KPKT 12392-3 | Kuala LangatSelangor | 467 | 16 May 20161st sale agreement 16 May 2014 | CCC 31 Mar 2016 | CCC before deadline; handover not recorded |
| SEREMBAN TWO HOLDING SDN. BHD.KPKT 9567-13 | SerembanNegeri Sembilan | 90 | 6 May 20161st sale agreement 6 May 2014 | CCC 15 Dec 2015 | CCC before deadline; handover not recorded |
| ALAM SURIA (PHASE 5A5-1)KPKT 8104-15 | Kuala SelangorSelangor | 77 | 13 Sep 20151st sale agreement 13 Sep 2013 | CCC 1 Dec 2015 | 79 days after |
| TITIAN TEGAS SDN BHDKPKT 10487-2 | SerembanNegeri Sembilan | 158 | 2 Nov 20151st sale agreement 2 Nov 2013 | CCC 12 Nov 2015 | 10 days after |
| SERI BINJAIKPKT 10487-3 | SerembanNegeri Sembilan | 90 | 6 Aug 20161st sale agreement 6 Aug 2014 | CCC 21 Oct 2015 | CCC before deadline; handover not recorded |
| SANCTUARY VILLAKPKT 6928-10 | Seberang Perai TengahPulau Pinang | 136 | 22 Jul 20151st sale agreement 22 Jul 2013 | CCC 8 Oct 2015 | 78 days after |
| BANDAR RIMBAYU SDN BHD (FASA 2)KPKT 12392-2 | Kuala LangatSelangor | 484 | 13 Aug 20151st sale agreement 13 Aug 2013 | CCC 16 Jul 2015 | CCC before deadline; handover not recorded |
| S2 HEIGHTSKPKT 9567-12 | SerembanNegeri Sembilan | 124 | 2 Dec 20151st sale agreement 2 Dec 2013 | CCC 25 May 2015 | CCC before deadline; handover not recorded |
| SANCTUARY COURTKPKT 6928-11 | Seberang Perai TengahPulau Pinang | 247 | 18 Sep 20161st sale agreement 18 Sep 2013 | CCC 20 May 2015 | CCC before deadline; handover not recorded |
| SHNG VILLASKPKT 11790-1 | Hulu LangatSelangor | 44 | 28 Mar 20141st sale agreement 28 Mar 2012 | CCC 5 May 2015 | 403 days after |
| ALAM SURIA (PHASE 5A4)KPKT 8104-13 | Kuala SelangorSelangor | 332 | 15 Mar 20141st sale agreement 15 Mar 2012 | CCC 22 Apr 2015 | 403 days after |
| TARIKAN ABADI SDN BHDKPKT 10919-10 | Johor BahruJohor | 28 | 30 May 20151st sale agreement 30 May 2013 | CCC 30 Mar 2015 | CCC before deadline; handover not recorded |
| TARIKAN ABADI SDN BHDKPKT 10919-9 | Johor BahruJohor | 28 | 30 May 20151st sale agreement 30 May 2013 | CCC 30 Mar 2015 | CCC before deadline; handover not recorded |
| IJM PROPERTIES SDN BHDKPKT 8326-7 | Daerah Timor LautPulau Pinang | 505 | 7 Mar 20151st sale agreement 7 Mar 2012 | CFO 25 Mar 2015 | 18 days after |
| S2 HEIGHTSKPKT 9567-11 | SerembanNegeri Sembilan | 263 | 3 Jul 20151st sale agreement 3 Jul 2013 | CCC 17 Mar 2015 | CCC before deadline; handover not recorded |
| THE ADDRESSKPKT 7334-3 | Daerah Timor LautPulau Pinang | 148 | 15 Mar 20151st sale agreement 15 Mar 2012 | CCC 10 Mar 2015 | CCC before deadline; handover not recorded |
| BANDAR PUNCAK ALAMKPKT 8104-16 | Kuala SelangorSelangor | 224 | 7 Mar 20151st sale agreement 7 Mar 2013 | CCC 6 Mar 2015 | CCC before deadline; handover not recorded |
| BANDAR RIMBAYU FASA 1KPKT 12392-1 | Kuala LangatSelangor | 518 | 6 Mar 20151st sale agreement 6 Mar 2013 | CCC 24 Feb 2015 | CCC before deadline; handover not recorded |
| ALTITUDE 236KPKT 6928-8 | Kuala LumpurWP Kuala Lumpur | 236 | 18 Nov 20141st sale agreement 18 Nov 2011 | CCC 10 Oct 2014 | CCC before deadline; handover not recorded |
