Scientex (Scientex Berhad)
Scientex Berhad is a Bursa Malaysia-listed manufacturer and property developer with 241 housing projects in the KPKT register: 180 completed, 59 under construction and 2 not yet started, under seven Scientex companies in seven states, none classed Sick or Abandoned. Founded in Johor in 1968, it has built homes since 1995, mainly affordable homes in its own townships.
- 241 projects in the KPKT register
- 180 completed
- 59 under construction
- 2 not yet started
- None Sick or Abandoned
Has Scientex handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 241 housing projects under 7 Scientex companies in 7 states: 180 completed, 59 under construction, 2 not yet started. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 180 completed projects, 163 have both a handover deadline and a completion date in the register: 86 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 30 handed over or certified complete after that deadline (5 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 47 received the completion certificate before the deadline (handover date not recorded).
27 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 180
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| SCIENTEX SUNGAI DUAKPKT 11295-25 | Seberang Perai UtaraPulau Pinang | 364 | 31 Dec 20261st sale agreement 31 Dec 2024 | CCC 9 Oct 2026 Handover 9 Oct 2026 | 83 days before |
| TAMAN KLEBANG SEROJAKPKT 9294-71 | Perak | 115 | 24 Jan 20271st sale agreement 24 Jan 2025 | CCC 24 Sep 2026 Handover 28 Sep 2026 | 118 days before |
| TAMAN AROWANA EMASKPKT 11295-26 | Kuala MudaKedah | 227 | 31 Mar 20271st sale agreement 31 Mar 2025 | CCC 18 Sep 2026 Handover 18 Sep 2026 | 194 days before |
| TAMAN PULAI DUTAKPKT 9294-66 | Johor BahruJohor | 235 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 27 Jul 2026 Handover 27 Jul 2026 | 4 days before |
| TAMAN AROWANA EMASKPKT 11295-24 | Kuala MudaKedah | 214 | 31 Aug 20261st sale agreement 31 Aug 2024 | CCC 9 Jul 2026 Handover 9 Jul 2026 | 53 days before |
| TAMAN KLEBANG SEROJAKPKT 9294-68 | KintaPerak | 210 | 30 Oct 20261st sale agreement 30 Oct 2024 | CCC 3 Jul 2026 Handover 6 Jul 2026 | 116 days before |
| BANDAR SCIENTEX JASIN PRESINT 1KPKT 6575-46 | JasinMelaka | 159 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 30 Jun 2026 Handover 30 Jun 2026 | 31 days before |
| BANDAR SCIENTEX JASIN PRESINT 1KPKT 6575-47 | JasinMelaka | 170 | 30 Nov 20261st sale agreement 30 Nov 2024 | CCC 30 Jun 2026 Handover 30 Jun 2026 | 153 days before |
| TAMAN PULAI DUTAKPKT 9294-65 | Johor BahruJohor | 272 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 29 Jun 2026 Handover 29 Jun 2026 | 1 day before |
| SCIENTEX JENJAROMKPKT 30714-2 | Kuala LangatSelangor | 224 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 25 Jun 2026 Handover 25 Jun 2026 | 5 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-23 | Seberang Perai UtaraPulau Pinang | 291 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 23 Jun 2026 Handover 23 Jun 2026 | 38 days before |
| SCIENTEX JENJAROMKPKT 30714-1 | Kuala LangatSelangor | 224 | 25 May 20261st sale agreement 25 May 2024 | CCC 22 May 2026 Handover 22 May 2026 | 3 days before |
Handed over or certified complete after the deadline — 12 most recent of 30
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-9 | Seberang Perai UtaraPulau Pinang | 386 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 30 Nov 2023 Handover 30 Nov 2023 | 61 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-15 | GombakSelangor | 218 | 30 Jun 20231st sale agreement 30 Jun 2021 | CCC 20 Oct 2023 Handover 20 Oct 2023 | 112 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-14 | GombakSelangor | 277 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 16 Oct 2023 Handover 16 Oct 2023 | 16 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-11 | Seberang Perai UtaraPulau Pinang | 203 | 31 Aug 20231st sale agreement 31 Aug 2021 | CCC 6 Oct 2023 Handover 6 Oct 2023 | 36 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-10 | Seberang Perai UtaraPulau Pinang | 279 | 30 Jul 20231st sale agreement 30 Jul 2021 | CCC 14 Aug 2023 Handover 14 Aug 2023 | 15 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-13 | GombakSelangor | 248 | 30 Jun 2023Extended 5 months from 30 Jan 20231st sale agreement 30 Jan 2021 | CCC 1 Aug 2023 Handover 1 Aug 2023 | 32 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-8 | Seberang Perai UtaraPulau Pinang | 314 | 1 Jul 2023Extended 5 months from 31 Jan 20231st sale agreement 31 Jan 2021 | CCC 3 Jul 2023 Handover 3 Jul 2023 | 2 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-12 | GombakSelangor | 393 | 30 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020 | CCC 7 Apr 2023 Handover 7 Apr 2023 | 8 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-54 | Johor BahruJohor | 84 | 11 Jan 20211st sale agreement 11 Jan 2019 | CCC 27 Jan 2021 | 16 days after † |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-12 | Alor GajahMelaka | 104 | 15 Oct 20201st sale agreement 15 Oct 2018 | CCC 27 Nov 2020 | 43 days after † |
| SCIENTEX QUATARI SDN BHDKPKT 9294-45 | Johor BahruJohor | 160 | 31 Dec 20191st sale agreement 31 Dec 2017 | CCC 21 Oct 2020 | 295 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-37 | KulaiJohor | 43 | 31 May 20201st sale agreement 31 May 2018 | CFO 1 Sep 2020 | 93 days after † |
Show all 30
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-9 | Seberang Perai UtaraPulau Pinang | 386 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 30 Nov 2023 Handover 30 Nov 2023 | 61 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-15 | GombakSelangor | 218 | 30 Jun 20231st sale agreement 30 Jun 2021 | CCC 20 Oct 2023 Handover 20 Oct 2023 | 112 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-14 | GombakSelangor | 277 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 16 Oct 2023 Handover 16 Oct 2023 | 16 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-11 | Seberang Perai UtaraPulau Pinang | 203 | 31 Aug 20231st sale agreement 31 Aug 2021 | CCC 6 Oct 2023 Handover 6 Oct 2023 | 36 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-10 | Seberang Perai UtaraPulau Pinang | 279 | 30 Jul 20231st sale agreement 30 Jul 2021 | CCC 14 Aug 2023 Handover 14 Aug 2023 | 15 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-13 | GombakSelangor | 248 | 30 Jun 2023Extended 5 months from 30 Jan 20231st sale agreement 30 Jan 2021 | CCC 1 Aug 2023 Handover 1 Aug 2023 | 32 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-8 | Seberang Perai UtaraPulau Pinang | 314 | 1 Jul 2023Extended 5 months from 31 Jan 20231st sale agreement 31 Jan 2021 | CCC 3 Jul 2023 Handover 3 Jul 2023 | 2 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-12 | GombakSelangor | 393 | 30 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020 | CCC 7 Apr 2023 Handover 7 Apr 2023 | 8 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-54 | Johor BahruJohor | 84 | 11 Jan 20211st sale agreement 11 Jan 2019 | CCC 27 Jan 2021 | 16 days after † |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-12 | Alor GajahMelaka | 104 | 15 Oct 20201st sale agreement 15 Oct 2018 | CCC 27 Nov 2020 | 43 days after † |
