OSK Property (OSK Holdings Berhad)
OSK Property, the property arm of Bursa Malaysia-listed OSK Holdings Berhad, has 121 housing projects in the KPKT register under 21 group companies: 100 completed and 21 not yet completed — 18 under construction, one of them classed Late (Lewat), and 3 with the permit cancelled; none is Sick or Abandoned. OSK began in 1963 as a stockbroker and entered property in 1996.
- 121 projects in the KPKT register
- 100 completed
- 18 under construction
- 3 with the permit cancelled
- None Sick or Abandoned
Has OSK Property handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 121 housing projects under 21 OSK Property companies in 6 states: 100 completed, 18 under construction, 3 with the permit cancelled. 0 classed Sick (Sakit), 0 Abandoned (Terbengkalai), 1 Late (Lewat).
Of the 100 completed projects, 73 have both a handover deadline and a completion date in the register: 28 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 23 handed over or certified complete after that deadline; 22 received the completion certificate before the deadline (handover date not recorded).
27 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 100
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IRINGAN BAYUKPKT 9902-19 | SerembanNegeri Sembilan | 137 | 22 Nov 20261st sale agreement 22 Nov 2024 | CCC 21 Sep 2026 | CCC before deadline; handover not recorded |
| LEA BY THE HILLSKPKT 11519-3LEA BY THE HILLS · on PropertySifu | GombakSelangor | 344 | 30 Jul 2026Extended 12 months from 30 Jul 20251st sale agreement 30 Jul 2022 | CCC 18 Mar 2026 Handover 20 Apr 2026 | 101 days before |
| IRINGAN BAYUKPKT 9902-18 | SerembanNegeri Sembilan | 290 | 14 Apr 20261st sale agreement 14 Apr 2024 | CCC 15 Jan 2026 Handover 13 Mar 2026 | 32 days before |
| PANGSAPURI PERKHIDMATAN RUBICAKPKT 8555-10 | Seberang Perai UtaraPulau Pinang | 230 | 30 Aug 2026Extended 12 months from 30 Aug 20251st sale agreement 30 Aug 2022 | CCC 2 Sep 2025 Handover 1 Dec 2025 | 272 days before |
| ANYA RESIDENCESKPKT 10139-4Anya Residence @ Shorea Park · on PropertySifu | SepangSelangor | 750 | 17 Sep 2026Extended 12 months from 17 Sep 20251st sale agreement 17 Sep 2022 | CCC 10 Sep 2025 Handover 30 Sep 2025 | 352 days before |
| IRINGAN BAYUKPKT 9902-16 | SerembanNegeri Sembilan | 162 | 16 Nov 20251st sale agreement 16 Nov 2023 | CCC 24 Jul 2025 Handover 17 Sep 2025 | 60 days before |
| IRINGAN BAYUKPKT 9902-17 | SerembanNegeri Sembilan | 239 | 16 Nov 20251st sale agreement 16 Nov 2023 | CCC 23 Jul 2025 Handover 1 Aug 2025 | 107 days before |
| IRINGAN BAYUKPKT 9902-15 | SerembanNegeri Sembilan | 241 | 17 Oct 20251st sale agreement 17 Oct 2023 | CCC 26 May 2025 Handover 28 May 2025 | 142 days before |
| PRECINT 6 (RUMAH MAKMUR)KPKT 7103-52 | Kuala MudaKedah | 226 | 29 Apr 20251st sale agreement 29 Apr 2023 | CCC 18 Dec 2024 Handover 20 Dec 2024 | 130 days before |
| SOUTHFIELD VILLA @ YARRA PARKKPKT 7103-49 | Kuala MudaKedah | 81 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 7 Aug 2024 Handover 5 Sep 2024 | 86 days before |
| EASTFIELD @ YARRA PARKKPKT 7103-53 | Kuala MudaKedah | 39 | 13 Jul 20251st sale agreement 13 Jul 2023 | CCC 12 Aug 2024 Handover 16 Aug 2024 | 331 days before |
| IRINGAN BAYUKPKT 9902-4 | SerembanNegeri Sembilan | 200 | — | CCC 6 Aug 2024 | — |
Handed over or certified complete after the deadline — 12 most recent of 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IRINGAN BAYUKPKT 9902-12 | SerembanNegeri Sembilan | 306 | 17 Nov 20231st sale agreement 17 Nov 2021 | CCC 28 Nov 2023 Handover 29 Nov 2023 | 12 days after |
| IRINGAN BAYUKPKT 9902-11 | SerembanNegeri Sembilan | 86 | 9 Sep 20231st sale agreement 9 Sep 2021 | CCC 17 Oct 2023 Handover 17 Oct 2023 | 38 days after |
| OSK PROPERTIES SDN. BHD.KPKT 7103-39 | Kuala MudaKedah | 13 | 26 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020 | CCC 27 Mar 2023 Handover 6 May 2022 / 31 Mar 2023 | 5 days after |
| SPLENDOURS OF THE SEAKPKT 11643-2 | KuantanPahang | 760 | 18 Jun 20191st sale agreement 18 Jun 2016 | CCC 23 Sep 2019 | 97 days after |
| HARBOUR PLACEKPKT 8555-8 | Seberang Perai UtaraPulau Pinang | 462 | 1 Sep 20191st sale agreement 1 Sep 2016 | CCC 12 Sep 2019 | 11 days after |
| WINDMILL UPON HILLSKPKT 11871-2 | BentongPahang | 1,108 | 5 Jun 20181st sale agreement 5 Jun 2015 | CCC 30 May 2019 | 359 days after |
