UOA (UOA Development Bhd)
UOA Development Bhd, the Bursa Malaysia-listed development arm of United Overseas Australia Ltd, has 30 housing projects in the KPKT register under 21 UOA companies: 27 completed and 3 under construction, none classed Sick, Abandoned or Late. All but one are in Kuala Lumpur. The group was founded in 1987 and has been based in Kuala Lumpur since 1989.
- 30 projects in the KPKT register
- 27 completed
- 3 under construction
- None Sick or Abandoned
Has UOA handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 30 housing projects under 21 UOA companies in 2 states: 27 completed, 3 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 27 completed projects, 19 have both a handover deadline and a completion date in the register: 1 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 3 handed over or certified complete after that deadline; 15 received the completion certificate before the deadline (handover date not recorded).
12 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 27
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BUKIT ASTER SRI PETALINGKPKT 19787-3Aster Hill · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 575 | 5 Mar 2027Extended 12 months from 5 Mar 20261st sale agreement 5 Mar 2023 | CCC 14 Apr 2026 Handover 3 Jun 2026 | 275 days before |
| BUKIT ASTER SRI PETALINGKPKT 19787-2Aster Hill · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 575 | 11 Jul 2027Extended 12 months from 11 Jul 20261st sale agreement 11 Jul 2023 | CCC 14 Apr 2026 | CCC before deadline; handover not recorded |
| RESIDENSI LAUREL, BANGSAR SELATANKPKT 10697-4Laurel Residence · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,260 | 16 Mar 2026Extended 12 months from 16 Mar 20251st sale agreement 16 Mar 2022 | CCC 30 Oct 2024 | CCC before deadline; handover not recorded |
| ASTER GREEN RESIDENCEKPKT 19787-1 | Kuala LumpurWP Kuala Lumpur | 440 | 27 Apr 2023Extended 6 months from 27 Oct 20221st sale agreement 27 Oct 2019 | CCC 29 Aug 2022 | CCC before deadline; handover not recorded |
| RESIDENSI LAMAN PERMAIKPKT 10697-3The Goodwood Residence · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 678 | 9 Feb 2023Extended 6 months from 9 Aug 20221st sale agreement 9 Aug 2019 | CCC 6 Apr 2022 | CCC before deadline; handover not recorded |
| RESIDENSI SAMBUNGAN SELATANKPKT 19274-1 | Kuala LumpurWP Kuala Lumpur | 1,422 | 29 May 2023Extended 28 months from 29 Jan 20211st sale agreement 29 Jan 2018 | CCC 15 Apr 2021 | CCC before deadline; handover not recorded |
| PUNCAK SENTULKPKT 14395-2 | Kuala LumpurWP Kuala Lumpur | 952 | 8 Jan 2022Extended 18 months from 8 Jul 20201st sale agreement 8 Jul 2017 | CCC 17 Feb 2021 | CCC before deadline; handover not recorded |
| RESIDENSI SELAYANG DAMAIKPKT 19181-1 | Kuala LumpurWP Kuala Lumpur | 304 | 22 May 20211st sale agreement 22 May 2018 | CCC 14 Aug 2020 | CCC before deadline; handover not recorded |
| PUNCAK SENTULKPKT 14395-1 | Kuala LumpurWP Kuala Lumpur | 1,400 | 12 Jul 2020Extended 12 months from 12 Jul 20191st sale agreement 12 Jul 2016 | CCC 2 Jun 2020 | CCC before deadline; handover not recorded |
