BRDB (BRDB Developments Sdn Bhd)
BRDB Developments Sdn Bhd, the former Bandar Raya Developments Bhd, is a privately held developer with 31 housing projects in the KPKT register under six companies: 19 completed, 11 under construction (1 of them classed Sick) and 1 not yet started, none Abandoned. Incorporated in 1964, it was listed from 1968 until it was taken private in 2012.
- 31 projects in the KPKT register
- 19 completed
- 11 under construction (of which 1 Sick)
- 1 not yet started
Has BRDB handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 31 housing projects under 6 BRDB companies in 3 states: 19 completed, 11 under construction (of which 1 Sick), 1 not yet started.
Of the 19 completed projects, 14 have both a handover deadline and a completion date in the register: 4 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 9 handed over or certified complete after that deadline (2 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 1 received the completion certificate before the deadline (handover date not recorded).
7 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 19
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| APARTMEN BAYU PERMASKPKT 835-12 | Johor BahruJohor | 100 | 17 Dec 20261st sale agreement 17 Dec 2023 | CCC 24 Dec 2025 Handover 22 Jun 2026 | 178 days before |
| JASMINKPKT 13819-4 | GombakSelangor | 173 | 10 Oct 20251st sale agreement 10 Oct 2022 | CCC 13 Jun 2025 Handover 16 Jun 2025 | 116 days before |
| ZONE 2-1, BANDAR BARU PERMAS JAYAKPKT 835-11 | Johor BahruJohor | 142 | 6 Sep 20241st sale agreement 6 Sep 2022 | CCC 31 Dec 2024 Handover 31 Dec 2024 | 116 days after |
| TAMANSARIKPKT 13819-3 | GombakSelangor | 173 | 8 Jan 2024Extended 5 months from 8 Aug 20231st sale agreement 8 Aug 2020 | CCC 16 Oct 2023 Handover 16 Oct 2023 | 84 days before |
| PERMAS VILLEKPKT 835-10 | Johor BahruJohor | 291 | 23 Sep 20231st sale agreement 23 Sep 2020 | CCC 10 Sep 2023 Handover 21 Sep 2023 | 2 days before |
| RUMAH TERES 2 TINGKAT, ZONE 2-3KPKT 835-8 | Johor BahruJohor | 119 | 28 Jul 20201st sale agreement 28 Jul 2018 | CCC 24 Dec 2020 | 149 days after † |
| RUMAH TERES 2 TINGKATKPKT 835-9 | Johor BahruJohor | 150 | 28 Jul 20201st sale agreement 28 Jul 2018 | CCC 24 Dec 2020 | 149 days after † |
| TAMANSARIKPKT 13819-2 | GombakSelangor | 149 | 3 Jun 20191st sale agreement 3 Jun 2016 | CCC 21 Aug 2019 | 79 days after |
| TAMANSARIKPKT 13819-1 | GombakSelangor | 117 | 15 May 20181st sale agreement 15 May 2015 | CCC 7 Sep 2018 | 115 days after |
| SENJA RESIDENCEKPKT 11807-1 | PetalingSelangor | 114 | 27 Sep 20161st sale agreement 27 Sep 2013 | CCC 17 Oct 2016 | 20 days after |
| SERAI BUKIT BANDARAYAKPKT 32-14 | Kuala LumpurWP Kuala Lumpur | 121 | 3 Sep 20151st sale agreement 3 Sep 2012 | CCC 7 Oct 2016 | 400 days after |
| VERDANAKPKT 11611-1The Edge reported in 2022 that Verdana in North Kiara was completed in 2014; the KPKT register records the CCC on 1 July 2015.[2] | Kuala LumpurWP Kuala Lumpur | 298 | 18 Aug 20141st sale agreement 18 Aug 2011 | CCC 1 Jul 2015 | 317 days after |