| EMIRAKPKT 13952-1 | PetalingSelangor | 400 | 18 Apr 20181st sale agreement 18 Apr 2015 | CCC 28 Jun 2018 | 71 days after |
| BANDAR PUTERI JAYA & HILL PARKKPKT 7103-28 | Kuala MudaKedah | 266 | 11 Dec 20161st sale agreement 11 Dec 2014 | CCC 19 Mar 2018 | 463 days after |
| PAN'GAEAKPKT 12229-2 | SepangSelangor | 666 | 20 Dec 20161st sale agreement 20 Dec 2013 | CCC 15 Sep 2017 | 269 days after |
| HARBOUR PLACEKPKT 8555-7 | Seberang Perai UtaraPulau Pinang | 420 | 30 Sep 20161st sale agreement 30 Sep 2013 | CCC 9 Mar 2017 | 160 days after |
| YOU CITY - YOU VISTAKPKT 10662-3 | Hulu LangatSelangor | 730 | 8 Feb 20161st sale agreement 8 Feb 2013 | CCC 19 Jan 2017 | 346 days after |
| PANGAEA - SOLSTICEKPKT 12229-1 | SepangSelangor | 946 | 1 Apr 20151st sale agreement 1 Apr 2012 | CCC 5 Sep 2016 | 523 days after |
Show all 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IRINGAN BAYUKPKT 9902-12 | SerembanNegeri Sembilan | 306 | 17 Nov 20231st sale agreement 17 Nov 2021 | CCC 28 Nov 2023 Handover 29 Nov 2023 | 12 days after |
| IRINGAN BAYUKPKT 9902-11 | SerembanNegeri Sembilan | 86 | 9 Sep 20231st sale agreement 9 Sep 2021 | CCC 17 Oct 2023 Handover 17 Oct 2023 | 38 days after |
| OSK PROPERTIES SDN. BHD.KPKT 7103-39 | Kuala MudaKedah | 13 | 26 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020 | CCC 27 Mar 2023 Handover 6 May 2022 / 31 Mar 2023 | 5 days after |
| SPLENDOURS OF THE SEAKPKT 11643-2 | KuantanPahang | 760 | 18 Jun 20191st sale agreement 18 Jun 2016 | CCC 23 Sep 2019 | 97 days after |
| HARBOUR PLACEKPKT 8555-8 | Seberang Perai UtaraPulau Pinang | 462 | 1 Sep 20191st sale agreement 1 Sep 2016 | CCC 12 Sep 2019 | 11 days after |
| WINDMILL UPON HILLSKPKT 11871-2 | BentongPahang | 1,108 | 5 Jun 20181st sale agreement 5 Jun 2015 | CCC 30 May 2019 | 359 days after |
| EMIRAKPKT 13952-1 | PetalingSelangor | 400 | 18 Apr 20181st sale agreement 18 Apr 2015 | CCC 28 Jun 2018 | 71 days after |
| BANDAR PUTERI JAYA & HILL PARKKPKT 7103-28 | Kuala MudaKedah | 266 | 11 Dec 20161st sale agreement 11 Dec 2014 | CCC 19 Mar 2018 | 463 days after |
| PAN'GAEAKPKT 12229-2 | SepangSelangor | 666 | 20 Dec 20161st sale agreement 20 Dec 2013 | CCC 15 Sep 2017 | 269 days after |
| HARBOUR PLACEKPKT 8555-7 | Seberang Perai UtaraPulau Pinang | 420 | 30 Sep 20161st sale agreement 30 Sep 2013 | CCC 9 Mar 2017 | 160 days after |
| YOU CITY - YOU VISTAKPKT 10662-3 | Hulu LangatSelangor | 730 | 8 Feb 20161st sale agreement 8 Feb 2013 | CCC 19 Jan 2017 | 346 days after |
| PANGAEA - SOLSTICEKPKT 12229-1 | SepangSelangor | 946 | 1 Apr 20151st sale agreement 1 Apr 2012 | CCC 5 Sep 2016 | 523 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-26 | Kuala MudaKedah | 243 | 13 May 20151st sale agreement 13 May 2013 | CCC 13 Jul 2016 | 427 days after |
| PJD LANDMARKS SDN BHDKPKT 12063-1 | PetalingSelangor | 457 | 30 Jul 20151st sale agreement 30 Jul 2012 | CCC 4 Jul 2016 | 340 days after |
| SUTERA DAMANSARAKPKT 10561-4 | PetalingSelangor | 98 | 20 Mar 20151st sale agreement 20 Mar 2012 | CCC 11 Apr 2016 | 388 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-27 | Kuala MudaKedah | 138 | 11 Nov 20141st sale agreement 11 Nov 2012 | CCC 6 Dec 2015 | 390 days after |
| YOU CITY - YOU RESIDENCESKPKT 10662-2 | Hulu LangatSelangor | 370 | 15 Aug 20151st sale agreement 15 Aug 2012 | CCC 17 Sep 2015 | 33 days after |
| SUTERA DAMANSARAKPKT 10561-5 | PetalingSelangor | 28 | 28 Jun 20151st sale agreement 28 Jun 2013 | CCC 10 Aug 2015 | 43 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-24 | Kuala MudaKedah | 290 | 25 Jun 20141st sale agreement 25 Jun 2012 | CCC 15 Jun 2015 | 355 days after |
| D'MAJESTICKPKT 11871-1 | Kuala LumpurWP Kuala Lumpur | 135 | 2 Mar 20151st sale agreement 2 Mar 2012 | CCC 31 Mar 2015 | 29 days after |
| HARBOUR PLACEKPKT 8555-6 | Seberang Perai UtaraPulau Pinang | 410 | 18 Aug 20141st sale agreement 18 Aug 2011 | CCC 5 Mar 2015 | 199 days after |
| JELANG VISTA SDN BHDKPKT 11519-1 | SepangSelangor | 231 | 16 Aug 20131st sale agreement 16 Aug 2011 | CCC 21 Oct 2014 | 431 days after |
| SWISS-GARDEN RESORT RESIDENCESKPKT 11643-1 | KuantanPahang | 275 | 30 Apr 20141st sale agreement 30 Apr 2011 | CCC 20 Oct 2014 | 173 days after |
Show all 100 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IRINGAN BAYUKPKT 9902-19 | SerembanNegeri Sembilan | 137 | 22 Nov 20261st sale agreement 22 Nov 2024 | CCC 21 Sep 2026 | CCC before deadline; handover not recorded |
