Plenitude (Plenitude Berhad)

Last updated 28 Oct 2026
Who is Plenitude?

Plenitude Berhad is a Bursa Malaysia Main Market-listed property and hotel group with 66 housing projects in the KPKT register, in Johor, Kedah, Selangor, Penang and Kuala Lumpur, under six Plenitude companies: 54 completed, 9 under construction, 2 not yet started and 1 with the permit cancelled, none classed Sick or Abandoned. It has been listed since 2003.

  • 66 projects in the KPKT register
  • 54 completed
  • 9 under construction
  • 2 not yet started
  • 1 with the permit cancelled
  • None Sick or Abandoned

Has Plenitude handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists 66 housing projects under 6 Plenitude companies in 5 states: 54 completed, 9 under construction, 2 not yet started, 1 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).

Of the 54 completed projects, 30 have both a handover deadline and a completion date in the register: 10 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 6 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 14 received the completion certificate before the deadline (handover date not recorded).

4 projects had the delivery period extended with KPKT approval.

Completed projects — the 12 most recent of 54

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN DESA TEBRAU - HARP 2CKPKT 6418-37Johor BahruJohor7630 Jun 20261st sale agreement 30 Jun 2024CCC 26 Jun 2026
Handover 26 Jun 2026
4 days before
TAMAN DESA TERBAU - HARP 2CKPKT 6418-38Johor BahruJohor2428 Oct 20261st sale agreement 28 Oct 2024CCC 26 Jun 2026
Handover 26 Jun 2026
124 days before
TAMAN DESA TEBRAU - CELLO 3CKPKT 6418-36Johor BahruJohor14130 Dec 20251st sale agreement 30 Dec 2023CCC 12 Dec 2025
Handover 16 Dec 2025
14 days before
TAMAN KOTA IMPIANKPKT 30170-2Kota TinggiJohor15428 Aug 20251st sale agreement 28 Aug 2023CCC 18 Aug 2025
Handover 18 Aug 2025
10 days before
TAMAN KOTA IMPIANKPKT 30170-3Kota TinggiJohor4528 Sep 20251st sale agreement 28 Sep 2023CCC 18 Aug 2025
Handover 18 Aug 2025
41 days before
RAMLEE BUKIT BINTANGKPKT 3850-15Kuala MudaKedah4423 Aug 20251st sale agreement 23 Aug 2023CCC 29 Apr 2025CCC before deadline; handover not recorded
TAMAN KOTA IMPIANKPKT 30170-1Kota TinggiJohor14318 Dec 20241st sale agreement 18 Dec 2022CCC 15 Nov 2024
Handover 16 Dec 2024
2 days before
TAMAN DESA TEBRAU - (CELLO 3B)KPKT 6418-35Johor BahruJohor1627 Mar 20251st sale agreement 7 Mar 2023CCC 21 Oct 2024CCC before deadline; handover not recorded
RAMLEE BUKIT BINTANGKPKT 3850-13Kuala MudaKedah2631 Jan 20251st sale agreement 31 Jan 2023CCC 26 Jun 2024
Handover 28 Jun 2024
217 days before
RAMLEE BUKIT BINTANGKPKT 3850-14Kuala MudaKedah2610 Apr 20251st sale agreement 10 Apr 2023CCC 26 Jun 2024
Handover 28 Jun 2024
286 days before
TAMAN DESA TEBRAUKPKT 6418-34Johor BahruJohor9331 Dec 20231st sale agreement 31 Dec 2021CCC 7 Sep 2023
Handover 15 Sep 2023
107 days before
TAMAN PUTRA PRIMAKPKT 7521-21Diamond @ Taman Putra Prima, Puchong · on PropertySifuSepangSelangor16619 Oct 2023Extended 5 months from 19 May 20231st sale agreement 19 May 2021CCC 2 May 2023CCC before deadline; handover not recorded

Handed over or certified complete after the deadline (6)

