Plenitude (Plenitude Berhad)
Plenitude Berhad is a Bursa Malaysia Main Market-listed property and hotel group with 66 housing projects in the KPKT register, in Johor, Kedah, Selangor, Penang and Kuala Lumpur, under six Plenitude companies: 54 completed, 9 under construction, 2 not yet started and 1 with the permit cancelled, none classed Sick or Abandoned. It has been listed since 2003.
- 66 projects in the KPKT register
- 54 completed
- 9 under construction
- 2 not yet started
- 1 with the permit cancelled
- None Sick or Abandoned
Has Plenitude handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 66 housing projects under 6 Plenitude companies in 5 states: 54 completed, 9 under construction, 2 not yet started, 1 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 54 completed projects, 30 have both a handover deadline and a completion date in the register: 10 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 6 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 14 received the completion certificate before the deadline (handover date not recorded).
4 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 54
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN DESA TEBRAU - HARP 2CKPKT 6418-37 | Johor BahruJohor | 76 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 26 Jun 2026 Handover 26 Jun 2026 | 4 days before |
| TAMAN DESA TERBAU - HARP 2CKPKT 6418-38 | Johor BahruJohor | 24 | 28 Oct 20261st sale agreement 28 Oct 2024 | CCC 26 Jun 2026 Handover 26 Jun 2026 | 124 days before |
| TAMAN DESA TEBRAU - CELLO 3CKPKT 6418-36 | Johor BahruJohor | 141 | 30 Dec 20251st sale agreement 30 Dec 2023 | CCC 12 Dec 2025 Handover 16 Dec 2025 | 14 days before |
| TAMAN KOTA IMPIANKPKT 30170-2 | Kota TinggiJohor | 154 | 28 Aug 20251st sale agreement 28 Aug 2023 | CCC 18 Aug 2025 Handover 18 Aug 2025 | 10 days before |
| TAMAN KOTA IMPIANKPKT 30170-3 | Kota TinggiJohor | 45 | 28 Sep 20251st sale agreement 28 Sep 2023 | CCC 18 Aug 2025 Handover 18 Aug 2025 | 41 days before |
| RAMLEE BUKIT BINTANGKPKT 3850-15 | Kuala MudaKedah | 44 | 23 Aug 20251st sale agreement 23 Aug 2023 | CCC 29 Apr 2025 | CCC before deadline; handover not recorded |
| TAMAN KOTA IMPIANKPKT 30170-1 | Kota TinggiJohor | 143 | 18 Dec 20241st sale agreement 18 Dec 2022 | CCC 15 Nov 2024 Handover 16 Dec 2024 | 2 days before |
| TAMAN DESA TEBRAU - (CELLO 3B)KPKT 6418-35 | Johor BahruJohor | 162 | 7 Mar 20251st sale agreement 7 Mar 2023 | CCC 21 Oct 2024 | CCC before deadline; handover not recorded |
| RAMLEE BUKIT BINTANGKPKT 3850-13 | Kuala MudaKedah | 26 | 31 Jan 20251st sale agreement 31 Jan 2023 | CCC 26 Jun 2024 Handover 28 Jun 2024 | 217 days before |
| RAMLEE BUKIT BINTANGKPKT 3850-14 | Kuala MudaKedah | 26 | 10 Apr 20251st sale agreement 10 Apr 2023 | CCC 26 Jun 2024 Handover 28 Jun 2024 | 286 days before |
| TAMAN DESA TEBRAUKPKT 6418-34 | Johor BahruJohor | 93 | 31 Dec 20231st sale agreement 31 Dec 2021 | CCC 7 Sep 2023 Handover 15 Sep 2023 | 107 days before |