| LEA BY THE HILLSKPKT 11519-3LEA BY THE HILLS · on PropertySifu | GombakSelangor | 344 | 30 Jul 2026Extended 12 months from 30 Jul 20251st sale agreement 30 Jul 2022 | CCC 18 Mar 2026 Handover 20 Apr 2026 | 101 days before |
| IRINGAN BAYUKPKT 9902-18 | SerembanNegeri Sembilan | 290 | 14 Apr 20261st sale agreement 14 Apr 2024 | CCC 15 Jan 2026 Handover 13 Mar 2026 | 32 days before |
| PANGSAPURI PERKHIDMATAN RUBICAKPKT 8555-10 | Seberang Perai UtaraPulau Pinang | 230 | 30 Aug 2026Extended 12 months from 30 Aug 20251st sale agreement 30 Aug 2022 | CCC 2 Sep 2025 Handover 1 Dec 2025 | 272 days before |
| ANYA RESIDENCESKPKT 10139-4Anya Residence @ Shorea Park · on PropertySifu | SepangSelangor | 750 | 17 Sep 2026Extended 12 months from 17 Sep 20251st sale agreement 17 Sep 2022 | CCC 10 Sep 2025 Handover 30 Sep 2025 | 352 days before |
| IRINGAN BAYUKPKT 9902-16 | SerembanNegeri Sembilan | 162 | 16 Nov 20251st sale agreement 16 Nov 2023 | CCC 24 Jul 2025 Handover 17 Sep 2025 | 60 days before |
| IRINGAN BAYUKPKT 9902-17 | SerembanNegeri Sembilan | 239 | 16 Nov 20251st sale agreement 16 Nov 2023 | CCC 23 Jul 2025 Handover 1 Aug 2025 | 107 days before |
| IRINGAN BAYUKPKT 9902-15 | SerembanNegeri Sembilan | 241 | 17 Oct 20251st sale agreement 17 Oct 2023 | CCC 26 May 2025 Handover 28 May 2025 | 142 days before |
| PRECINT 6 (RUMAH MAKMUR)KPKT 7103-52 | Kuala MudaKedah | 226 | 29 Apr 20251st sale agreement 29 Apr 2023 | CCC 18 Dec 2024 Handover 20 Dec 2024 | 130 days before |
| SOUTHFIELD VILLA @ YARRA PARKKPKT 7103-49 | Kuala MudaKedah | 81 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 7 Aug 2024 Handover 5 Sep 2024 | 86 days before |
| EASTFIELD @ YARRA PARKKPKT 7103-53 | Kuala MudaKedah | 39 | 13 Jul 20251st sale agreement 13 Jul 2023 | CCC 12 Aug 2024 Handover 16 Aug 2024 | 331 days before |
| IRINGAN BAYUKPKT 9902-4 | SerembanNegeri Sembilan | 200 | — | CCC 6 Aug 2024 | — |
| SOUTHFIELD RESIDENCE @ YARRA PARKKPKT 7103-48 | Kuala MudaKedah | 40 | 20 Oct 20241st sale agreement 20 Oct 2022 | CCC 8 Jul 2024 Handover 30 Jul 2024 | 82 days before |
| MIRAKPKT 10139-3 | SepangSelangor | 908 | 10 Aug 2025Extended 12 months from 10 Aug 20241st sale agreement 10 Aug 2021 | CCC 13 Jul 2024 Handover 24 Jul 2024 | 382 days before |
| SPRINGFIELD @ YARRA PARKKPKT 7103-47 | Kuala MudaKedah | 257 | 12 Aug 20241st sale agreement 12 Aug 2022 | CCC 2 Jul 2024 Handover 5 Jul 2024 | 38 days before |
| EASTFIELD @ YARRA PARKKPKT 7103-50 | Kuala MudaKedah | 126 | 29 Dec 20241st sale agreement 29 Dec 2022 | CCC 2 Jul 2024 Handover 5 Jul 2024 | 177 days before |
| SPRINGFIELD @ YARRA PARKKPKT 7103-51 | Kuala MudaKedah | 99 | 29 Dec 20241st sale agreement 29 Dec 2022 | CCC 2 Jul 2024 Handover 5 Jul 2024 | 177 days before |
| IRINGAN BAYUKPKT 9902-14 | SerembanNegeri Sembilan | 316 | 18 Jun 20241st sale agreement 18 Jun 2022 | CCC 12 Jun 2024 Handover 14 Jun 2024 | 4 days before |
| SOUTHFIELD RESIDENCE @ YARRA PARKKPKT 7103-43 | Kuala MudaKedah | 51 | 31 Jan 20241st sale agreement 31 Jan 2022 | CCC 29 Nov 2023 Handover 29 Dec 2023 | 33 days before |
| SOUTHFIELD RESIDENCE @ YARRA PARKKPKT 7103-46 | Kuala MudaKedah | 50 | 31 Jan 20241st sale agreement 31 Jan 2022 | CCC 29 Nov 2023 Handover 29 Dec 2023 | 33 days before |
| IRINGAN BAYUKPKT 9902-13 | SerembanNegeri Sembilan | 56 | 19 Mar 20241st sale agreement 19 Mar 2022 | CCC 8 Dec 2023 Handover 12 Dec 2023 | 98 days before |
| IRINGAN BAYUKPKT 9902-12 | SerembanNegeri Sembilan | 306 | 17 Nov 20231st sale agreement 17 Nov 2021 | CCC 28 Nov 2023 Handover 29 Nov 2023 | 12 days after |
| NORTHFIELD @ YARRA PARKKPKT 7103-45 | Kuala MudaKedah | 171 | 2 Mar 20241st sale agreement 2 Mar 2022 | CCC 3 Nov 2023 Handover 24 Nov 2023 | 99 days before |
| IRINGAN BAYUKPKT 9902-11 | SerembanNegeri Sembilan | 86 | 9 Sep 20231st sale agreement 9 Sep 2021 | CCC 17 Oct 2023 Handover 17 Oct 2023 | 38 days after |
| SOUTHFIELD VILLA @ YARRA PARKKPKT 7103-44 | Kuala MudaKedah | 66 | 15 Dec 20231st sale agreement 15 Dec 2021 | CCC 3 Oct 2023 Handover 16 Oct 2023 | 60 days before |
| IRINGAN BAYUKPKT 9902-10 | SerembanNegeri Sembilan | 180 | 26 Aug 2023Extended 5 months from 26 Mar 20231st sale agreement 26 Mar 2021 | CCC 14 Jun 2023 Handover 16 Jun 2023 | 71 days before |
| EASTFIELD @ YARRA PARKKPKT 7103-42 | Kuala MudaKedah | 132 | 17 Sep 20231st sale agreement 17 Sep 2021 | CCC 10 Apr 2023 Handover 26 May 2023 | 114 days before |
