Developer profile · KPKT records

Asiabina Group (Asiabina Holdings Sdn Bhd)

Last updated 28 Oct 2026
Who is Asiabina Group?

Asiabina Group is a privately held developer from Perak with 34 housing projects in the KPKT register under the five companies we could confirm: 24 completed and 10 under construction, none classed Sick or Abandoned. Most are terrace-house schemes in Perak's Kerian district; One Seputeh in Kuala Lumpur is its first Klang Valley project.

  • 34 projects in the KPKT register
  • 24 completed
  • 10 under construction
  • None Sick or Abandoned

Has Asiabina Group handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists 34 housing projects under 5 Asiabina Group companies in 4 states: 24 completed, 10 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).

Of the 24 completed projects, 17 have both a handover deadline and a completion date in the register: 6 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 11 handed over or certified complete after that deadline (2 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†).

7 projects had the delivery period extended with KPKT approval.

Completed projects — the 12 most recent of 24

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN CAHAYA BIDURIKPKT 8401-18Bandar BaharuKedah1222 Apr 20271st sale agreement 22 Apr 2025CCC 15 Sep 2026
Handover 15 Sep 2026
219 days before
TAMAN KERIAN SENTOSAKPKT 8401-17KerianPerak9027 May 20261st sale agreement 27 May 2024CCC 9 Jun 2026
Handover 9 Jun 2026
13 days after
TAMAN KERIAN SENTOSAKPKT 8401-16KerianPerak742 May 20261st sale agreement 2 May 2024CCC 13 May 2026
Handover 13 May 2026
11 days after
TAMAN SERAI SEMAMBUKPKT 12435-2KerianPerak2024 Jan 20261st sale agreement 24 Jan 2024CCC 15 May 2025
Handover 15 May 2025
254 days before
TAMAN SERAI SEMAMBUKPKT 12435-3KerianPerak2027 Feb 20271st sale agreement 27 Feb 2025CCC 15 May 2025
Handover 15 May 2025
653 days before
TAMAN KERIAN PUTRAKPKT 8401-12KerianPerak1505 Oct 20241st sale agreement 5 Oct 2021CCC 5 Jun 2024
Handover 10 Jul 2024
87 days before
TAMAN KERIAN PUTRAKPKT 8401-15KerianPerak11023 Feb 20241st sale agreement 23 Feb 2022CCC 16 May 2024
Handover 7 May 2024 / 16 May 2024
74–83 days after
TAMAN KERIAN PUTRAKPKT 8401-14KerianPerak8019 Nov 20231st sale agreement 19 Nov 2021CCC 7 Feb 2024
Handover 7 Feb 2024
80 days after
TAMAN KERIAN PUTRAKPKT 8401-13KerianPerak2215 Jul 20231st sale agreement 15 Jul 2021CCC 4 Dec 2023
Handover 4 Dec 2023
142 days after
TAMAN KERIAN PUTRAKPKT 8401-9KerianPerak2830 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020CCC 5 Sep 2023
Handover 5 Sep 2023
159 days after
TAMAN KERIAN PUTRAKPKT 8401-11KerianPerak1022 Apr 2023Extended 5 months from 2 Nov 20221st sale agreement 2 Nov 2020CCC 2 Jun 2023
Handover 2 Jun 2023
61 days after
TAMAN KERIAN PUTRAKPKT 8401-10KerianPerak6526 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020CCC 29 May 2023
Handover 29 May 2023
64 days after

Handed over or certified complete after the deadline (11)