Handed over or certified complete after the deadline (9)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| ZONE 2-1, BANDAR BARU PERMAS JAYAKPKT 835-11 | Johor BahruJohor | 142 | 6 Sep 20241st sale agreement 6 Sep 2022 | CCC 31 Dec 2024 Handover 31 Dec 2024 | 116 days after |
| RUMAH TERES 2 TINGKAT, ZONE 2-3KPKT 835-8 | Johor BahruJohor | 119 | 28 Jul 20201st sale agreement 28 Jul 2018 | CCC 24 Dec 2020 | 149 days after † |
| RUMAH TERES 2 TINGKATKPKT 835-9 | Johor BahruJohor | 150 | 28 Jul 20201st sale agreement 28 Jul 2018 | CCC 24 Dec 2020 | 149 days after † |
| TAMANSARIKPKT 13819-2 | GombakSelangor | 149 | 3 Jun 20191st sale agreement 3 Jun 2016 | CCC 21 Aug 2019 | 79 days after |
| TAMANSARIKPKT 13819-1 | GombakSelangor | 117 | 15 May 20181st sale agreement 15 May 2015 | CCC 7 Sep 2018 | 115 days after |
| SENJA RESIDENCEKPKT 11807-1 | PetalingSelangor | 114 | 27 Sep 20161st sale agreement 27 Sep 2013 | CCC 17 Oct 2016 | 20 days after |
| SERAI BUKIT BANDARAYAKPKT 32-14 | Kuala LumpurWP Kuala Lumpur | 121 | 3 Sep 20151st sale agreement 3 Sep 2012 | CCC 7 Oct 2016 | 400 days after |
| VERDANAKPKT 11611-1The Edge reported in 2022 that Verdana in North Kiara was completed in 2014; the KPKT register records the CCC on 1 July 2015.[2] | Kuala LumpurWP Kuala Lumpur | 298 | 18 Aug 20141st sale agreement 18 Aug 2011 | CCC 1 Jul 2015 | 317 days after |
| THE STRAITS VIEW RESIDENCESKPKT 835-7 | Johor BahruJohor | 112 | 22 Sep 20141st sale agreement 22 Sep 2011 | CCC 14 Dec 2014 | 83 days after |
Show all 19 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| APARTMEN BAYU PERMASKPKT 835-12 | Johor BahruJohor | 100 | 17 Dec 20261st sale agreement 17 Dec 2023 | CCC 24 Dec 2025 Handover 22 Jun 2026 | 178 days before |
| JASMINKPKT 13819-4 | GombakSelangor | 173 | 10 Oct 20251st sale agreement 10 Oct 2022 | CCC 13 Jun 2025 Handover 16 Jun 2025 | 116 days before |
| ZONE 2-1, BANDAR BARU PERMAS JAYAKPKT 835-11 | Johor BahruJohor | 142 | 6 Sep 20241st sale agreement 6 Sep 2022 | CCC 31 Dec 2024 Handover 31 Dec 2024 | 116 days after |
| TAMANSARIKPKT 13819-3 | GombakSelangor | 173 | 8 Jan 2024Extended 5 months from 8 Aug 20231st sale agreement 8 Aug 2020 | CCC 16 Oct 2023 Handover 16 Oct 2023 | 84 days before |
| PERMAS VILLEKPKT 835-10 | Johor BahruJohor | 291 | 23 Sep 20231st sale agreement 23 Sep 2020 | CCC 10 Sep 2023 Handover 21 Sep 2023 | 2 days before |
| RUMAH TERES 2 TINGKAT, ZONE 2-3KPKT 835-8 | Johor BahruJohor | 119 | 28 Jul 20201st sale agreement 28 Jul 2018 | CCC 24 Dec 2020 | 149 days after † |
| RUMAH TERES 2 TINGKATKPKT 835-9 | Johor BahruJohor | 150 | 28 Jul 20201st sale agreement 28 Jul 2018 | CCC 24 Dec 2020 | 149 days after † |
| TAMANSARIKPKT 13819-2 | GombakSelangor | 149 | 3 Jun 20191st sale agreement 3 Jun 2016 | CCC 21 Aug 2019 | 79 days after |
| TAMANSARIKPKT 13819-1 | GombakSelangor | 117 | 15 May 20181st sale agreement 15 May 2015 | CCC 7 Sep 2018 | 115 days after |
| SENJA RESIDENCEKPKT 11807-1 | PetalingSelangor | 114 | 27 Sep 20161st sale agreement 27 Sep 2013 | CCC 17 Oct 2016 | 20 days after |
| SERAI BUKIT BANDARAYAKPKT 32-14 | Kuala LumpurWP Kuala Lumpur | 121 | 3 Sep 20151st sale agreement 3 Sep 2012 | CCC 7 Oct 2016 | 400 days after |