| SCIENTEX QUATARI SDN BHDKPKT 9294-45 | Johor BahruJohor | 160 | 31 Dec 20191st sale agreement 31 Dec 2017 | CCC 21 Oct 2020 | 295 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-37 | KulaiJohor | 43 | 31 May 20201st sale agreement 31 May 2018 | CFO 1 Sep 2020 | 93 days after † |
| SCIENTEX MERU 2KPKT 9294-39 | KintaPerak | 235 | 7 Jun 20201st sale agreement 7 Jun 2018 | CCC 12 Aug 2020 | 66 days after † |
| TAMAN SCIENTEXKPKT 9294-23 | Johor BahruJohor | 538 | 28 Aug 20191st sale agreement 28 Aug 2017 | CCC 30 Jul 2020 | 337 days after |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-7 | Alor GajahMelaka | 320 | 5 Jun 20201st sale agreement 5 Jun 2018 | CCC 7 Jul 2020 | 32 days after † |
| SCIENTEX QUATARI SDN BHDKPKT 9294-27 | Johor BahruJohor | 466 | 9 Oct 20181st sale agreement 9 Oct 2016 | CCC 30 Nov 2019 | 417 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-28 | Johor BahruJohor | 622 | 17 Oct 20171st sale agreement 17 Oct 2015 | CFO 22 Oct 2018 | 370 days after |
| THE HEIGHTS RESIDENCE - TAMAN MUZAFFAR HEIGHTSKPKT 6575-5 | Melaka TengahMelaka | 786 | 28 Aug 20171st sale agreement 28 Aug 2014 | CCC 28 Mar 2018 | 212 days after |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-3 | Johor BahruJohor | 1,148 | 15 Feb 20161st sale agreement 15 Feb 2013 | CCC 1 Nov 2017 | 625 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-20 | KulaiJohor | 416 | 19 May 20171st sale agreement 19 May 2015 | CCC 29 Sep 2017 | 133 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-19 | Batu PahatJohor | 350 | 9 Jan 20171st sale agreement 9 Jan 2015 | CCC 10 Jul 2017 | 182 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-21 | Johor BahruJohor | 718 | 4 Jul 20171st sale agreement 4 Jul 2015 | CCC 5 Jul 2017 | 1 day after |
| TAMAN SCIENTEXKPKT 6331-7 | Johor BahruJohor | 492 | 24 Sep 20161st sale agreement 24 Sep 2014 | CCC 14 Feb 2017 | 143 days after |
| TAMAN MUZAFFAR HEIGHTSKPKT 6575-4 | Melaka TengahMelaka | 226 | 14 Mar 20141st sale agreement 14 Mar 2012 | CFO 14 Jul 2016 | 853 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-16 | KulaiJohor | 379 | 18 Mar 20161st sale agreement 18 Mar 2014 | CFO 25 May 2016 | 68 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-15 | KulaiJohor | 350 | 26 Dec 20151st sale agreement 26 Dec 2013 | CFO 15 Mar 2016 | 80 days after |
| TAMAN SCIENTEXKPKT 9294-11 | Johor BahruJohor | 174 | 12 Dec 20131st sale agreement 12 Dec 2011 | CCC 10 Feb 2016 | 790 days after |
| TAMAN SCIENTEXKPKT 9294-14 | Johor BahruJohor | 599 | 21 Feb 20151st sale agreement 21 Feb 2013 | CCC 11 Jan 2016 | 324 days after |
| SCIENTEX - KULAIKPKT 9294-13 | KulaiJohor | 442 | 8 Oct 20141st sale agreement 8 Oct 2012 | CCC 1 Sep 2015 | 328 days after |
| TAMAN SCIENTEXKPKT 6331-5 | Johor BahruJohor | 254 | 8 Apr 20141st sale agreement 8 Apr 2012 | CCC 1 Jun 2015 | 419 days after |
Show all 180 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| SCIENTEX SUNGAI DUAKPKT 11295-25 | Seberang Perai UtaraPulau Pinang | 364 | 31 Dec 20261st sale agreement 31 Dec 2024 | CCC 9 Oct 2026 Handover 9 Oct 2026 | 83 days before |
| TAMAN KLEBANG SEROJAKPKT 9294-71 | Perak | 115 | 24 Jan 20271st sale agreement 24 Jan 2025 | CCC 24 Sep 2026 Handover 28 Sep 2026 | 118 days before |
| TAMAN AROWANA EMASKPKT 11295-26 | Kuala MudaKedah | 227 | 31 Mar 20271st sale agreement 31 Mar 2025 | CCC 18 Sep 2026 Handover 18 Sep 2026 | 194 days before |
| TAMAN PULAI DUTAKPKT 9294-66 | Johor BahruJohor | 235 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 27 Jul 2026 Handover 27 Jul 2026 | 4 days before |
| TAMAN AROWANA EMASKPKT 11295-24 | Kuala MudaKedah | 214 | 31 Aug 20261st sale agreement 31 Aug 2024 | CCC 9 Jul 2026 Handover 9 Jul 2026 | 53 days before |
| TAMAN KLEBANG SEROJAKPKT 9294-68 | KintaPerak | 210 | 30 Oct 20261st sale agreement 30 Oct 2024 | CCC 3 Jul 2026 Handover 6 Jul 2026 | 116 days before |
| BANDAR SCIENTEX JASIN PRESINT 1KPKT 6575-46 | JasinMelaka | 159 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 30 Jun 2026 Handover 30 Jun 2026 | 31 days before |
| BANDAR SCIENTEX JASIN PRESINT 1KPKT 6575-47 | JasinMelaka | 170 | 30 Nov 20261st sale agreement 30 Nov 2024 | CCC 30 Jun 2026 Handover 30 Jun 2026 | 153 days before |
| TAMAN PULAI DUTAKPKT 9294-65 | Johor BahruJohor | 272 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 29 Jun 2026 Handover 29 Jun 2026 | 1 day before |
| SCIENTEX JENJAROMKPKT 30714-2 | Kuala LangatSelangor | 224 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 25 Jun 2026 Handover 25 Jun 2026 | 5 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-23 | Seberang Perai UtaraPulau Pinang | 291 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 23 Jun 2026 Handover 23 Jun 2026 | 38 days before |
| SCIENTEX JENJAROMKPKT 30714-1 | Kuala LangatSelangor | 224 | 25 May 20261st sale agreement 25 May 2024 | CCC 22 May 2026 Handover 22 May 2026 | 3 days before |
| TAMAN SCIENTEX JASIN MUTIARAKPKT 6575-45 | JasinMelaka | 281 | 30 Sep 20261st sale agreement 30 Sep 2024 | CCC 21 May 2026 Handover 21 May 2026 | 132 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-22 | Seberang Perai UtaraPulau Pinang | 204 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 29 Apr 2026 Handover 30 Apr 2026 | 61 days before |
| SCIENTEX BANDAR JASINKPKT 6575-44 | JasinMelaka | 289 | 28 Jun 20261st sale agreement 28 Jun 2024 | CCC 30 Apr 2026 Handover 30 Apr 2026 | 59 days before |
| TAMAN KLEBANG LESTARIKPKT 9294-64 | KintaPerak | 122 | 25 May 20261st sale agreement 25 May 2024 | CCC 30 Mar 2026 Handover 31 Mar 2026 | 55 days before |
| SCIENTEX BANDAR JASINKPKT 6575-42 | JasinMelaka | 188 | 30 Apr 20261st sale agreement 30 Apr 2024 | CCC 6 Mar 2026 Handover 6 Mar 2026 | 55 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-21 | Seberang Perai UtaraPulau Pinang | 282 | 30 Apr 20261st sale agreement 30 Apr 2024 | CCC 20 Feb 2026 Handover 24 Feb 2026 | 65 days before |
| TAMAN PULAI DUTAKPKT 9294-62 | Johor BahruJohor | 342 | 31 Jan 20261st sale agreement 31 Jan 2024 | CCC 29 Jan 2026 Handover 29 Jan 2026 | 2 days before |
| SCIENTEX IPOHKPKT 9294-63 | KintaPerak | 238 | 31 Jan 20261st sale agreement 31 Jan 2024 | CCC 29 Jan 2026 Handover 29 Jan 2026 | 2 days before |
