Map Profile
Helping you buy right
EN
Developer profile · KPKT records

Eng Han Group

Last updated 28 Oct 2026
Who is Eng Han Group?

Eng Han Group, which develops as EH Property, is a privately held Malaysian developer and builder with 16 housing projects in the KPKT register under five Eng Han companies we could confirm: 12 completed and 4 under construction, none classed Sick or Abandoned. It began in construction in 1992 and has developed property since 2005.

  • 16 projects in the KPKT register
  • 12 completed
  • 4 under construction
  • None Sick or Abandoned

Has Eng Han Group handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists 16 housing projects under 5 Eng Han Group companies in 5 states: 12 completed, 4 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).

Of the 12 completed projects, 12 have both a handover deadline and a completion date in the register: 4 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 8 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†).

2 projects had the delivery period extended with KPKT approval.

Completed projects — most recent first

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN EMASKPKT 10437-8Kuala LipisPahang2816 Dec 20261st sale agreement 16 Dec 2024CCC 17 Apr 2026
Handover 27 Apr 2026
233 days before
TAMAN SUTERAMASKPKT 12239-3KemamanTerengganu7815 Nov 20251st sale agreement 15 Nov 2023CCC 18 Mar 2026
Handover 19 Mar 2026
124 days after
TAMAN GREENHILLKPKT 10437-7PetalingSelangor2011 Jul 20261st sale agreement 11 Jul 2024CCC 13 Mar 2025
Handover 25 Mar 2025
473 days before
TAMAN GREENHILLKPKT 10437-6PetalingSelangor5815 Dec 20241st sale agreement 15 Dec 2022CCC 23 Dec 2024
Handover 23 Dec 2024
8 days after
ALINEAKPKT 20029-1PetalingSelangor4802 Oct 2024Extended 8 months from 2 Feb 20241st sale agreement 2 Feb 2021CCC 6 Sep 2024
Handover 13 Sep 2024
19 days before
TAMAN EMAS 2KPKT 10437-5Kuala LipisPahang4829 Jun 20231st sale agreement 29 Jun 2021CCC 8 Feb 2024
Handover 15 Feb 2024
231 days after
SUTERAMASKPKT 12239-2KemamanTerengganu709 May 20231st sale agreement 9 May 2021CCC 26 Feb 2023
Handover 6 Mar 2023
64 days before
TAMAN BUKIT SARIMBANKPKT 10437-4SerembanNegeri Sembilan8217 May 20201st sale agreement 17 May 2018CCC 6 Aug 202081 days after †
TAMAN BUKIT SARIMBANKPKT 10437-3SerembanNegeri Sembilan13228 Sep 20181st sale agreement 28 Sep 2016CCC 15 Jan 2019109 days after
SUTERAMASKPKT 12239-1KemamanTerengganu38229 Apr 20151st sale agreement 29 Apr 2013CCC 6 Dec 20181,317 days after
TAMAN EMASKPKT 10437-2Kuala LipisPahang3081 Apr 20131st sale agreement 1 Apr 2011CCC 2 Apr 20181,827 days after
TAMAN EMASKPKT 10437-1Kuala LipisPahang15216 Nov 20091st sale agreement 16 Nov 2007CFO 21 Aug 20141,739 days after

Under construction

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
RESIDENSI TANGENKPKT 30349-1Tangen Residences · on PropertySifuKuala LumpurWP Kuala Lumpur413SmoothOn schedule16 Oct 2027Extended 12 months from 16 Oct 20261st sale agreement 16 Oct 202374%
TAMAN EMASKPKT 10437-9Kuala LipisPahang19SmoothOn schedule13 Mar 20281st sale agreement 13 Mar 202690%
TAMAN GREENHILLKPKT 10437-10Selangor28SmoothOn schedule10 Sep 20281st sale agreement 10 Sep 202642%
ERIA RESIDENCESKPKT 30847-1SepangSelangor104SmoothOn schedule13 Oct 20281st sale agreement 13 Oct 202528–60%

† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

Eng Han Group at a glance

ListedNo stock-exchange listing found — the Eng Han developer companies are private limited companies (Sdn Bhd)
Started1992, when Eng Han Bina was established (company account); property development since 2005[1]
Head officePetaling Jaya, Selangor[8]
Companies in the KPKT registerENG HAN PROPERTY SDN. BHD. KPKT 10437[4][7][1]
ANGKASA ARMADA SDN. BHD. KPKT 30349[5][6]
KUALA NILAM DEVELOPMENT SDN. BHD. KPKT 30847[3]
WIRAMA DEVELOPMENT SDN. BHD. KPKT 12239[1][7]
DATARAN MATRIKS SDN. BHD. KPKT 20029[1][7]
Websiteehproperty.com.my
Experience (company figure)34 years in construction and 21 years in property development, as stated on its website in 2026[1]
First property projectTaman Desa Penaga, Kulim, Kedah (2005)[1]
Where it builds (company list)Klang Valley and Seremban, Pahang, Terengganu, Penang, Kedah and Sabah[7]
Construction armEH Construction also builds for other developers; the group says it was an early adopter of the Industrialised Building System (IBS), with its own precast plant[2]

Eng Han Group projects on sale on PropertySifu

Tangen Residences

Mont Kiara, Kuala Lumpur · From RM626,050
KPKT 30349-1: On schedule · handover deadline 16 Oct 2027

Who is Eng Han Group? The company behind the projects

Eng Han Group dates its start to 1992, when Eng Han Bina was established, and moved into property development in 2005 with Taman Desa Penaga in Kulim, Kedah [1]. It describes itself as a developer with an in-house construction arm, with 34 years of construction experience and 21 years in property development, as stated on its website in 2026 [1]; the construction arm also builds for other developers [2]. Its property arm trades as EH Property, which the Eria Residences website identifies as Eng Han Property Sdn Bhd [4]. The group's office is in Petaling Jaya, Selangor [8]. No stock-exchange listing was found.

Ten of its 16 KPKT records are under Eng Han Property Sdn Bhd (KPKT 10437-1 to 10437-10), and they match projects on EH Property's own list [7][1]: Taman Emas in Kuala Lipis, Pahang, a 49.9-acre township launched in 2007, with Taman Emas 2 on 9.9 acres beside it [1] — five records named TAMAN EMAS or TAMAN EMAS 2; Shang Garden at Taman Bukit Sarimban, Seremban, the group's first guarded landed scheme, launched in 2015 [1] — two records named TAMAN BUKIT SARIMBAN; and Greenhill Residence in Section U10, Shah Alam, where the group says the 20 semi-detached homes of its Phase 2 received their CCC in 2025 [1] — three records named TAMAN GREENHILL. Taman Suteramas in Kemaman, Terengganu, a 54.4-acre project launched in 2013 [1], is registered under Wirama Development Sdn Bhd (12239-1 to 12239-3), and Alinea Suites in Section 14, Shah Alam — 480 SOHO units completed in 2024, according to the group [1] — under Dataran Matriks Sdn Bhd as ALINEA (20029-1).

The two newest projects are under their own companies. Eria Residences, 104 freehold townhouses at Taman Orkid, Sepang, is shown on EH Property's site under Kuala Nilam Development Sdn Bhd [3]; KPKT registers it as ERIA RESIDENCES (30847-1, 104 units), under construction. Tangen Residences in North Kiara, Kuala Lumpur, is developed by Angkasa Armada Sdn Bhd under the Eng Han Group [5][6]: a freehold tower of 49 floors on about 2.8 acres [5], registered by KPKT as RESIDENSI TANGEN (30349-1) with 413 units.

EH Property's site also lists ARI Permaisuri in Bandar Sri Permaisuri, Kuala Lumpur, as one of its projects [7]; KPKT registers its three towers under Dwitasik Sdn Bhd, which we could not confirm as an Eng Han company, so they are not in the table above. Older projects on the list, such as Taman Desa Penaga, and its projects in Sabah have no matching record under these five companies in the KPKT register used here.

