OIB Group (Oriental Interest Berhad)
Oriental Interest Berhad (OIB Group), the Bursa Malaysia-listed developer behind the Myra brand, has 109 housing projects in the KPKT register: 80 completed, 24 under construction and 5 not yet started, under 11 companies in Selangor, Kedah, Melaka and Negeri Sembilan, none classed Sick or Abandoned. It was listed in 1994.
- 109 projects in the KPKT register
- 80 completed
- 24 under construction
- 5 not yet started
- None Sick or Abandoned
Has OIB Group handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 109 housing projects under 11 OIB Group companies in 4 states: 80 completed, 24 under construction, 5 not yet started. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 80 completed projects, 62 have both a handover deadline and a completion date in the register: 17 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 23 handed over or certified complete after that deadline (4 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 22 received the completion certificate before the deadline (handover date not recorded).
24 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 80
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| SP SAUJANA PERMAIKPKT 2998-47 | Kuala MudaKedah | 125 | 9 Dec 20261st sale agreement 9 Dec 2024 | CCC 3 Aug 2026 | CCC before deadline; handover not recorded |
| TAMAN KULIM UTAMAKPKT 2998-46 | KulimKedah | 374 | 14 Jun 20261st sale agreement 14 Jun 2024 | CCC 18 Jun 2026 Handover 22 Jun 2026 / 25 Jun 2026 | 8–11 days after |
| SERAI RESIDENSIKPKT 8502-6 | KulimKedah | 159 | 28 May 20261st sale agreement 28 May 2024 | CCC 5 Mar 2026 Handover 27 Mar 2026 | 62 days before |
| PANGSAPURI PERKHIDMATAN ARA NILAI IMPIANKPKT 7935-8 | SerembanNegeri Sembilan | 224 | 23 Oct 20261st sale agreement 23 Oct 2023 | CCC 24 Feb 2026 Handover 26 Mar 2026 | 211 days before |
| RESIDENSI ALEAKPKT 5534-30 | Kuala SelangorSelangor | 364 | 13 Feb 20261st sale agreement 13 Feb 2023 | CCC 17 Mar 2026 Handover 18 Mar 2026 | 33 days after |
| MYRA COVEKPKT 20164-1 | SepangSelangor | 279 | 15 Apr 2026Extended 12 months from 15 Apr 20251st sale agreement 15 Apr 2022 | CCC 3 Dec 2025 Handover 5 Jan 2026 | 100 days before |
| SERAI RESIDENSIKPKT 8502-5 | KulimKedah | 117 | 25 Nov 20251st sale agreement 25 Nov 2023 | CCC 17 Nov 2025 Handover 24 Nov 2025 | 1 day before |
| MYRA GARDENSKPKT 20014-3 | GombakSelangor | 91 | 31 Oct 20251st sale agreement 31 Oct 2022 | CCC 28 Oct 2025 Handover 29 Oct 2025 | 2 days before |
| TAMAN PERMAIPURAKPKT 13769-6 | Kuala MudaKedah | 121 | 23 Jan 20261st sale agreement 23 Jan 2024 | CCC 23 Oct 2025 Handover 28 Oct 2025 | 87 days before |
| SERAI RESIDENSIKPKT 8502-4 | KulimKedah | 278 | 15 May 20251st sale agreement 15 May 2023 | CCC 8 Sep 2025 Handover 15 Aug 2025 / 17 Sep 2025 | 92–125 days after |
| SP SAUJANA PERMAIKPKT 2998-44 | Kuala MudaKedah | 127 | 22 Aug 20251st sale agreement 22 Aug 2023 | CCC 31 Jul 2025 | CCC before deadline; handover not recorded |