| OSK PROPERTIES SDN. BHD.KPKT 7103-39 | Kuala MudaKedah | 13 | 26 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020 | CCC 27 Mar 2023 Handover 6 May 2022 / 31 Mar 2023 | 5 days after |
| OSK PROPERTIES SDN. BHD.KPKT 7103-40 | Kuala MudaKedah | 38 | 15 Jul 20231st sale agreement 15 Jul 2021 | CCC 27 Mar 2023 Handover 31 Mar 2023 | 106 days before |
| IRINGAN BAYUKPKT 9902-9 | SerembanNegeri Sembilan | 215 | 21 May 2023Extended 5 months from 21 Dec 20221st sale agreement 21 Dec 2020 | CCC 20 Dec 2022 Handover 30 Dec 2022 | 142 days before |
| OSK PROPERTIES SDN. BHD.KPKT 7103-41 | Kuala MudaKedah | 141 | 31 May 20231st sale agreement 31 May 2021 | CCC 12 Dec 2022 Handover 16 Dec 2022 | 166 days before |
| IRINGAN BAYUKPKT 9902-8 | SerembanNegeri Sembilan | 219 | 4 Jan 2023Extended 5 months from 4 Aug 20221st sale agreement 4 Aug 2020 | CCC 31 May 2022 Handover 10 Jun 2022 | 208 days before |
| OSK PROPERTIES SDN. BHD.KPKT 7103-38 | Kuala MudaKedah | 44 | 11 Apr 2023Extended 5 months from 11 Nov 20221st sale agreement 11 Nov 2020 | CCC 5 May 2022 | CCC before deadline; handover not recorded |
| WESTFIELD (PRECINCT 4)KPKT 7103-35 | Kuala MudaKedah | 108 | 16 Jun 20221st sale agreement 16 Jun 2020 | CCC 25 Apr 2022 | CCC before deadline; handover not recorded |
| OSK PROPERTIES SDN. BHD.KPKT 7103-37 | Kuala MudaKedah | 162 | 17 Aug 20221st sale agreement 17 Aug 2020 | CCC 21 Apr 2022 | CCC before deadline; handover not recorded |
| IRINGAN BAYUKPKT 9902-7 | SerembanNegeri Sembilan | 318 | 13 Jul 2022Extended 6 months from 13 Jan 20221st sale agreement 13 Jan 2020 | CCC 31 Jan 2022 Handover 31 Mar 2022 | 104 days before |
| OSK PROPERTIES SDN. BHD.KPKT 7103-36 | Kuala MudaKedah | 43 | 21 Aug 20221st sale agreement 21 Aug 2020 | CCC 24 Jan 2022 | CCC before deadline; handover not recorded |
| RYAN & MIHOKPKT 19225-2 | PetalingSelangor | 542 | 19 May 2023Extended 18 months from 19 Nov 20211st sale agreement 19 Nov 2018 | CCC 2 Nov 2021 | CCC before deadline; handover not recorded |
| OSK PROPERTIES SDN. BHD.KPKT 7103-34 | Kuala MudaKedah | 32 | 23 Jun 2022Extended 6 months from 23 Dec 20211st sale agreement 23 Dec 2019 | CCC 10 Sep 2021 | CCC before deadline; handover not recorded |
| IRINGAN BAYUKPKT 9902-6 | SerembanNegeri Sembilan | 312 | 22 Apr 2022Extended 6 months from 22 Oct 20211st sale agreement 22 Oct 2019 | CCC 13 Aug 2021 | CCC before deadline; handover not recorded |
| RYAN & MIHOKPKT 19225-1 | PetalingSelangor | 542 | 13 Jun 2022Extended 18 months from 13 Dec 20201st sale agreement 13 Dec 2017 | CCC 12 Jul 2021 | CCC before deadline; handover not recorded |
| OSK PROPERTIES SDN BHDKPKT 7103-32 | Kuala MudaKedah | 80 | 17 Dec 2021Extended 6 months from 17 Jun 20211st sale agreement 17 Jun 2019 | CCC 21 Apr 2021 | CCC before deadline; handover not recorded |
| OSK PROPERTIES SDN BHDKPKT 7103-33 | Kuala MudaKedah | 40 | 17 Dec 2021Extended 6 months from 17 Jun 20211st sale agreement 17 Jun 2019 | CCC 21 Apr 2021 | CCC before deadline; handover not recorded |
| RUMAH KASIH RAKYATKPKT 7103-30 | Kuala MudaKedah | 160 | 21 Apr 2022Extended 6 months from 21 Oct 20211st sale agreement 21 Oct 2018 | CCC 15 Mar 2021 | CCC before deadline; handover not recorded |
| IRINGAN BAYUKPKT 9902-5 | SerembanNegeri Sembilan | 342 | 21 May 2021Extended 6 months from 21 Nov 20201st sale agreement 21 Nov 2018 | CCC 20 Nov 2020 | CCC before deadline; handover not recorded |
| IRINGAN BAYUKPKT 9902-3 | SerembanNegeri Sembilan | 198 | 29 Aug 20201st sale agreement 29 Aug 2018 | CCC 25 Aug 2020 | CCC before deadline; handover not recorded |
| IRINGAN BAYUKPKT 9902-2 | SerembanNegeri Sembilan | 221 | 2 Feb 20201st sale agreement 2 Feb 2018 | CCC 31 Jan 2020 | CCC before deadline; handover not recorded |
| SPLENDOURS OF THE SEAKPKT 11643-2 | KuantanPahang | 760 | 18 Jun 20191st sale agreement 18 Jun 2016 | CCC 23 Sep 2019 | 97 days after |
| HARBOUR PLACEKPKT 8555-8 | Seberang Perai UtaraPulau Pinang | 462 | 1 Sep 20191st sale agreement 1 Sep 2016 | CCC 12 Sep 2019 | 11 days after |
| WINDMILL UPON HILLSKPKT 11871-2 | BentongPahang | 1,108 | 5 Jun 20181st sale agreement 5 Jun 2015 | CCC 30 May 2019 | 359 days after |
| EMIRAKPKT 13952-1 | PetalingSelangor | 400 | 18 Apr 20181st sale agreement 18 Apr 2015 | CCC 28 Jun 2018 | 71 days after |
| BANDAR PUTERI JAYA & HILL PARKKPKT 7103-28 | Kuala MudaKedah | 266 | 11 Dec 20161st sale agreement 11 Dec 2014 | CCC 19 Mar 2018 | 463 days after |