| TAMAN PUTRA PRIMAKPKT 7521-21Diamond @ Taman Putra Prima, Puchong · on PropertySifu | SepangSelangor | 166 | 19 Oct 2023Extended 5 months from 19 May 20231st sale agreement 19 May 2021 | CCC 2 May 2023 | CCC before deadline; handover not recorded |
Handed over or certified complete after the deadline (6)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN DESA TEBRAUKPKT 6418-33 | Johor BahruJohor | 117 | 25 Nov 2022Extended 5 months from 25 Jun 20221st sale agreement 25 Jun 2020 | CCC 8 Dec 2022 Handover 13 Dec 2022 | 18 days after † |
| THE MARINKPKT 13646-1 | Daerah Timor LautPulau Pinang | 149 | 24 Dec 20171st sale agreement 24 Dec 2014 | CCC 4 Oct 2018 | 284 days after |
| BINTANG MAYAKPKT 3850-9 | Kuala MudaKedah | 164 | 28 May 20171st sale agreement 28 May 2015 | CCC 30 Aug 2017 | 94 days after |
| TAMAN DESA TEBRAUKPKT 6418-27 | Johor BahruJohor | 94 | 18 Feb 20161st sale agreement 18 Feb 2014 | CCC 29 Mar 2016 | 40 days after |
| TAMAN DESA TEBRAUKPKT 6418-26 | Johor BahruJohor | 250 | 6 Jun 20141st sale agreement 6 Jun 2012 | CCC 9 Dec 2014 | 186 days after |
| PERDANA HEIGHTSKPKT 3850-5 | Kuala MudaKedah | 347 | 28 Feb 20141st sale agreement 28 Feb 2012 | CCC 21 Mar 2014 | 21 days after |
Show all 54 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN DESA TEBRAU - HARP 2CKPKT 6418-37 | Johor BahruJohor | 76 | 30 Jun 20261st sale agreement 30 Jun 2024 | CCC 26 Jun 2026 Handover 26 Jun 2026 | 4 days before |
| TAMAN DESA TERBAU - HARP 2CKPKT 6418-38 | Johor BahruJohor | 24 | 28 Oct 20261st sale agreement 28 Oct 2024 | CCC 26 Jun 2026 Handover 26 Jun 2026 | 124 days before |
| TAMAN DESA TEBRAU - CELLO 3CKPKT 6418-36 | Johor BahruJohor | 141 | 30 Dec 20251st sale agreement 30 Dec 2023 | CCC 12 Dec 2025 Handover 16 Dec 2025 | 14 days before |
| TAMAN KOTA IMPIANKPKT 30170-2 | Kota TinggiJohor | 154 | 28 Aug 20251st sale agreement 28 Aug 2023 | CCC 18 Aug 2025 Handover 18 Aug 2025 | 10 days before |
| TAMAN KOTA IMPIANKPKT 30170-3 | Kota TinggiJohor | 45 | 28 Sep 20251st sale agreement 28 Sep 2023 | CCC 18 Aug 2025 Handover 18 Aug 2025 | 41 days before |
| RAMLEE BUKIT BINTANGKPKT 3850-15 | Kuala MudaKedah | 44 | 23 Aug 20251st sale agreement 23 Aug 2023 | CCC 29 Apr 2025 | CCC before deadline; handover not recorded |
| TAMAN KOTA IMPIANKPKT 30170-1 | Kota TinggiJohor | 143 | 18 Dec 20241st sale agreement 18 Dec 2022 | CCC 15 Nov 2024 Handover 16 Dec 2024 | 2 days before |
| TAMAN DESA TEBRAU - (CELLO 3B)KPKT 6418-35 | Johor BahruJohor | 162 | 7 Mar 20251st sale agreement 7 Mar 2023 | CCC 21 Oct 2024 | CCC before deadline; handover not recorded |
| RAMLEE BUKIT BINTANGKPKT 3850-13 | Kuala MudaKedah | 26 | 31 Jan 20251st sale agreement 31 Jan 2023 | CCC 26 Jun 2024 Handover 28 Jun 2024 | 217 days before |
| RAMLEE BUKIT BINTANGKPKT 3850-14 | Kuala MudaKedah | 26 | 10 Apr 20251st sale agreement 10 Apr 2023 | CCC 26 Jun 2024 Handover 28 Jun 2024 | 286 days before |