| PERMAIPURA VILLAKPKT 13769-5 | Kuala MudaKedah | 91 | 16 Jan 20251st sale agreement 16 Jan 2023 | CCC 10 Mar 2025 Handover 13 Mar 2025 | 56 days after |
Handed over or certified complete after the deadline — 12 most recent of 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN KULIM UTAMAKPKT 2998-46 | KulimKedah | 374 | 14 Jun 20261st sale agreement 14 Jun 2024 | CCC 18 Jun 2026 Handover 22 Jun 2026 / 25 Jun 2026 | 8–11 days after |
| RESIDENSI ALEAKPKT 5534-30 | Kuala SelangorSelangor | 364 | 13 Feb 20261st sale agreement 13 Feb 2023 | CCC 17 Mar 2026 Handover 18 Mar 2026 | 33 days after |
| SERAI RESIDENSIKPKT 8502-4 | KulimKedah | 278 | 15 May 20251st sale agreement 15 May 2023 | CCC 8 Sep 2025 Handover 15 Aug 2025 / 17 Sep 2025 | 92–125 days after |
| PERMAIPURA VILLAKPKT 13769-5 | Kuala MudaKedah | 91 | 16 Jan 20251st sale agreement 16 Jan 2023 | CCC 10 Mar 2025 Handover 13 Mar 2025 | 56 days after |
| TAMAN DESA KAYANGANKPKT 7935-6 | KulimKedah | 585 | 8 Oct 20231st sale agreement 8 Oct 2021 | CCC 14 Aug 2024 Handover 12 Nov 2023 / 2 Apr 2024 / 30 Aug 2024 | 35–327 days after |
| MYRA GARDENSKPKT 20014-1 | GombakSelangor | 96 | 31 May 2024Extended 5 months from 31 Dec 20231st sale agreement 31 Dec 2020 | CCC 27 Aug 2024 Handover 27 Aug 2024 | 88 days after |
| MYRA GARDENSKPKT 20014-2 | GombakSelangor | 128 | 19 Jul 20241st sale agreement 19 Jul 2021 | CCC 27 Aug 2024 Handover 27 Aug 2024 | 39 days after |
| TAMAN BELIA ANTARABANGSA 2E(III)KPKT 5534-24 | Melaka TengahMelaka | 32 | 31 May 20231st sale agreement 31 May 2021 | CCC 23 May 2024 Handover 23 May 2024 | 358 days after |
| TAMAN SERAI WANGIKPKT 8502-3 | KulimKedah | 1,723 | 4 Jun 2014Extended 5 months from 4 Jan 20141st sale agreement 4 Jan 2012 | CCC 5 May 2024 | 3,623 days after |
| TAMAN PERMAIPURAKPKT 13769-3 | Kuala MudaKedah | 307 | 13 May 2022Extended 6 months from 13 Nov 20211st sale agreement 13 Nov 2019 | CCC 30 Apr 2024 | 718 days after † |
| TAMAN CENGAL JAYAKPKT 2998-41 | Kuala MudaKedah | 26 | 12 Nov 20231st sale agreement 12 Nov 2021 | CCC 17 Jan 2024 | 66 days after |
| MYRA SAUJANAKPKT 19355-3 | SepangSelangor | 66 | 19 Jul 20231st sale agreement 19 Jul 2021 | CCC 11 Aug 2023 Handover 11 Aug 2023 | 23 days after |
Show all 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN KULIM UTAMAKPKT 2998-46 | KulimKedah | 374 | 14 Jun 20261st sale agreement 14 Jun 2024 | CCC 18 Jun 2026 Handover 22 Jun 2026 / 25 Jun 2026 | 8–11 days after |
| RESIDENSI ALEAKPKT 5534-30 | Kuala SelangorSelangor | 364 | 13 Feb 20261st sale agreement 13 Feb 2023 | CCC 17 Mar 2026 Handover 18 Mar 2026 | 33 days after |
| SERAI RESIDENSIKPKT 8502-4 | KulimKedah | 278 | 15 May 20251st sale agreement 15 May 2023 | CCC 8 Sep 2025 Handover 15 Aug 2025 / 17 Sep 2025 | 92–125 days after |
| PERMAIPURA VILLAKPKT 13769-5 | Kuala MudaKedah | 91 | 16 Jan 20251st sale agreement 16 Jan 2023 | CCC 10 Mar 2025 Handover 13 Mar 2025 | 56 days after |
| TAMAN DESA KAYANGANKPKT 7935-6 | KulimKedah | 585 | 8 Oct 20231st sale agreement 8 Oct 2021 | CCC 14 Aug 2024 Handover 12 Nov 2023 / 2 Apr 2024 / 30 Aug 2024 | 35–327 days after |