Frequently asked questions

Is Eng Han Group a listed company?

No stock-exchange listing was found. Eng Han's developer companies are private limited companies (Sdn Bhd); its property arm, EH Property, is Eng Han Property Sdn Bhd [4].

Who develops Tangen Residences?

Angkasa Armada Sdn Bhd (KPKT developer code 30349), under the Eng Han Group [5][6]. KPKT registers the project as RESIDENSI TANGEN (30349-1): 413 units in a 49-floor block in Kuala Lumpur.

Has Tangen Residences' handover deadline been extended?

Yes. KPKT records the first sale agreement on 16 October 2023 and a handover deadline of 16 October 2026, extended with approval by 12 months to 16 October 2027. The project is recorded as on schedule (Lancar), with reported construction progress of 74%.

Does Eng Han have any Sick or Abandoned projects?

No. As at 27 October 2026, none of the 16 Eng Han projects in the KPKT register is classed Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). The 4 under construction — RESIDENSI TANGEN (30349-1), ERIA RESIDENCES (30847-1), TAMAN EMAS (10437-9) and TAMAN GREENHILL (10437-10) — are recorded as on schedule (Lancar).

Were Eng Han's completed projects handed over on time?

All 12 completed projects have dates that can be compared with a deadline (the extended deadline where an extension was approved). Four were handed over before it: ALINEA (20029-1, 19 days before its extended deadline), TAMAN GREENHILL (10437-7, 473 days before), TAMAN EMAS (10437-8, 233 days before) and SUTERAMAS (12239-2, 64 days before). Eight have a handover or CCC date after the deadline: TAMAN EMAS 10437-1 (1,739 days) and 10437-2 (1,827 days) in Kuala Lipis, SUTERAMAS 12239-1 in Kemaman (1,317 days), TAMAN EMAS 2 (10437-5, 231 days), TAMAN SUTERAMAS (12239-3, 124 days), TAMAN BUKIT SARIMBAN 10437-3 (109 days) and 10437-4 (81 days) in Seremban, and TAMAN GREENHILL (10437-6, 8 days). TAMAN BUKIT SARIMBAN 10437-4 was under construction during 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether its deadline already reflects it.

Which company is behind Eria Residences?

Kuala Nilam Development Sdn Bhd (KPKT developer code 30847), named on EH Property's Eria Residences page [3]. KPKT registers ERIA RESIDENCES (30847-1): 104 townhouses in Sepang district, Selangor; first sale agreement 13 October 2025, handover deadline 13 October 2028; on schedule (Lancar), with reported construction progress of 28–60% across its components.

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
  2. [1] Our Story · EH Property (Eng Han Group) · accessed 28 Oct 2026
    https://ehproperty.com.my/our-story
  3. [2] Construction Profile · EH Property (Eng Han Group) · accessed 28 Oct 2026
    https://ehproperty.com.my/construction
  4. [3] Eria Residences · EH Property (Eng Han Group) · accessed 28 Oct 2026
    https://ehproperty.com.my/property/eria-residences/
  5. [4] Eria Residences — official project website (terms and conditions) · Eng Han Property Sdn Bhd · accessed 28 Oct 2026
    https://eriaresidences.com.my
  6. [5] Tangen Residences: A "Sky Semi-D" Concept in North Kiara · EdgeProp · 13 Jul 2026 · accessed 28 Oct 2026
    https://www.edgeprop.my/content/1916647/tangen-residences-%E2%80%9Csky-semi-d%E2%80%9D-concept-north-kiara
  7. [6] Tangen Residences · EH Property (Eng Han Group) · accessed 28 Oct 2026
    https://ehproperty.com.my/property/tangen-residences/
  8. [7] Our Properties · EH Property (Eng Han Group) · accessed 28 Oct 2026
    https://ehproperty.com.my/property/
  9. [8] EH Property — home page · EH Property (Eng Han Group) · accessed 28 Oct 2026
    https://ehproperty.com.my/

Last updated 28 Oct 2026