| TAMAN DESA TEBRAUKPKT 6418-34 | Johor BahruJohor | 93 | 31 Dec 20231st sale agreement 31 Dec 2021 | CCC 7 Sep 2023 Handover 15 Sep 2023 | 107 days before |
| TAMAN PUTRA PRIMAKPKT 7521-21Diamond @ Taman Putra Prima, Puchong · on PropertySifu | SepangSelangor | 166 | 19 Oct 2023Extended 5 months from 19 May 20231st sale agreement 19 May 2021 | CCC 2 May 2023 | CCC before deadline; handover not recorded |
| BINTANG MAYA IIIKPKT 3850-12 | Kuala MudaKedah | 60 | 27 Sep 20231st sale agreement 27 Sep 2021 | CCC 3 Feb 2023 Handover 13 Feb 2023 | 226 days before |
| TAMAN DESA TEBRAUKPKT 6418-33 | Johor BahruJohor | 117 | 25 Nov 2022Extended 5 months from 25 Jun 20221st sale agreement 25 Jun 2020 | CCC 8 Dec 2022 Handover 13 Dec 2022 | 18 days after † |
| TAMAN DESA TEBRAUKPKT 6418-32 | Johor BahruJohor | 112 | 1 Oct 2021Extended 6 months from 31 Mar 20211st sale agreement 31 Mar 2019 | CCC 12 Jul 2021 | CCC before deadline; handover not recorded |
| TAMAN DESA TEBRAUKPKT 6418-31 | Johor BahruJohor | 100 | 28 Jun 20201st sale agreement 28 Jun 2018 | CCC 9 Mar 2020 | CCC before deadline; handover not recorded |
| TAMAN PUTRA PRIMAKPKT 7521-20 | SepangSelangor | 136 | 31 Aug 20201st sale agreement 31 Aug 2018 | CCC 3 Mar 2020 | CCC before deadline; handover not recorded |
| BINTANG MAYA IIKPKT 3850-11 | Kuala MudaKedah | 56 | 25 Mar 20211st sale agreement 25 Mar 2019 | CCC 15 Jan 2020 | CCC before deadline; handover not recorded |
| TAMAN DESA TEBRAUKPKT 6418-30 | Johor BahruJohor | 116 | 31 Aug 20191st sale agreement 31 Aug 2017 | CCC 30 May 2019 | CCC before deadline; handover not recorded |
| BINTANG MAYA IIKPKT 3850-10 | Kuala MudaKedah | 81 | 24 Aug 20191st sale agreement 24 Aug 2017 | CCC 27 Mar 2019 | CCC before deadline; handover not recorded |
| TAMAN DESA TEBRAUKPKT 6418-29 | Johor BahruJohor | 118 | 29 Dec 20181st sale agreement 29 Dec 2016 | CCC 27 Dec 2018 | CCC before deadline; handover not recorded |
| THE MARINKPKT 13646-1 | Daerah Timor LautPulau Pinang | 149 | 24 Dec 20171st sale agreement 24 Dec 2014 | CCC 4 Oct 2018 | 284 days after |
| BINTANG MAYAKPKT 3850-9 | Kuala MudaKedah | 164 | 28 May 20171st sale agreement 28 May 2015 | CCC 30 Aug 2017 | 94 days after |
| TAMAN PUTRA PRIMAKPKT 7521-18 | SepangSelangor | 448 | 20 May 20181st sale agreement 20 May 2015 | CCC 25 May 2017 | CCC before deadline; handover not recorded |
| TAMAN PUTRA PRIMAKPKT 7521-19 | SepangSelangor | 150 | 29 May 20171st sale agreement 29 May 2015 | CCC 22 Feb 2017 | CCC before deadline; handover not recorded |
| TAMAN DESA TEBRAUKPKT 6418-27 | Johor BahruJohor | 94 | 18 Feb 20161st sale agreement 18 Feb 2014 | CCC 29 Mar 2016 | 40 days after |
| TAMAN PUTRA PRIMAKPKT 7521-17 | SepangSelangor | 85 | 31 Mar 20161st sale agreement 31 Mar 2014 | CCC 30 Dec 2015 | CCC before deadline; handover not recorded |
| TAMAN PUTRA PRIMAKPKT 7521-16 | SepangSelangor | 105 | 23 Mar 20151st sale agreement 23 Mar 2013 | CCC 20 Mar 2015 | CCC before deadline; handover not recorded |