| LAMAN GRANVIEWKPKT 8326-6 | PetalingSelangor | 134 | 2 May 20151st sale agreement 2 May 2013 | CCC 22 Sep 2014 | CCC before deadline; handover not recorded |
| IKATAN FLORA SDN BHDKPKT 11728-1 | Johor BahruJohor | 234 | 19 Oct 20141st sale agreement 19 Oct 2011 | CCC 17 Sep 2014 | CCC before deadline; handover not recorded |
| IKATAN FLORA SDN BHDKPKT 11728-2 | Johor BahruJohor | 234 | 5 Apr 20151st sale agreement 5 Apr 2012 | CCC 17 Sep 2014 | CCC before deadline; handover not recorded |
| IKATAN FLORA SDN BHDKPKT 11728-3 | Johor BahruJohor | 312 | 11 Jul 20151st sale agreement 11 Jul 2012 | CCC 17 Sep 2014 | CCC before deadline; handover not recorded |
| TARIKAN ABADI SDN BHDKPKT 10919-5 | Johor BahruJohor | 328 | 17 Jan 20151st sale agreement 17 Jan 2012 | CCC 28 Aug 2014 | CCC before deadline; handover not recorded |
| S2 HEIGHTSKPKT 9567-10 | SerembanNegeri Sembilan | 176 | 24 Jan 20151st sale agreement 24 Jan 2013 | CCC 11 Jul 2014 | CCC before deadline; handover not recorded |
| TARIKAN ABADI SDN BHDKPKT 10919-8 | Johor BahruJohor | 28 | 19 Oct 20141st sale agreement 19 Oct 2012 | CCC 25 Jun 2014 | CCC before deadline; handover not recorded |
| TARIKAN ABADI SDN BHDKPKT 10919-7 | Johor BahruJohor | 48 | 26 Jul 20141st sale agreement 26 Jul 2012 | CCC 11 Jun 2014 | CCC before deadline; handover not recorded |
| ALAM SURIA (PHASE SEMI-D)KPKT 8104-14 | Kuala SelangorSelangor | 24 | 11 May 20141st sale agreement 11 May 2012 | CCC 31 Mar 2014 | CCC before deadline; handover not recorded |
| S2 HEIGHTSKPKT 9567-7 | SerembanNegeri Sembilan | 230 | — | CCC 27 Dec 2013 | — |
| SURIAMAS SUITES PANGSAPURIKPKT 7828-3 | Johor BahruJohor | 119 | — | CFO 15 Nov 2013 | — |
| TAMAN NUSA DUTAKPKT 10919-4 | Johor BahruJohor | 64 | — | CCC 18 Oct 2013 | — |
| S2 HEIGHTSKPKT 9567-9 | SerembanNegeri Sembilan | 58 | — | CCC 16 Oct 2013 | — |
| BANDAR PUNCAK ALAMKPKT 8104-12 | Kuala SelangorSelangor | 344 | — | CCC 23 Sep 2013 | — |
| SURIAMAS SUITES PANGSAPURIKPKT 7828-4 | Johor BahruJohor | 152 | — | CFO 21 Aug 2013 | — |
| DESA LATANIAKPKT 8326-1 | KlangSelangor | 875 | — | CFO 1 Jan 2013 | — |
| MANDA'RINA SDN BHDKPKT 6928-7 | Kuala LumpurWP Kuala Lumpur | 33 | — | CCC 14 Nov 2012 | — |
| THE LIGHT LINEARKPKT 8140-6 | Daerah Timor LautPulau Pinang | 328 | — | CCC 8 Aug 2012 | — |
| S2 HEIGHTSKPKT 9567-6 | SerembanNegeri Sembilan | 157 | — | CCC 19 Jul 2012 | — |
| TARIKAN ABADI SDN BHDKPKT 10919-3 | Johor BahruJohor | 158 | — | CCC 25 Jun 2012 | — |
| BANDAR PUNCAK ALAMKPKT 8104-11 | Kuala SelangorSelangor | 281 | — | CCC 12 Jun 2012 | — |
| SRI CARCOSA SEMI-DKPKT 6516-32 | SerembanNegeri Sembilan | 46 | — | CFO 8 Mar 2012 | — |
| S2 HEIGHTSKPKT 9567-5 | SerembanNegeri Sembilan | 116 | — | CFO 2 Mar 2012 | — |
| VISION HOMESKPKT 6516-33 | SerembanNegeri Sembilan | 132 | — | CCC 17 Jan 2012 | — |
| S2 HEIGHTSKPKT 9567-4 | SerembanNegeri Sembilan | 18 | — | CFO 20 Sep 2011 | — |
| LAMAN BAIDURIKPKT 3585-4 | PetalingSelangor | 228 | — | CCC 18 Aug 2011 | — |
| TAMAN NUSA DUTAKPKT 10919-2 | Johor BahruJohor | 62 | — | CCC 15 Aug 2011 | — |
| TAMAN NUSA DUTAKPKT 10919-1 | Johor BahruJohor | 199 | — | CCC 24 Jun 2011 | — |
