Paramount (Paramount Corporation Berhad)
Paramount Corporation Berhad, listed on Bursa Malaysia's Main Market, is a property-led group with 111 housing projects in the KPKT register under 12 group companies: 95 completed and 16 under construction, none classed Sick or Abandoned. Incorporated in 1969 as Malaysia Rice Industries Berhad, it builds under the Paramount Property brand in Kedah, Penang, Selangor and Kuala Lumpur.
- 111 projects in the KPKT register
- 95 completed
- 16 under construction
- None Sick or Abandoned
Has Paramount handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 111 housing projects under 12 Paramount companies in 4 states: 95 completed, 16 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 95 completed projects, 62 have both a handover deadline and a completion date in the register: 22 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 9 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 31 received the completion certificate before the deadline (handover date not recorded).
24 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 95
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BUKIT BANYAN - ASPERA ELITEKPKT 2003-75 | Kuala MudaKedah | 80 | 5 Aug 20261st sale agreement 5 Aug 2024 | CCC 30 Mar 2026 Handover 15 Apr 2026 | 112 days before |
| BUKIT BANYAN - CASSIAKPKT 2003-73 | Kuala MudaKedah | 137 | 21 Mar 20261st sale agreement 21 Mar 2024 | CCC 28 Jan 2026 Handover 25 Feb 2026 | 24 days before |
| BUKIT BANYAN - ASPERAKPKT 2003-74 | Kuala MudaKedah | 111 | 28 Mar 20261st sale agreement 28 Mar 2024 | CCC 6 Nov 2025 Handover 31 Dec 2025 | 87 days before |
| PANGSAPURI PERKHIDMATAN SAVANAKPKT 14638-4 | Seberang Perai SelatanPulau Pinang | 522 | 10 Mar 2027Extended 12 months from 10 Mar 20261st sale agreement 10 Mar 2023 | CCC 22 Aug 2025 Handover 20 Nov 2025 | 475 days before |
| BUKIT BANYANKPKT 2003-72 | Kuala MudaKedah | 49 | 19 Nov 20251st sale agreement 19 Nov 2023 | CCC 30 Oct 2025 Handover 12 Nov 2025 | 7 days before |
| ARINNA, KEMUNING UTAMAKPKT 9202-23 | KlangSelangor | 356 | 19 Sep 20251st sale agreement 19 Sep 2022 | CCC 17 Oct 2025 | 28 days after |
| SEJATI LAKESIDE 2KPKT 30178-2 | SepangSelangor | 112 | 22 Jun 20251st sale agreement 22 Jun 2023 | CCC 4 Jun 2025 Handover 15 Jun 2025 | 7 days before |
| BUKIT BANYAN - SIERRA 3A ELEGANTKPKT 2003-70 | Kuala MudaKedah | 34 | 24 Mar 20251st sale agreement 24 Mar 2023 | CCC 10 Dec 2024 Handover 26 Dec 2024 | 88 days before |
| GREENWOODS SERAYA @ SALAK PERDANAKPKT 14134-5 | SepangSelangor | 260 | 16 Dec 20251st sale agreement 16 Dec 2022 | CCC 1 Oct 2024 Handover 22 Oct 2024 | 420 days before |
| SEJATI LAKESIDE 2KPKT 30178-1 | SepangSelangor | 122 | 3 Nov 20241st sale agreement 3 Nov 2022 | CCC 12 Oct 2024 Handover 18 Oct 2024 | 16 days before |
| ATRIUMKPKT 20172-1 | Kuala LumpurWP Kuala Lumpur | 241 | 4 Nov 20241st sale agreement 4 Nov 2021 | CCC 19 Jul 2024 Handover 29 Jul 2024 | 98 days before |
| BUKIT BANYAN - SENNI 3AKPKT 2003-71 | Kuala MudaKedah | 129 | 14 Feb 20251st sale agreement 14 Feb 2023 | CCC 20 Jun 2024 Handover 23 Jul 2024 | 206 days before |
Handed over or certified complete after the deadline (9)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| ARINNA, KEMUNING UTAMAKPKT 9202-23 | KlangSelangor | 356 | 19 Sep 20251st sale agreement 19 Sep 2022 | CCC 17 Oct 2025 | 28 days after |
| SEJATI LAKESIDEKPKT 19806-3 | SepangSelangor | 149 | 20 Nov 20231st sale agreement 20 Nov 2021 | CCC 10 Nov 2023 Handover 15 Nov 2023 / 29 Jan 2024 | 70 days after |