| MYRA GARDENSKPKT 20014-1 | GombakSelangor | 96 | 31 May 2024Extended 5 months from 31 Dec 20231st sale agreement 31 Dec 2020 | CCC 27 Aug 2024 Handover 27 Aug 2024 | 88 days after |
| MYRA GARDENSKPKT 20014-2 | GombakSelangor | 128 | 19 Jul 20241st sale agreement 19 Jul 2021 | CCC 27 Aug 2024 Handover 27 Aug 2024 | 39 days after |
| TAMAN BELIA ANTARABANGSA 2E(III)KPKT 5534-24 | Melaka TengahMelaka | 32 | 31 May 20231st sale agreement 31 May 2021 | CCC 23 May 2024 Handover 23 May 2024 | 358 days after |
| TAMAN SERAI WANGIKPKT 8502-3 | KulimKedah | 1,723 | 4 Jun 2014Extended 5 months from 4 Jan 20141st sale agreement 4 Jan 2012 | CCC 5 May 2024 | 3,623 days after |
| TAMAN PERMAIPURAKPKT 13769-3 | Kuala MudaKedah | 307 | 13 May 2022Extended 6 months from 13 Nov 20211st sale agreement 13 Nov 2019 | CCC 30 Apr 2024 | 718 days after † |
| TAMAN CENGAL JAYAKPKT 2998-41 | Kuala MudaKedah | 26 | 12 Nov 20231st sale agreement 12 Nov 2021 | CCC 17 Jan 2024 | 66 days after |
| MYRA SAUJANAKPKT 19355-3 | SepangSelangor | 66 | 19 Jul 20231st sale agreement 19 Jul 2021 | CCC 11 Aug 2023 Handover 11 Aug 2023 | 23 days after |
| TAMAN SERI BESTARI 2KPKT 5649-6 | SepangSelangor | 12 | 11 Jan 2023Extended 7 months from 11 Jun 20221st sale agreement 11 Jun 2020 | CCC 31 Mar 2023 Handover 31 Mar 2023 | 79 days after † |
| TAMAN PERMAIPURAKPKT 13769-2 | Kuala MudaKedah | 600 | 1 Dec 20181st sale agreement 1 Dec 2016 | CCC 2 Feb 2023 | 1,524 days after |
| SMART BUDGET ECONOMY SDN. BHD.KPKT 7935-5 | Kubang PasuKedah | 152 | 5 May 2022Extended 6 months from 5 Nov 20211st sale agreement 5 Nov 2019 | CCC 29 Sep 2022 Handover 3 Oct 2022 | 151 days after † |
| MYRA SAUJANAKPKT 19355-1 | SepangSelangor | 63 | 13 Apr 20201st sale agreement 13 Apr 2018 | CCC 27 Aug 2020 | 136 days after † |
| MYRA MERANTIKPKT 5649-3 | SepangSelangor | 31 | 4 Jan 20201st sale agreement 4 Jan 2018 | CCC 24 Jan 2020 | 20 days after |
| TAMAN BELIA ANTARABANGSAKPKT 5534-14 | Melaka TengahMelaka | 106 | 1 Jun 20141st sale agreement 1 Jun 2012 | CCC 30 Jun 2018 | 1,490 days after |
| TAMAN DAHLIAKPKT 4625-4 | SepangSelangor | 636 | 8 May 20151st sale agreement 8 May 2012 | CFO 6 Jun 2016 | 395 days after |
| TAMAN BELIMBINGKPKT 7935-3 | Kubang PasuKedah | 310 | 28 Sep 20131st sale agreement 28 Sep 2011 | CCC 10 Mar 2016 | 894 days after |
| PUNCAK PINGGIRAN PUTRAKPKT 5649-2 | SepangSelangor | 46 | 17 Aug 20131st sale agreement 17 Aug 2011 | CFO 19 Feb 2016 | 916 days after |
| TAMAN BELIA ANTARABANGSAKPKT 5534-15 | Melaka TengahMelaka | 43 | 1 Oct 20141st sale agreement 1 Oct 2012 | CCC 7 Jan 2015 | 98 days after |
| TAMAN KEMUNTINGKPKT 2998-31 | KulimKedah | 147 | 15 Oct 20141st sale agreement 15 Oct 2012 | CCC 5 Dec 2014 | 51 days after |
Show all 80 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| SP SAUJANA PERMAIKPKT 2998-47 | Kuala MudaKedah | 125 | 9 Dec 20261st sale agreement 9 Dec 2024 | CCC 3 Aug 2026 | CCC before deadline; handover not recorded |