| TAMAN SCIENTEX JASIN MUTIARAKPKT 6575-43 | JasinMelaka | 211 | 28 May 20261st sale agreement 28 May 2024 | CCC 3 Dec 2025 Handover 4 Dec 2025 | 175 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-20 | Seberang Perai UtaraPulau Pinang | 240 | 31 Jan 20261st sale agreement 31 Jan 2024 | CCC 21 Nov 2025 Handover 21 Nov 2025 | 71 days before |
| TAMAN AROWANAKPKT 11295-19 | Kuala MudaKedah | 268 | 31 Jan 20261st sale agreement 31 Jan 2024 | CCC 29 Sep 2025 Handover 29 Sep 2025 | 124 days before |
| TAMAN SCIENTEX KOTA TINGGIKPKT 19794-17 | Kota TinggiJohor | 99 | 1 Mar 20261st sale agreement 29 Feb 2024 | CCC 11 Sep 2025 Handover 11 Sep 2025 | 171 days before |
| SCIENTEX BANDAR JASINKPKT 6575-41 | JasinMelaka | 118 | 29 Dec 20251st sale agreement 29 Dec 2023 | CCC 31 Jul 2025 Handover 31 Jul 2025 | 151 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-18 | Pulau Pinang | 222 | 28 Sep 20251st sale agreement 28 Sep 2023 | CCC 28 Jul 2025 Handover 28 Jul 2025 | 62 days before |
| TAMAN AROWANAKPKT 11295-17 | Kuala MudaKedah | 251 | 31 Jul 20251st sale agreement 31 Jul 2023 | CCC 23 Jul 2025 Handover 23 Jul 2025 | 8 days before |
| SCIENTEX BANDAR JASINKPKT 6575-40 | JasinMelaka | 336 | 31 Oct 20251st sale agreement 31 Oct 2023 | CCC 10 Jul 2025 Handover 11 Jul 2025 | 112 days before |
| MORI RESIDENCESKPKT 6331-16 | GombakSelangor | 638 | 29 Jun 2026Extended 12 months from 29 Jun 20251st sale agreement 29 Jun 2022 | CCC 30 Jun 2025 Handover 10 Jul 2025 | 354 days before |
| SCIENTEX SEREMBANKPKT 6331-24 | SerembanNegeri Sembilan | 97 | 15 Sep 20251st sale agreement 15 Sep 2023 | CCC 8 Jul 2025 Handover 8 Jul 2025 | 69 days before |
| SCIENTEX JASINKPKT 6575-36 | JasinMelaka | 224 | 31 Oct 20251st sale agreement 31 Oct 2023 | CCC 26 Jun 2025 Handover 30 Jun 2025 | 123 days before |
| SCIENTEX KUNDANG JAYAKPKT 6331-23 | GombakSelangor | 298 | 31 Jul 20251st sale agreement 31 Jul 2023 | CCC 26 Jun 2025 Handover 30 Jun 2025 | 31 days before |
| PANGSAPURI CENDERA 1KPKT 19794-5 | Johor BahruJohor | 609 | 10 Dec 20251st sale agreement 10 Dec 2022 | CCC 13 Jun 2025 Handover 13 Jun 2025 | 180 days before |
| SCIENTEX SUNGAI DUAKPKT 11295-16 | Seberang Perai UtaraPulau Pinang | 309 | 30 Jun 20251st sale agreement 30 Jun 2023 | CCC 12 Jun 2025 Handover 12 Jun 2025 | 18 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-16 | Johor BahruJohor | 256 | 31 May 20251st sale agreement 31 May 2023 | CCC 28 May 2025 Handover 28 May 2025 | 3 days before |
| SCIENTEX SEREMBANKPKT 6331-21 | SerembanNegeri Sembilan | 93 | 28 Apr 20251st sale agreement 28 Apr 2023 | CCC 27 Feb 2025 Handover 28 Feb 2025 | 59 days before |
| SCIENTEX BANDAR JASINKPKT 6575-37 | JasinMelaka | 175 | 28 Apr 20251st sale agreement 28 Apr 2023 | CCC 6 Feb 2025 Handover 10 Feb 2025 | 77 days before |
| SCIENTEX KUNDANG JAYAKPKT 6331-20 | GombakSelangor | 275 | 31 Mar 20251st sale agreement 31 Mar 2023 | CCC 28 Jan 2025 Handover 28 Jan 2025 | 62 days before |
| TAMAN BUKIT TAMBUN PERDANA 2KPKT 6575-38 | Alor GajahMelaka | 215 | 28 Apr 20251st sale agreement 28 Apr 2023 | CCC 23 Jan 2025 Handover 27 Jan 2025 | 91 days before |
| TAMAN SCIENTEX JASIN MUTIARAKPKT 6575-39 | JasinMelaka | 204 | 31 Jul 20251st sale agreement 31 Jul 2023 | CCC 10 Jan 2025 Handover 10 Jan 2025 | 202 days before |
| TAMAN AROWANAKPKT 11295-15 | Kedah | 291 | 31 Jan 20251st sale agreement 31 Jan 2023 | CCC 6 Jan 2025 Handover 6 Jan 2025 | 25 days before |
| TAMAN AROWANAKPKT 11295-14 | Kedah | 322 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 28 Nov 2024 Handover 28 Nov 2024 | 2 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-15 | Johor BahruJohor | 254 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 14 Nov 2024 Handover 14 Nov 2024 | 16 days before |
| SCIENTEX KUNDANG JAYA (ORCHID 2)KPKT 6331-19 | GombakSelangor | 325 | 30 Dec 20241st sale agreement 30 Dec 2022 | CCC 11 Nov 2024 Handover 11 Nov 2024 | 49 days before |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-13 | Seberang Perai UtaraPulau Pinang | 367 | 31 Oct 20241st sale agreement 31 Oct 2022 | CCC 30 Oct 2024 Handover 30 Oct 2024 | 1 day before |
| CLOVER 3KPKT 19794-14 | Kota TinggiJohor | 309 | 31 Oct 20241st sale agreement 31 Oct 2022 | CCC 29 Oct 2024 Handover 29 Oct 2024 | 2 days before |
| SCIENTEX JASINKPKT 6575-34 | JasinMelaka | 231 | 30 Dec 20241st sale agreement 30 Dec 2022 | CCC 28 Oct 2024 Handover 28 Oct 2024 | 63 days before |
| SCIENTEX BANDAR JASINKPKT 6575-33 | JasinMelaka | 210 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 43 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-13 | Johor BahruJohor | 175 | 31 Oct 20241st sale agreement 31 Oct 2022 | CCC 15 Oct 2024 Handover 15 Oct 2024 | 16 days before |
| TAMAN BUKIT TAMBUN PERDANA 2KPKT 6575-32 | Alor GajahMelaka | 211 | 15 Nov 20241st sale agreement 15 Nov 2022 | CCC 20 Sep 2024 Handover 26 Sep 2024 | 50 days before |
| SCIENTEX MERU 3KPKT 9294-61 | KintaPerak | 70 | 30 Apr 20251st sale agreement 30 Apr 2023 | CCC 3 Sep 2024 Handover 10 Sep 2024 | 232 days before |
| SCIENTEX SEREMBANKPKT 6331-17 | SerembanNegeri Sembilan | 192 | 29 Jul 20241st sale agreement 29 Jul 2022 | CCC 26 Jul 2024 Handover 26 Jul 2024 | 3 days before |
| SCIENTEX SEREMBANKPKT 6331-18 | SerembanNegeri Sembilan | 173 | 29 Jul 20241st sale agreement 29 Jul 2022 | CCC 26 Jul 2024 Handover 26 Jul 2024 | 3 days before |
| PANGSAPURI 1 SCIENTEX UTAMAKPKT 9294-59 | KulaiJohor | 300 | 31 Dec 20241st sale agreement 31 Dec 2021 | CCC 22 Jul 2024 Handover 22 Jul 2024 | 162 days before |
| SCIENTEX BANDAR JASINKPKT 6575-30 | JasinMelaka | 240 | 29 Jul 20241st sale agreement 29 Jul 2022 | CCC 19 Jul 2024 Handover 19 Jul 2024 | 10 days before |
| SCIENTEX JASINKPKT 6575-31 | JasinMelaka | 291 | 30 Sep 20241st sale agreement 30 Sep 2022 | CCC 18 Jul 2024 Handover 19 Jul 2024 | 73 days before |
| SCIENTEX BANDAR JASINKPKT 6575-35 | JasinMelaka | 162 | 31 Jan 20251st sale agreement 31 Jan 2023 | CCC 30 Apr 2024 Handover 30 Apr 2024 | 276 days before |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-12 | Seberang Perai UtaraPulau Pinang | 401 | 31 Mar 20241st sale agreement 31 Mar 2022 | CCC 29 Mar 2024 Handover 29 Mar 2024 | 2 days before |
| PANGSAPURI PULAI MUTIARA 3KPKT 9294-56 | Johor BahruJohor | 614 | 30 Apr 2024Extended 5 months from 30 Nov 20231st sale agreement 30 Nov 2020 | CCC 29 Mar 2024 Handover 29 Mar 2024 | 32 days before |
| SCIENTEX BANDAR JASINKPKT 6575-28 | JasinMelaka | 232 | 31 Mar 20241st sale agreement 31 Mar 2022 | CCC 28 Mar 2024 Handover 28 Mar 2024 | 3 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-12 | Johor BahruJohor | 236 | 20 Mar 20241st sale agreement 20 Mar 2022 | CCC 19 Mar 2024 Handover 19 Mar 2024 | 1 day before |