| BUKIT BANYANKPKT 2003-58 | Kuala MudaKedah | 195 | 30 Mar 20201st sale agreement 30 Mar 2018 | CCC 7 Feb 2021 | 314 days after † |
| BUKIT BANYANKPKT 2003-57 | Kuala MudaKedah | 49 | 15 Nov 20191st sale agreement 15 Nov 2017 | CCC 10 Jun 2020 | 208 days after |
| BUKIT BANYANKPKT 2003-55 | Kuala MudaKedah | 220 | 1 Jun 20191st sale agreement 1 Jun 2017 | CCC 30 Jan 2020 | 243 days after |
| BUKIT BANYANKPKT 2003-51 | Kuala MudaKedah | 72 | 16 Aug 20171st sale agreement 16 Aug 2015 | CCC 28 Feb 2019 | 561 days after |
| BUKIT BANYANKPKT 2003-50 | Kuala MudaKedah | 211 | 25 Mar 20171st sale agreement 25 Mar 2015 | CCC 30 Mar 2017 | 5 days after |
| BUKIT BANYANKPKT 2003-47 | Kuala MudaKedah | 216 | 28 Oct 20151st sale agreement 28 Oct 2013 | CCC 10 Jan 2016 | 74 days after |
| KEMUNING UTAMAKPKT 9202-19 | KlangSelangor | 596 | 5 May 20141st sale agreement 5 May 2011 | CCC 5 Sep 2014 | 123 days after |
Show all 95 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BUKIT BANYAN - ASPERA ELITEKPKT 2003-75 | Kuala MudaKedah | 80 | 5 Aug 20261st sale agreement 5 Aug 2024 | CCC 30 Mar 2026 Handover 15 Apr 2026 | 112 days before |
| BUKIT BANYAN - CASSIAKPKT 2003-73 | Kuala MudaKedah | 137 | 21 Mar 20261st sale agreement 21 Mar 2024 | CCC 28 Jan 2026 Handover 25 Feb 2026 | 24 days before |
| BUKIT BANYAN - ASPERAKPKT 2003-74 | Kuala MudaKedah | 111 | 28 Mar 20261st sale agreement 28 Mar 2024 | CCC 6 Nov 2025 Handover 31 Dec 2025 | 87 days before |
| PANGSAPURI PERKHIDMATAN SAVANAKPKT 14638-4 | Seberang Perai SelatanPulau Pinang | 522 | 10 Mar 2027Extended 12 months from 10 Mar 20261st sale agreement 10 Mar 2023 | CCC 22 Aug 2025 Handover 20 Nov 2025 | 475 days before |
| BUKIT BANYANKPKT 2003-72 | Kuala MudaKedah | 49 | 19 Nov 20251st sale agreement 19 Nov 2023 | CCC 30 Oct 2025 Handover 12 Nov 2025 | 7 days before |
| ARINNA, KEMUNING UTAMAKPKT 9202-23 | KlangSelangor | 356 | 19 Sep 20251st sale agreement 19 Sep 2022 | CCC 17 Oct 2025 | 28 days after |
| SEJATI LAKESIDE 2KPKT 30178-2 | SepangSelangor | 112 | 22 Jun 20251st sale agreement 22 Jun 2023 | CCC 4 Jun 2025 Handover 15 Jun 2025 | 7 days before |
| BUKIT BANYAN - SIERRA 3A ELEGANTKPKT 2003-70 | Kuala MudaKedah | 34 | 24 Mar 20251st sale agreement 24 Mar 2023 | CCC 10 Dec 2024 Handover 26 Dec 2024 | 88 days before |
| GREENWOODS SERAYA @ SALAK PERDANAKPKT 14134-5 | SepangSelangor | 260 | 16 Dec 20251st sale agreement 16 Dec 2022 | CCC 1 Oct 2024 Handover 22 Oct 2024 | 420 days before |
| SEJATI LAKESIDE 2KPKT 30178-1 | SepangSelangor | 122 | 3 Nov 20241st sale agreement 3 Nov 2022 | CCC 12 Oct 2024 Handover 18 Oct 2024 | 16 days before |
| ATRIUMKPKT 20172-1 | Kuala LumpurWP Kuala Lumpur | 241 | 4 Nov 20241st sale agreement 4 Nov 2021 | CCC 19 Jul 2024 Handover 29 Jul 2024 | 98 days before |
| BUKIT BANYAN - SENNI 3AKPKT 2003-71 | Kuala MudaKedah | 129 | 14 Feb 20251st sale agreement 14 Feb 2023 | CCC 20 Jun 2024 Handover 23 Jul 2024 | 206 days before |
| UPTOWN RESIDENCESKPKT 18-4 | KlangSelangor | 736 | 4 Jan 2025Extended 29 months from 4 Aug 20221st sale agreement 4 Aug 2019 | CCC 31 May 2024 Handover 10 Jun 2024 | 208 days before |
| PANGSAPURI PERKHIDMATAN SINARANKPKT 14638-3 | Seberang Perai SelatanPulau Pinang | 964 | 12 Nov 2024Extended 17 months from 12 Jun 20231st sale agreement 12 Jun 2020 | CCC 16 Feb 2024 Handover 20 Mar 2024 / 26 Mar 2024 | 231 days before |