| TAMAN KULIM UTAMAKPKT 2998-46 | KulimKedah | 374 | 14 Jun 20261st sale agreement 14 Jun 2024 | CCC 18 Jun 2026 Handover 22 Jun 2026 / 25 Jun 2026 | 8–11 days after |
| SERAI RESIDENSIKPKT 8502-6 | KulimKedah | 159 | 28 May 20261st sale agreement 28 May 2024 | CCC 5 Mar 2026 Handover 27 Mar 2026 | 62 days before |
| PANGSAPURI PERKHIDMATAN ARA NILAI IMPIANKPKT 7935-8 | SerembanNegeri Sembilan | 224 | 23 Oct 20261st sale agreement 23 Oct 2023 | CCC 24 Feb 2026 Handover 26 Mar 2026 | 211 days before |
| RESIDENSI ALEAKPKT 5534-30 | Kuala SelangorSelangor | 364 | 13 Feb 20261st sale agreement 13 Feb 2023 | CCC 17 Mar 2026 Handover 18 Mar 2026 | 33 days after |
| MYRA COVEKPKT 20164-1 | SepangSelangor | 279 | 15 Apr 2026Extended 12 months from 15 Apr 20251st sale agreement 15 Apr 2022 | CCC 3 Dec 2025 Handover 5 Jan 2026 | 100 days before |
| SERAI RESIDENSIKPKT 8502-5 | KulimKedah | 117 | 25 Nov 20251st sale agreement 25 Nov 2023 | CCC 17 Nov 2025 Handover 24 Nov 2025 | 1 day before |
| MYRA GARDENSKPKT 20014-3 | GombakSelangor | 91 | 31 Oct 20251st sale agreement 31 Oct 2022 | CCC 28 Oct 2025 Handover 29 Oct 2025 | 2 days before |
| TAMAN PERMAIPURAKPKT 13769-6 | Kuala MudaKedah | 121 | 23 Jan 20261st sale agreement 23 Jan 2024 | CCC 23 Oct 2025 Handover 28 Oct 2025 | 87 days before |
| SERAI RESIDENSIKPKT 8502-4 | KulimKedah | 278 | 15 May 20251st sale agreement 15 May 2023 | CCC 8 Sep 2025 Handover 15 Aug 2025 / 17 Sep 2025 | 92–125 days after |
| SP SAUJANA PERMAIKPKT 2998-44 | Kuala MudaKedah | 127 | 22 Aug 20251st sale agreement 22 Aug 2023 | CCC 31 Jul 2025 | CCC before deadline; handover not recorded |
| PERMAIPURA VILLAKPKT 13769-5 | Kuala MudaKedah | 91 | 16 Jan 20251st sale agreement 16 Jan 2023 | CCC 10 Mar 2025 Handover 13 Mar 2025 | 56 days after |
| MYRA IMPIANKPKT 7935-7 | SerembanNegeri Sembilan | 322 | 22 Dec 20241st sale agreement 22 Dec 2021 | CCC 20 Dec 2024 Handover 20 Dec 2024 | 2 days before |
| TAMAN DESA KAYANGANKPKT 7935-6 | KulimKedah | 585 | 8 Oct 20231st sale agreement 8 Oct 2021 | CCC 14 Aug 2024 Handover 12 Nov 2023 / 2 Apr 2024 / 30 Aug 2024 | 35–327 days after |
| MYRA GARDENSKPKT 20014-1 | GombakSelangor | 96 | 31 May 2024Extended 5 months from 31 Dec 20231st sale agreement 31 Dec 2020 | CCC 27 Aug 2024 Handover 27 Aug 2024 | 88 days after |
| MYRA GARDENSKPKT 20014-2 | GombakSelangor | 128 | 19 Jul 20241st sale agreement 19 Jul 2021 | CCC 27 Aug 2024 Handover 27 Aug 2024 | 39 days after |
| SP SAUJANAKPKT 2998-45 | Kuala MudaKedah | 64 | 9 May 20251st sale agreement 9 May 2023 | CCC 31 Jul 2024 Handover 1 Aug 2024 | 281 days before |
| TAMAN CENDERAWASIHKPKT 2998-42 | BalingKedah | 84 | 25 Mar 20261st sale agreement 25 Mar 2024 | CCC 20 Jun 2024 Handover 3 Jul 2024 | 630 days before |
| PANGSAPURI IRINAKPKT 5534-27 | Kuala SelangorSelangor | 394 | 31 May 20241st sale agreement 31 May 2021 | CCC 29 May 2024 Handover 29 May 2024 | 2 days before |
| TAMAN BELIA ANTARABANGSA 2E(III)KPKT 5534-24 | Melaka TengahMelaka | 32 | 31 May 20231st sale agreement 31 May 2021 | CCC 23 May 2024 Handover 23 May 2024 | 358 days after |