| PUSAT PERDAGANGAN BERPADUKPKT 14325-1 | Kuala LumpurWP Kuala Lumpur | 2,509 | 26 May 2021Extended 24 months from 26 May 20191st sale agreement 26 May 2016 | CCC 19 Dec 2019 | CCC before deadline; handover not recorded |
| PANGSAPURI SUITE DANAU KOTAKPKT 14260-1 | Kuala LumpurWP Kuala Lumpur | 285 | 1 Mar 20191st sale agreement 29 Feb 2016 | CCC 16 Aug 2018 | CCC before deadline; handover not recorded |
| RESIDENSI TEBING SELATANKPKT 13512-1 | Kuala LumpurWP Kuala Lumpur | 674 | 27 May 20171st sale agreement 27 May 2014 | CCC 29 Aug 2017 | 94 days after |
Handed over or certified complete after the deadline (3)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI TEBING SELATANKPKT 13512-1 | Kuala LumpurWP Kuala Lumpur | 674 | 27 May 20171st sale agreement 27 May 2014 | CCC 29 Aug 2017 | 94 days after |
| KEDIAMAN INDAH SELATANKPKT 13226-1 | Kuala LumpurWP Kuala Lumpur | 1,204 | 24 Oct 20161st sale agreement 24 Oct 2013 | CCC 18 May 2017 | 206 days after |
| DESA GREENKPKT 11684-2 | Kuala LumpurWP Kuala Lumpur | 1,388 | 3 Dec 20141st sale agreement 3 Dec 2011 | CCC 3 Jun 2016 | 548 days after |
Show all 27 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BUKIT ASTER SRI PETALINGKPKT 19787-3Aster Hill · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 575 | 5 Mar 2027Extended 12 months from 5 Mar 20261st sale agreement 5 Mar 2023 | CCC 14 Apr 2026 Handover 3 Jun 2026 | 275 days before |
| BUKIT ASTER SRI PETALINGKPKT 19787-2Aster Hill · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 575 | 11 Jul 2027Extended 12 months from 11 Jul 20261st sale agreement 11 Jul 2023 | CCC 14 Apr 2026 | CCC before deadline; handover not recorded |
| RESIDENSI LAUREL, BANGSAR SELATANKPKT 10697-4Laurel Residence · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,260 | 16 Mar 2026Extended 12 months from 16 Mar 20251st sale agreement 16 Mar 2022 | CCC 30 Oct 2024 | CCC before deadline; handover not recorded |
| ASTER GREEN RESIDENCEKPKT 19787-1 | Kuala LumpurWP Kuala Lumpur | 440 | 27 Apr 2023Extended 6 months from 27 Oct 20221st sale agreement 27 Oct 2019 | CCC 29 Aug 2022 | CCC before deadline; handover not recorded |
| RESIDENSI LAMAN PERMAIKPKT 10697-3The Goodwood Residence · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 678 | 9 Feb 2023Extended 6 months from 9 Aug 20221st sale agreement 9 Aug 2019 | CCC 6 Apr 2022 | CCC before deadline; handover not recorded |
| RESIDENSI SAMBUNGAN SELATANKPKT 19274-1 | Kuala LumpurWP Kuala Lumpur | 1,422 | 29 May 2023Extended 28 months from 29 Jan 20211st sale agreement 29 Jan 2018 | CCC 15 Apr 2021 | CCC before deadline; handover not recorded |
| PUNCAK SENTULKPKT 14395-2 | Kuala LumpurWP Kuala Lumpur | 952 | 8 Jan 2022Extended 18 months from 8 Jul 20201st sale agreement 8 Jul 2017 | CCC 17 Feb 2021 | CCC before deadline; handover not recorded |
| RESIDENSI SELAYANG DAMAIKPKT 19181-1 | Kuala LumpurWP Kuala Lumpur | 304 | 22 May 20211st sale agreement 22 May 2018 | CCC 14 Aug 2020 | CCC before deadline; handover not recorded |
| PUNCAK SENTULKPKT 14395-1 | Kuala LumpurWP Kuala Lumpur | 1,400 | 12 Jul 2020Extended 12 months from 12 Jul 20191st sale agreement 12 Jul 2016 | CCC 2 Jun 2020 | CCC before deadline; handover not recorded |