| BUKIT BANYAN - SIERRA PRIMEKPKT 2003-69 | Kuala MudaKedah | 29 | 27 Oct 20241st sale agreement 27 Oct 2022 | CCC 20 Feb 2024 | CCC before deadline; handover not recorded |
| SEJATI LAKESIDEKPKT 19806-3 | SepangSelangor | 149 | 20 Nov 20231st sale agreement 20 Nov 2021 | CCC 10 Nov 2023 Handover 15 Nov 2023 / 29 Jan 2024 | 70 days after |
| BUKIT BANYAN - SENNI 3KPKT 2003-68 | Kuala MudaKedah | 78 | 22 Sep 20241st sale agreement 22 Sep 2022 | CCC 1 Nov 2023 Handover 7 Dec 2023 | 290 days before |
| BUKIT BANYANKPKT 2003-67 | Kuala MudaKedah | 120 | 8 Nov 20231st sale agreement 8 Nov 2021 | CCC 22 Aug 2023 Handover 28 Aug 2023 | 72 days before |
| BUKIT BANYANKPKT 2003-66 | Kuala MudaKedah | 61 | 26 Aug 2023Extended 5 months from 26 Mar 20231st sale agreement 26 Mar 2021 | CCC 10 Apr 2023 Handover 17 Apr 2023 | 131 days before |
| BUKIT BANYANKPKT 2003-65 | Kuala MudaKedah | 99 | 21 Aug 2023Extended 5 months from 21 Mar 20231st sale agreement 21 Mar 2021 | CCC 7 Feb 2023 Handover 15 Feb 2023 | 187 days before |
| SEJATI LAKESIDEKPKT 19806-2 | SepangSelangor | 139 | 26 Jan 2023Extended 5 months from 26 Aug 20221st sale agreement 26 Aug 2020 | CCC 27 Dec 2022 Handover 15 Jan 2023 | 11 days before |
| GREENWOODS CENDANA @ SALAK PERDANAKPKT 14134-4 | SepangSelangor | 237 | 27 Jan 2023Extended 5 months from 27 Aug 20221st sale agreement 27 Aug 2020 | CCC 9 Jan 2023 Handover 15 Jan 2023 | 12 days before |
| ATWATERKPKT 9202-21 | PetalingSelangor | 493 | 6 Feb 2023Extended 23 months from 6 Mar 20211st sale agreement 6 Mar 2018 | CCC 19 Dec 2022 Handover 29 Dec 2022 | 39 days before |
| KEMUNING IDAMANKPKT 9202-22 | KlangSelangor | 650 | 12 Jan 2023Extended 6 months from 12 Jul 20221st sale agreement 12 Jul 2019 | CCC 17 Nov 2022 Handover 8 Dec 2022 | 35 days before |
| SEJATI LAKESIDEKPKT 19806-1 | SepangSelangor | 130 | 28 Oct 2022Extended 11 months from 28 Nov 20211st sale agreement 28 Nov 2019 | CCC 30 Sep 2022 Handover 8 Oct 2022 | 20 days before |
| BUKIT BANYANKPKT 2003-63 | Kuala MudaKedah | 41 | 25 Feb 2023Extended 5 months from 25 Sep 20221st sale agreement 25 Sep 2020 | CCC 2 Aug 2022 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-64 | Kuala MudaKedah | 50 | 26 Jun 2023Extended 5 months from 26 Jan 20231st sale agreement 26 Jan 2021 | CCC 2 Aug 2022 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-61 | Kuala MudaKedah | 49 | 12 Sep 2022Extended 6 months from 12 Mar 20221st sale agreement 12 Mar 2020 | CCC 9 Feb 2022 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-62 | Kuala MudaKedah | 100 | 27 Mar 2022Extended 6 months from 27 Sep 20211st sale agreement 27 Sep 2019 | CCC 15 Sep 2021 | CCC before deadline; handover not recorded |
| TAMAN BUKIT BANYANKPKT 2003-60 | Kuala MudaKedah | 185 | 24 Jun 20211st sale agreement 24 Jun 2019 | CCC 30 Apr 2021 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-59 | Kuala MudaKedah | 69 | 12 Oct 2021Extended 6 months from 12 Apr 20211st sale agreement 12 Apr 2019 | CCC 1 Apr 2021 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-58 | Kuala MudaKedah | 195 | 30 Mar 20201st sale agreement 30 Mar 2018 | CCC 7 Feb 2021 | 314 days after † |
| UTROPOLIS BATU KAWANKPKT 14638-2 | Seberang Perai SelatanPulau Pinang | 491 | 8 Dec 2021Extended 9 months from 8 Mar 20211st sale agreement 8 Mar 2018 | CCC 4 Nov 2020 | CCC before deadline; handover not recorded |