| SP SAUJANA PERMAIKPKT 2998-43 | Kuala MudaKedah | 124 | 11 May 20241st sale agreement 11 May 2022 | CCC 5 May 2024 Handover 7 May 2024 | 4 days before |
| TAMAN SERAI WANGIKPKT 8502-3 | KulimKedah | 1,723 | 4 Jun 2014Extended 5 months from 4 Jan 20141st sale agreement 4 Jan 2012 | CCC 5 May 2024 | 3,623 days after |
| TAMAN PERMAIPURAKPKT 13769-4 | Kuala MudaKedah | 127 | 17 Jun 20241st sale agreement 17 Jun 2022 | CCC 30 Apr 2024 Handover 2 May 2024 | 46 days before |
| TAMAN PERMAIPURAKPKT 13769-3 | Kuala MudaKedah | 307 | 13 May 2022Extended 6 months from 13 Nov 20211st sale agreement 13 Nov 2019 | CCC 30 Apr 2024 | 718 days after † |
| TAMAN CENGAL JAYAKPKT 2998-41 | Kuala MudaKedah | 26 | 12 Nov 20231st sale agreement 12 Nov 2021 | CCC 17 Jan 2024 | 66 days after |
| SP SAUJANAKPKT 2998-39 | Kuala MudaKedah | 180 | 25 Oct 2023Extended 5 months from 25 May 20231st sale agreement 25 May 2021 | CCC 23 Oct 2023 Handover 24 Oct 2023 / 25 Oct 2023 | On the deadline |
| MYRA ALAMKPKT 5534-28 | Kuala SelangorSelangor | 65 | 23 Jan 2024Extended 7 months from 23 Jun 20231st sale agreement 23 Jun 2021 | CCC 18 Sep 2023 Handover 18 Sep 2023 | 127 days before |
| MYRA SAUJANAKPKT 19355-3 | SepangSelangor | 66 | 19 Jul 20231st sale agreement 19 Jul 2021 | CCC 11 Aug 2023 Handover 11 Aug 2023 | 23 days after |
| SP SAUJANA PERMAIKPKT 2998-40 | Kuala MudaKedah | 111 | 15 Sep 2023Extended 5 months from 15 Apr 20231st sale agreement 15 Apr 2021 | CCC 16 Apr 2023 | CCC before deadline; handover not recorded |
| TAMAN SERI BESTARI 2KPKT 5649-6 | SepangSelangor | 12 | 11 Jan 2023Extended 7 months from 11 Jun 20221st sale agreement 11 Jun 2020 | CCC 31 Mar 2023 Handover 31 Mar 2023 | 79 days after † |
| MYRA VISTAKPKT 5534-26 | SepangSelangor | 89 | 2 Apr 2023Extended 5 months from 2 Nov 20221st sale agreement 2 Nov 2020 | CCC 30 Mar 2023 Handover 30 Mar 2023 | 3 days before |
| TAMAN PERMAIPURAKPKT 13769-2 | Kuala MudaKedah | 600 | 1 Dec 20181st sale agreement 1 Dec 2016 | CCC 2 Feb 2023 | 1,524 days after |
| TAMAN SERI BESTARI 2KPKT 5649-5 | SepangSelangor | 38 | 24 Jan 2023Extended 13 months from 24 Dec 20211st sale agreement 24 Dec 2019 | CCC 20 Dec 2022 Handover 20 Dec 2022 | 35 days before |
| MYRA ALAM 2AKPKT 5534-25 | Kuala SelangorSelangor | 52 | 30 Jan 2023Extended 7 months from 30 Jun 20221st sale agreement 30 Jun 2020 | CCC 30 Nov 2022 | CCC before deadline; handover not recorded |
| SMART BUDGET ECONOMY SDN. BHD.KPKT 7935-5 | Kubang PasuKedah | 152 | 5 May 2022Extended 6 months from 5 Nov 20211st sale agreement 5 Nov 2019 | CCC 29 Sep 2022 Handover 3 Oct 2022 | 151 days after † |
| MYRA PUTRAKPKT 5534-23 | SepangSelangor | 200 | 2 Mar 2023Extended 6 months from 30 Aug 20221st sale agreement 30 Aug 2019 | CCC 30 Aug 2022 Handover 6 Sep 2022 | 177 days before |
| TAMAN CENDERAWASIHKPKT 2998-38 | BalingKedah | 58 | 14 Oct 20221st sale agreement 14 Oct 2020 | CCC 23 Jun 2022 | CCC before deadline; handover not recorded |