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN KERIAN SENTOSAKPKT 8401-17KerianPerak9027 May 20261st sale agreement 27 May 2024CCC 9 Jun 2026
Handover 9 Jun 2026
13 days after
TAMAN KERIAN SENTOSAKPKT 8401-16KerianPerak742 May 20261st sale agreement 2 May 2024CCC 13 May 2026
Handover 13 May 2026
11 days after
TAMAN KERIAN PUTRAKPKT 8401-15KerianPerak11023 Feb 20241st sale agreement 23 Feb 2022CCC 16 May 2024
Handover 7 May 2024 / 16 May 2024
74–83 days after
TAMAN KERIAN PUTRAKPKT 8401-14KerianPerak8019 Nov 20231st sale agreement 19 Nov 2021CCC 7 Feb 2024
Handover 7 Feb 2024
80 days after
TAMAN KERIAN PUTRAKPKT 8401-13KerianPerak2215 Jul 20231st sale agreement 15 Jul 2021CCC 4 Dec 2023
Handover 4 Dec 2023
142 days after
TAMAN KERIAN PUTRAKPKT 8401-9KerianPerak2830 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020CCC 5 Sep 2023
Handover 5 Sep 2023
159 days after
TAMAN KERIAN PUTRAKPKT 8401-11KerianPerak1022 Apr 2023Extended 5 months from 2 Nov 20221st sale agreement 2 Nov 2020CCC 2 Jun 2023
Handover 2 Jun 2023
61 days after
TAMAN KERIAN PUTRAKPKT 8401-10KerianPerak6526 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020CCC 29 May 2023
Handover 29 May 2023
64 days after
TAMAN KERIAN PUTRAKPKT 8401-7KerianPerak13916 Apr 2022Extended 11 months from 16 May 20211st sale agreement 16 May 2019CCC 17 Aug 2022
Handover 13 Aug 2022 / 17 Aug 2022
119–123 days after †
TAMAN KERIAN PUTRAKPKT 8401-6KerianPerak11616 Apr 2022Extended 11 months from 16 May 20211st sale agreement 16 May 2019CCC 5 Aug 2022
Handover 5 Aug 2022
111 days after †
TAMAN PIANDANG SENTOSAKPKT 8401-3KerianPerak7416 Oct 20051st sale agreement 16 Oct 2003CCC 2 Mar 20205,251 days after
Show all 24 completed projects
Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN CAHAYA BIDURIKPKT 8401-18Bandar BaharuKedah1222 Apr 20271st sale agreement 22 Apr 2025CCC 15 Sep 2026
Handover 15 Sep 2026
219 days before
TAMAN KERIAN SENTOSAKPKT 8401-17KerianPerak9027 May 20261st sale agreement 27 May 2024CCC 9 Jun 2026
Handover 9 Jun 2026
13 days after
TAMAN KERIAN SENTOSAKPKT 8401-16KerianPerak742 May 20261st sale agreement 2 May 2024CCC 13 May 2026
Handover 13 May 2026
11 days after
TAMAN SERAI SEMAMBUKPKT 12435-2KerianPerak2024 Jan 20261st sale agreement 24 Jan 2024CCC 15 May 2025
Handover 15 May 2025
254 days before
TAMAN SERAI SEMAMBUKPKT 12435-3KerianPerak2027 Feb 20271st sale agreement 27 Feb 2025CCC 15 May 2025
Handover 15 May 2025
653 days before
TAMAN KERIAN PUTRAKPKT 8401-12KerianPerak1505 Oct 20241st sale agreement 5 Oct 2021CCC 5 Jun 2024
Handover 10 Jul 2024
87 days before
TAMAN KERIAN PUTRAKPKT 8401-15KerianPerak11023 Feb 20241st sale agreement 23 Feb 2022CCC 16 May 2024
Handover 7 May 2024 / 16 May 2024
74–83 days after
TAMAN KERIAN PUTRAKPKT 8401-14KerianPerak8019 Nov 20231st sale agreement 19 Nov 2021CCC 7 Feb 2024
Handover 7 Feb 2024
80 days after
TAMAN KERIAN PUTRAKPKT 8401-13KerianPerak2215 Jul 20231st sale agreement 15 Jul 2021CCC 4 Dec 2023
Handover 4 Dec 2023
142 days after
TAMAN KERIAN PUTRAKPKT 8401-9KerianPerak2830 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020CCC 5 Sep 2023
Handover 5 Sep 2023
159 days after
TAMAN KERIAN PUTRAKPKT 8401-11KerianPerak1022 Apr 2023Extended 5 months from 2 Nov 20221st sale agreement 2 Nov 2020CCC 2 Jun 2023
Handover 2 Jun 2023
61 days after
TAMAN KERIAN PUTRAKPKT 8401-10KerianPerak6526 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020CCC 29 May 2023
Handover 29 May 2023
64 days after
TAMAN KERIAN PUTRAKPKT 8401-7KerianPerak13916 Apr 2022Extended 11 months from 16 May 20211st sale agreement 16 May 2019CCC 17 Aug 2022
Handover 13 Aug 2022 / 17 Aug 2022
119–123 days after †
TAMAN KERIAN PUTRAKPKT 8401-6KerianPerak11616 Apr 2022Extended 11 months from 16 May 20211st sale agreement 16 May 2019CCC 5 Aug 2022
Handover 5 Aug 2022
111 days after †
TAMAN KERIAN PUTRAKPKT 8401-8KerianPerak1621 Sep 2022Extended 11 months from 21 Oct 20211st sale agreement 21 Oct 2019CCC 4 Aug 2022
Handover 5 Aug 2022
47 days before
TAMAN SERAI SEMAMBUKPKT 12435-1KerianPerak528 Nov 20201st sale agreement 8 Nov 2018CCC 17 Sep 2020
Handover 21 Oct 2020 / 3 Nov 2020
5 days before
TAMAN PIANDANG SENTOSAKPKT 8401-3KerianPerak7416 Oct 20051st sale agreement 16 Oct 2003CCC 2 Mar 20205,251 days after
TAMAN SRI NIBONG EMASKPKT 6484-4Daerah Barat DayaPulau Pinang11—CCC 2 May 2014—
TAMAN SERAI MAKMURKPKT 8401-2KerianPerak103—CFO 18 Jun 2013—
TAMAN SERI EMASKPKT 7436-2Seberang Perai SelatanPulau Pinang410—CCC 10 Oct 2012—
TAMAN CAHAYAKPKT 6484-3Daerah Barat DayaPulau Pinang25—CCC 16 Dec 2011—
TAMAN SERAI SENTOSAKPKT 8401-5KerianPerak36—CFO 8 Aug 2011—
TAMAN SERAI MAJUKPKT 8401-4KerianPerak45—CFO 28 Aug 2006—
TAMAN SRI BAYUKPKT 6484-2Daerah Barat DayaPulau Pinang23—CFO 16 Jun 2006—