| SCIENTEX BANDAR JASINKPKT 6575-26 | JasinMelaka | 192 | 31 Jan 20241st sale agreement 31 Jan 2022 | CCC 30 Jan 2024 Handover 30 Jan 2024 | 1 day before |
| SCIENTEX JASINKPKT 6575-29 | JasinMelaka | 188 | 31 Mar 20241st sale agreement 31 Mar 2022 | CCC 30 Jan 2024 Handover 30 Jan 2024 | 61 days before |
| TAMAN SCIENTEX KOTA TINGGIKPKT 19794-11 | Kota TinggiJohor | 224 | 10 Jan 20241st sale agreement 10 Jan 2022 | CCC 9 Jan 2024 Handover 9 Jan 2024 | 1 day before |
| SCIENTEX JASINKPKT 6575-25 | JasinMelaka | 235 | 15 Dec 20231st sale agreement 15 Dec 2021 | CCC 5 Dec 2023 Handover 5 Dec 2023 | 10 days before |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-9 | Seberang Perai UtaraPulau Pinang | 386 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 30 Nov 2023 Handover 30 Nov 2023 | 61 days after |
| TAMAN BUKIT TAMBUN PERDANA 2KPKT 6575-27 | Alor GajahMelaka | 128 | 29 Apr 20241st sale agreement 29 Apr 2022 | CCC 30 Nov 2023 Handover 30 Nov 2023 | 151 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-10 | Johor BahruJohor | 214 | 30 Nov 20231st sale agreement 30 Nov 2021 | CCC 29 Nov 2023 Handover 29 Nov 2023 | 1 day before |
| SCIENTEX KUNDANG JAYAKPKT 6331-15 | GombakSelangor | 218 | 30 Jun 20231st sale agreement 30 Jun 2021 | CCC 20 Oct 2023 Handover 20 Oct 2023 | 112 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-14 | GombakSelangor | 277 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 16 Oct 2023 Handover 16 Oct 2023 | 16 days after |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-11 | Seberang Perai UtaraPulau Pinang | 203 | 31 Aug 20231st sale agreement 31 Aug 2021 | CCC 6 Oct 2023 Handover 6 Oct 2023 | 36 days after |
| TAMAN PULAI MUTIARA 2KPKT 19794-9 | Johor BahruJohor | 177 | 30 Sep 20231st sale agreement 30 Sep 2021 | CCC 29 Sep 2023 Handover 29 Sep 2023 | 1 day before |
| TAMAN SCIENTEX PARKKPKT 6331-11 | GombakSelangor | 239 | 22 Jan 2024Extended 5 months from 22 Aug 20231st sale agreement 22 Aug 2020 | CCC 23 Aug 2023 Handover 19 Sep 2023 | 125 days before |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-10 | Seberang Perai UtaraPulau Pinang | 279 | 30 Jul 20231st sale agreement 30 Jul 2021 | CCC 14 Aug 2023 Handover 14 Aug 2023 | 15 days after |
| SCIENTEX KUNDANG JAYAKPKT 6331-13 | GombakSelangor | 248 | 30 Jun 2023Extended 5 months from 30 Jan 20231st sale agreement 30 Jan 2021 | CCC 1 Aug 2023 Handover 1 Aug 2023 | 32 days after |
| SCIENTEX DURIAN TUNGGAL 2KPKT 6575-22 | Alor GajahMelaka | 271 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 25 Jul 2023 Handover 25 Jul 2023 | 67 days before |
| SCIENTEX MERU 3KPKT 9294-60 | KintaPerak | 304 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 18 Jul 2023 Handover 25 Jul 2023 | 67 days before |
| TAMAN BUKIT TAMBUN PERDANA 2KPKT 6575-24 | Alor GajahMelaka | 212 | 30 Jul 20231st sale agreement 30 Jul 2021 | CCC 14 Jul 2023 Handover 14 Jul 2023 | 16 days before |
| TAMAN SCIENTEX TASEK GELUGORKPKT 11295-8 | Seberang Perai UtaraPulau Pinang | 314 | 1 Jul 2023Extended 5 months from 31 Jan 20231st sale agreement 31 Jan 2021 | CCC 3 Jul 2023 Handover 3 Jul 2023 | 2 days after |
| TAMAN SCIENTEX KOTA TINGGIKPKT 19794-7 | Kota TinggiJohor | 128 | 29 Jun 2023Extended 5 months from 29 Jan 20231st sale agreement 29 Jan 2021 | CCC 21 Jun 2023 Handover 21 Jun 2023 | 8 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-8 | Johor BahruJohor | 184 | 24 Oct 2023Extended 5 months from 24 May 20231st sale agreement 24 May 2021 | CCC 13 Jun 2023 Handover 13 Jun 2023 | 133 days before |
| SCIENTEX KUNDANG JAYAKPKT 6331-12 | GombakSelangor | 393 | 30 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020 | CCC 7 Apr 2023 Handover 7 Apr 2023 | 8 days after |
| TAMAN BUKIT TAMBUN PERDANA 2KPKT 6575-23 | Alor GajahMelaka | 196 | 31 May 20231st sale agreement 31 May 2021 | CCC 31 Mar 2023 Handover 31 Mar 2023 | 61 days before |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-7 | Seberang Perai UtaraPulau Pinang | 382 | 30 Mar 2023Extended 5 months from 30 Oct 20221st sale agreement 30 Oct 2020 | CCC 22 Mar 2023 Handover 22 Mar 2023 | 8 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-6 | Johor BahruJohor | 184 | 11 Jun 2023Extended 5 months from 11 Jan 20231st sale agreement 11 Jan 2021 | CCC 13 Mar 2023 Handover 13 Mar 2023 | 90 days before |
| SCIENTEX DURIAN TUNGGAL 2KPKT 6575-21 | Alor GajahMelaka | 192 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 30 Dec 2022 Handover 30 Dec 2022 | 274 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-3 | Johor BahruJohor | 201 | 30 Nov 2022Extended 5 months from 30 Jun 20221st sale agreement 30 Jun 2020 | CCC 25 Nov 2022 Handover 25 Nov 2022 | 5 days before |
| TAMAN PULAI MUTIARA 2KPKT 19794-4 | Johor BahruJohor | 163 | 30 Nov 2022Extended 5 months from 30 Jun 20221st sale agreement 30 Jun 2020 | CCC 13 Oct 2022 Handover 13 Oct 2022 | 48 days before |
| SCIENTEX DURIAN TUNGGAL 2KPKT 6575-20 | Alor GajahMelaka | 159 | 29 Jun 2023Extended 5 months from 29 Jan 20231st sale agreement 29 Jan 2021 | CCC 6 Oct 2022 Handover 7 Oct 2022 | 265 days before |
| PANGSAPURI PULAI MUTIARA 2KPKT 9294-52 | Johor BahruJohor | 420 | 30 Jul 20231st sale agreement 30 Jul 2020 | CCC 29 Aug 2022 Handover 4 Oct 2022 / 6 Oct 2022 | 297 days before |
| SCIENTEX DURIAN TUNGGAL 2KPKT 6575-19 | Alor GajahMelaka | 331 | 28 May 2023Extended 5 months from 28 Dec 20221st sale agreement 28 Dec 2020 | CCC 29 Jul 2022 Handover 29 Jul 2022 | 303 days before |
| SCIENTEX DURIAN TUNGGAL 2KPKT 6575-18 | Alor GajahMelaka | 234 | 31 Dec 2022Extended 5 months from 31 Jul 20221st sale agreement 31 Jul 2020 | CCC 29 Jun 2022 | CCC before deadline; handover not recorded |
| TAMAN PULAI MUTIARAKPKT 9294-58 | Johor BahruJohor | 172 | 31 Aug 2022Extended 5 months from 31 Mar 20221st sale agreement 31 Mar 2020 | CCC 28 Jun 2022 Handover 29 Jun 2022 | 63 days before |
| AMBER LAND BERHADKPKT 19794-1 | Johor BahruJohor | 199 | 1 Jul 2022Extended 6 months from 31 Dec 20211st sale agreement 31 Dec 2019 | CCC 13 Jun 2022 Handover 13 Jun 2022 | 18 days before |
| RUMAH BANDAR TAMAN SCIENTEX KULAI 2KPKT 9294-51 | KulaiJohor | 150 | 31 Jan 20231st sale agreement 31 Jan 2020 | CCC 31 May 2022 Handover 31 May 2022 | 245 days before |
| TAMAN BUKIT TAMBUN PERDANAKPKT 6575-17 | Alor GajahMelaka | 173 | 31 Jul 20221st sale agreement 31 Jul 2020 | CCC 15 Dec 2021 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEX PARKKPKT 6331-8 | GombakSelangor | 209 | 31 Jan 20221st sale agreement 31 Jan 2019 | CCC 18 Oct 2021 | CCC before deadline; handover not recorded |