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN DESA TEBRAUKPKT 6418-33Johor BahruJohor11725 Nov 2022Extended 5 months from 25 Jun 20221st sale agreement 25 Jun 2020CCC 8 Dec 2022
Handover 13 Dec 2022
18 days after †
THE MARINKPKT 13646-1Daerah Timor LautPulau Pinang14924 Dec 20171st sale agreement 24 Dec 2014CCC 4 Oct 2018284 days after
BINTANG MAYAKPKT 3850-9Kuala MudaKedah16428 May 20171st sale agreement 28 May 2015CCC 30 Aug 201794 days after
TAMAN DESA TEBRAUKPKT 6418-27Johor BahruJohor9418 Feb 20161st sale agreement 18 Feb 2014CCC 29 Mar 201640 days after
TAMAN DESA TEBRAUKPKT 6418-26Johor BahruJohor2506 Jun 20141st sale agreement 6 Jun 2012CCC 9 Dec 2014186 days after
PERDANA HEIGHTSKPKT 3850-5Kuala MudaKedah34728 Feb 20141st sale agreement 28 Feb 2012CCC 21 Mar 201421 days after
Show all 54 completed projects
Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN DESA TEBRAU - HARP 2CKPKT 6418-37Johor BahruJohor7630 Jun 20261st sale agreement 30 Jun 2024CCC 26 Jun 2026
Handover 26 Jun 2026
4 days before
TAMAN DESA TERBAU - HARP 2CKPKT 6418-38Johor BahruJohor2428 Oct 20261st sale agreement 28 Oct 2024CCC 26 Jun 2026
Handover 26 Jun 2026
124 days before
TAMAN DESA TEBRAU - CELLO 3CKPKT 6418-36Johor BahruJohor14130 Dec 20251st sale agreement 30 Dec 2023CCC 12 Dec 2025
Handover 16 Dec 2025
14 days before
TAMAN KOTA IMPIANKPKT 30170-2Kota TinggiJohor15428 Aug 20251st sale agreement 28 Aug 2023CCC 18 Aug 2025
Handover 18 Aug 2025
10 days before
TAMAN KOTA IMPIANKPKT 30170-3Kota TinggiJohor4528 Sep 20251st sale agreement 28 Sep 2023CCC 18 Aug 2025
Handover 18 Aug 2025
41 days before
RAMLEE BUKIT BINTANGKPKT 3850-15Kuala MudaKedah4423 Aug 20251st sale agreement 23 Aug 2023CCC 29 Apr 2025CCC before deadline; handover not recorded
TAMAN KOTA IMPIANKPKT 30170-1Kota TinggiJohor14318 Dec 20241st sale agreement 18 Dec 2022CCC 15 Nov 2024
Handover 16 Dec 2024
2 days before
TAMAN DESA TEBRAU - (CELLO 3B)KPKT 6418-35Johor BahruJohor1627 Mar 20251st sale agreement 7 Mar 2023CCC 21 Oct 2024CCC before deadline; handover not recorded
RAMLEE BUKIT BINTANGKPKT 3850-13Kuala MudaKedah2631 Jan 20251st sale agreement 31 Jan 2023CCC 26 Jun 2024
Handover 28 Jun 2024
217 days before
RAMLEE BUKIT BINTANGKPKT 3850-14Kuala MudaKedah2610 Apr 20251st sale agreement 10 Apr 2023CCC 26 Jun 2024
Handover 28 Jun 2024
286 days before
TAMAN DESA TEBRAUKPKT 6418-34Johor BahruJohor9331 Dec 20231st sale agreement 31 Dec 2021CCC 7 Sep 2023
Handover 15 Sep 2023
107 days before
TAMAN PUTRA PRIMAKPKT 7521-21Diamond @ Taman Putra Prima, Puchong · on PropertySifuSepangSelangor16619 Oct 2023Extended 5 months from 19 May 20231st sale agreement 19 May 2021CCC 2 May 2023CCC before deadline; handover not recorded
BINTANG MAYA IIIKPKT 3850-12Kuala MudaKedah6027 Sep 20231st sale agreement 27 Sep 2021CCC 3 Feb 2023
Handover 13 Feb 2023
226 days before
TAMAN DESA TEBRAUKPKT 6418-33Johor BahruJohor11725 Nov 2022Extended 5 months from 25 Jun 20221st sale agreement 25 Jun 2020CCC 8 Dec 2022
Handover 13 Dec 2022
18 days after †
TAMAN DESA TEBRAUKPKT 6418-32Johor BahruJohor1121 Oct 2021Extended 6 months from 31 Mar 20211st sale agreement 31 Mar 2019CCC 12 Jul 2021CCC before deadline; handover not recorded
TAMAN DESA TEBRAUKPKT 6418-31Johor BahruJohor10028 Jun 20201st sale agreement 28 Jun 2018CCC 9 Mar 2020CCC before deadline; handover not recorded