| PUSAT PERDAGANGAN BERPADUKPKT 14325-1 | Kuala LumpurWP Kuala Lumpur | 2,509 | 26 May 2021Extended 24 months from 26 May 20191st sale agreement 26 May 2016 | CCC 19 Dec 2019 | CCC before deadline; handover not recorded |
| PANGSAPURI SUITE DANAU KOTAKPKT 14260-1 | Kuala LumpurWP Kuala Lumpur | 285 | 1 Mar 20191st sale agreement 29 Feb 2016 | CCC 16 Aug 2018 | CCC before deadline; handover not recorded |
| RESIDENSI TEBING SELATANKPKT 13512-1 | Kuala LumpurWP Kuala Lumpur | 674 | 27 May 20171st sale agreement 27 May 2014 | CCC 29 Aug 2017 | 94 days after |
| KEDIAMAN INDAH SELATANKPKT 13226-1 | Kuala LumpurWP Kuala Lumpur | 1,204 | 24 Oct 20161st sale agreement 24 Oct 2013 | CCC 18 May 2017 | 206 days after |
| PANGSAPURI SERVIS DESA SENTULKPKT 13555-1 | Kuala LumpurWP Kuala Lumpur | 462 | 26 Jun 20171st sale agreement 26 Jun 2014 | CCC 11 Apr 2017 | CCC before deadline; handover not recorded |
| SUITE SERVIS SURIAKPKT 14073-1 | Kuala LumpurWP Kuala Lumpur | 175 | 25 Jul 20181st sale agreement 25 Jul 2015 | CCC 7 Apr 2017 | CCC before deadline; handover not recorded |
| DESA GREENKPKT 11684-2 | Kuala LumpurWP Kuala Lumpur | 1,388 | 3 Dec 20141st sale agreement 3 Dec 2011 | CCC 3 Jun 2016 | 548 days after |
| LAMAN SCENARIA KIARAKPKT 8421-2 | Kuala LumpurWP Kuala Lumpur | 981 | 6 Dec 20151st sale agreement 6 Dec 2012 | CCC 25 Nov 2015 | CCC before deadline; handover not recorded |
| LE YUAN (RESIDENSI GEMBIRA)KPKT 11799-1 | Kuala LumpurWP Kuala Lumpur | 670 | 23 Nov 20141st sale agreement 23 Nov 2011 | CCC 6 Nov 2014 | CCC before deadline; handover not recorded |
| DESA 2KPKT 11684-1 | Kuala LumpurWP Kuala Lumpur | 24 | 1 Mar 20151st sale agreement 1 Mar 2012 | CCC 4 Aug 2014 | CCC before deadline; handover not recorded |
| LOT 58191 & LOT 58192KPKT 10697-2 | Kuala LumpurWP Kuala Lumpur | 720 | — | CCC 27 Sep 2013 | — |
| SETAPAK GREEN RESIDENCESKPKT 10115-2 | Kuala LumpurWP Kuala Lumpur | 445 | — | CCC 17 Jan 2013 | — |
| BINJAI 8KPKT 11087-1 | Kuala LumpurWP Kuala Lumpur | 310 | — | CCC 5 Oct 2012 | — |
| LOT 61588 - LOT 61591 & PT 25759KPKT 11201-1 | Kuala LumpurWP Kuala Lumpur | 20 | — | CCC 20 Jan 2012 | — |
| BANGSAR SOUTHKPKT 10697-1 | Kuala LumpurWP Kuala Lumpur | 470 | — | CCC 3 Aug 2010 | — |
| Plaza ManjalaraKPKT 8603-4 | Kuala LumpurWP Kuala Lumpur | 234 | — | CFO 9 Nov 2009 | — |
| PRIMA SETAPAK IIKPKT 7343-3 | Kuala LumpurWP Kuala Lumpur | 248 | — | CFO 10 Sep 2008 | — |
| TAMAN MEGAH KEPONGKPKT 8603-2 | Kuala LumpurWP Kuala Lumpur | 219 | — | CCC 9 Aug 2005 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI BUKIT BAMBOOKPKT 30343-2Bamboo Hills Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 755 | SmoothOn schedule | 13 Jul 2029Extended 24 months from 13 Jul 20271st sale agreement 13 Jul 2024 | 54% |
| RESIDENSI BUKIT BAMBOOKPKT 30343-1Bamboo Hills Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,762 | SmoothOn schedule | 2 Aug 2029Extended 24 months from 2 Aug 20271st sale agreement 2 Aug 2024 | 55% |
| RESIDENSI AETHERAKPKT 31157-1 | Johor | 786 | SmoothOn schedule | 11 Aug 2030Extended 18 months from 11 Feb 20291st sale agreement 11 Feb 2026 | 20% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
UOA at a glance