| S2 HEIGHTSKPKT 9567-3 | SerembanNegeri Sembilan | 248 | — | CCC 12 May 2011 | — |
| SUMMER PLACEKPKT 8140-5 | Daerah Timor LautPulau Pinang | 531 | — | CFO 7 Jan 2011 | — |
| PLATINOKPKT 8326-5 | Daerah Timor LautPulau Pinang | 228 | — | CFO 30 Nov 2010 | — |
| BAYU SRI BINTANGKPKT 10487-1 | Kuala LumpurWP Kuala Lumpur | 30 | — | CFO 29 Sep 2010 | — |
| S2 GARDEN CITY HOMESKPKT 9299-2 | SerembanNegeri Sembilan | 361 | — | CFO 21 Aug 2010 | — |
| SERENIA GARDENSKPKT 10296-1 | GombakSelangor | 207 | — | CFO 9 Jun 2010 | — |
| SERENIA GARDENS FASA 1BKPKT 10296-2 | GombakSelangor | 102 | — | CFO 9 Jun 2010 | — |
| SECOND ENCLAVEKPKT 6928-6 | Kuala LumpurWP Kuala Lumpur | 55 | — | CFO 8 Jun 2010 | — |
| SUIRA HEIGHTS PANGSAPURIKPKT 7828-2 | Johor BahruJohor | 522 | — | CFO 24 May 2010 | — |
| BANDAR PUNCAK ALAM ALAM SURIA 3 (5A3)KPKT 8104-10 | Kuala SelangorSelangor | 260 | — | CFO 19 May 2010 | — |
| BUKIT BAYUKPKT 8326-4 | Hulu LangatSelangor | 530 | — | CFO 5 May 2010 | — |
| BANDAR PUNCAK ALAMKPKT 8104-9 | Kuala SelangorSelangor | 338 | — | CFO 7 Apr 2010 | — |
| BANDAR PUNCAK ALAMKPKT 8104-8 | Kuala SelangorSelangor | 261 | — | CFO 11 Dec 2009 | — |
| S2 GARDEN CITY HOMES FASA 5KPKT 9299-5 | SerembanNegeri Sembilan | 72 | — | CCC 16 Nov 2009 | — |
| BUKIT JAMBUL INDAHKPKT 6212-1 | Daerah Timor LautPulau Pinang | 1,079 | — | CFO 2 Nov 2009 | — |
| BAYU SEGARKPKT 10427-1 | Kuala LumpurWP Kuala Lumpur | 100 | — | CFO 23 Oct 2009 | — |
| S2 HEIGHTSKPKT 9567-2 | SerembanNegeri Sembilan | 274 | —Extended 6 months (date not registered) | CFO 25 Aug 2009 | — |
| THE SPRINGKPKT 8140-4 | Daerah Timor LautPulau Pinang | 396 | — | CFO 13 May 2009 | — |
| S2 GARDEN CITY HOMESKPKT 9299-4 | SerembanNegeri Sembilan | 264 | — | CFO 23 Mar 2009 | — |
| TAMAN IDAMANKPKT 6928-5 | Seberang Perai SelatanPulau Pinang | 170 | — | CFO 26 Feb 2009 | — |
| DESA PINANG 2KPKT 8140-3 | Daerah Timor LautPulau Pinang | 1,324 | — | CFO 15 Jan 2009 | — |
| 10 BAIDURIKPKT 3585-3 | PetalingSelangor | 10 | — | CFO 8 Oct 2008 | — |
| VISION HOMESKPKT 6516-31 | SerembanNegeri Sembilan | 364 | — | CFO 29 Jul 2008 | — |
| TAMAN JAWAKPKT 8326-2 | Seberang Perai UtaraPulau Pinang | 140 | — | CFO 16 Jul 2008 | — |
| S2 HEIGHTSKPKT 9567-1 | SerembanNegeri Sembilan | 214 | — | CFO 10 Jul 2008 | — |
| GARDEN AVENUE - APARTMEN KOS RENDAHKPKT 6516-24 | SerembanNegeri Sembilan | 678 | — | CFO 21 Dec 2007 | — |
| NAUTILUS BAYKPKT 8140-2 | Daerah Timor LautPulau Pinang | 78 | — | CFO 12 Dec 2007 | — |
| S2 GARDEN CITY HOMESKPKT 9299-3 | SerembanNegeri Sembilan | 354 | — | CFO 12 Dec 2007 | — |
| BUKIT MANDA RINAKPKT 6928-3 | Kuala LumpurWP Kuala Lumpur | 88 | — | CFO 17 Sep 2007 | — |
| BAYSWATER RESORT CONDOMINIUMKPKT 8326-3 | Daerah Timor LautPulau Pinang | 396 | — | CFO 22 May 2007 | — |
| TAMAN IDAMANKPKT 6928-2 | Seberang Perai SelatanPulau Pinang | 504 | — | CFO 18 Jan 2007 | — |
| BOULEVARD SUBANG JAYAKPKT 3585-2 | PetalingSelangor | 384 | — | CFO 20 Jul 2006 | — |
| S2 GARDEN CITY HOMESKPKT 9299-1 | SerembanNegeri Sembilan | 244 | — | CFO 23 May 2006 | — |
| VISIONS HOMES FASA 2KPKT 6516-30 | SerembanNegeri Sembilan | 208 | — | CFO 14 Mar 2006 | — |