TAMAN PUTRA PRIMAKPKT 7521-20SepangSelangor13631 Aug 20201st sale agreement 31 Aug 2018CCC 3 Mar 2020CCC before deadline; handover not recorded
BINTANG MAYA IIKPKT 3850-11Kuala MudaKedah5625 Mar 20211st sale agreement 25 Mar 2019CCC 15 Jan 2020CCC before deadline; handover not recorded
TAMAN DESA TEBRAUKPKT 6418-30Johor BahruJohor11631 Aug 20191st sale agreement 31 Aug 2017CCC 30 May 2019CCC before deadline; handover not recorded
BINTANG MAYA IIKPKT 3850-10Kuala MudaKedah8124 Aug 20191st sale agreement 24 Aug 2017CCC 27 Mar 2019CCC before deadline; handover not recorded
TAMAN DESA TEBRAUKPKT 6418-29Johor BahruJohor11829 Dec 20181st sale agreement 29 Dec 2016CCC 27 Dec 2018CCC before deadline; handover not recorded
THE MARINKPKT 13646-1Daerah Timor LautPulau Pinang14924 Dec 20171st sale agreement 24 Dec 2014CCC 4 Oct 2018284 days after
BINTANG MAYAKPKT 3850-9Kuala MudaKedah16428 May 20171st sale agreement 28 May 2015CCC 30 Aug 201794 days after
TAMAN PUTRA PRIMAKPKT 7521-18SepangSelangor44820 May 20181st sale agreement 20 May 2015CCC 25 May 2017CCC before deadline; handover not recorded
TAMAN PUTRA PRIMAKPKT 7521-19SepangSelangor15029 May 20171st sale agreement 29 May 2015CCC 22 Feb 2017CCC before deadline; handover not recorded
TAMAN DESA TEBRAUKPKT 6418-27Johor BahruJohor9418 Feb 20161st sale agreement 18 Feb 2014CCC 29 Mar 201640 days after
TAMAN PUTRA PRIMAKPKT 7521-17SepangSelangor8531 Mar 20161st sale agreement 31 Mar 2014CCC 30 Dec 2015CCC before deadline; handover not recorded
TAMAN PUTRA PRIMAKPKT 7521-16SepangSelangor10523 Mar 20151st sale agreement 23 Mar 2013CCC 20 Mar 2015CCC before deadline; handover not recorded
TAMAN DESA TEBRAUKPKT 6418-26Johor BahruJohor2506 Jun 20141st sale agreement 6 Jun 2012CCC 9 Dec 2014186 days after
BANDAR PERDANAKPKT 3850-4Kuala MudaKedah437—CCC 17 Apr 2014—
PERDANA HEIGHTSKPKT 3850-5Kuala MudaKedah34728 Feb 20141st sale agreement 28 Feb 2012CCC 21 Mar 201421 days after
TAMAN DESA TEBRAUKPKT 6418-25Johor BahruJohor98—CCC 23 Dec 2013—
TAMAN DESA TEBRAUKPKT 6418-24Johor BahruJohor55—CCC 2 Sep 2013—
TAMAN PUTRA PRIMAKPKT 7521-15SepangSelangor248—CCC 19 Jun 2012—
BANDAR PERDANAKPKT 3850-6Kuala MudaKedah201—CCC 9 Apr 2012—
TAMAN DESA TEBRAUKPKT 6418-23Johor BahruJohor201—CCC 9 Dec 2011—
BAYU FERRINGHIKPKT 3850-8Daerah Timor LautPulau Pinang112—CCC 12 Sep 2011—
BAYU FERRINGHIKPKT 3850-7Daerah Timor LautPulau Pinang38—CCC 2 Jun 2011—
TAMAN PUTRA PRIMAKPKT 7521-14SepangSelangor197—CCC 31 Mar 2011—
CHANGKAT VIEW CONDOKPKT 8934-3Kuala LumpurWP Kuala Lumpur796—CFO 30 Dec 2009—
TAMAN PUTRA PRIMA FASA 4BKPKT 7521-12SepangSelangor224—CFO 3 Mar 2009—
TAMAN PUTRA PRIMA FASA 3CKPKT 7521-13SepangSelangor22—CFO 3 Mar 2009—
TAMAN DESA TEBRAUKPKT 6418-14Johor BahruJohor42—CFO 29 Jul 2008—
TAMAN DESA TEBRAUKPKT 6418-6Johor BahruJohor310—CFO 26 May 2008—
TAMAN DESA TEBRAUKPKT 6418-11Johor BahruJohor288—CFO 13 Feb 2008—
TAMAN PUTRA PRIMAKPKT 7521-11SepangSelangor220—CFO 25 Jan 2008—
TAMAN PUTRA PRIMAKPKT 7521-10SepangSelangor180—CFO 14 Feb 2007—
TAMAN DESA TEBRAUKPKT 6418-13Johor BahruJohor221—CFO 25 Apr 2006—
TAMAN PUTRA PRIMAKPKT 7521-9SepangSelangor208—CFO 14 Feb 2006—
CHANGKAT KIARAKPKT 8934-2Kuala LumpurWP Kuala Lumpur66—CFO 19 Jan 2006—
CHANGKAT KIARAKPKT 8934-1Kuala LumpurWP Kuala Lumpur29—CFO 28 Nov 2005—
TAMAN DESA TEBRAUKPKT 6418-9Johor BahruJohor212—CFO 27 Apr 2002—
TAMAN KOTA IMPIANKPKT 30170-4Kota TinggiJohor15630 Sep 20261st sale agreement 30 Sep 2024——
BANDAR PERDANAKPKT 3850-3Kuala MudaKedah1,222———