| PAN'GAEAKPKT 12229-2 | SepangSelangor | 666 | 20 Dec 20161st sale agreement 20 Dec 2013 | CCC 15 Sep 2017 | 269 days after |
| PRESINT 3KPKT 7103-29 | Kuala MudaKedah | 47 | 24 Aug 20171st sale agreement 24 Aug 2015 | CCC 21 Aug 2017 | CCC before deadline; handover not recorded |
| BANDAR PUTERI JAYA & HILL PARKKPKT 7103-23 | Kuala MudaKedah | 220 | 30 Jun 20171st sale agreement 30 Jun 2014 | CCC 4 May 2017 | CCC before deadline; handover not recorded |
| HARBOUR PLACEKPKT 8555-7 | Seberang Perai UtaraPulau Pinang | 420 | 30 Sep 20161st sale agreement 30 Sep 2013 | CCC 9 Mar 2017 | 160 days after |
| SUTERA DAMANSARAKPKT 10561-6 | PetalingSelangor | 36 | 24 Mar 20171st sale agreement 24 Mar 2014 | CCC 9 Mar 2017 | CCC before deadline; handover not recorded |
| YOU CITY - YOU VISTAKPKT 10662-3 | Hulu LangatSelangor | 730 | 8 Feb 20161st sale agreement 8 Feb 2013 | CCC 19 Jan 2017 | 346 days after |
| PANGAEA - SOLSTICEKPKT 12229-1 | SepangSelangor | 946 | 1 Apr 20151st sale agreement 1 Apr 2012 | CCC 5 Sep 2016 | 523 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-26 | Kuala MudaKedah | 243 | 13 May 20151st sale agreement 13 May 2013 | CCC 13 Jul 2016 | 427 days after |
| PJD LANDMARKS SDN BHDKPKT 12063-1 | PetalingSelangor | 457 | 30 Jul 20151st sale agreement 30 Jul 2012 | CCC 4 Jul 2016 | 340 days after |
| SUTERA DAMANSARAKPKT 10561-4 | PetalingSelangor | 98 | 20 Mar 20151st sale agreement 20 Mar 2012 | CCC 11 Apr 2016 | 388 days after |
| SUTERA DAMANSARAKPKT 10524-4 | PetalingSelangor | 236 | 2 Jul 20171st sale agreement 2 Jul 2014 | CCC 8 Mar 2016 | CCC before deadline; handover not recorded |
| OSK PROPERTIES SDN.BHD.KPKT 7103-27 | Kuala MudaKedah | 138 | 11 Nov 20141st sale agreement 11 Nov 2012 | CCC 6 Dec 2015 | 390 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-22 | Kuala MudaKedah | 116 | 11 Dec 20151st sale agreement 11 Dec 2013 | CCC 13 Oct 2015 | CCC before deadline; handover not recorded |
| MIRAGE RESIDENCEKPKT 11604-1 | Kuala LumpurWP Kuala Lumpur | 102 | —1st sale agreement 11 Oct 2011 | CCC 2 Oct 2015 | — |
| YOU CITY - YOU RESIDENCESKPKT 10662-2 | Hulu LangatSelangor | 370 | 15 Aug 20151st sale agreement 15 Aug 2012 | CCC 17 Sep 2015 | 33 days after |
| SUTERA DAMANSARAKPKT 10561-5 | PetalingSelangor | 28 | 28 Jun 20151st sale agreement 28 Jun 2013 | CCC 10 Aug 2015 | 43 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-24 | Kuala MudaKedah | 290 | 25 Jun 20141st sale agreement 25 Jun 2012 | CCC 15 Jun 2015 | 355 days after |
| MIRAGE BY THE LAKEKPKT 11519-2 | SepangSelangor | 246 | 25 Jun 20151st sale agreement 25 Jun 2012 | CCC 5 Jun 2015 | CCC before deadline; handover not recorded |
| D'MAJESTICKPKT 11871-1 | Kuala LumpurWP Kuala Lumpur | 135 | 2 Mar 20151st sale agreement 2 Mar 2012 | CCC 31 Mar 2015 | 29 days after |
| HARBOUR PLACEKPKT 8555-6 | Seberang Perai UtaraPulau Pinang | 410 | 18 Aug 20141st sale agreement 18 Aug 2011 | CCC 5 Mar 2015 | 199 days after |
| JELANG VISTA SDN BHDKPKT 11519-1 | SepangSelangor | 231 | 16 Aug 20131st sale agreement 16 Aug 2011 | CCC 21 Oct 2014 | 431 days after |
| SWISS-GARDEN RESORT RESIDENCESKPKT 11643-1 | KuantanPahang | 275 | 30 Apr 20141st sale agreement 30 Apr 2011 | CCC 20 Oct 2014 | 173 days after |
| OSK PROPERTIES SDN.BHD.KPKT 7103-25 | Kuala MudaKedah | 86 | 18 Sep 20151st sale agreement 18 Sep 2013 | CCC 21 Aug 2014 | CCC before deadline; handover not recorded |
| OSK PROPERTIES SDN.BHD.KPKT 7103-18 | Kuala MudaKedah | 152 | — | CFO 1 Dec 2013 | — |
| SEMPONIA SDN BHDKPKT 10561-3 | PetalingSelangor | 42 | — | CCC 16 May 2013 | — |
| OSK PROPERTIES SDN.BHD.KPKT 7103-19 | Kuala MudaKedah | 60 | — | CFO 7 Apr 2013 | — |
| SEREMBAN 3KPKT 9173-4 | SerembanNegeri Sembilan | 88 | — | CFO 1 Jan 2013 | — |
| SUTERA DAMANSARAKPKT 10524-2 | PetalingSelangor | 51 | — | CCC 17 Oct 2012 | — |
| BANDAR PUTERI JAYAKPKT 7103-15 | Kuala MudaKedah | 167 | — | CFO 30 Jul 2012 | — |
| COUNTRY WHEEL SDN BHDKPKT 10524-3 | PetalingSelangor | 82 | — | CCC 30 Apr 2012 | — |
| HARBOUR PLACEKPKT 8555-4 | Seberang Perai UtaraPulau Pinang | 382 | — | CCC 27 Apr 2012 | — |
| SUTERA DAMANSARAKPKT 10561-1 | PetalingSelangor | 78 | — | CCC 1 Apr 2012 | — |
| SUTERA DAMANSARAKPKT 10561-2 | PetalingSelangor | 9 | — | CCC 5 Mar 2012 | — |
| SUTERA DAMANSARAKPKT 10524-1 | PetalingSelangor | 271 | — | CCC 4 Jan 2012 | — |