| KERANJI 2KPKT 14134-3 | SepangSelangor | 254 | 25 Mar 2021Extended 6 months from 25 Sep 20201st sale agreement 25 Sep 2018 | CCC 22 Oct 2020 | CCC before deadline; handover not recorded |
| UTROPOLIS PHASE 3KPKT 12427-4 | PetalingSelangor | 389 | 2 Mar 2021Extended 6 months from 30 Aug 20201st sale agreement 30 Aug 2017 | CCC 14 Sep 2020 | CCC before deadline; handover not recorded |
| -KPKT 2003-56 | Kuala MudaKedah | 284 | 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 30 Jun 2020 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-57 | Kuala MudaKedah | 49 | 15 Nov 20191st sale agreement 15 Nov 2017 | CCC 10 Jun 2020 | 208 days after |
| BUKIT BANYANKPKT 2003-55 | Kuala MudaKedah | 220 | 1 Jun 20191st sale agreement 1 Jun 2017 | CCC 30 Jan 2020 | 243 days after |
| KERANJIKPKT 14134-2 | SepangSelangor | 204 | 11 Apr 20201st sale agreement 11 Apr 2018 | CCC 23 Jan 2020 | CCC before deadline; handover not recorded |
| UTROPOLIS BATU KAWANKPKT 14638-1 | Seberang Perai SelatanPulau Pinang | 612 | 6 Mar 20201st sale agreement 6 Mar 2017 | CCC 18 Oct 2019 | CCC before deadline; handover not recorded |
| SEJATI RESIDENCESKPKT 12293-6 | SepangSelangor | 47 | 23 May 20201st sale agreement 23 May 2017 | CCC 15 Aug 2019 | CCC before deadline; handover not recorded |
| SEJATI RESIDENCESKPKT 12293-7 | SepangSelangor | 30 | 22 Mar 20201st sale agreement 22 Mar 2017 | CCC 10 May 2019 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-54 | Kuala MudaKedah | 100 | 11 May 20191st sale agreement 11 May 2017 | CCC 22 Apr 2019 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-51 | Kuala MudaKedah | 72 | 16 Aug 20171st sale agreement 16 Aug 2015 | CCC 28 Feb 2019 | 561 days after |
| SEJATI RESIDENCESKPKT 12293-4 | SepangSelangor | 40 | 26 Aug 20191st sale agreement 26 Aug 2016 | CCC 17 Dec 2018 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-53 | Kuala MudaKedah | 141 | 30 Dec 20181st sale agreement 30 Dec 2016 | CCC 30 Jul 2018 | CCC before deadline; handover not recorded |
| SEJATI RESIDENCESKPKT 12293-5 | SepangSelangor | 16 | 28 Aug 20191st sale agreement 28 Aug 2016 | CCC 23 Feb 2018 | CCC before deadline; handover not recorded |
| SEJATI RESIDENCESKPKT 12293-2 | SepangSelangor | 22 | 13 Mar 20181st sale agreement 13 Mar 2015 | CCC 20 Dec 2017 | CCC before deadline; handover not recorded |
| SEJATI RESIDENCESKPKT 12293-3 | SepangSelangor | 16 | 21 Jun 20181st sale agreement 21 Jun 2015 | CCC 20 Dec 2017 | CCC before deadline; handover not recorded |
| SALAK PERDANA FASA 1KPKT 14134-1 | SepangSelangor | 96 | 15 Nov 20171st sale agreement 15 Nov 2015 | CCC 13 Nov 2017 | CCC before deadline; handover not recorded |
| UTROPOLIS SUITES 2KPKT 12427-3 | PetalingSelangor | 253 | 22 Nov 20171st sale agreement 22 Nov 2014 | CCC 5 Oct 2017 | CCC before deadline; handover not recorded |
| LAGUNA MERBOK BUSINESS PARKKPKT 2003-52 | Kuala MudaKedah | 37 | 29 Jun 20181st sale agreement 29 Jun 2016 | CCC 6 Jun 2017 | CCC before deadline; handover not recorded |
| UTROPOLIS LIFESTYLE SUITESKPKT 12427-2 | PetalingSelangor | 428 | 30 May 20171st sale agreement 30 May 2014 | CCC 8 May 2017 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-50 | Kuala MudaKedah | 211 | 25 Mar 20171st sale agreement 25 Mar 2015 | CCC 30 Mar 2017 | 5 days after |
| BUKIT BANYANKPKT 2003-49 | Kuala MudaKedah | 53 | 20 Jul 20161st sale agreement 20 Jul 2014 | CCC 20 Mar 2016 | CCC before deadline; handover not recorded |