Under construction (9) and not yet started (2)

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
TAMAN DESA TEBRAU - 8E (1)KPKT 6418-39Johor BahruJohor66SmoothOn schedule28 Mar 20271st sale agreement 28 Mar 202580–85%
TAMAN KOTA IMPIANKPKT 30170-5Kota TinggiJohor108SmoothOn schedule31 May 20271st sale agreement 31 May 202566–72%
TAMAN KOTA IMPIANKPKT 30170-6Kota TinggiJohor116SmoothOn schedule18 Aug 20271st sale agreement 18 Aug 202580%
TAMAN KOTA IMPIANKPKT 30170-7Kota TinggiJohor122SmoothOn schedule18 Aug 20271st sale agreement 18 Aug 202580%
BINTANG BAYU SARIKPKT 3850-16Kedah96SmoothOn schedule25 Sep 20271st sale agreement 25 Sep 202558%
TAMAN DESA TEBRAU - 8E (2)KPKT 6418-40Johor BahruJohor66SmoothOn schedule27 Oct 20271st sale agreement 27 Oct 202585%
TAMAN DESA TEBRAU - 4AKPKT 6418-42Johor BahruJohor130SmoothOn schedule17 Sep 20281st sale agreement 17 Sep 20260%
RESIDENSI MANDOLINKPKT 6418-41Johor712SmoothOn schedule23 Feb 2030Extended 12 months from 23 Feb 20291st sale agreement 23 Feb 202622%
BINTANG BAYU SARIKPKT 3850-17Kedah68Not startedNot started—0%
TAMAN KOTA IMPIAN - FASA 7KPKT 30170-8Kota TinggiJohor157SmoothOn schedule—5%
RMMJ P18 TAMAN DESA TEBRAUKPKT 6418-43Johor BahruJohor486Not startedNot started—0%

Permit cancelled or other KPKT status (1)

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
TAMAN DESA TEBRAUKPKT 6418-28Johor BahruJohor1,048Permit cancelledPermit cancelled—0%

† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

Plenitude at a glance

ListedBursa Malaysia Main Market · stock code 5075 · listed 18 November 2003[1]
StartedIncorporated on 6 November 2000[1]
Head officeIlham Tower, Jalan Binjai, Kuala Lumpur[1]
LeadershipChua Elsie — Non-Independent Non-Executive Chairman (since 1 November 2018; previously Executive Chairman)[1]
Ng Yoon Thai — Chief Executive Officer (since 16 April 2026)[1]
Companies in the KPKT registerPLENITUDE TEBRAU SDN. BHD. KPKT 6418[1]
PLENITUDE HEIGHTS SDN. BHD. KPKT 3850[1]
PLENITUDE PERMAI SDN. BHD. KPKT 7521[1]
PLENITUDE HILLS SDN. BHD. KPKT 30170[1]
PLENITUDE BUILDERS SDN. BHD. (FORMERLY CHANGKAT KIARA SDN. BHD.) KPKT 8934[1]
PLENITUDE BAYU SDN. BHD. KPKT 13646[1]
Websiteplenitude.com.my
Units completed (company figure)More than 15,000 units, group-wide (Annual Report 2026)[1]
Land bankAbout 963 acres, mostly in Kedah (562 acres) and Johor Bahru (304 acres) (Annual Report 2026)[1]
Main townshipsTaman Desa Tebrau and Impian Hills (Johor), Bukit Bintang (Sungai Petani, Kedah), Taman Putra Prima (Puchong, Selangor)[1]
Hotels (company figure)12 hotels and residences with more than 2,400 rooms in Malaysia, South Korea and Japan (Annual Report 2026)[1]