| SP SAUJANA PERMAIKPKT 2998-37 | Kuala MudaKedah | 117 | 19 Aug 20221st sale agreement 19 Aug 2020 | CCC 10 Mar 2022 | CCC before deadline; handover not recorded |
| MYRA SAUJANAKPKT 19355-2 | SepangSelangor | 76 | 18 Mar 2022Extended 6 months from 18 Sep 20211st sale agreement 18 Sep 2019 | CCC 10 Feb 2022 | CCC before deadline; handover not recorded |
| TAMAN BEMBANKPKT 2998-36 | BalingKedah | 83 | 3 Nov 2021Extended 6 months from 3 May 20211st sale agreement 3 May 2019 | CCC 14 Sep 2021 | CCC before deadline; handover not recorded |
| MYRA ALAMKPKT 5534-21 | Kuala SelangorSelangor | 56 | 25 Dec 2021Extended 6 months from 25 Jun 20211st sale agreement 25 Jun 2019 | CCC 26 Aug 2021 | CCC before deadline; handover not recorded |
| OIB PROPERTIES (CV) SDN. BHD.KPKT 5534-22 | SepangSelangor | 18 | 2 Jun 20211st sale agreement 2 Jun 2019 | CCC 28 May 2021 | CCC before deadline; handover not recorded |
| MYRA ALAMKPKT 5534-20 | Kuala SelangorSelangor | 50 | 30 Mar 2021Extended 6 months from 30 Sep 20201st sale agreement 30 Sep 2018 | CCC 11 Mar 2021 | CCC before deadline; handover not recorded |
| DAHLIA IMPIANAKPKT 4625-6 | SepangSelangor | 300 | 15 Dec 20201st sale agreement 15 Dec 2017 | CCC 2 Oct 2020 | CCC before deadline; handover not recorded |
| MYRA SAUJANAKPKT 19355-1 | SepangSelangor | 63 | 13 Apr 20201st sale agreement 13 Apr 2018 | CCC 27 Aug 2020 | 136 days after † |
| APARTMENT BESTARIKPKT 5534-19 | SepangSelangor | 65 | 29 Sep 20201st sale agreement 29 Sep 2017 | CCC 30 Jun 2020 | CCC before deadline; handover not recorded |
| TAMAN DELIMAKPKT 2998-35 | KulimKedah | 23 | 13 Feb 20211st sale agreement 13 Feb 2019 | CCC 27 Feb 2020 | CCC before deadline; handover not recorded |
| MYRA MERANTIKPKT 5649-3 | SepangSelangor | 31 | 4 Jan 20201st sale agreement 4 Jan 2018 | CCC 24 Jan 2020 | 20 days after |
| MYRA MERANTIKPKT 5649-4 | SepangSelangor | 53 | 2 May 20201st sale agreement 2 May 2018 | CCC 24 Jan 2020 | CCC before deadline; handover not recorded |
| SP SAUJANAKPKT 2998-34 | Kuala MudaKedah | 101 | 11 Apr 20201st sale agreement 11 Apr 2018 | CCC 13 Oct 2019 | CCC before deadline; handover not recorded |
| SEROJA HILLSKPKT 5534-18 | SepangSelangor | 256 | 18 Jul 20191st sale agreement 18 Jul 2016 | CCC 12 Jul 2019 | CCC before deadline; handover not recorded |
| TAMAN BELIA ANTARABANGSAKPKT 5534-14 | Melaka TengahMelaka | 106 | 1 Jun 20141st sale agreement 1 Jun 2012 | CCC 30 Jun 2018 | 1,490 days after |
| TAMAN SENAKPKT 7935-4 | Kubang PasuKedah | 44 | 5 Apr 20191st sale agreement 5 Apr 2017 | CCC 26 Apr 2018 | CCC before deadline; handover not recorded |
| OIB PROPERTIES (K) SDN. BHD.KPKT 2998-33 | KulimKedah | 9 | 6 Sep 20181st sale agreement 6 Sep 2016 | CCC 26 Oct 2017 | CCC before deadline; handover not recorded |
| MAXILUX PROPERTIES SDN BHDKPKT 4625-5 | SepangSelangor | 280 | 21 Nov 20171st sale agreement 21 Nov 2014 | CCC 30 Jun 2017 | CCC before deadline; handover not recorded |
| TAMAN SALAK MULIAKPKT 5534-17 | SepangSelangor | 29 | 8 Aug 20171st sale agreement 8 Aug 2015 | CCC 30 Jun 2017 | CCC before deadline; handover not recorded |