| BANDAR LAGUNA MERBOKKPKT 2003-48 | Kuala MudaKedah | 42 | 15 May 20161st sale agreement 15 May 2014 | CCC 15 Mar 2016 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-47 | Kuala MudaKedah | 216 | 28 Oct 20151st sale agreement 28 Oct 2013 | CCC 10 Jan 2016 | 74 days after |
| PARAMOUNT UTROPOLISKPKT 12427-1 | PetalingSelangor | 414 | 10 May 20161st sale agreement 10 May 2013 | CCC 14 Dec 2015 | CCC before deadline; handover not recorded |
| SEJATI RESIDENCESKPKT 12293-1 | SepangSelangor | 78 | 2 Feb 20161st sale agreement 2 Feb 2013 | CCC 2 Oct 2015 | CCC before deadline; handover not recorded |
| KEMUNING UTAMAKPKT 9202-20 | KlangSelangor | 238 | 16 Mar 20151st sale agreement 16 Mar 2012 | CCC 6 Feb 2015 | CCC before deadline; handover not recorded |
| KEMUNING UTAMAKPKT 9202-19 | KlangSelangor | 596 | 5 May 20141st sale agreement 5 May 2011 | CCC 5 Sep 2014 | 123 days after |
| BUKIT BANYANKPKT 2003-46 | Kuala MudaKedah | 112 | 21 Feb 20151st sale agreement 21 Feb 2013 | CCC 19 Aug 2014 | CCC before deadline; handover not recorded |
| BUKIT BANYANKPKT 2003-45 | Kuala MudaKedah | 236 | — | CCC 14 Jul 2014 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-44 | Kuala MudaKedah | 140 | — | CCC 29 Aug 2013 | — |
| KEMUNING UTAMAKPKT 9202-18 | KlangSelangor | 133 | — | CCC 3 Jan 2013 | — |
| KEMUNING UTAMAKPKT 9202-17 | KlangSelangor | 125 | — | CCC 17 Aug 2012 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-42 | Kuala MudaKedah | 68 | — | CCC 1 Jul 2012 | — |
| KEMUNING UTAMAKPKT 9202-16 | KlangSelangor | 231 | — | CCC 6 Apr 2012 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-43 | Kuala MudaKedah | 47 | — | CCC 4 Mar 2012 | — |
| KEMUNING UTAMAKPKT 9202-15 | KlangSelangor | 175 | — | CCC 19 Dec 2011 | — |
| 78515-78563, 78664-78718, 78719-78741, 78639-78663,78564-78638,78755-78769, 78742-78754KPKT 2003-40 | Kuala MudaKedah | 255 | — | CCC 17 Jul 2011 | — |
| KEMUNING UTAMAKPKT 9202-14 | KlangSelangor | 115 | — | CCC 1 Jun 2011 | — |
| PARAMOUNT PROPERTY DEVELOPMENT SDN BHDKPKT 9202-13 | KlangSelangor | 108 | — | CCC 31 May 2011 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-41 | Kuala MudaKedah | 3 | — | CCC 15 Jun 2010 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-39 | Kuala MudaKedah | 26 | — | CCC 16 May 2010 | — |
| BANDAR LAGUNA MERBOK FASA 6KPKT 2003-38 | Kuala MudaKedah | 82 | — | CCC 12 Oct 2009 | — |
| KEMUNING UTAMAKPKT 9202-9 | KlangSelangor | 117 | — | CFO 20 Jul 2009 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-37 | Kuala MudaKedah | 226 | — | CFO 7 May 2009 | — |
| KEMUNING UTAMAKPKT 9202-11 | KlangSelangor | 335 | — | CFO 20 Feb 2009 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-36 | Kuala MudaKedah | 70 | — | CFO 28 Dec 2008 | — |
| KEMUNING UTAMA FASA 2BKPKT 9202-5 | KlangSelangor | 349 | — | CFO 29 Oct 2008 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-28 | Kuala MudaKedah | 253 | — | CFO 9 Sep 2007 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-33 | Kuala MudaKedah | 97 | — | CFO 9 Sep 2007 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-35 | Kuala MudaKedah | 146 | — | CFO 11 Jul 2007 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-34 | Kuala MudaKedah | 32 | — | CFO 11 Apr 2007 | — |
| KEMUNING UTAMAKPKT 9202-10 | KlangSelangor | 20 | — | CFO 4 Apr 2007 | — |
| KEMUNING UTAMAKPKT 9202-6 | KlangSelangor | 68 | — | CFO 4 Apr 2007 | — |
| KEMUNING UTAMAKPKT 9202-7 | KlangSelangor | 147 | — | CFO 4 Apr 2007 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-25 | Kuala MudaKedah | 115 | — | CFO 28 Jan 2007 | — |