| TAMAN DESA TEBRAUKPKT 6418-26 | Johor BahruJohor | 250 | 6 Jun 20141st sale agreement 6 Jun 2012 | CCC 9 Dec 2014 | 186 days after |
| BANDAR PERDANAKPKT 3850-4 | Kuala MudaKedah | 437 | — | CCC 17 Apr 2014 | — |
| PERDANA HEIGHTSKPKT 3850-5 | Kuala MudaKedah | 347 | 28 Feb 20141st sale agreement 28 Feb 2012 | CCC 21 Mar 2014 | 21 days after |
| TAMAN DESA TEBRAUKPKT 6418-25 | Johor BahruJohor | 98 | — | CCC 23 Dec 2013 | — |
| TAMAN DESA TEBRAUKPKT 6418-24 | Johor BahruJohor | 55 | — | CCC 2 Sep 2013 | — |
| TAMAN PUTRA PRIMAKPKT 7521-15 | SepangSelangor | 248 | — | CCC 19 Jun 2012 | — |
| BANDAR PERDANAKPKT 3850-6 | Kuala MudaKedah | 201 | — | CCC 9 Apr 2012 | — |
| TAMAN DESA TEBRAUKPKT 6418-23 | Johor BahruJohor | 201 | — | CCC 9 Dec 2011 | — |
| BAYU FERRINGHIKPKT 3850-8 | Daerah Timor LautPulau Pinang | 112 | — | CCC 12 Sep 2011 | — |
| BAYU FERRINGHIKPKT 3850-7 | Daerah Timor LautPulau Pinang | 38 | — | CCC 2 Jun 2011 | — |
| TAMAN PUTRA PRIMAKPKT 7521-14 | SepangSelangor | 197 | — | CCC 31 Mar 2011 | — |
| CHANGKAT VIEW CONDOKPKT 8934-3 | Kuala LumpurWP Kuala Lumpur | 796 | — | CFO 30 Dec 2009 | — |
| TAMAN PUTRA PRIMA FASA 4BKPKT 7521-12 | SepangSelangor | 224 | — | CFO 3 Mar 2009 | — |
| TAMAN PUTRA PRIMA FASA 3CKPKT 7521-13 | SepangSelangor | 22 | — | CFO 3 Mar 2009 | — |
| TAMAN DESA TEBRAUKPKT 6418-14 | Johor BahruJohor | 42 | — | CFO 29 Jul 2008 | — |
| TAMAN DESA TEBRAUKPKT 6418-6 | Johor BahruJohor | 310 | — | CFO 26 May 2008 | — |
| TAMAN DESA TEBRAUKPKT 6418-11 | Johor BahruJohor | 288 | — | CFO 13 Feb 2008 | — |
| TAMAN PUTRA PRIMAKPKT 7521-11 | SepangSelangor | 220 | — | CFO 25 Jan 2008 | — |
| TAMAN PUTRA PRIMAKPKT 7521-10 | SepangSelangor | 180 | — | CFO 14 Feb 2007 | — |
| TAMAN DESA TEBRAUKPKT 6418-13 | Johor BahruJohor | 221 | — | CFO 25 Apr 2006 | — |
| TAMAN PUTRA PRIMAKPKT 7521-9 | SepangSelangor | 208 | — | CFO 14 Feb 2006 | — |
| CHANGKAT KIARAKPKT 8934-2 | Kuala LumpurWP Kuala Lumpur | 66 | — | CFO 19 Jan 2006 | — |
| CHANGKAT KIARAKPKT 8934-1 | Kuala LumpurWP Kuala Lumpur | 29 | — | CFO 28 Nov 2005 | — |
| TAMAN DESA TEBRAUKPKT 6418-9 | Johor BahruJohor | 212 | — | CFO 27 Apr 2002 | — |
| TAMAN KOTA IMPIANKPKT 30170-4 | Kota TinggiJohor | 156 | 30 Sep 20261st sale agreement 30 Sep 2024 | — | — |
| BANDAR PERDANAKPKT 3850-3 | Kuala MudaKedah | 1,222 | — | — | — |
Under construction (9) and not yet started (2)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN DESA TEBRAU - 8E (1)KPKT 6418-39 | Johor BahruJohor | 66 | SmoothOn schedule | 28 Mar 20271st sale agreement 28 Mar 2025 | 80–85% |
| TAMAN KOTA IMPIANKPKT 30170-5 | Kota TinggiJohor | 108 | SmoothOn schedule | 31 May 20271st sale agreement 31 May 2025 | 66–72% |
| TAMAN KOTA IMPIANKPKT 30170-6 | Kota TinggiJohor | 116 | SmoothOn schedule | 18 Aug 20271st sale agreement 18 Aug 2025 | 80% |
| TAMAN KOTA IMPIANKPKT 30170-7 | Kota TinggiJohor | 122 | SmoothOn schedule | 18 Aug 20271st sale agreement 18 Aug 2025 | 80% |