Plenitude projects on sale on PropertySifu

Diamond @ Taman Putra Prima, Puchong

Puchong, Selangor · From RM972,000
KPKT 7521-21: Completed with CCC (2 May 2023)
Completed Plenitude projects nearby (KPKT):
  • TAMAN PUTRA PRIMA — 1.1 km, 2015
  • TAMAN PUTRA PRIMA — 1.2 km, 2020
  • TAMAN PUTRA PRIMA — 1.2 km, 2017

Who is Plenitude? The company behind the projects

Plenitude Berhad was incorporated on 6 November 2000 and has been listed on the Main Market of Bursa Malaysia since 18 November 2003, under stock code 5075 [1]. Its core businesses are property development, property investment and hospitality; it went into hotels in 2001 and says it now owns more than 2,400 hotel rooms in Malaysia, South Korea and Japan [1]. The non-executive chairman is Chua Elsie, previously the executive chairman, and Ng Yoon Thai has been chief executive officer since 16 April 2026 [1].

Its main townships are Taman Desa Tebrau in Johor Bahru, Impian Hills in Ulu Tiram, Johor, Bukit Bintang in Sungai Petani, Kedah and Taman Putra Prima in Puchong, Selangor [1]. KPKT registers Impian Hills as Taman Kota Impian, under Plenitude Hills Sdn Bhd in Kota Tinggi district, and lists Taman Putra Prima under Sepang district. In its 2026 annual report the company says it has completed more than 15,000 units and holds about 963 acres of land for future development [1]; these are group-wide figures, while the KPKT register counts only projects licensed as housing.

Diamond @ Taman Putra Prima, listed on PropertySifu, is the township's final residential phase: 166 two- and three-storey terrace houses, which the 2026 annual report says were completed and handed over to buyers in May 2023 [1]. It is developed by Plenitude Permai Sdn Bhd and registered with KPKT as 7521-21. All six Plenitude companies in the KPKT register, including Plenitude Builders Sdn Bhd (formerly Changkat Kiara Sdn Bhd) in Kuala Lumpur and Plenitude Bayu Sdn Bhd in Penang, are wholly owned by the group [1].

Frequently asked questions

Is Plenitude a listed company?

Yes. Plenitude Berhad has been listed on the Main Market of Bursa Malaysia since 18 November 2003, under stock code 5075 [1].

Does Plenitude have any Sick or Abandoned projects?

No. As at 27 October 2026, the KPKT register classes none of the 66 Plenitude projects as Sick (Sakit) or Abandoned (Terbengkalai), and none of the 9 projects under construction is classed Late (Lewat). One project in Taman Desa Tebrau, 6418-28 (1,048 units), is recorded with its permit cancelled.

How many homes has Plenitude completed?

Plenitude says it has completed more than 15,000 units group-wide [1]. In the KPKT register, 54 of the 66 housing projects under six Plenitude companies are completed, with 9,571 units.

Which company develops Diamond @ Taman Putra Prima?

Plenitude Permai Sdn Bhd (KPKT developer code 7521), a wholly owned subsidiary of Plenitude Berhad according to its 2026 annual report [1]. KPKT registers the project as 7521-21.

Was Diamond @ Taman Putra Prima completed on time?

KPKT records the first sale agreement on 19 May 2021 and a handover deadline of 19 May 2023, extended with approval by 5 months to 19 October 2023. The CCC for all four components is dated 2 May 2023, before both the original and the extended deadline; KPKT has not registered a handover date, and Plenitude's 2026 annual report says the 166 houses were handed over to buyers in May 2023, the same month as the CCC [1].

Have any Plenitude handover deadlines been extended?

Four, according to KPKT: two completed Taman Desa Tebrau phases (6418-32, extended by 6 months, and 6418-33, by 5 months), Diamond @ Taman Putra Prima (7521-21, by 5 months) and Residensi Mandolin in Taman Desa Tebrau (6418-41, 712 serviced apartments, under construction, by 12 months to 23 February 2030).

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
  2. [1] Plenitude Berhad Annual Report 2026 · Plenitude Berhad · 2026-10 · accessed 28 Oct 2026
    https://plenitu.investors-centre.com/investor-relations/pdf/agm-2026/annual-report.pdf

Last updated 28 Oct 2026