| KEMUNING UTAMAKPKT 9202-4 | KlangSelangor | 329 | — | CFO 31 Oct 2006 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-14 | Kuala MudaKedah | 31 | — | CFO 25 Jul 2006 | — |
| KEMUNING UTAMAKPKT 9202-1 | KlangSelangor | 279 | — | CFO 28 Mar 2006 | — |
| KEMUNING UTAMAKPKT 9202-3 | KlangSelangor | 170 | — | CFO 20 Mar 2006 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-32 | Kuala MudaKedah | 118 | — | CFO 8 Mar 2006 | — |
| BANDAR LAGUNA MERBOKKPKT 2003-30 | Kuala MudaKedah | 87 | — | CFO 25 Jan 2006 | — |
Under construction — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| BUKIT BANYAN - MEERA GRANDKPKT 2003-76 | Kuala MudaKedah | 30 | SmoothOn schedule | 23 Mar 20271st sale agreement 23 Mar 2025 | 98% |
| SEJATI RESIDENCESKPKT 12293-8 | SepangSelangor | 170 | SmoothOn schedule | 28 Jun 20271st sale agreement 28 Jun 2024 | 72–77% |
| BUKIT BANYAN - ASPERA 2KPKT 2003-77 | Kedah | 64 | SmoothOn schedule | 8 Aug 20271st sale agreement 8 Aug 2025 | 98% |
| GREENWOODS SENNAKPKT 14134-7 | SepangSelangor | 368 | SmoothOn schedule | 27 Sep 20271st sale agreement 27 Sep 2024 | 74% |
| BUKIT BANYAN - ASPERA ELITE 2KPKT 2003-78 | Kuala MudaKedah | 96 | SmoothOn schedule | 28 Oct 20271st sale agreement 28 Oct 2025 | 50% |
| THE ATERAKPKT 30161-1The Atera · on PropertySifu | PetalingSelangor | 756 | SmoothOn schedule | 11 Nov 2027Extended 24 months from 11 Nov 20251st sale agreement 11 Nov 2022 | 96% |
| BUKIT BANYAN - ASPERA 3KPKT 2003-79 | Kuala MudaKedah | 129 | SmoothOn schedule | 29 Jun 20281st sale agreement 29 Jun 2026 | 16% |
| TAMAN BUKIT EMBUNKPKT 30948-1 | Pulau Pinang | 201 | SmoothOn schedule | 15 Aug 20281st sale agreement 15 Aug 2025 | 46–60% |
| BUKIT BANYAN - MEERA GRAND 2KPKT 2003-80 | Kuala MudaKedah | 88 | SmoothOn schedule | 24 Aug 20281st sale agreement 24 Aug 2026 | 9–16% |
| THE ATERAKPKT 30161-2The Atera · on PropertySifu | PetalingSelangor | 876 | SmoothOn schedule | 9 Oct 2028Extended 16 months from 9 Jun 20271st sale agreement 9 Jun 2024 | 46% |
| THE ASHWOODKPKT 20172-2The Ashwood · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 354 | SmoothOn schedule | 1 Dec 2028Extended 18 months from 31 May 20271st sale agreement 31 May 2024 | 47–61% |
| PANGSAPURI BERKELEY AVENUE (B)KPKT 18-5 | KlangSelangor | 652 | SmoothOn schedule | 18 Dec 2028Extended 12 months from 18 Dec 20271st sale agreement 18 Dec 2024 | 29–43% |
Show all 16 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| BUKIT BANYAN - MEERA GRANDKPKT 2003-76 | Kuala MudaKedah | 30 | SmoothOn schedule | 23 Mar 20271st sale agreement 23 Mar 2025 | 98% |
| SEJATI RESIDENCESKPKT 12293-8 | SepangSelangor | 170 | SmoothOn schedule | 28 Jun 20271st sale agreement 28 Jun 2024 | 72–77% |
| BUKIT BANYAN - ASPERA 2KPKT 2003-77 | Kedah | 64 | SmoothOn schedule | 8 Aug 20271st sale agreement 8 Aug 2025 | 98% |
| GREENWOODS SENNAKPKT 14134-7 | SepangSelangor | 368 | SmoothOn schedule | 27 Sep 20271st sale agreement 27 Sep 2024 | 74% |
| BUKIT BANYAN - ASPERA ELITE 2KPKT 2003-78 | Kuala MudaKedah | 96 | SmoothOn schedule | 28 Oct 20271st sale agreement 28 Oct 2025 | 50% |
| THE ATERAKPKT 30161-1The Atera · on PropertySifu | PetalingSelangor | 756 | SmoothOn schedule | 11 Nov 2027Extended 24 months from 11 Nov 20251st sale agreement 11 Nov 2022 | 96% |
| BUKIT BANYAN - ASPERA 3KPKT 2003-79 | Kuala MudaKedah | 129 | SmoothOn schedule | 29 Jun 20281st sale agreement 29 Jun 2026 | 16% |