| Listed | Bursa Malaysia Main Market · UOADEV (5200) · listed 8 June 2011; parent United Overseas Australia Ltd is listed in Australia and Singapore[1][4][2] |
|---|---|
| Started | 1987, as United Overseas Australia Ltd (listed on the Australian Stock Exchange that year); headquartered in Kuala Lumpur since 1989[3] |
| Head office | Bangsar South City, Jalan Kerinchi, Kuala Lumpur[1] |
| Leadership | Kong Pak Lim — Chairman[1] Kong Chong Soon @ Chi Suim — Managing Director; co-founded United Overseas Australia in 1987[1] |
| Companies in the KPKT register | SUNNY UPTOWN SDN. BHD. KPKT 10697[1][5] CONCORD HOUSING DEVELOPMENT SDN. BHD. KPKT 30343[1] COSMO HOUSING DEVELOPMENT SDN. BHD. KPKT 19787[1] CITRA JAYA SEJAHTERA SDN. BHD. KPKT 19274[1] INFINITE ACCOMPLISHMENT SDN. BHD. KPKT 14395[1] IDP INDUSTRIAL DEVELOPMENT SDN. BHD. KPKT 14325[1] TOPVIEW HOUSING SDN. BHD. KPKT 19181[1] NOVA METRO DEVELOPMENT SDN. BHD. (85%) KPKT 14260[1] SERI TIARA DEVELOPMENT SDN. BHD. (85%) KPKT 11684[1] MIDTOWN SANCTUARY SDN. BHD. (75%) KPKT 31157[1] EUREKA EQUITY SDN. BHD. (60%) KPKT 13512[1] EVERISE TIARA (M) SDN. BHD. (60%) KPKT 8421[1] SCENIC POINT DEVELOPMENT SDN. BHD. (60%) KPKT 11087[1] PARAMOUNT PROPERTIES SDN. BHD KPKT 13226[1] ORIENT HOUSING DEVELOPMENT SDN. BHD. KPKT 13555[1] MAXIM DEVELOPMENT SDN. BHD. KPKT 14073[1] MAGNA TIARA DEVELOPMENT SDN. BHD. KPKT 11799[1] SAGAHARTA SDN. BHD. KPKT 10115[1] PARAMOUNT HILLS SDN. BHD. KPKT 11201[1] WINDSOR TRIUMPH SDN. BHD. KPKT 8603[1] KUMPULAN SEJAHTERA SDN. BHD. KPKT 7343[1] |
| Website | uoa.com.my |
| Completed projects (company figure) | More than RM21.5 billion in gross development value completed and delivered, as at 31 December 2025 (group-wide)[3] |
| Land bank (company figure) | About 80 acres, to be developed over the next 10 years (as at 31 December 2025)[3] |
| Holding companies | Ultimate holding company: United Overseas Australia Ltd (incorporated in Australia, listed on the Australian and Singapore stock exchanges); immediate holding company: UOA Holdings Sdn Bhd[1] |
UOA projects on sale on PropertySifu
Aster Hill
- RESIDENSI TEBING SELATAN — 3.3 km, 2017
- DESA GREEN — 3.4 km, 2016
- RESIDENSI LAMAN PERMAI — 4.7 km, 2022
Bamboo Hills Residences
- PANGSAPURI SERVIS DESA SENTUL — 1.5 km, 2017
- PUNCAK SENTUL — 1.6 km, 2021
- PUNCAK SENTUL — 1.8 km, 2020
Laurel Residence
- RESIDENSI SAMBUNGAN SELATAN — 0.5 km, 2021
- KEDIAMAN INDAH SELATAN — 0.5 km, 2017
- RESIDENSI TEBING SELATAN — 1.5 km, 2017
The Goodwood Residence
- RESIDENSI SAMBUNGAN SELATAN — 0.5 km, 2021
- KEDIAMAN INDAH SELATAN — 0.5 km, 2017
- RESIDENSI TEBING SELATAN — 1.6 km, 2017
Who is UOA? The company behind the projects
UOA was founded in 1987 as United Overseas Australia Ltd, which listed on the Australian Stock Exchange that year, and it has been headquartered in Kuala Lumpur since 1989 [3]. Its managing director, Kong Chong Soon @ Chi Suim, co-founded the company [1]. On 8 June 2011 the group listed its construction and development arm, UOA Development Bhd, on the Main Market of Bursa Malaysia [4][3]; United Overseas Australia, listed in Australia and Singapore, remains the ultimate holding company [1]. The chairman is Kong Pak Lim [1].