| PUNCAK BANGIKPKT 10797-1 | Hulu LangatSelangor | 74 | — | CCC 4 Jan 2012 | — |
| SEREMBAN 3KPKT 9173-5 | SerembanNegeri Sembilan | 50 | — | CFO 20 Oct 2011 | — |
| BANDAR PUTERI JAYAKPKT 7103-12 | Kuala MudaKedah | 456 | — | CFO 28 Mar 2011 | — |
| BANDAR PUTERI JAYAKPKT 7103-10 | Kuala MudaKedah | 558 | — | CFO 25 Mar 2010 | — |
| BANDAR PUTERI JAYAKPKT 7103-14 | Kuala MudaKedah | 160 | — | CFO 9 Aug 2009 | — |
| SIARAH OAKLEAFKPKT 8555-5 | GombakSelangor | 20 | — | CFO 16 Jul 2009 | — |
| BANDAR PUTERI JAYAKPKT 7103-9 | Kuala MudaKedah | 240 | — | CFO 24 Feb 2009 | — |
| HARBOUR PLACEKPKT 8555-2 | Seberang Perai UtaraPulau Pinang | 354 | — | CFO 17 Jun 2008 | — |
| LOT 1806 MUKIM KAJANGKPKT 9902-1 | Kuala LumpurWP Kuala Lumpur | 26 | — | CFO 25 Apr 2008 | — |
| SEREMBAN 3KPKT 9173-2 | SerembanNegeri Sembilan | 192 | — | CFO 24 May 2006 | — |
| HARBOUR PLACEKPKT 8555-1 | Seberang Perai UtaraPulau Pinang | 312 | — | CFO 11 Oct 2005 | — |
| PT 15748- PT 15984KPKT 9173-3 | SerembanNegeri Sembilan | 237 | — | — | — |
| OSK PROPERTIES SDN BHDKPKT 7103-16 | Kuala MudaKedah | 60 | — | — | — |
| OSK PROPERTIES SDN.BHD.KPKT 7103-17 | Kuala MudaKedah | 206 | — | — | — |
Under construction — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| IRINGAN BAYU - ALERIAKPKT 9902-20 | SerembanNegeri Sembilan | 212 | SmoothOn schedule | 30 Nov 20261st sale agreement 30 Nov 2024 | 98% |
| TAMAN LANG AMANKPKT 30899-1 | Kuala MudaKedah | 197 | DelayLate | 23 Feb 20271st sale agreement 23 Feb 2025 | 80% |
| RESIDENSI NURIAKPKT 30564-1 | GombakSelangor | 275 | SmoothOn schedule | 18 Mar 20271st sale agreement 18 Mar 2024 | 98% |
| SIERRA AT OSK YARRA PARKKPKT 7103-54 | Kuala MudaKedah | 193 | SmoothOn schedule | 13 Sep 20271st sale agreement 13 Sep 2025 | 27–67% |
| AYRA AT OSK YARRA PARKKPKT 7103-55 | Kedah | 239 | SmoothOn schedule | 4 Oct 20271st sale agreement 4 Oct 2025 | 50–61% |
| RESIDENSI HANAKPKT 30564-2Hana Hills · on PropertySifu | GombakSelangor | 297 | SmoothOn schedule | 3 Jan 2028Extended 6 months from 3 Jul 20271st sale agreement 3 Jul 2024 | 69% |
| ALIAKPKT 30670-1Alia Mori Park · on PropertySifu | PetalingSelangor | 812 | SmoothOn schedule | 1 Jun 2028Extended 12 months from 1 Jun 20271st sale agreement 1 Jun 2024 | 76% |
| NARA AT SHOREA PARKKPKT 10139-5Nara Residence · on PropertySifu | SepangSelangor | 709 | SmoothOn schedule | 8 Jun 2028Extended 12 months from 8 Jun 20271st sale agreement 8 Jun 2024 | 98% |
| IRINGAN BAYUKPKT 9902-21 | Negeri Sembilan | 79 | SmoothOn schedule | 24 Jun 20281st sale agreement 24 Jun 2026 | 0% |
| TAMAN LANG AMANKPKT 30899-2 | Kedah | 233 | SmoothOn schedule | 29 Jun 20281st sale agreement 29 Jun 2026 | 5–10% |
| HARBOUR VIEW RESIDENCEKPKT 8555-11 | Seberang Perai UtaraPulau Pinang | 373 | SmoothOn schedule | 14 Mar 2029Extended 12 months from 14 Mar 20281st sale agreement 14 Mar 2025 | 36% |
| RESIDENSI BAYUKPKT 30670-2 | PetalingSelangor | 841 | SmoothOn schedule | 29 May 2029Extended 12 months from 29 May 20281st sale agreement 29 May 2025 | 20% |
Show all 18 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| IRINGAN BAYU - ALERIAKPKT 9902-20 | SerembanNegeri Sembilan | 212 | SmoothOn schedule | 30 Nov 20261st sale agreement 30 Nov 2024 | 98% |
| TAMAN LANG AMANKPKT 30899-1 | Kuala MudaKedah | 197 | DelayLate | 23 Feb 20271st sale agreement 23 Feb 2025 | 80% |
| RESIDENSI NURIAKPKT 30564-1 | GombakSelangor | 275 | SmoothOn schedule | 18 Mar 20271st sale agreement 18 Mar 2024 | 98% |
| SIERRA AT OSK YARRA PARKKPKT 7103-54 | Kuala MudaKedah | 193 | SmoothOn schedule | 13 Sep 20271st sale agreement 13 Sep 2025 | 27–67% |
| AYRA AT OSK YARRA PARKKPKT 7103-55 | Kedah | 239 | SmoothOn schedule | 4 Oct 20271st sale agreement 4 Oct 2025 | 50–61% |
| RESIDENSI HANAKPKT 30564-2Hana Hills · on PropertySifu | GombakSelangor | 297 | SmoothOn schedule | 3 Jan 2028Extended 6 months from 3 Jul 20271st sale agreement 3 Jul 2024 | 69% |
| ALIAKPKT 30670-1Alia Mori Park · on PropertySifu | PetalingSelangor | 812 | SmoothOn schedule | 1 Jun 2028Extended 12 months from 1 Jun 20271st sale agreement 1 Jun 2024 | 76% |
| NARA AT SHOREA PARKKPKT 10139-5Nara Residence · on PropertySifu | SepangSelangor | 709 | SmoothOn schedule | 8 Jun 2028Extended 12 months from 8 Jun 20271st sale agreement 8 Jun 2024 | 98% |
| IRINGAN BAYUKPKT 9902-21 | Negeri Sembilan | 79 | SmoothOn schedule | 24 Jun 20281st sale agreement 24 Jun 2026 | 0% |