| TAMAN BUKIT EMBUNKPKT 30948-1 | Pulau Pinang | 201 | SmoothOn schedule | 15 Aug 20281st sale agreement 15 Aug 2025 | 46–60% |
| BUKIT BANYAN - MEERA GRAND 2KPKT 2003-80 | Kuala MudaKedah | 88 | SmoothOn schedule | 24 Aug 20281st sale agreement 24 Aug 2026 | 9–16% |
| THE ATERAKPKT 30161-2The Atera · on PropertySifu | PetalingSelangor | 876 | SmoothOn schedule | 9 Oct 2028Extended 16 months from 9 Jun 20271st sale agreement 9 Jun 2024 | 46% |
| THE ASHWOODKPKT 20172-2The Ashwood · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 354 | SmoothOn schedule | 1 Dec 2028Extended 18 months from 31 May 20271st sale agreement 31 May 2024 | 47–61% |
| PANGSAPURI BERKELEY AVENUE (B)KPKT 18-5 | KlangSelangor | 652 | SmoothOn schedule | 18 Dec 2028Extended 12 months from 18 Dec 20271st sale agreement 18 Dec 2024 | 29–43% |
| PANGSAPURI PERKHIDMATAN SEIRASKPKT 14638-5 | Seberang Perai SelatanPulau Pinang | 411 | SmoothOn schedule | 10 Feb 2029Extended 9 months from 10 May 20281st sale agreement 10 May 2025 | 52% |
| TAMAN BUKIT EMBUNKPKT 30948-2 | Pulau Pinang | 350 | SmoothOn schedule | — | 0–5% |
| GREENWOODS AMARIA @ SALAK PERDANAKPKT 14134-6 | SepangSelangor | 538 | SmoothOn schedule | —Extended 12 months (date not registered) | 5% |
| KEMUNING UTAMAKPKT 9202-8 | KlangSelangor | 284 | SmoothOn schedule | — | 5–31% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Paramount at a glance
| Listed | Bursa Malaysia Main Market · PARAMON (1724) · listed 15 July 1971[1] |
|---|---|
| Started | 15 April 1969, as Malaysia Rice Industries Berhad[1] |
| Head office | Dataran Atwater, Petaling Jaya, Selangor[1] |
| Leadership | Quah Chek Tin — Chairman and Independent Non-Executive Director[1] Jeffrey Chew Sun Teong — Group Chief Executive Officer and Executive Director[1] Benjamin Teo Jong Hian — Deputy Chairman and Executive Director[1] |
| Companies in the KPKT register | PARAMOUNT PROPERTY (UTARA) SDN. BHD. KPKT 2003[1] PARAMOUNT PROPERTY DEVELOPMENT SDN. BHD. KPKT 9202[1] PARAMOUNT PROPERTY (CJAYA) SDN. BHD. KPKT 12293[1] PARAMOUNT PROPERTY (SEPANG) SDN. BHD. KPKT 14134[1] PARAMOUNT PROPERTY (PW) SDN. BHD. KPKT 14638[1] PARAMOUNT PROPERTY (GLENMARIE) SDN. BHD. KPKT 12427[1] PARAMOUNT PROPERTY (LAKESIDE) SDN. BHD. KPKT 19806[1] ANEKA SEPAKAT SDN. BHD. KPKT 30161[1] BERKELEY SDN BHD KPKT 18[1] PARAMOUNT PROPERTY (CITYVIEW) SDN. BHD. KPKT 20172[1] PARAMOUNT PROPERTY (PG) SDN. BHD. KPKT 30948[1] UTROPOLIS SDN. BHD. KPKT 30178[1] |
| Website | pcb.my |
| Where it builds | Kedah, Penang, Selangor and Kuala Lumpur under the Paramount Property brand, plus a 49% equity venture in Bangkok[1] |
| Land bank (company figure) | 321.6 acres of undeveloped land remaining in Malaysia at 31 December 2025[1] |
| Land bought in 2025 (company figure) | 363.1 acres in Penang, Kedah and the Klang Valley, subject to completion of the purchases[1] |
| Other businesses | Co-labs Coworking (nine spaces in the Klang Valley, one in Johor), restaurants and the Mercure Kuala Lumpur Glenmarie hotel[1] |
Paramount projects on sale on PropertySifu
Who is Paramount? The company behind the projects
Paramount traces its origins to rice milling: it was incorporated as Malaysia Rice Industries Berhad on 15 April 1969 and listed on the Kuala Lumpur Stock Exchange on 15 July 1971 [1]. Paramount Corporation Berhad now trades on Bursa Malaysia's Main Market under stock code 1724 (PARAMON) and reports three segments: property, coworking, and investment and others [1]. Its head office is at Dataran Atwater in Petaling Jaya, Selangor [1].