| TAMAN BUKIT TAMBUN PERDANAKPKT 6575-16 | Alor GajahMelaka | 176 | 14 Apr 20221st sale agreement 14 Apr 2020 | CCC 13 Oct 2021 | CCC before deadline; handover not recorded |
| TAMAN PULAI MUTIARA 2KPKT 19794-2 | Johor BahruJohor | 392 | 15 Dec 20211st sale agreement 15 Dec 2019 | CCC 26 Jul 2021 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEXKPKT 6331-10 | Johor BahruJohor | 23 | 16 Mar 20221st sale agreement 16 Mar 2020 | CCC 23 Jul 2021 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEX PASIR GUDANGKPKT 6331-9 | Johor BahruJohor | 90 | 28 Feb 20221st sale agreement 28 Feb 2020 | CCC 23 Jul 2021 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-14 | Alor GajahMelaka | 346 | 30 Sep 20211st sale agreement 30 Sep 2019 | CCC 15 Jul 2021 | CCC before deadline; handover not recorded |
| TAMAN BUKIT TAMBUN PERDANAKPKT 6575-15 | Alor GajahMelaka | 193 | 31 Dec 20211st sale agreement 31 Dec 2019 | CCC 15 Jul 2021 | CCC before deadline; handover not recorded |
| TAMAN CHEPOR IDAMANKPKT 9294-53 | KintaPerak | 288 | 31 Jan 2022Extended 6 months from 31 Jul 20211st sale agreement 31 Jul 2019 | CCC 15 Jul 2021 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-55 | Johor BahruJohor | 160 | 31 Jul 20211st sale agreement 31 Jul 2019 | CCC 23 Apr 2021 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-13 | Alor GajahMelaka | 200 | 29 Jul 20211st sale agreement 29 Jul 2019 | CCC 9 Apr 2021 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-9 | Alor GajahMelaka | 223 | 21 May 20211st sale agreement 21 May 2019 | CCC 9 Apr 2021 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEXKPKT 9294-38 | KulaiJohor | 502 | 18 Dec 2021Extended 6 months from 18 Jun 20211st sale agreement 18 Jun 2018 | CCC 24 Mar 2021 | CCC before deadline; handover not recorded |
| TAMAN PULAI MUTIARAKPKT 9294-44 | Johor BahruJohor | 570 | 25 Jan 20221st sale agreement 25 Jan 2019 | CCC 24 Mar 2021 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEX UTAMAKPKT 9294-50 | KulaiJohor | 195 | 30 Apr 20211st sale agreement 30 Apr 2019 | CCC 24 Mar 2021 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-54 | Johor BahruJohor | 84 | 11 Jan 20211st sale agreement 11 Jan 2019 | CCC 27 Jan 2021 | 16 days after † |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-10 | Alor GajahMelaka | 169 | 13 May 20211st sale agreement 13 May 2019 | CCC 8 Jan 2021 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGTHS SDN BHDKPKT 6575-11 | Alor GajahMelaka | 247 | 13 May 20211st sale agreement 13 May 2019 | CCC 8 Jan 2021 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-12 | Alor GajahMelaka | 104 | 15 Oct 20201st sale agreement 15 Oct 2018 | CCC 27 Nov 2020 | 43 days after † |
| SCIENTEX QUATARI SDN BHDKPKT 9294-45 | Johor BahruJohor | 160 | 31 Dec 20191st sale agreement 31 Dec 2017 | CCC 21 Oct 2020 | 295 days after |
| TAMAN SCIENTEX UTAMAKPKT 9294-49 | KulaiJohor | 243 | 30 Jan 20211st sale agreement 30 Jan 2019 | CFO 9 Sep 2020 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-37 | KulaiJohor | 43 | 31 May 20201st sale agreement 31 May 2018 | CFO 1 Sep 2020 | 93 days after † |
| SCIENTEX MERU 2KPKT 9294-47 | KintaPerak | 84 | 31 Dec 20201st sale agreement 31 Dec 2018 | CCC 26 Aug 2020 | CCC before deadline; handover not recorded |
| SCIENTEX MERU 2KPKT 9294-48 | KintaPerak | 92 | 11 Jan 20211st sale agreement 11 Jan 2019 | CCC 26 Aug 2020 | CCC before deadline; handover not recorded |
| SCIENTEX MERU 2KPKT 9294-39 | KintaPerak | 235 | 7 Jun 20201st sale agreement 7 Jun 2018 | CCC 12 Aug 2020 | 66 days after † |
| TAMAN SCIENTEXKPKT 9294-23 | Johor BahruJohor | 538 | 28 Aug 20191st sale agreement 28 Aug 2017 | CCC 30 Jul 2020 | 337 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-42 | Johor BahruJohor | 221 | 31 Oct 20201st sale agreement 31 Oct 2018 | CCC 30 Jul 2020 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-8 | Alor GajahMelaka | 116 | 30 Jul 20201st sale agreement 30 Jul 2018 | CCC 29 Jul 2020 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-43 | Johor BahruJohor | 144 | 31 Oct 20201st sale agreement 31 Oct 2018 | CCC 13 Jul 2020 | CCC before deadline; handover not recorded |
| SCIENTEX SENAI UTAMAKPKT 9294-46 | KulaiJohor | 267 | 28 Dec 20201st sale agreement 28 Dec 2018 | CFO 13 Jul 2020 | CCC before deadline; handover not recorded |
| SCIENTEX QUATRAI SDN BHDKPKT 9294-35 | KintaPerak | 174 | 28 Feb 20211st sale agreement 28 Feb 2018 | CCC 10 Jul 2020 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-40 | KintaPerak | 174 | 15 May 20211st sale agreement 15 May 2018 | CCC 10 Jul 2020 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-7 | Alor GajahMelaka | 320 | 5 Jun 20201st sale agreement 5 Jun 2018 | CCC 7 Jul 2020 | 32 days after † |
| SCIENTEX QUATARI SDN BHDKPKT 9294-41 | Johor BahruJohor | 251 | 30 Jun 20201st sale agreement 30 Jun 2018 | CCC 29 Jun 2020 | CCC before deadline; handover not recorded |
| SCIENTEX HEIGHTS SDN BHDKPKT 6575-6 | Alor GajahMelaka | 224 | 5 Jun 20201st sale agreement 5 Jun 2018 | CCC 17 Mar 2020 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-36 | KulaiJohor | 27 | 30 Apr 20201st sale agreement 30 Apr 2018 | CFO 22 Jan 2020 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-27 | Johor BahruJohor | 466 | 9 Oct 20181st sale agreement 9 Oct 2016 | CCC 30 Nov 2019 | 417 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-34 | Johor BahruJohor | 194 | 16 Jan 20201st sale agreement 16 Jan 2018 | CFO 15 Jul 2019 | CCC before deadline; handover not recorded |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-5 | Johor BahruJohor | 100 | 2 Oct 20191st sale agreement 2 Oct 2017 | CCC 30 Jun 2019 | CCC before deadline; handover not recorded |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-6 | Johor BahruJohor | 76 | 5 Feb 20201st sale agreement 5 Feb 2018 | CCC 30 Jun 2019 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-32 | KintaPerak | 208 | 5 Jul 20201st sale agreement 5 Jul 2017 | CCC 28 Jun 2019 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-33 | KulaiJohor | 38 | 13 Nov 20191st sale agreement 13 Nov 2017 | CFO 7 May 2019 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-30 | KulaiJohor | 45 | 25 Apr 20191st sale agreement 25 Apr 2017 | CFO 11 Dec 2018 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-28 | Johor BahruJohor | 622 | 17 Oct 20171st sale agreement 17 Oct 2015 | CFO 22 Oct 2018 | 370 days after |
| TAMAN SCIENTEX KULAI 2KPKT 9294-31 | KulaiJohor | 32 | 6 Jun 20191st sale agreement 6 Jun 2017 | CFO 29 Aug 2018 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-29 | KintaPerak | 118 | 18 Jan 20191st sale agreement 18 Jan 2017 | CCC 1 Aug 2018 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-26 | KulaiJohor | 33 | 20 Jul 20181st sale agreement 20 Jul 2016 | CCC 14 May 2018 | CCC before deadline; handover not recorded |