| TAMAN LANG AMANKPKT 30899-2 | Kedah | 233 | SmoothOn schedule | 29 Jun 20281st sale agreement 29 Jun 2026 | 5–10% |
| HARBOUR VIEW RESIDENCEKPKT 8555-11 | Seberang Perai UtaraPulau Pinang | 373 | SmoothOn schedule | 14 Mar 2029Extended 12 months from 14 Mar 20281st sale agreement 14 Mar 2025 | 36% |
| RESIDENSI BAYUKPKT 30670-2 | PetalingSelangor | 841 | SmoothOn schedule | 29 May 2029Extended 12 months from 29 May 20281st sale agreement 29 May 2025 | 20% |
| RESIDENSI TAMUKPKT 30670-3 | PetalingSelangor | 946 | SmoothOn schedule | 19 Jul 2030Extended 12 months from 19 Jul 20291st sale agreement 19 Jul 2026 | 0% |
| OSK OMBAKKPKT 11643-4 | KuantanPahang | 616 | SmoothOn schedule | 23 Sep 2030Extended 12 months from 23 Sep 20291st sale agreement 23 Sep 2026 | 10% |
| OSK OMBAKKPKT 11643-3 | KuantanPahang | 658 | SmoothOn schedule | 8 Nov 2030Extended 18 months from 8 May 20291st sale agreement 8 May 2026 | 12–20% |
| OSK ARECAKPKT 31179-1 | SerembanNegeri Sembilan | 944 | SmoothOn schedule | 24 Dec 2030Extended 24 months from 24 Dec 20281st sale agreement 24 Dec 2025 | 22% |
| RESIDENSI BESTARIKPKT 30899-3 | Kedah | 14 | SmoothOn schedule | — | 80% |
| PANGSAPURI SURIAKPKT 8555-9 | Seberang Perai UtaraPulau Pinang | 439 | SmoothOn schedule | — | 20% |
Permit cancelled or other KPKT status (3)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RUMAH KASIH RAKYATKPKT 7103-31 | Kuala MudaKedah | 160 | Permit cancelledPermit cancelled | — | 5% |
| HARBOUR PLACEKPKT 8555-3 | Seberang Perai UtaraPulau Pinang | 439 | Permit cancelledPermit cancelled | — | 0% |
| K3 HARTAMASKPKT 10662-1 | Kuala LumpurWP Kuala Lumpur | 267 | Permit cancelledPermit cancelled | — | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
OSK Property at a glance
| Listed | Bursa Malaysia Main Market · OSK Holdings Berhad, OSK (5053) · listed 1991[1] |
|---|---|
| Started | 1963, as a small stockbroking company; in property development since 1996[1] |
| Head office | Plaza OSK, Jalan Ampang, Kuala Lumpur[2][3] |
| Leadership | Tan Sri Ong Leong Huat @ Wong Joo Hwa — Executive Chairman[1] Ong Ju Yan — Group Managing Director[1] Ong Ghee Bin — Chief Executive Officer, Property Development, Malaysia[1] |
| Companies in the KPKT register | OSK PROPERTIES SDN. BHD. (99.96%) KPKT 7103[2] ASPECT SYNERGY SDN. BHD. (99.96%) KPKT 9902[2] PJD EASTERN LAND SDN. BHD. (97.48%) KPKT 8555[2] ASPECT POTENTIAL SDN. BHD. (99.96%) KPKT 10139[2] JELANG VISTA SDN. BHD. (99.96%) KPKT 11519[2] MORI PARK SDN. BHD. (99.96%) KPKT 30670[2] OSK AMANJAYA SDN. BHD. (99.96%) KPKT 30899[2] WARISAN RAJAWALI SDN. BHD. (99.96%) KPKT 30564[2] ASTANA HARMONI SDN. BHD. (99.96%) KPKT 31179[2] RIBUAN EKUITI SDN. BHD. (99.96%) KPKT 13952[2] COUNTRY WHEELS SDN. BHD. (50.98%) KPKT 10524[2] OSK PROPERTIES (SEREMBAN) SDN. BHD. (99.96%) KPKT 9173[2] PERSPEKTIF VISTA SDN. BHD. (99.96%) KPKT 11604[2] RIMULIA SDN. BHD. (54.98%) KPKT 10797[2] SEMPONIA SDN. BHD. (50.98%) KPKT 10561[2] WAWASAN RAJAWALI SDN. BHD. (99.96%) KPKT 12229[2] PJD CENTRAL SDN. BHD. (97.48%) KPKT 19225[2] PJD LANDMARKS SDN. BHD. (97.48%) KPKT 12063[2] PJD REALTY SDN. BHD. (97.48%) KPKT 11871[2] PJD REGENCY SDN. BHD. (97.48%) KPKT 10662[2] PJD SEJAHTERA SDN. BHD. (97.48%) KPKT 11643[2] |
| Website | oskproperty.com.my |
| Property since | 1996 (the OSK group started in 1963 as a stockbroker)[1] |
| Property company | OSK Property Holdings Berhad, 99.96% owned by OSK Holdings Berhad (end-2025)[2] |
| Land bank (company figure) | 2,454 acres with an estimated effective GDV of RM19.1 billion, in Malaysia and Australia (2025 annual report)[1] |
| Group structure | A 2015 merger made PJ Development Holdings Berhad and OSK Property Holdings Berhad subsidiaries of OSK[1] |
OSK Property projects on sale on PropertySifu
Alia Mori Park
- EMIRA — 0.7 km, 2018
- PJD LANDMARKS SDN BHD — 5.7 km, 2016
Who is OSK Property? The company behind the projects
OSK began in 1963 as a small stockbroking company and was listed on the Main Board in 1991 [1]. It diversified into property development in 1996 [1]. In 2012 it sold its investment bank arm to RHB in a share swap, and in 2015 a merger made PJ Development Holdings Berhad and OSK Property Holdings Berhad subsidiaries of the group [1]. OSK Holdings Berhad trades on Bursa Malaysia's Main Market as OSK (stock code 5053); besides property, the group runs construction, industrial, hospitality and financing businesses [1].