Under construction

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
TAMAN KERIAN PUTRAKPKT 8401-19KerianPerak78SmoothOn schedule3 Mar 20271st sale agreement 3 Mar 202581–82%
TAMAN KERIAN PUTRAKPKT 8401-21KerianPerak53SmoothOn schedule18 Sep 20271st sale agreement 18 Sep 202554–65%
TAMAN KERIAN PUTRAKPKT 8401-22KerianPerak24SmoothOn schedule9 Oct 20271st sale agreement 9 Oct 202551–71%
TAMAN KERIAN PUTRAKPKT 8401-25KerianPerak46SmoothOn schedule4 Mar 20281st sale agreement 4 Mar 202646–48%
TAMAN SERAI DAMAIKPKT 7436-3Perak32SmoothOn schedule15 May 20281st sale agreement 15 May 20265%
RUMAH PERAKKU KERIAN PUTRAKPKT 8401-20Perak100SmoothOn schedule4 Jun 20281st sale agreement 4 Jun 202576%
TAMAN SERAI DAMAIKPKT 7436-4KerianPerak32SmoothOn schedule17 Aug 20281st sale agreement 17 Aug 202632%
RUMAH BANDAR TAMAN KERIAN SENTOSA BLOK BKPKT 8401-23Perak46SmoothOn schedule9 Sep 20281st sale agreement 9 Sep 202589%
RUMAH BANDAR TAMAN KERIAN SENTOSA BLOK AKPKT 8401-24Perak30SmoothOn schedule15 Apr 20291st sale agreement 15 Apr 202674%
RESIDENSI SEPUTEH 1KPKT 30947-1One Seputeh · on PropertySifuWP Kuala Lumpur383SmoothOn schedule26 Jul 2030Extended 16 months from 26 Mar 20291st sale agreement 26 Mar 202621%

† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

Asiabina Group at a glance

ListedNot listed — Asiabina's developer companies are private limited companies (Sdn Bhd)
Started1989, according to the company's website and The Edge (2026); a sponsored feature by the group gives 1988[1][2][4]
Head officePerak — offices in Taiping, Parit Buntar and Pantai Remis, plus Penang and Kuala Lumpur[1][2]
LeadershipYong Chai Seng — Group Managing Director[4]
Companies in the KPKT registerSEPUTEH KUKUH SDN. BHD. KPKT 30947[5][2]
BUMI JOHAN SDN. BHD. KPKT 8401[1]
UNAJAYA SDN. BHD. KPKT 7436[1]
SURIA TAKBIR CONSTRUCTION SDN. BHD. KPKT 12435[1]
ASIABINA SDN. BHD. KPKT 6484[1]
Websiteasiabina.com
Where it buildsMainly Perak, also Penang, Kedah and, since One Seputeh, Kuala Lumpur[2][3]
Other businessesShopping malls (Taiping Sentral Mall, Kerian Sentral Mall), hotels (Sense Hotel, Hotel Damai), a memorial park business, energy and plantations[3]
One Seputeh ResidencesOne 50-storey freehold tower with 383 serviced residences on Jalan Syed Putra, Kuala Lumpur — the group's first Klang Valley project[2][5]

Asiabina Group projects on sale on PropertySifu

One Seputeh

Seputeh, Kuala Lumpur · From RM699,800
KPKT 30947-1: On schedule · handover deadline 26 Jul 2030

Who is Asiabina Group? The company behind the projects

Asiabina Group describes itself as a developer since 1989 [1]. The Edge reported in 2026 that Perak-based Asiabina Holdings Sdn Bhd had been developing property since its inception in 1989, mainly in Perak, Penang and Kedah [2]; a sponsored feature by the group gives 1988 as the founding year [4]. Its website lists offices in Taiping, Parit Buntar and Pantai Remis in Perak, as well as Penang and Kuala Lumpur [1], and businesses beyond housing: shopping malls, hotels, a memorial park business, energy and plantations [3]. Its group managing director is Yong Chai Seng [4].