| FASA 2B6 BANDAR BARU PUNCAK ALAMKPKT 8104-6 | Kuala SelangorSelangor | 152 | — | CFO 16 Feb 2006 | — |
| PARK AVENUE FASA 2, SEREMBAN 2.KPKT 6516-25 | SerembanNegeri Sembilan | 184 | — | CFO 5 Jul 2005 | — |
| PARK AVENUE FASA 1CKPKT 6516-21 | SerembanNegeri Sembilan | 129 | — | CFO 29 Dec 2004 | — |
| VISION HOMES FASA 1KPKT 6516-28 | SerembanNegeri Sembilan | 320 | — | CFO 2 Nov 2004 | — |
| EMERALD PARK SEMI - DKPKT 6516-29 | SerembanNegeri Sembilan | 12 | — | CFO 16 Sep 2004 | — |
| EMERALD PARK FASA 2KPKT 6516-22 | SerembanNegeri Sembilan | 109 | — | CFO 11 May 2004 | — |
| PARK AVENUE FASA 1B, SEREMBAN 2.KPKT 6516-20 | SerembanNegeri Sembilan | 107 | — | CFO 11 Feb 2004 | — |
| PARK AVENUE FASA 1AKPKT 6516-19 | SerembanNegeri Sembilan | 96 | — | CFO 13 Nov 2003 | — |
| SEREMBAN 2 - EMERALD PARK FASA 1KPKT 6516-18 | SerembanNegeri Sembilan | 100 | — | CFO 13 Jun 2003 | — |
| BANDAR BARU PUNCAK ALAM FASA 2B3KPKT 8104-3 | Kuala SelangorSelangor | 188 | — | CFO 23 May 2003 | — |
| BANDAR BARU PUNCAK ALAM - FASA 2B1KPKT 8104-1 | Kuala SelangorSelangor | 222 | — | CFO 31 Mar 2003 | — |
| BANDAR BARU PUNCAK ALAM - FASA 2B2KPKT 8104-2 | Kuala SelangorSelangor | 232 | — | CFO 31 Mar 2003 | — |
| SEREMBAN 2 AFFORDABLE HOMES FASA 2KPKT 6516-14 | SerembanNegeri Sembilan | 398 | — | CFO 14 Mar 2003 | — |
| GARDEN AVENUE FASA 4KPKT 6516-16 | SerembanNegeri Sembilan | 217 | — | CFO 1 Aug 2002 | — |
| GARDEN AVENUE FASA 5KPKT 6516-17 | SerembanNegeri Sembilan | 127 | — | CFO 1 Aug 2002 | — |
| SEREMBAN 2 (FASA 2B)KPKT 6516-2 | Tiada Maklumat DaerahNegeri Sembilan | 351 | — | CFO 27 Jun 2002 | — |
| SEREMBAN 2 AFFORDABLE HOMES (FASA I)KPKT 6516-10 | SerembanNegeri Sembilan | 331 | — | CFO 13 May 2002 | — |
| SEREMBAN 2 AFFORDABLE HOMES FASA 1KPKT 6516-13 | SerembanNegeri Sembilan | 478 | — | CFO 12 Oct 2001 | — |
| GARDEN HOMES FASA 4KPKT 6516-15 | SerembanNegeri Sembilan | 119 | — | CFO 4 Sep 2001 | — |
| SEREMBAN 2 GARDEN HOMES FASA 3AKPKT 6516-7 | Tiada Maklumat DaerahNegeri Sembilan | 192 | — | CFO 28 Jul 2001 | — |
| SEREMBAN 2, AFFORDABLE HOMES (FASA 3)KPKT 6516-12 | SerembanNegeri Sembilan | 117 | — | CFO 17 Jul 2001 | — |
| SEREMBAN 2 FASA 1KPKT 6516-1 | SerembanNegeri Sembilan | 731 | — | CFO 20 Jun 2001 | — |
| SEREMBAN 2 GARDEN HOMES FASA 3BKPKT 6516-8 | SerembanNegeri Sembilan | 133 | — | CFO 5 Mar 2001 | — |
| SEREMBAN 2 GARDEN HOMES FASA 3CKPKT 6516-9 | SerembanNegeri Sembilan | 240 | — | CFO 5 Mar 2001 | — |
| SEREMBAN 2 GARDEN HOMES FASA 2 (JASMINE)KPKT 6516-6 | SerembanNegeri Sembilan | 556 | — | CFO 13 Jan 2001 | — |
| GARDEN HOMES FASA IKPKT 6516-5 | SerembanNegeri Sembilan | 345 | — | CFO 12 Dec 2000 | — |
| TAMAN IDAMAN SIMPANG AMPATKPKT 6928-1 | Seberang Perai SelatanPulau Pinang | 348 | — | CFO 29 Feb 2000 | — |
| FASA 1 "AFFORDABLE HOMES" SEREMBAN 2KPKT 6516-4 | SerembanNegeri Sembilan | 116 | — | CFO 13 Apr 1999 | — |
| SEREMBAN 2 CENTRAL PARK II FASA 1A 1KPKT 6516-3 | SerembanNegeri Sembilan | 168 | — | CFO 29 Aug 1998 | — |
| Pangsapuri PantaiKPKT 6016-1 | Seberang Perai UtaraPulau Pinang | 144 | — | CFO 26 Nov 1996 | — |