| THE HEIGHTS RESIDENCE - TAMAN MUZAFFAR HEIGHTSKPKT 6575-5 | Melaka TengahMelaka | 786 | 28 Aug 20171st sale agreement 28 Aug 2014 | CCC 28 Mar 2018 | 212 days after |
| TAMAN SCIENTEXKPKT 9294-25 | Johor BahruJohor | 316 | 21 Jul 20181st sale agreement 21 Jul 2016 | CCC 10 Jan 2018 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-24 | KulaiJohor | 160 | 1 Mar 20181st sale agreement 1 Mar 2016 | CFO 30 Nov 2017 | CCC before deadline; handover not recorded |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-3 | Johor BahruJohor | 1,148 | 15 Feb 20161st sale agreement 15 Feb 2013 | CCC 1 Nov 2017 | 625 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-20 | KulaiJohor | 416 | 19 May 20171st sale agreement 19 May 2015 | CCC 29 Sep 2017 | 133 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-19 | Batu PahatJohor | 350 | 9 Jan 20171st sale agreement 9 Jan 2015 | CCC 10 Jul 2017 | 182 days after |
| SCIENTEX QUATARI SDN BHDKPKT 9294-21 | Johor BahruJohor | 718 | 4 Jul 20171st sale agreement 4 Jul 2015 | CCC 5 Jul 2017 | 1 day after |
| TAMAN SCIENTEXKPKT 6331-7 | Johor BahruJohor | 492 | 24 Sep 20161st sale agreement 24 Sep 2014 | CCC 14 Feb 2017 | 143 days after |
| SCIENTEX (QUATARI) SDN BHDKPKT 9294-18 | KulaiJohor | 42 | 30 Apr 20171st sale agreement 30 Apr 2015 | CFO 24 Jan 2017 | CCC before deadline; handover not recorded |
| SCIENTEX QUATARI SDN BHDKPKT 9294-22 | KulaiJohor | 256 | 1 Jan 20171st sale agreement 1 Jan 2015 | CCC 17 Oct 2016 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEXKPKT 9294-17 | Johor BahruJohor | 150 | 5 Sep 20161st sale agreement 5 Sep 2014 | CCC 15 Aug 2016 | CCC before deadline; handover not recorded |
| TAMAN MUZAFFAR HEIGHTSKPKT 6575-4 | Melaka TengahMelaka | 226 | 14 Mar 20141st sale agreement 14 Mar 2012 | CFO 14 Jul 2016 | 853 days after |
| TAMAN SCIENTEX SENAIKPKT 9294-16 | KulaiJohor | 379 | 18 Mar 20161st sale agreement 18 Mar 2014 | CFO 25 May 2016 | 68 days after |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-4 | Johor BahruJohor | 178 | 9 Jan 20171st sale agreement 9 Jan 2014 | CCC 6 Apr 2016 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEXKPKT 6331-6 | Johor BahruJohor | 110 | 23 May 20161st sale agreement 23 May 2014 | CCC 15 Mar 2016 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEX SENAIKPKT 9294-15 | KulaiJohor | 350 | 26 Dec 20151st sale agreement 26 Dec 2013 | CFO 15 Mar 2016 | 80 days after |
| TAMAN SCIENTEXKPKT 9294-11 | Johor BahruJohor | 174 | 12 Dec 20131st sale agreement 12 Dec 2011 | CCC 10 Feb 2016 | 790 days after |
| TAMAN SCIENTEXKPKT 9294-14 | Johor BahruJohor | 599 | 21 Feb 20151st sale agreement 21 Feb 2013 | CCC 11 Jan 2016 | 324 days after |
| SCIENTEX - KULAIKPKT 9294-13 | KulaiJohor | 442 | 8 Oct 20141st sale agreement 8 Oct 2012 | CCC 1 Sep 2015 | 328 days after |
| TAMAN SCIENTEXKPKT 6331-5 | Johor BahruJohor | 254 | 8 Apr 20141st sale agreement 8 Apr 2012 | CCC 1 Jun 2015 | 419 days after |
| SCIENTEX (SKUDAI) SDN BHDKPKT 11295-2 | Johor BahruJohor | 232 | 17 May 20161st sale agreement 17 May 2013 | CCC 12 Feb 2015 | CCC before deadline; handover not recorded |
| TAMAN SCIENTEXKPKT 9294-9 | Johor BahruJohor | 330 | — | CCC 31 Dec 2013 | — |
| SCIENTEX - KULAIKPKT 9294-5 | KulaiJohor | 995 | — | CCC 1 Jul 2013 | — |
| LOT 947KPKT 11295-1 | Johor BahruJohor | 204 | — | CCC 30 Jan 2013 | — |
| TAMAN SCIENTEXKPKT 9294-10 | Johor BahruJohor | 481 | — | CCC 31 Oct 2012 | — |
| TAMAN SCIENTEXKPKT 6331-4 | Johor BahruJohor | 134 | — | CCC 20 Apr 2012 | — |
| TAMAN MUZAFFAR HEIGHTSKPKT 6575-3 | Melaka TengahMelaka | 150 | — | CCC 22 Mar 2012 | — |
| TAMAN SCIENTEXKPKT 9294-8 | Johor BahruJohor | 179 | — | CCC 9 Jan 2012 | — |
| TAMAN SCIENTEXKPKT 9294-6 | Johor BahruJohor | 812 | — | CCC 12 Jul 2011 | — |
| TAMAN SCIENTEXKPKT 6331-3 | Johor BahruJohor | 140 | — | CCC 9 Jun 2011 | — |
| SCIENTEX - KULAIKPKT 9294-7 | KulaiJohor | 259 | — | CCC 29 Apr 2011 | — |
| TAMAN SCIENTEXKPKT 9294-4 | Johor BahruJohor | 1,577 | — | CCC 29 Apr 2010 | — |
| TAMAN MUZAFFAR HEIGHTSKPKT 6575-1 | Melaka TengahMelaka | 373 | — | CFO 19 Jun 2008 | — |
| TAMAN SCIENTEXKPKT 9294-3 | Johor BahruJohor | 473 | — | CFO 28 May 2007 | — |
| TAMAN SCIENTEXKPKT 9294-2 | Johor BahruJohor | 1,004 | — | CFO 23 Mar 2007 | — |
| TAMAN SCIENTEXKPKT 6331-1 | Johor BahruJohor | 76 | — | CFO 15 May 2006 | — |
| TAMAN SCIENTEX PASIR GUDANGKPKT 6331-2 | Johor BahruJohor | 67 | — | CFO 25 Jul 2001 | — |
| PANGSAPURI PULAI MUTIARA 4KPKT 9294-57 | Johor BahruJohor | 210 | 1 Mar 20271st sale agreement 29 Feb 2024 | — | — |
Under construction (59) and not yet started (2) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN PULAI DUTAKPKT 9294-69 | Johor BahruJohor | 215 | SmoothOn schedule | 15 Nov 20261st sale agreement 15 Nov 2024 | 98% |
| SCIENTEX JENJAROMKPKT 30714-3 | Kuala LangatSelangor | 303 | SmoothOn schedule | 30 Nov 20261st sale agreement 30 Nov 2024 | 98% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-1 | KulaiJohor | 263 | SmoothOn schedule | 15 Jan 20271st sale agreement 15 Jan 2025 | 96% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-72 | Seberang Perai UtaraPulau Pinang | 252 | SmoothOn schedule | 31 Jan 20271st sale agreement 31 Jan 2025 | 90% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-2 | Johor | 182 | SmoothOn schedule | 25 Feb 20271st sale agreement 25 Feb 2025 | 92% |
| SCIENTEX JENJAROMKPKT 30714-4 | Kuala LangatSelangor | 263 | SmoothOn schedule | 28 Mar 20271st sale agreement 28 Mar 2025 | 91% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-3 | KulaiJohor | 244 | SmoothOn schedule | 15 Apr 20271st sale agreement 15 Apr 2025 | 81% |
| TAMAN SCIENTEX JASIN MUTIARAKPKT 6575-50 | JasinMelaka | 206 | SmoothOn schedule | 30 Apr 20271st sale agreement 30 Apr 2025 | 98% |
| TAMAN PULAI DUTAKPKT 9294-74 | Johor BahruJohor | 207 | SmoothOn schedule | 30 Apr 20271st sale agreement 30 Apr 2025 | 93% |
| BANDAR SCIENTEX JASIN PRESINT 2KPKT 6575-48 | JasinMelaka | 234 | SmoothOn schedule | 2 May 20271st sale agreement 2 May 2025 | 98% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-75 | Seberang Perai UtaraPulau Pinang | 238 | SmoothOn schedule | 31 May 20271st sale agreement 31 May 2025 | 54% |
| SCIENTEX IPOHKPKT 9294-76 | KintaPerak | 134 | SmoothOn schedule | 25 Jun 20271st sale agreement 25 Jun 2025 | 80% |
Show all 61 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN PULAI DUTAKPKT 9294-69 | Johor BahruJohor | 215 | SmoothOn schedule | 15 Nov 20261st sale agreement 15 Nov 2024 | 98% |