| VERDANAKPKT 11611-1The Edge reported in 2022 that Verdana in North Kiara was completed in 2014; the KPKT register records the CCC on 1 July 2015.[2] | Kuala LumpurWP Kuala Lumpur | 298 | 18 Aug 20141st sale agreement 18 Aug 2011 | CCC 1 Jul 2015 | 317 days after |
| BANDAR BARU PERMAS JAYAKPKT 835-5 | Johor BahruJohor | 92 | — | CCC 14 Dec 2014 | — |
| THE STRAITS VIEW RESIDENCESKPKT 835-7 | Johor BahruJohor | 112 | 22 Sep 20141st sale agreement 22 Sep 2011 | CCC 14 Dec 2014 | 83 days after |
| BANDAR BARU PERMAS JAYAKPKT 835-2 | Johor BahruJohor | 8,257 | 28 Jun 20141st sale agreement 28 Jun 2011 | CFO 25 Jun 2014 | CCC before deadline; handover not recorded |
| THE STRAITS VIEW RESIDENCESKPKT 835-6 | Johor BahruJohor | 108 | — | CCC 16 Apr 2013 | — |
| ONE MENERUNGKPKT 32-13 | Kuala LumpurWP Kuala Lumpur | 229 | — | CFO 4 Nov 2009 | — |
| BANDAR BARU PERMAS JAYAKPKT 835-4 | Johor BahruJohor | 170 | — | CFO 14 Jan 2009 | — |
| INARAKPKT 32-12 | Kuala LumpurWP Kuala Lumpur | 22 | — | CFO 18 Oct 2006 | — |
Under construction (11) and not yet started (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| PANGSAPURI SELANGORKU @ SARIKPKT 13819-5 | GombakSelangor | 200 | SickSick | 23 Oct 20261st sale agreement 23 Oct 2023 | 98% |
| SENJA RESIDENCEKPKT 11807-2 | PetalingSelangor | 83 | SmoothOn schedule | 22 Jan 20271st sale agreement 22 Jan 2024 | 95% |
| RESIDENSI MENERUNG 111KPKT 32-15One Eleven Menerung · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 111 | SmoothOn schedule | 16 Feb 2027Extended 24 months from 16 Feb 20251st sale agreement 16 Feb 2022 | 92% |
| RESIDENSI BUKIT MIRANDAKPKT 11611-2Miranda Hill @ North Kiara · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 552 | SmoothOn schedule | 3 Sep 2027Extended 18 months from 3 Mar 20261st sale agreement 3 Mar 2023 | 78–80% |
| RIMBUNANKPKT 835-13 | Johor BahruJohor | 198 | SmoothOn schedule | 1 Nov 20271st sale agreement 1 Nov 2024 | 77–79% |
| SENJA RESIDENCEKPKT 11807-4 | PetalingSelangor | 47 | SmoothOn schedule | 30 Sep 20281st sale agreement 30 Sep 2025 | 19–39% |
| SENJA RESIDENCEKPKT 11807-3 | PetalingSelangor | 34 | SmoothOn schedule | 31 Oct 20281st sale agreement 31 Oct 2025 | 20–22% |
| RESIDENSI DWI PESONAKPKT 835-14 | Johor BahruJohor | 715 | SmoothOn schedule | 31 Oct 2029Extended 12 months from 31 Oct 20281st sale agreement 31 Oct 2025 | 16% |
| FEDERAL AVENUEKPKT 30367-1 | PetalingSelangor | 751 | SmoothOn schedule | 26 Dec 2029Extended 18 months from 26 Jun 20281st sale agreement 26 Jun 2025 | 20% |
| RESIDENSI EDENKPKT 32-16 | Kuala LumpurWP Kuala Lumpur | 146 | SmoothOn schedule | 5 Jan 2030Extended 12 months from 5 Jan 20291st sale agreement 5 Jan 2026 | 20% |
| RESIDENSI SUASANA PERMASKPKT 835-15 | Johor BahruJohor | 399 | SmoothOn schedule | —Extended 12 months (date not registered) | 4% |
| MURRAYAKPKT 13819-6 | Selangor | 179 | Not startedNot started | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
BRDB at a glance
| Listed | Not listed — listed on the Kuala Lumpur Stock Exchange from 1968 as Bandar Raya Developments Bhd and taken private in 2012[2][3] |
|---|---|
| Started | Incorporated in 1964 as Bandar Raya Developments Bhd[2] |
| Head office | Menara BRDB, Bukit Bandaraya, Bangsar, Kuala Lumpur[1] |
| Leadership | Dato' Sri Akbar Khan — Chairman[4] Christopher Manivannan — Group Chief Executive Officer[5] |