| SRI CARCOSA BUNGALOWSKPKT 6516-27 | SerembanNegeri Sembilan | 178 | 1 Jun 20151st sale agreement 1 Jun 2013 | — | — |
| PARK AVENUEKPKT 6516-26 | SerembanNegeri Sembilan | 298 | — | — | — |
Under construction (25) and not yet started (1) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| AUSTIN DUTAKPKT 8326-26 | Johor BahruJohor | 117 | DelayLate | 21 Feb 20271st sale agreement 21 Feb 2025 | 82% |
| AUSTIN DUTAKPKT 8326-27 | Johor BahruJohor | 75 | DelayLate | 22 Feb 20271st sale agreement 22 Feb 2025 | 82% |
| BATIQ @ S2 HEIGHTS AMAN - PHASE 1KPKT 9567-31 | SerembanNegeri Sembilan | 82 | SmoothOn schedule | 2 Mar 20271st sale agreement 2 Mar 2025 | 97% |
| S2 HEIGHTS NOVA - PHASE 2KPKT 9567-30 | SerembanNegeri Sembilan | 88 | SmoothOn schedule | 10 Mar 20271st sale agreement 10 Mar 2025 | 90% |
| LAMAN GRANVIEWKPKT 8326-21 | PetalingSelangor | 35 | SmoothOn schedule | 13 Mar 2027Extended 12 months from 13 Mar 20261st sale agreement 13 Mar 2024 | 88–92% |
| AMBANG SURIAKPKT 8104-30 | Kuala SelangorSelangor | 142 | SmoothOn schedule | 14 Mar 20271st sale agreement 14 Mar 2025 | 75% |
| RESIDENSI PANTAI SENTRAL 3KPKT 13619-4Riana Trees Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 336 | SmoothOn schedule | 23 Mar 2027Extended 12 months from 23 Mar 20261st sale agreement 23 Mar 2023 | 91% |
| LAMAN GRANVIEWKPKT 8326-18 | PetalingSelangor | 38 | SmoothOn schedule | 28 Jun 2027Extended 12 months from 28 Jun 20261st sale agreement 28 Jun 2024 | 86% |
| LAMAN GRANVIEWKPKT 8326-23 | PetalingSelangor | 11 | SmoothOn schedule | 26 Jul 2027Extended 6 months from 26 Jan 20271st sale agreement 26 Jan 2025 | 90% |
| AUSTIN DUTAKPKT 8326-28 | Johor BahruJohor | 60 | SmoothOn schedule | 23 Aug 20271st sale agreement 23 Aug 2025 | 60% |
| SUTERA - PHASE 2 @ S2 HEIGHTS AMANKPKT 9567-32 | SerembanNegeri Sembilan | 104 | SmoothOn schedule | 21 Nov 20271st sale agreement 21 Nov 2025 | 98% |
| AUSTIN DUTAKPKT 8326-25 | Johor BahruJohor | 80 | SmoothOn schedule | 22 Feb 20281st sale agreement 22 Feb 2026 | 88% |
Show all 26 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| AUSTIN DUTAKPKT 8326-26 | Johor BahruJohor | 117 | DelayLate | 21 Feb 20271st sale agreement 21 Feb 2025 | 82% |
| AUSTIN DUTAKPKT 8326-27 | Johor BahruJohor | 75 | DelayLate | 22 Feb 20271st sale agreement 22 Feb 2025 | 82% |
| BATIQ @ S2 HEIGHTS AMAN - PHASE 1KPKT 9567-31 | SerembanNegeri Sembilan | 82 | SmoothOn schedule | 2 Mar 20271st sale agreement 2 Mar 2025 | 97% |
| S2 HEIGHTS NOVA - PHASE 2KPKT 9567-30 | SerembanNegeri Sembilan | 88 | SmoothOn schedule | 10 Mar 20271st sale agreement 10 Mar 2025 | 90% |
| LAMAN GRANVIEWKPKT 8326-21 | PetalingSelangor | 35 | SmoothOn schedule | 13 Mar 2027Extended 12 months from 13 Mar 20261st sale agreement 13 Mar 2024 | 88–92% |
| AMBANG SURIAKPKT 8104-30 | Kuala SelangorSelangor | 142 | SmoothOn schedule | 14 Mar 20271st sale agreement 14 Mar 2025 | 75% |
| RESIDENSI PANTAI SENTRAL 3KPKT 13619-4Riana Trees Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 336 | SmoothOn schedule | 23 Mar 2027Extended 12 months from 23 Mar 20261st sale agreement 23 Mar 2023 | 91% |