The property business is run through OSK Property Holdings Berhad, which OSK Holdings owned 99.96% of at the end of 2025 [2]; its office is at Plaza OSK on Jalan Ampang, Kuala Lumpur [2][3]. The company says its land bank is 2,454 acres with an estimated effective gross development value of RM19.1 billion, in Malaysia and Australia [1]. That is a group-wide figure; the KPKT register covers only projects licensed as housing in Malaysia, which for OSK means the 121 projects above.
The OSK projects on PropertySifu are developed by subsidiaries listed in the 2025 annual report [2]: Anya Residence and Nara Residence at Shorea Park in Puchong by Aspect Potential Sdn Bhd (KPKT developer code 10139); Alia at Mori Park in Shah Alam by Mori Park Sdn Bhd (30670); and, in Taman Melawati, LEA by the Hills by Jelang Vista Sdn Bhd (11519) and Hana Hills by Warisan Rajawali Sdn Bhd (30564). The same report lists OSK sales galleries for Shorea Park, Mori Park and the two Taman Melawati projects [1].
As at 19 February 2026, the Executive Chairman was Tan Sri Ong Leong Huat @ Wong Joo Hwa, the Group Managing Director Ong Ju Yan, and the Chief Executive Officer of property development in Malaysia Ong Ghee Bin [1].
Frequently asked questions
Is OSK Property a listed company?
How many projects has OSK completed?
In the KPKT register (as at 27 October 2026), 100 of the 121 housing projects under 21 OSK companies are completed. For 73 of them the register has both a handover deadline and a completion date: 28 were handed over on or before the deadline (the extended deadline where KPKT approved an extension), 23 were handed over or certified complete after that deadline, and 22 received the completion certificate before the deadline with no handover date recorded.
Does OSK have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of OSK's 121 projects as Sick (Sakit) or Abandoned (Terbengkalai). One is classed Late (Lewat): Taman Lang Aman in Bandar Amanjaya, Kedah (KPKT 30899-1, 197 units), with a first sale agreement on 23 February 2025, a handover deadline of 23 February 2027 and reported construction progress of 80%. Three other projects are recorded with the permit cancelled.
Which companies develop Hana Hills and LEA by the Hills?
Hana Hills is developed by Warisan Rajawali Sdn Bhd (KPKT developer code 30564) and LEA by the Hills by Jelang Vista Sdn Bhd (11519). OSK's 2025 annual report lists both as OSK Property Holdings subsidiaries with a 99.96% effective OSK interest [2], and both projects share OSK's sales gallery in Taman Melawati [1].
Were LEA by the Hills and Anya Residence handed over on time?
According to KPKT: LEA by the Hills (11519-3, 344 units) had its first sale agreement on 30 July 2022 and a deadline of 30 July 2025, extended with approval by 12 months to 30 July 2026; it received the CCC on 18 March 2026 and was handed over on 20 April 2026, 264 days after the original deadline and 101 days before the extended one. Anya (10139-4, 750 units) had its first sale agreement on 17 September 2022 and a deadline of 17 September 2025, extended by 12 months to 17 September 2026; it received the CCC on 10 September 2025 and was handed over on 30 September 2025, 13 days after the original deadline and 352 days before the extended one.
Have the handover deadlines of Nara, Alia and Hana Hills been extended?
Yes, according to KPKT (as at 27 October 2026). Nara at Shorea Park (10139-5, 709 units): deadline 8 June 2027, extended with approval by 12 months to 8 June 2028, reported progress 97.5%. Alia (30670-1, 812 units): deadline 1 June 2027, extended by 12 months to 1 June 2028, progress 75.69%. Hana Hills, registered as RESIDENSI HANA (30564-2, 297 units): deadline 3 July 2027, extended by 6 months to 3 January 2028, progress 68.64%. All three are recorded as on schedule (Lancar).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] OSK Holdings Berhad Integrated Annual Report 2025 (milestones, corporate information, business highlights) · OSK Holdings Berhad · 25 Mar 2026 · accessed 28 Oct 2026
https://www.oskgroup.com/ar2025/documents/OSKH_IAR25.pdf - [2] OSK Holdings Berhad Integrated Annual Report 2025 — Financial Statements (Note 1.1 and Note 3.3(f) List of subsidiaries) · OSK Holdings Berhad · 25 Mar 2026 · accessed 28 Oct 2026
https://www.oskgroup.com/ar2025/documents/Financial_Statements.pdf - [3] OSK Property — official website · OSK Property Holdings Berhad · accessed 28 Oct 2026
https://www.oskproperty.com.my/
Last updated 28 Oct 2026