| Companies in the KPKT register | BRDB DEVELOPMENTS SDN. BHD. KPKT 32[6][2] PERMAS JAYA SDN. BHD. KPKT 835[8][12] PINGGIR MENTARI SDN. BHD. KPKT 13819[9] EARTH PAVILION SDN. BHD. KPKT 11807[10] IMPIANA IMPRESIF SDN. BHD. KPKT 30367[11] FREEDOM ESTATES SDN. BHD. KPKT 11611[7] |
| Website | brdb.com.my |
| Former name | Bandar Raya Developments Bhd, listed on the Kuala Lumpur Stock Exchange from 1968 to 2012[2] |
| Owner (media, 2024) | Fully owned by A Khan Sdn Bhd[3] |
| Undeveloped land (media, 2022) | Over 500 acres, mainly in Kuala Lumpur, Selangor and Johor[2] |
| Permas Jaya township | 1,400 acres in Johor Bahru, launched in 1981; about 250 acres left to develop (company, 2023)[8] |
| Markets | Malaysia (Kuala Lumpur, Selangor, Johor); Australia, London and Pakistan[1] |
BRDB projects on sale on PropertySifu
Miranda Hill @ North Kiara
- SERAI BUKIT BANDARAYA — 4.4 km, 2016
Who is BRDB? The company behind the projects
BRDB Developments Sdn Bhd, formerly Bandar Raya Developments Bhd, was incorporated in 1964, listed on the Kuala Lumpur Stock Exchange in 1968 and taken private in 2012 [2]. The Edge reported in 2024 that it is now fully owned by A Khan Sdn Bhd [3]. Its office is at Menara BRDB in Bukit Bandaraya, Bangsar, Kuala Lumpur [1]. The chairman is Dato' Sri Akbar Khan [4]; Christopher Manivannan is group chief executive officer, with Yasmin Khan and Nazim Khan as co-deputy chief executive officers [5].
In Kuala Lumpur, BRDB is known for its developments in Bangsar, among them One Menerung and Serai Bukit Bandaraya [3]. One Eleven Menerung, one of two BRDB projects on PropertySifu, is a single 23-storey tower of 111 units [6] on a 0.83-acre freehold site [2]; KPKT registers it as 32-15 under BRDB Developments Sdn Bhd. Eden in Taman Duta, 146 units on 12.25 acres of freehold land, is also developed by BRDB Developments [5]. The other, Miranda Hill @ North Kiara, is developed by Freedom Estates Sdn Bhd under developer licence 11611, according to its project website [7]; KPKT registers it as RESIDENSI BUKIT MIRANDA (11611-2), with 552 units, and also registers Verdana under that company.
In Johor Bahru, Bandar Baru Permas Jaya, a 1,400-acre township launched in 1981, is developed by BRDB's wholly-owned subsidiary Permas Jaya Sdn Bhd [8]. In Selangor, the project websites name Pinggir Mentari Sdn Bhd (licence 13819) as developer of Tamansari in Rawang [9], Earth Pavilion Sdn Bhd (licence 11807) of Senja Lakeside Estate [10] and Impiana Impresif Sdn Bhd (licence 30367) of Federal Avenue [11]. The sources found do not state who holds the shares of these three companies or of Freedom Estates.
The Edge reported in 2022 that BRDB had over 500 acres of undeveloped land, mainly in Kuala Lumpur, Selangor and Johor [2]; in 2023 its chief executive said about 250 acres remained at Permas Jaya [8]. BRDB also lists projects in Australia, London and Pakistan [1]. The KPKT register covers only Malaysian projects licensed as housing, so its shopping centre, offices and overseas projects are not in the records above.
Frequently asked questions
Is BRDB a listed company?
How many projects has BRDB completed?