| LAMAN GRANVIEWKPKT 8326-18 | PetalingSelangor | 38 | SmoothOn schedule | 28 Jun 2027Extended 12 months from 28 Jun 20261st sale agreement 28 Jun 2024 | 86% |
| LAMAN GRANVIEWKPKT 8326-23 | PetalingSelangor | 11 | SmoothOn schedule | 26 Jul 2027Extended 6 months from 26 Jan 20271st sale agreement 26 Jan 2025 | 90% |
| AUSTIN DUTAKPKT 8326-28 | Johor BahruJohor | 60 | SmoothOn schedule | 23 Aug 20271st sale agreement 23 Aug 2025 | 60% |
| SUTERA - PHASE 2 @ S2 HEIGHTS AMANKPKT 9567-32 | SerembanNegeri Sembilan | 104 | SmoothOn schedule | 21 Nov 20271st sale agreement 21 Nov 2025 | 98% |
| AUSTIN DUTAKPKT 8326-25 | Johor BahruJohor | 80 | SmoothOn schedule | 22 Feb 20281st sale agreement 22 Feb 2026 | 88% |
| ANTHEA RIMBAYUKPKT 12392-28 | Kuala LangatSelangor | 180 | SmoothOn schedule | 26 Feb 20281st sale agreement 26 Feb 2025 | 55% |
| LAMAN GRANVIEWKPKT 8326-29 | PetalingSelangor | 16 | SmoothOn schedule | 28 Feb 20281st sale agreement 28 Feb 2026 | 20% |
| RESIDENSI DAFFODILKPKT 8104-29 | Kuala SelangorSelangor | 354 | SmoothOn schedule | 14 Mar 2028Extended 12 months from 14 Mar 20271st sale agreement 14 Mar 2024 | 70% |
| ENLACE @ PANTAI SENTRAL PARKKPKT 13619-5Enlace Suite @ Pantai Sentral Park · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 438 | SmoothOn schedule | 15 Sep 2029Extended 18 months from 15 Mar 20281st sale agreement 15 Mar 2025 | 20% |
| RESIDENSI RIANA DUTAMAS 3KPKT 19221-3Stellaris @ Riana Dutamas · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,143 | SmoothOn schedule | 23 Oct 2029Extended 16 months from 23 Jun 20281st sale agreement 23 Jun 2025 | 20% |
| IKON RESIDENSIKPKT 6516-44 | SerembanNegeri Sembilan | 778 | SmoothOn schedule | 15 Dec 2029Extended 12 months from 15 Dec 20281st sale agreement 15 Dec 2025 | 20% |
| MERIONEKPKT 8140-10 | Pulau Pinang | 145 | SmoothOn schedule | 4 Feb 2030Extended 12 months from 4 Feb 20291st sale agreement 4 Feb 2026 | 22% |
| ENLACE, PANTAI SENTRAL PARKKPKT 13619-6 | WP Kuala Lumpur | 290 | SmoothOn schedule | 18 Apr 2030Extended 12 months from 18 Apr 20291st sale agreement 18 Apr 2026 | 20% |
| ESRA RESIDENCESKPKT 30653-2 | Pulau Pinang | 92 | SmoothOn schedule | — | 5–7% |
| LAMAN GRANVIEWKPKT 8326-17 | PetalingSelangor | 26 | SmoothOn schedule | —Extended 12 months (date not registered) | 5% |
| AUSTIN DUTAKPKT 8326-30 | Johor BahruJohor | 76 | SmoothOn schedule | — | 5% |
| AMBANG SURIAKPKT 8104-31 | Kuala SelangorSelangor | 48 | SmoothNot started | — | 0% |
| AMBANG SURIAKPKT 8104-32 | Kuala SelangorSelangor | 122 | SmoothOn schedule | — | 37% |
| NUSA DUTAKPKT 10919-11 | Johor BahruJohor | 52 | SmoothOn schedule | — | 5% |
Permit cancelled or other KPKT status (3)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TREHAUS CONDO VILLAKPKT 6212-3 | Daerah Timor LautPulau Pinang | 46 | Permit cancelledPermit cancelled | — | 100% |
| SKIM PANGSAPURI RUMAH SELANGORKU (FASA 8A2)KPKT 12392-16 | Kuala LangatSelangor | 180 | Permit cancelledPermit cancelled | — | 0% |
| SAUJANA INTANKPKT 9567-26 | SerembanNegeri Sembilan | 42 | Permit cancelledPermit cancelled | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