| TAMAN PERUDAKPKT 13769-1 | Kuala MudaKedah | 65 | 20 Apr 20171st sale agreement 20 Apr 2015 | CCC 19 Apr 2017 | CCC before deadline; handover not recorded |
| TAMAN DAHLIAKPKT 4625-4 | SepangSelangor | 636 | 8 May 20151st sale agreement 8 May 2012 | CFO 6 Jun 2016 | 395 days after |
| TAMAN BELIMBINGKPKT 7935-3 | Kubang PasuKedah | 310 | 28 Sep 20131st sale agreement 28 Sep 2011 | CCC 10 Mar 2016 | 894 days after |
| PUNCAK PINGGIRAN PUTRAKPKT 5649-2 | SepangSelangor | 46 | 17 Aug 20131st sale agreement 17 Aug 2011 | CFO 19 Feb 2016 | 916 days after |
| PESAKA SAUJANA (M) SDN BHDKPKT 5534-16 | SepangSelangor | 59 | —1st sale agreement 18 Sep 2013 | CFO 17 Aug 2015 | — |
| TAMAN BELIA ANTARABANGSAKPKT 5534-15 | Melaka TengahMelaka | 43 | 1 Oct 20141st sale agreement 1 Oct 2012 | CCC 7 Jan 2015 | 98 days after |
| TAMAN KEMUNTINGKPKT 2998-31 | KulimKedah | 147 | 15 Oct 20141st sale agreement 15 Oct 2012 | CCC 5 Dec 2014 | 51 days after |
| TAMAN ARKEDKPKT 5534-5 | SepangSelangor | 350 | — | CFO 8 Mar 2014 | — |
| TAMAN KEMUNINGKPKT 2998-30 | KulimKedah | 21 | — | CCC 29 Mar 2013 | — |
| DESA BESTARIKPKT 5534-13 | SepangSelangor | 48 | — | CCC 22 Nov 2012 | — |
| TAMAN CAMARKPKT 2998-29 | KulimKedah | 27 | — | CFO 10 Sep 2012 | — |
| LOT 263 & 1043KPKT 2998-27 | KulimKedah | 58 | — | CFO 23 Aug 2010 | — |
| LOT 45KPKT 2998-28 | KulimKedah | 50 | — | CFO 9 Jun 2010 | — |
| DESA PINGGIRAN PUTRAKPKT 5534-11 | SepangSelangor | 34 | — | CFO 2 Sep 2009 | — |
| TAMAN SEROJAKPKT 5534-10 | SepangSelangor | 12 | — | CFO 25 Jun 2009 | — |
| TAMAN SELASIHKPKT 2998-26 | KulimKedah | 9 | — | CFO 24 Mar 2009 | — |
| DESA PINGGIRAN PUTRAKPKT 5534-9 | SepangSelangor | 26 | — | CFO 15 May 2007 | — |
| TAMAN SELASIHKPKT 2998-20 | KulimKedah | 9 | — | CFO 23 Apr 2006 | — |
| TAMAN SEROJAKPKT 5534-6 | SepangSelangor | 110 | — | CFO 12 Dec 2005 | — |
| TAMAN DAHLIAKPKT 4625-3 | SepangSelangor | 200 | — | CFO 18 Nov 2003 | — |
| DESA PINGGIRAN PUTRAKPKT 5534-4 | SepangSelangor | 1,264 | — | CFO 9 Nov 2002 | — |
| DESA SAUJANAKPKT 5534-3 | Selangor | 251 | — | CFO 2 Dec 1998 | — |
| MYRA PUTRIKPKT 5534-31 | SepangSelangor | 310 | 15 Aug 20261st sale agreement 15 Aug 2023 | — | — |
| TAMAN SERAI WANGIKPKT 8502-2 | KulimKedah | 902 | — | — | — |
Under construction (24) and not yet started (5) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| PERMAIPURA VILLAKPKT 13769-7 | Kuala MudaKedah | 93 | SmoothOn schedule | 7 Mar 20271st sale agreement 7 Mar 2025 | 88% |
| SERAI RESIDENSIKPKT 8502-7 | Kedah | 79 | SmoothOn schedule | 12 Mar 20271st sale agreement 12 Mar 2025 | 80% |
| SERAI RESIDENSIKPKT 8502-8 | Kedah | 97 | SmoothOn schedule | 20 Mar 20271st sale agreement 20 Mar 2025 | 80% |
| MYRA SAUJANAKPKT 19355-5 | SepangSelangor | 20 | SmoothOn schedule | 3 May 20271st sale agreement 3 May 2025 | 80% |
| MYRA SAUJANAKPKT 19355-4 | SepangSelangor | 28 | SmoothOn schedule | 22 Aug 20271st sale agreement 22 Aug 2025 | 98% |