Most of its homes in the KPKT register are in the Kerian district of Perak. Taman Kerian Putra, Rumah Perakku @ Taman Kerian Putra and Taman Kerian Sentosa, all on the group's project list [1], are registered by Bumi Johan Sdn Bhd (KPKT 8401). Taman Serai Semambu is registered by Suria Takbir Construction Sdn Bhd and Taman Serai Damai by Unajaya Sdn Bhd, both also on that list [1]. Asiabina Sdn Bhd, the company named on the group's website [1], has three completed projects in Penang in the register.

One Seputeh Residences in Kuala Lumpur, a single 50-storey freehold tower of 383 serviced residences, is the group's first project in the Klang Valley [2][5]. KPKT registers it as Residensi Seputeh 1 (30947-1, 383 serviced apartments) under Seputeh Kukuh Sdn Bhd.

The KPKT figures on this page count only the five companies above, which we could link to the group through its website or the developer licence on its PropertySifu listing. The register covers housing-licensed projects only, so the group's shops, malls and hotels are not in the tables.

Frequently asked questions

Is Asiabina Group a listed company?

No stock-exchange listing was found. The Edge refers to the group as Asiabina Holdings Sdn Bhd [2], and its housing projects are registered with KPKT under private companies (Sdn Bhd): for example, One Seputeh under Seputeh Kukuh Sdn Bhd and Taman Kerian Putra under Bumi Johan Sdn Bhd.

How many projects has Asiabina Group completed?

In the KPKT register, 24 of the 34 housing projects under the five companies counted here are completed, covering 1,823 of the 2,647 approved units. 17 are Bumi Johan Sdn Bhd projects, mostly Taman Kerian Putra and Taman Kerian Sentosa phases in Kerian, Perak; the others are three Taman Serai Semambu phases, Taman Seri Emas in Seberang Perai Selatan, Penang (410 units, CCC 10 October 2012) and three small projects in Penang under Asiabina Sdn Bhd.

Does Asiabina Group have any Sick or Abandoned projects?

No. As at 27 October 2026, the KPKT register classes none of the 34 projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). All 10 under construction are recorded as on schedule (Lancar): One Seputeh (30947-1), two Taman Serai Damai phases (Unajaya Sdn Bhd) and seven Bumi Johan Sdn Bhd phases in Taman Kerian Putra and Taman Kerian Sentosa.

Has Asiabina Group handed over its projects on time?

Of the 24 completed projects, 17 have both a handover deadline and a completion date in the KPKT register: 6 were handed over on or before the deadline (the extended deadline where KPKT approved an extension) and 11 after it. Eight Taman Kerian Putra phases completed in 2022–2024 were handed over 61 to 159 days after their deadlines, and two Taman Kerian Sentosa phases 11 and 13 days after; for two of the Taman Kerian Putra phases, construction spanned 18 March–31 August 2020, a period that Act 829 excludes from handover deadlines. The widest gap is Taman Piandang Sentosa (8401-3, 74 houses): first sale agreement 16 October 2003, deadline 16 October 2005, CCC 2 March 2020.

Has One Seputeh's handover deadline been extended?

Yes, according to KPKT. One Seputeh is registered as Residensi Seputeh 1 (30947-1, 383 serviced apartments, Seputeh Kukuh Sdn Bhd). The first sale agreement is dated 26 March 2026 and the handover deadline of 26 March 2029 has been extended with approval by 16 months to 26 July 2030. It is recorded as on schedule (Lancar), with 21% reported progress.

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
  2. [1] Asiabina Group — home page (projects, offices) · Asiabina Sdn Bhd · accessed 28 Oct 2026
    https://asiabina.com/
  3. [2] Perak-based Asiabina Group to launch first Klang Valley project next month · The Edge Malaysia · 9 Aug 2026 · accessed 28 Oct 2026
    https://theedgemalaysia.com/node/813678
  4. [3] About us · Asiabina Sdn Bhd · accessed 28 Oct 2026
    https://asiabina.com/about-us/
  5. [4] Asiabina powering Perak's growth through vision, innovation and impact (sponsored content) · Asiabina Group, in The Edge Malaysia · accessed 28 Oct 2026
    https://theedgemalaysia.com/content/advertise/asiabina-powering-peraks-growth-through-vision-innovation-and-impact
  6. [5] One Seputeh Residences — project page · Asiabina Sdn Bhd · accessed 28 Oct 2026
    https://asiabina.com/property/one-seputeh-freehold-luxury/

Last updated 28 Oct 2026