IJM Land at a glance
| Listed | IJM Land itself is not listed (delisted 15 April 2015); its parent IJM Corporation Berhad is on Bursa Malaysia's Main Market · IJM (3336) · listed 1986[1][2][6] |
|---|---|
| Started | Parent IJM Corporation formed in 1983; IJM Land wholly owned by it since the 2015 privatisation[1][2] |
| Head office | Wisma IJM, Petaling Jaya, Selangor[1] |
| Leadership | Datuk Johan Idris — Chairman of IJM Corporation (appointed October 2026)[5] Dato' Lee Chun Fai — Group Chief Executive Officer and Managing Director, IJM Corporation[1] Dato' Ling Thou Lung — Chief Executive Officer, IJM Land (since 1 November 2024)[1] |
| Companies in the KPKT register | RB LAND SDN. BHD. KPKT 6516[1] SEREMBAN TWO HOLDINGS SDN. BHD. KPKT 9567[1] IJM PROPERTIES SDN. BHD. KPKT 8326[1] BANDAR RIMBAYU SDN. BHD. KPKT 12392[1] SHAH ALAM 2 SDN. BHD. KPKT 8104[1] MANDA'RINA SDN. BHD. KPKT 6928[1] TARIKAN ABADI SDN. BHD. KPKT 10919[1] JELUTONG DEVELOPMENT SDN. BHD. (80%) KPKT 8140[1] SIERRA UKAY SDN. BHD. KPKT 10296[1] SEREMBAN TWO PROPERTIES SDN. BHD. KPKT 9299[1] SURIA BISTARI DEVELOPMENT SDN. BHD. (51%) KPKT 7828[1] WORLDWIDE VENTURES SDN. BHD. (86%) KPKT 6212[1] CYPRESS POTENTIAL SDN. BHD. (70%) KPKT 13695[1] EMKO PR0PERTIES SDN. BHD. KPKT 3585[1] CHEN YU LAND SDN. BHD. KPKT 30653[1] DIAN WARNA SDN. BHD. KPKT 10427[1] ISLAND GOLF VIEW SDN. BHD. (86%) KPKT 7334[1] TITIAN TEGAS SDN. BHD. KPKT 10487[1] IKATAN FLORA SDN. BHD. KPKT 11728[1] VALENCIA TERRACE SDN. BHD. KPKT 11790[1] IJM CORPORATION BHD KPKT 6016[1] 368 SEGAMBUT SDN. BHD. (50%) KPKT 19221[1][4] AMONA DEVELOPMENT SDN. BHD. KPKT 13619[3][1] |
| Website | ijmland.com |
| Property pipeline (company figure) | Gross development value of RM47.74 billion across a 3,155.3-acre landbank, at 31 March 2026[1] |
| Listing history | IJM Land was delisted from Bursa Malaysia on 15 April 2015 after IJM Corporation privatised it[2] |
| Riana Dutamas, Segambut | Developed by 368 Segambut Sdn Bhd, a joint venture of FCW Holdings Bhd and IJM Land; IJM's effective interest 50%[4][1] |
| Pantai Sentral Park, Kuala Lumpur | 58-acre master development; IJM Land develops it through a joint development with the Amona Group[3] |
IJM Land projects on sale on PropertySifu
Enlace Suite @ Pantai Sentral Park
- PANTAI SENTRAL — 0.3 km, 2019
- PANTAI SENTRAL PARK — 0.4 km, 2019
- RESIDENSI SURIA PANTAI — 1.0 km, 2020
Riana Trees Residences
- RESIDENSI SURIA PANTAI — 1.2 km, 2020
- KONDOMINIUM RIANA SELATAN — 8.0 km, 2020
Who is IJM Land? The company behind the projects
IJM Land Berhad is the property arm of IJM Corporation Berhad, which was formed in 1983 and listed on the Kuala Lumpur Stock Exchange in 1986 [1]; IJM trades on Bursa Malaysia's Main Market under stock code 3336 [1]. IJM Land itself was listed until IJM Corporation privatised it, and its shares were removed from Bursa Malaysia on 15 April 2015 [2]; it is now wholly owned [1]. A voluntary takeover offer for IJM made by Sunway Berhad in January 2026 ended in April 2026, and IJM remains listed [1]. The head office is Wisma IJM in Petaling Jaya [1].