| BINTANG BAYU SARIKPKT 3850-16 | Kedah | 96 | SmoothOn schedule | 25 Sep 20271st sale agreement 25 Sep 2025 | 58% |
| TAMAN DESA TEBRAU - 8E (2)KPKT 6418-40 | Johor BahruJohor | 66 | SmoothOn schedule | 27 Oct 20271st sale agreement 27 Oct 2025 | 85% |
| TAMAN DESA TEBRAU - 4AKPKT 6418-42 | Johor BahruJohor | 130 | SmoothOn schedule | 17 Sep 20281st sale agreement 17 Sep 2026 | 0% |
| RESIDENSI MANDOLINKPKT 6418-41 | Johor | 712 | SmoothOn schedule | 23 Feb 2030Extended 12 months from 23 Feb 20291st sale agreement 23 Feb 2026 | 22% |
| BINTANG BAYU SARIKPKT 3850-17 | Kedah | 68 | Not startedNot started | — | 0% |
| TAMAN KOTA IMPIAN - FASA 7KPKT 30170-8 | Kota TinggiJohor | 157 | SmoothOn schedule | — | 5% |
| RMMJ P18 TAMAN DESA TEBRAUKPKT 6418-43 | Johor BahruJohor | 486 | Not startedNot started | — | 0% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN DESA TEBRAUKPKT 6418-28 | Johor BahruJohor | 1,048 | Permit cancelledPermit cancelled | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Plenitude at a glance
| Listed | Bursa Malaysia Main Market · stock code 5075 · listed 18 November 2003[1] |
|---|---|
| Started | Incorporated on 6 November 2000[1] |
| Head office | Ilham Tower, Jalan Binjai, Kuala Lumpur[1] |
| Leadership | Chua Elsie — Non-Independent Non-Executive Chairman (since 1 November 2018; previously Executive Chairman)[1] Ng Yoon Thai — Chief Executive Officer (since 16 April 2026)[1] |
| Companies in the KPKT register | PLENITUDE TEBRAU SDN. BHD. KPKT 6418[1] PLENITUDE HEIGHTS SDN. BHD. KPKT 3850[1] PLENITUDE PERMAI SDN. BHD. KPKT 7521[1] PLENITUDE HILLS SDN. BHD. KPKT 30170[1] PLENITUDE BUILDERS SDN. BHD. (FORMERLY CHANGKAT KIARA SDN. BHD.) KPKT 8934[1] PLENITUDE BAYU SDN. BHD. KPKT 13646[1] |
| Website | plenitude.com.my |
| Units completed (company figure) | More than 15,000 units, group-wide (Annual Report 2026)[1] |
| Land bank | About 963 acres, mostly in Kedah (562 acres) and Johor Bahru (304 acres) (Annual Report 2026)[1] |
| Main townships | Taman Desa Tebrau and Impian Hills (Johor), Bukit Bintang (Sungai Petani, Kedah), Taman Putra Prima (Puchong, Selangor)[1] |
| Hotels (company figure) | 12 hotels and residences with more than 2,400 rooms in Malaysia, South Korea and Japan (Annual Report 2026)[1] |
Plenitude projects on sale on PropertySifu
Diamond @ Taman Putra Prima, Puchong
- TAMAN PUTRA PRIMA — 1.1 km, 2015
- TAMAN PUTRA PRIMA — 1.2 km, 2020
- TAMAN PUTRA PRIMA — 1.2 km, 2017
Who is Plenitude? The company behind the projects
Plenitude Berhad was incorporated on 6 November 2000 and has been listed on the Main Market of Bursa Malaysia since 18 November 2003, under stock code 5075 [1]. Its core businesses are property development, property investment and hospitality; it went into hotels in 2001 and says it now owns more than 2,400 hotel rooms in Malaysia, South Korea and Japan [1]. The non-executive chairman is Chua Elsie, previously the executive chairman, and Ng Yoon Thai has been chief executive officer since 16 April 2026 [1].