| SCIENTEX JENJAROMKPKT 30714-3 | Kuala LangatSelangor | 303 | SmoothOn schedule | 30 Nov 20261st sale agreement 30 Nov 2024 | 98% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-1 | KulaiJohor | 263 | SmoothOn schedule | 15 Jan 20271st sale agreement 15 Jan 2025 | 96% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-72 | Seberang Perai UtaraPulau Pinang | 252 | SmoothOn schedule | 31 Jan 20271st sale agreement 31 Jan 2025 | 90% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-2 | Johor | 182 | SmoothOn schedule | 25 Feb 20271st sale agreement 25 Feb 2025 | 92% |
| SCIENTEX JENJAROMKPKT 30714-4 | Kuala LangatSelangor | 263 | SmoothOn schedule | 28 Mar 20271st sale agreement 28 Mar 2025 | 91% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-3 | KulaiJohor | 244 | SmoothOn schedule | 15 Apr 20271st sale agreement 15 Apr 2025 | 81% |
| TAMAN SCIENTEX JASIN MUTIARAKPKT 6575-50 | JasinMelaka | 206 | SmoothOn schedule | 30 Apr 20271st sale agreement 30 Apr 2025 | 98% |
| TAMAN PULAI DUTAKPKT 9294-74 | Johor BahruJohor | 207 | SmoothOn schedule | 30 Apr 20271st sale agreement 30 Apr 2025 | 93% |
| BANDAR SCIENTEX JASIN PRESINT 2KPKT 6575-48 | JasinMelaka | 234 | SmoothOn schedule | 2 May 20271st sale agreement 2 May 2025 | 98% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-75 | Seberang Perai UtaraPulau Pinang | 238 | SmoothOn schedule | 31 May 20271st sale agreement 31 May 2025 | 54% |
| SCIENTEX IPOHKPKT 9294-76 | KintaPerak | 134 | SmoothOn schedule | 25 Jun 20271st sale agreement 25 Jun 2025 | 80% |
| PANGSAPURI CENDERA 2KPKT 19794-18 | Johor BahruJohor | 485 | SmoothOn schedule | 28 Jun 20271st sale agreement 28 Jun 2024 | 70% |
| BANDAR SCIENTEX JASIN PRESINT 2KPKT 6575-49 | JasinMelaka | 333 | SmoothOn schedule | 30 Jun 20271st sale agreement 30 Jun 2025 | 85% |
| PANGSAPURI SCIENTEX IDAMANKPKT 9294-67 | KulaiJohor | 516 | SmoothOn schedule | 22 Jul 20271st sale agreement 22 Jul 2024 | 97% |
| BANDAR SCIENTEX JASIN PRESINT 2KPKT 6575-51 | JasinMelaka | 232 | SmoothOn schedule | 25 Jul 20271st sale agreement 25 Jul 2025 | 72% |
| TAMAN PULAI DUTAKPKT 9294-78 | Johor BahruJohor | 200 | SmoothOn schedule | 25 Jul 20271st sale agreement 25 Jul 2025 | 77% |
| SCIENTEX JENJAROM - L'ENAKPKT 30714-5 | Kuala LangatSelangor | 168 | SmoothOn schedule | 31 Jul 20271st sale agreement 31 Jul 2025 | 80% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-80 | Seberang Perai UtaraPulau Pinang | 271 | SmoothOn schedule | 31 Jul 20271st sale agreement 31 Jul 2025 | 57% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-5 | Johor | 169 | SmoothOn schedule | 15 Aug 20271st sale agreement 15 Aug 2025 | 45% |
| TAMAN AROWANA EMASKPKT 11295-27 | Kuala MudaKedah | 149 | SmoothOn schedule | 31 Aug 20271st sale agreement 31 Aug 2025 | 70–85% |
| SCIENTEX JENJAROM - JASMINEKPKT 30714-6 | Kuala LangatSelangor | 322 | SmoothOn schedule | 13 Oct 20271st sale agreement 13 Oct 2025 | 77% |
| SCIENTEX JAWIKPKT 11295-28 | Seberang Perai SelatanPulau Pinang | 267 | SmoothOn schedule | 31 Oct 20271st sale agreement 31 Oct 2025 | 44% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-6 | KulaiJohor | 204 | SmoothOn schedule | 31 Oct 20271st sale agreement 31 Oct 2025 | 36% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-81 | Seberang Perai UtaraPulau Pinang | 234 | SmoothOn schedule | 31 Oct 20271st sale agreement 31 Oct 2025 | 41% |
| RESIDENSI MORI 2 SCIENTEX RAWANGKPKT 6331-22 | GombakSelangor | 489 | SmoothOn schedule | 1 Dec 2027Extended 16 months from 31 Jul 20261st sale agreement 31 Jul 2023 | 78% |
| BANDAR SCIENTEX JASIN PRESINT 2KPKT 6575-52 | JasinMelaka | 343 | SmoothOn schedule | 26 Dec 20271st sale agreement 26 Dec 2025 | 69% |
| SCIENTEX IPOH - ASPENKPKT 9294-83 | KintaPerak | 210 | SmoothOn schedule | 15 Jan 20281st sale agreement 15 Jan 2026 | 46% |
| PANGSAPURI SCIENTEX IDAMANKPKT 9294-70 | KulaiJohor | 522 | SmoothOn schedule | 20 Jan 20281st sale agreement 20 Jan 2025 | 97% |
| SCIENTEX IPOHKPKT 9294-82 | KintaPerak | 64 | SmoothOn schedule | 8 Mar 20281st sale agreement 8 Mar 2026 | 60% |
| TAMAN PULAI DUTA 2KPKT 9294-86 | Johor BahruJohor | 240 | SmoothOn schedule | 11 Mar 20281st sale agreement 11 Mar 2026 | 42% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-85 | Pulau Pinang | 252 | SmoothOn schedule | 8 May 20281st sale agreement 8 May 2026 | 28% |
| BANDAR BARU BAKRIKPKT 6575-54 | MuarJohor | 196 | SmoothOn schedule | 26 May 20281st sale agreement 26 May 2026 | 37% |
| SCIENTEX BESTARI JAYAKPKT 6331-28 | Kuala SelangorSelangor | 332 | SmoothOn schedule | 5 Jun 20281st sale agreement 5 Jun 2026 | 30% |
| TAMAN PUNCAK ASTANAKPKT 11295-29 | Kuala MudaKedah | 336 | SmoothOn schedule | 9 Jun 20281st sale agreement 9 Jun 2026 | 18% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-7 | Johor | 184 | SmoothOn schedule | 12 Jun 20281st sale agreement 12 Jun 2026 | 10% |
| SCIENTEX BESTARI JAYAKPKT 6331-27 | Kuala SelangorSelangor | 288 | SmoothOn schedule | 12 Jun 20281st sale agreement 12 Jun 2026 | 20% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-8 | Johor | 183 | SmoothOn schedule | 14 Jun 20281st sale agreement 14 Jun 2026 | 20% |
| BANDAR BARU BAKRIKPKT 6575-53 | MuarJohor | 209 | SmoothOn schedule | 15 Jun 20281st sale agreement 15 Jun 2026 | 18% |
| SCIENTEX MELAKAKPKT 6575-55 | Melaka TengahMelaka | 279 | SmoothOn schedule | 24 Jun 20281st sale agreement 24 Jun 2026 | 20% |
| TAMAN PULAI DUTA 2KPKT 9294-87 | Johor BahruJohor | 283 | SmoothOn schedule | 2 Jul 20281st sale agreement 2 Jul 2026 | 23% |
| SCIENTEX IPOH - DAISYKPKT 9294-89 | KintaPerak | 158 | SmoothOn schedule | 4 Jul 20281st sale agreement 4 Jul 2026 | 13% |
| SCIENTEX MELAKAKPKT 6575-56 | Melaka TengahMelaka | 288 | SmoothOn schedule | 8 Jul 20281st sale agreement 8 Jul 2026 | 14% |
| SCIENTEX JAWIKPKT 11295-30 | Seberang Perai SelatanPulau Pinang | 369 | SmoothOn schedule | 10 Jul 20281st sale agreement 10 Jul 2026 | 7% |
| SCIENTEX KUNDANG JAYAKPKT 6331-29 | GombakSelangor | 300 | SmoothOn schedule | 11 Jul 20281st sale agreement 11 Jul 2026 | 12% |
| BANDAR BARU BAKRIKPKT 6575-58 | Johor | 256 | SmoothOn schedule | 22 Jul 20281st sale agreement 22 Jul 2026 | 10% |
| PANGSAPURI CENDERA 3KPKT 19794-19 | Johor BahruJohor | 353 | SmoothOn schedule | 23 Jul 20281st sale agreement 23 Jul 2025 | 35–52% |
| RESIDENSI SENTRIO (N6)KPKT 6331-26Sentrio Residences Seremban · on PropertySifu | SerembanNegeri Sembilan | 384 | SmoothOn schedule | 25 Aug 20281st sale agreement 25 Aug 2025 | 34–54% |
| SCIENTEX BESTARI JAYAKPKT 6331-30 | Kuala SelangorSelangor | 220 | SmoothOn schedule | 23 Sep 20281st sale agreement 23 Sep 2026 | 8% |
| BANDAR SCIENTEX JASIN PRESINT 3KPKT 6575-60 | JasinMelaka | 252 | SmoothOn schedule | 9 Oct 20281st sale agreement 9 Oct 2026 | 5% |