IJM says its property arm had a gross development value of RM47.74 billion across a landbank of 3,155.3 acres at 31 March 2026 [1]. That is a group-wide figure; the KPKT register covers only Malaysian projects licensed as housing, and of the 243 projects above, 80 are in Negeri Sembilan, 76 in Selangor, 38 in Johor, 33 in Penang and 16 in Kuala Lumpur. Most are registered under subsidiaries such as Seremban Two Holdings, RB Land, IJM Properties, Bandar Rimbayu and Shah Alam 2, which IJM's 2026 annual report lists with their equity interests [1].
The four IJM projects on PropertySifu are in Kuala Lumpur and involve partners. At Pantai Sentral Park, a 58-acre master development, IJM Land works through a joint development with the Amona Group [3]; the developer registered with KPKT for Enlace Suite @ Pantai Sentral Park and Riana Trees Residences is Amona Development Sdn Bhd, which IJM's 2026 annual report does not list as a subsidiary or joint-venture company [1]. In Segambut, Savvy @ Riana Dutamas and Stellaris @ Riana Dutamas are developed by 368 Segambut Sdn Bhd, a joint venture of FCW Holdings Bhd and IJM Land [4] in which IJM has a 50% effective interest [1].
Datuk Johan Idris was appointed chairman of IJM Corporation in October 2026 [5]. The group chief executive officer and managing director is Dato' Lee Chun Fai, and IJM Land's chief executive officer since 1 November 2024 is Dato' Ling Thou Lung [1].
Frequently asked questions
Is IJM Land a listed company?
Which company develops Savvy @ Riana Dutamas and Stellaris @ Riana Dutamas?
Which company develops Enlace Suite @ Pantai Sentral Park and Riana Trees Residences?
Have the handover deadlines for Enlace Suite, Riana Trees Residences and Stellaris been extended?
Yes, according to KPKT, and all three are recorded as on schedule (Lancar). Enlace Suite (13619-5, 438 units, first sale agreement 15 March 2025): deadline 15 March 2028, extended with approval by 18 months to 15 September 2029, reported progress 20%. Riana Trees Residences (13619-4, 336 units, first sale agreement 23 March 2023): deadline 23 March 2026, extended by 12 months to 23 March 2027, progress 90.8%. Stellaris @ Riana Dutamas (19221-3, 1,143 units, first sale agreement 23 June 2025): deadline 23 June 2028, extended by 16 months to 23 October 2029, progress 20%.
Was Savvy @ Riana Dutamas handed over on time?
KPKT records the CCC on 3 October 2024 and handover on 1 November 2024 for Savvy (19221-2, 921 serviced apartments). Its deadline under the first sale agreement of 29 November 2020 was 29 November 2023, extended with approval by 17 months to 29 April 2025; handover was 179 days before the extended deadline.
Does IJM Land have any Sick or Abandoned projects?
No. As at 27 October 2026, none of the 243 projects is classed Sick (Sakit) or Abandoned (Terbengkalai). Two phases of AUSTIN DUTA in Johor Bahru, both by IJM Properties Sdn Bhd (8326-26, 117 terrace houses, and 8326-27, 75 terrace houses), are classed Late (Lewat); their reported progress is 81.6% and 82%, and their deadlines under the first sale agreements are 21 and 22 February 2027.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] IJM Corporation Berhad Integrated Annual Report 2026 · IJM Corporation Berhad · 2026-07 · accessed 28 Oct 2026
https://www.ijm.com/wp-content/uploads/2026/09/IJM-IAR-FY2026.pdf - [2] IJM Land shares to be delisted from Bursa on April 15 · The Edge Malaysia · 10 Apr 2015 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/ijm-land-shares-be-delisted-bursa-april-15 - [3] IJM Land, Amona Group Launch RM389m Enlace Suites II in Pantai Sentral Park · IJM Land Berhad · 10 Aug 2026 · accessed 28 Oct 2026
https://ijmland.com/news-events/ijm-land-amona-group-launch-rm389m-enlace-suites-ii-in-pantai-sentral-park/ - [4] IJM Land to launch Phase 2 of Savio Riana Dutamas by year-end · The Edge Malaysia (City & Country) · 9 Sep 2019 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/ijm-land-launch-phase-2-savio-riana-dutamas-yearend - [5] IJM appoints Johan Idris as its chairman · The Star · 5 Oct 2026 · accessed 28 Oct 2026
https://www.thestar.com.my/business/business-news/2026/10/05/ijm-appoints-johan-idris-as-its-chairman - [6] IJM联手财政部旗下公司 柔南打造20亿工业园 · 中国报 · 25 May 2026 · accessed 28 Oct 2026
https://www.chinapress.com.my/20260525/ijm%E8%81%94%E6%89%8B%E8%B4%A2%E6%94%BF%E9%83%A8%E6%97%97%E4%B8%8B%E5%85%AC%E5%8F%B8-%E6%9F%94%E5%8D%97%E6%89%93%E9%80%A020%E4%BA%BF%E5%B7%A5%E4%B8%9A%E5%9B%AD/
Last updated 28 Oct 2026