The property segment develops under the Paramount Property brand, with projects in Kedah, Penang, Selangor and Kuala Lumpur and a 49% equity venture in Bangkok [1]. Its 2025 annual report lists townships and developments including Bukit Banyan and Bandar Laguna Merbok in Sungai Petani, Utropolis Batu Kawan in Penang, Kemuning Utama in Shah Alam, Greenwoods Salak Perdana in Sepang and Sejati Residences in Cyberjaya; the company says 321.6 acres of undeveloped land remained in Malaysia at 31 December 2025 [1]. The KPKT register covers only projects licensed as housing, so the Bangkok venture and Paramount's office and retail buildings are not in the table above.
The two Paramount projects on PropertySifu are developed by wholly owned subsidiaries: The Ashwood in Kuala Lumpur by Paramount Property (Cityview) Sdn Bhd, and The Atera in Petaling Jaya by Aneka Sepakat Sdn Bhd [1]. KPKT registers The Ashwood as project 20172-2 and The Atera in two phases, 30161-1 and 30161-2.
The chairman is Quah Chek Tin, an independent non-executive director; Jeffrey Chew Sun Teong is group chief executive officer and Benjamin Teo Jong Hian is deputy chairman [1]. Beh Chun Chong was appointed deputy group chief executive officer on 4 September 2025 [1].
Frequently asked questions
Is Paramount a listed company?
Yes. Paramount Corporation Berhad has been listed since 15 July 1971 and trades on Bursa Malaysia's Main Market under stock code 1724 (PARAMON) [1].
How many housing projects has Paramount completed?
In the KPKT register, 95 of the 111 housing projects under 12 Paramount companies are completed. Of the 62 completed projects with both a handover deadline and a completion date recorded, 22 were handed over on or before the deadline (the extended deadline where KPKT approved an extension); 9 were handed over or certified complete after it, 1 of them under construction during the 18 March–31 August 2020 movement control period; 31 received the completion certificate before the deadline, with no handover date recorded. The other 33 completed projects do not have both dates in the register.
Does Paramount have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 111 Paramount projects as Sick (Sakit) or Abandoned (Terbengkalai). All 16 projects now under construction are recorded as on schedule (Lancar).
Which companies develop The Ashwood and The Atera?
The Ashwood is developed by Paramount Property (Cityview) Sdn Bhd (KPKT developer code 20172) and The Atera by Aneka Sepakat Sdn Bhd (KPKT developer code 30161). Paramount's 2025 annual report lists both as wholly owned subsidiaries [1].
Have the handover deadlines of The Ashwood and The Atera been extended?
Yes, according to KPKT. The Ashwood (20172-2, 354 units, first sale agreement 31 May 2024) had a deadline of 31 May 2027, extended with approval by 18 months to 1 December 2028; its two components report 46.7% and 60.8% progress. The Atera's first phase (30161-1, 756 units, first sale agreement 11 November 2022) had a deadline of 11 November 2025, extended by 24 months to 11 November 2027, with 96.5% reported progress. Its second phase (30161-2, 876 units, first sale agreement 9 June 2024) had a deadline of 9 June 2027, extended by 16 months to 9 October 2028, with 46% reported progress. All three are recorded as on schedule (Lancar).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.