| BANDAR BARU BAKRIKPKT 6575-61 | Johor | 181 | SmoothNot started | 22 Oct 20281st sale agreement 22 Oct 2026 | 0% |
| TAMAN PULAI DUTA 2KPKT 9294-84 | Johor BahruJohor | 246 | SmoothOn schedule | 16 Jan 2029Extended 12 months from 16 Jan 20281st sale agreement 16 Jan 2026 | 53% |
| RESIDENSI MORI 3KPKT 6331-25 | GombakSelangor | 498 | SmoothOn schedule | 17 Feb 2029Extended 12 months from 17 Feb 20281st sale agreement 17 Feb 2025 | 23–51% |
| PANGSAPURI LESTARI 1KPKT 30884-4 | KulaiJohor | 382 | SmoothOn schedule | 11 Mar 20291st sale agreement 11 Mar 2026 | 20–23% |
| PANGSAPURI PULAI DUTA 2KPKT 9294-79 | Johor BahruJohor | 142 | SmoothOn schedule | 26 May 20291st sale agreement 26 May 2026 | 5% |
| PANGSAPURI PULAI DUTA 1KPKT 9294-77 | Johor BahruJohor | 124 | SmoothOn schedule | 12 Jun 20291st sale agreement 12 Jun 2026 | 21% |
| PANGSAPURI SCIENTEX JAYAKPKT 9294-88 | KulaiJohor | 690 | SmoothOn schedule | 2 Jul 20291st sale agreement 2 Jul 2026 | 0–5% |
| TAMAN PUNCAK ASTANAKPKT 11295-31 | Kuala MudaKedah | 192 | SmoothOn schedule | — | 5% |
| BANDAR BARU BAKRIKPKT 6575-59 | Johor | 216 | SmoothOn schedule | — | 4% |
| TAMAN SCIENTEX KULAI 3KPKT 30884-9 | KulaiJohor | 300 | SmoothNot started | — | 0% |
| TAMAN SCIENTEX SUNGAI DUAKPKT 9294-90 | Seberang Perai UtaraPulau Pinang | 200 | SmoothOn schedule | — | 5% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Scientex at a glance
| Listed | Bursa Malaysia Main Market · SCIENTX (4731) · listed 8 February 1990[2][3][1] |
|---|---|
| Started | 25 June 1968 in Johor Bahru, as Scientific Textile Industries Sdn Bhd[2][4] |
| Head office | Seksyen 15, Shah Alam, Selangor[3] |
| Leadership | Lim Peng Cheong — Chairman (since 12 March 2025)[3] Lim Peng Jin — Managing Director and Chief Executive Officer[3] |
| Companies in the KPKT register | SCIENTEX PARK (M) SDN. BHD. KPKT 6331[3] SCIENTEX JENJAROM SDN. BHD. (70%) KPKT 30714[3] SCIENTEX QUATARI SDN. BHD. KPKT 9294[3] SCIENTEX HEIGHTS SDN. BHD. KPKT 6575[3] SCIENTEX (SKUDAI) SDN. BHD. KPKT 11295[3] SCIENTEX LESTARI SDN. BHD. (70%) KPKT 30884[3] AMBER LAND BERHAD KPKT 19794[3] |
| Website | scientex.com.my |
| Property since | 1995, Pasir Gudang, Johor (Taman Scientex)[5] |
| Homes completed (company figure) | 47,846 affordable homes priced below RM500,000, as of July 2026[5] |
| Land bank | 11,034 acres at 31 July 2025, 6,529 acres of it for future development[3] |
| States | Johor, Melaka, Negeri Sembilan, Selangor, Perak, Penang, Kedah[3] |
Scientex projects on sale on PropertySifu
Sentrio Residences Seremban
- SCIENTEX SEREMBAN — 0.6 km, 2025
Who is Scientex? The company behind the projects
Scientex was founded in Johor Bahru on 25 June 1968 as Scientific Textile Industries Sdn Bhd, making PVC leather and sheeting [4]. It was listed on the Main Board of the Kuala Lumpur Stock Exchange — today Bursa Malaysia's Main Market — on 8 February 1990 [2]. Its property division was set up in 1995 in Pasir Gudang, Johor [5]; the first township, Taman Scientex, grew out of a 1993 joint venture with Singapore's Lim Kah Ngam Group [4].
The company says its property division had completed 47,846 affordable homes priced below RM500,000 as of July 2026 [5], and it has set a target of 50,000 by 2028 [3]. Its land bank was 11,034 acres at 31 July 2025, with 6,529 acres earmarked for future development, across Johor, Melaka, Negeri Sembilan, Selangor, Perak, Penang and Kedah [3].
Scientex Jenjarom sits on about 251 acres in Kuala Langat, Selangor, bought under a 2021 agreement from Seriemas Development Sdn Bhd, a subsidiary of Permodalan Nasional Berhad [6]. Scientex and the seller invested jointly in Scientex Jenjarom Sdn Bhd, which completed the purchase on 11 January 2024 [7]; Scientex holds 70% of that company [3]. In Seremban, Sentrio Residences by Hillside is developed by Scientex Park (M) Sdn Bhd under developer licence 6331 [8].
The chairman is Lim Peng Cheong, in the role since 12 March 2025, and the managing director and chief executive officer is Lim Peng Jin [3].
Frequently asked questions
Is Scientex a listed company?
How many homes has Scientex completed?
Scientex says its property division had completed 47,846 affordable homes priced below RM500,000 as of July 2026 [5]. In the KPKT register, 180 of the 241 housing projects under seven Scientex companies are completed.
Does Scientex have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 241 Scientex projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat).
Has Scientex Jenjarom been handed over on time?
The first two phases registered with KPKT (30714-1 and 30714-2, 224 terrace houses each) received the CCC and vacant possession on 22 May 2026 and 25 June 2026, 3 and 5 days before their deadlines. Four more phases are under construction: 30714-3 (303 houses, 98% reported progress, deadline 30 November 2026), 30714-4 (263 houses, 91%, 28 March 2027), L'ENA 30714-5 (168 cluster houses, 80%, 31 July 2027) and JASMINE 30714-6 (322 houses, 77%, 13 October 2027).
Which company develops Scientex Jenjarom?
Scientex Jenjarom Sdn Bhd (KPKT developer code 30714), which Scientex Berhad owns 70% of, according to its 2025 annual report [3].
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Scientex to acquire 503 acres in Johor for RM580 mil · The Edge Malaysia · 6 Oct 2026 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/820695 - [2] Scientex Berhad — Corporate Information · Scientex Berhad · 10 Jun 2026 · accessed 28 Oct 2026
https://scientex.com.my/wp-content/uploads/2026/06/Scientex-Corporate-Information.pdf - [3] Scientex Integrated Annual Report 2025 · Scientex Berhad · 18 Nov 2025 · accessed 28 Oct 2026
https://scientex.com.my/wp-content/uploads/2025/11/IAR2025_Fullset.pdf - [4] Corporate milestones · Scientex Berhad · accessed 28 Oct 2026
https://scientex.com.my/corporate-milestones/ - [5] Scientex Corporate Profile (August 2026) · Scientex Berhad · 2026-08 · accessed 28 Oct 2026
https://scientex.com.my/wp-content/uploads/2026/09/Scientex-Corporate-Profile_2026-August-1.pdf - [6] Scientex expands Klang Valley footprint with 251-acre land purchase · Scientex Berhad · 30 Aug 2021 · accessed 28 Oct 2026
https://www.scientex.com.my/wp-content/uploads/2021/08/Scientex-expands-Klang-Valley-footprint-with-251-acre-land-purchase.pdf - [7] Scientex Integrated Annual Report 2024 (note 40) · Scientex Berhad · 19 Nov 2024 · accessed 28 Oct 2026
https://www.scientex.com.my/wp-content/uploads/2024/11/Integrated-Annual-Report_2024.pdf - [8] Sentrio Residences by Hillside (N6) · Scientex Berhad · accessed 28 Oct 2026
https://scientex.com.my/scientex-property/sentrio-residences-by-hillside-n6/
Last updated 28 Oct 2026