The KPKT register lists 31 housing projects under six BRDB companies: 19 completed, 11 under construction and 1 not yet started — 13 in Johor, 11 in Selangor and 7 in Kuala Lumpur. Of the 19 completed projects, 14 have dates that can be compared with a deadline (an approved extension is counted at the extended deadline): 4 were handed over on or before it, 9 after it (2 of them with construction during the 18 March–31 August 2020 period excluded by Act 829), and 1 received the completion certificate before the deadline with no handover date recorded.
Does BRDB have any Sick or Abandoned projects?
One project is classed Sick (Sakit) as at 27 October 2026: PANGSAPURI SELANGORKU @ SARI (KPKT 13819-5), 200 apartment units in Gombak, Selangor, registered under Pinggir Mentari Sdn Bhd. KPKT records its first sale agreement on 23 October 2023, a handover deadline of 23 October 2026 and reported construction progress of 97.5%. None of the 31 projects is classed Abandoned (Terbengkalai) or Late (Lewat).
Which BRDB projects are on PropertySifu, and which companies develop them?
Two. One Eleven Menerung in Bangsar is developed by BRDB Developments Sdn Bhd itself (KPKT developer code 32) [6]; KPKT registers it as RESIDENSI MENERUNG 111 (32-15), with 111 serviced-apartment units. Miranda Hill @ North Kiara is developed by Freedom Estates Sdn Bhd (developer licence 11611), according to its project website [7]; KPKT registers it as RESIDENSI BUKIT MIRANDA (11611-2), with 552 units.
Have the handover deadlines of One Eleven Menerung and Miranda Hill been extended?
Yes, both, according to KPKT. One Eleven Menerung (32-15): first sale agreement 16 February 2022, deadline 16 February 2025, extended with approval by 24 months to 16 February 2027; reported construction progress 92%. Miranda Hill (11611-2): first sale agreement 3 March 2023, deadline 3 March 2026, extended with approval by 18 months to 3 September 2027; reported construction progress 77.8%–79.8%. Both are recorded as on schedule (Lancar).
Is Permas Jaya Sdn Bhd part of BRDB?
Yes. The Edge reported in 2023 that Bandar Baru Permas Jaya in Johor Bahru is developed by BRDB's wholly-owned subsidiary Permas Jaya Sdn Bhd, established in 1981 [8]. KPKT registers 13 housing projects under Permas Jaya Sdn Bhd: 10 completed and 3 under construction.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] BRDB — Property · BRDB Developments Sdn Bhd · accessed 28 Oct 2026
https://brdb.com.my/property - [2] Cover Story: BRDB pushes ahead with two launches in mid-2022 · The Edge Malaysia Weekly (City & Country) · 25 Apr 2022 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/cover-story-brdb-pushes-ahead-two-launches-mid2022 - [3] BRDB buys Selangor Properties' prime Jalan Semantan land · The Edge Malaysia Weekly · 7 Oct 2024 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/729267 - [4] BRDB — Our Company (Board of Directors) · BRDB Developments Sdn Bhd · accessed 28 Oct 2026
https://www.brdb.com.my/company - [5] Cover Story: Creating a lasting legacy built on experience · The Edge Malaysia Weekly (City & Country) · 26 Jan 2026 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/790266 - [6] One Eleven Menerung · BRDB Developments Sdn Bhd · accessed 28 Oct 2026
https://brdb.com.my/portfolio/one-eleven-menerung - [7] Miranda Hill — official project website (developer and licence details) · Freedom Estates Sdn Bhd · accessed 28 Oct 2026
http://www.mirandahill.com.my/ - [8] Cover Story: BRDB gears up for three launches in Bandar Baru Permas Jaya, Johor · The Edge Malaysia Weekly (City & Country) · 5 Jun 2023 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/669585 - [9] Tamansari — official project website (developer and licence details) · Pinggir Mentari Sdn Bhd · accessed 28 Oct 2026
https://tamansari.brdb.com.my/ - [10] Senja Lakeside Estate — official project website (developer and licence details) · Earth Pavilion Sdn Bhd · accessed 28 Oct 2026
https://www.senjabrdb.com.my/ - [11] Federal Avenue — official project website (developer and licence details) · Impiana Impresif Sdn Bhd · accessed 28 Oct 2026