UOA says that, as at 31 December 2025, it had completed and delivered projects with a gross development value of more than RM21.5 billion, and held a land bank of about 80 acres to be developed over the next 10 years [3]. These are group-wide figures that include offices and shops; the KPKT register counts only projects licensed as housing.
The 30 registered projects sit under 21 subsidiaries named in UOA Development's 2025 annual report [1]. Most are wholly owned; the exceptions are Scenic Point Development, Eureka Equity and Everise Tiara (M) at 60%, Nova Metro Development and Seri Tiara Development at 85%, and Midtown Sanctuary at 75%, whose Residensi Aethera is the group's only registered project in Johor [1]. Laurel Residence in Bangsar South carries developer licence 10697 [5], held by Sunny Uptown Sdn Bhd; KPKT registers Bamboo Hills Residences in Segambut under Concord Housing Development Sdn Bhd and Aster Hill in Sri Petaling under Cosmo Housing Development Sdn Bhd.
Frequently asked questions
Is UOA a listed company?
How many projects has UOA completed?
In the KPKT register, 27 of the 30 housing projects under 21 UOA companies are completed, covering 18,644 of 21,947 approved units. UOA says its completed and delivered projects had a gross development value of more than RM21.5 billion as at 31 December 2025 [3]; that group figure also covers projects outside the KPKT housing register.
Does UOA have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 30 UOA projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat).
Has the handover deadline of Bamboo Hills Residences been extended?
Yes, according to KPKT. Both registrations, named Residensi Bukit Bamboo, carry an approved 24-month extension: 30343-1 (1,762 units, first sale agreement 2 August 2024) from 2 August 2027 to 2 August 2029, and 30343-2 (755 units, first sale agreement 13 July 2024) from 13 July 2027 to 13 July 2029. Both are recorded as on schedule (Lancar), at 54.5% reported progress.
Has Laurel Residence been completed?
Yes. KPKT records 10697-4 (registered as Residensi Laurel, Bangsar Selatan; 1,260 units in two blocks) as completed, with a CCC dated 30 October 2024 for both blocks, 502 days before its deadline, which had been extended with approval by 12 months to 16 March 2026. Vacant possession is registered for one block on 17 December 2024; the register shows no handover date for the other.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] UOA Development Bhd Annual Report 2025 (Note 1 General information; Note 7 Investment in subsidiaries; corporate information; directors' profiles) · UOA Development Bhd via Bursa Malaysia · 27 Apr 2026 · accessed 28 Oct 2026
https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3658927 - [2] UOA DEVELOPMENT BHD (5200) company profile · Bursa Malaysia · accessed 28 Oct 2026
https://www.bursamalaysia.com/trade/trading_resources/listing_directory/company-profile?stock_code=5200 - [3] Group profile · UOA Group · accessed 28 Oct 2026
https://uoa.com.my/about-us/group-profile/ - [4] UOA Development makes lacklustre debut · EdgeProp Malaysia (The Edge) · 8 Jun 2011 · accessed 28 Oct 2026