Its main townships are Taman Desa Tebrau in Johor Bahru, Impian Hills in Ulu Tiram, Johor, Bukit Bintang in Sungai Petani, Kedah and Taman Putra Prima in Puchong, Selangor [1]. KPKT registers Impian Hills as Taman Kota Impian, under Plenitude Hills Sdn Bhd in Kota Tinggi district, and lists Taman Putra Prima under Sepang district. In its 2026 annual report the company says it has completed more than 15,000 units and holds about 963 acres of land for future development [1]; these are group-wide figures, while the KPKT register counts only projects licensed as housing.
Diamond @ Taman Putra Prima, listed on PropertySifu, is the township's final residential phase: 166 two- and three-storey terrace houses, which the 2026 annual report says were completed and handed over to buyers in May 2023 [1]. It is developed by Plenitude Permai Sdn Bhd and registered with KPKT as 7521-21. All six Plenitude companies in the KPKT register, including Plenitude Builders Sdn Bhd (formerly Changkat Kiara Sdn Bhd) in Kuala Lumpur and Plenitude Bayu Sdn Bhd in Penang, are wholly owned by the group [1].
Frequently asked questions
Is Plenitude a listed company?
Yes. Plenitude Berhad has been listed on the Main Market of Bursa Malaysia since 18 November 2003, under stock code 5075 [1].
Does Plenitude have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 66 Plenitude projects as Sick (Sakit) or Abandoned (Terbengkalai), and none of the 9 projects under construction is classed Late (Lewat). One project in Taman Desa Tebrau, 6418-28 (1,048 units), is recorded with its permit cancelled.
How many homes has Plenitude completed?
Plenitude says it has completed more than 15,000 units group-wide [1]. In the KPKT register, 54 of the 66 housing projects under six Plenitude companies are completed, with 9,571 units.
Which company develops Diamond @ Taman Putra Prima?
Plenitude Permai Sdn Bhd (KPKT developer code 7521), a wholly owned subsidiary of Plenitude Berhad according to its 2026 annual report [1]. KPKT registers the project as 7521-21.
Was Diamond @ Taman Putra Prima completed on time?
KPKT records the first sale agreement on 19 May 2021 and a handover deadline of 19 May 2023, extended with approval by 5 months to 19 October 2023. The CCC for all four components is dated 2 May 2023, before both the original and the extended deadline; KPKT has not registered a handover date, and Plenitude's 2026 annual report says the 166 houses were handed over to buyers in May 2023, the same month as the CCC [1].
Have any Plenitude handover deadlines been extended?
Four, according to KPKT: two completed Taman Desa Tebrau phases (6418-32, extended by 6 months, and 6418-33, by 5 months), Diamond @ Taman Putra Prima (7521-21, by 5 months) and Residensi Mandolin in Taman Desa Tebrau (6418-41, 712 serviced apartments, under construction, by 12 months to 23 February 2030).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.