| TAMAN PERMAIPURAKPKT 13769-8 | Kuala MudaKedah | 85 | SmoothOn schedule | 27 Aug 20271st sale agreement 27 Aug 2025 | 98% |
| ALAM IMPIANKPKT 30962-1 | Selangor | 70 | SmoothOn schedule | 30 Sep 20271st sale agreement 30 Sep 2025 | 36% |
| SERAI RESIDENSIKPKT 8502-9 | Kedah | 117 | SmoothOn schedule | 1 Dec 20271st sale agreement 1 Dec 2025 | 47–75% |
| MYRA TENUMANKPKT 30962-2 | Selangor | 46 | SmoothOn schedule | 5 Feb 20281st sale agreement 5 Feb 2026 | 23% |
| SERAI RESIDENSIKPKT 8502-10 | Kedah | 140 | SmoothOn schedule | 17 Mar 20281st sale agreement 17 Mar 2026 | 53–62% |
| TAMAN KULIM UTAMAKPKT 2998-49 | KulimKedah | 158 | SmoothOn schedule | 1 May 20281st sale agreement 1 May 2026 | 9% |
| TAMAN KULIM UTAMAKPKT 2998-48 | KulimKedah | 102 | SmoothOn schedule | 11 May 20281st sale agreement 11 May 2026 | 5–35% |
Show all 29 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| PERMAIPURA VILLAKPKT 13769-7 | Kuala MudaKedah | 93 | SmoothOn schedule | 7 Mar 20271st sale agreement 7 Mar 2025 | 88% |
| SERAI RESIDENSIKPKT 8502-7 | Kedah | 79 | SmoothOn schedule | 12 Mar 20271st sale agreement 12 Mar 2025 | 80% |
| SERAI RESIDENSIKPKT 8502-8 | Kedah | 97 | SmoothOn schedule | 20 Mar 20271st sale agreement 20 Mar 2025 | 80% |
| MYRA SAUJANAKPKT 19355-5 | SepangSelangor | 20 | SmoothOn schedule | 3 May 20271st sale agreement 3 May 2025 | 80% |
| MYRA SAUJANAKPKT 19355-4 | SepangSelangor | 28 | SmoothOn schedule | 22 Aug 20271st sale agreement 22 Aug 2025 | 98% |
| TAMAN PERMAIPURAKPKT 13769-8 | Kuala MudaKedah | 85 | SmoothOn schedule | 27 Aug 20271st sale agreement 27 Aug 2025 | 98% |
| ALAM IMPIANKPKT 30962-1 | Selangor | 70 | SmoothOn schedule | 30 Sep 20271st sale agreement 30 Sep 2025 | 36% |
| SERAI RESIDENSIKPKT 8502-9 | Kedah | 117 | SmoothOn schedule | 1 Dec 20271st sale agreement 1 Dec 2025 | 47–75% |
| MYRA TENUMANKPKT 30962-2 | Selangor | 46 | SmoothOn schedule | 5 Feb 20281st sale agreement 5 Feb 2026 | 23% |
| SERAI RESIDENSIKPKT 8502-10 | Kedah | 140 | SmoothOn schedule | 17 Mar 20281st sale agreement 17 Mar 2026 | 53–62% |
| TAMAN KULIM UTAMAKPKT 2998-49 | KulimKedah | 158 | SmoothOn schedule | 1 May 20281st sale agreement 1 May 2026 | 9% |
| TAMAN KULIM UTAMAKPKT 2998-48 | KulimKedah | 102 | SmoothOn schedule | 11 May 20281st sale agreement 11 May 2026 | 5–35% |
| MYRA DAHLIAKPKT 4625-7 | SepangSelangor | 480 | SmoothOn schedule | 15 May 2028Extended 12 months from 15 May 20271st sale agreement 15 May 2024 | 50% |
| SP SAUJANA PERMAIKPKT 2998-50 | Kedah | 123 | SmoothOn schedule | 7 Jun 20281st sale agreement 7 Jun 2026 | 23% |
| MYRA COVEKPKT 20164-2 | SepangSelangor | 421 | SmoothOn schedule | 28 Nov 2028Extended 12 months from 28 Nov 20271st sale agreement 28 Nov 2024 | 20–35% |
| PANGSAPURI PUTRA IDAMANKPKT 5534-32 | SepangSelangor | 502 | SmoothOn schedule | 14 Feb 2029Extended 12 months from 14 Feb 20281st sale agreement 14 Feb 2025 | 67% |
| MYRA IDAMANKPKT 20014-4 | GombakSelangor | 616 | SmoothOn schedule | 29 Jun 20291st sale agreement 29 Jun 2026 | 12–19% |
| MYRA SENJAKPKT 20164-3Myra Senja · on PropertySifu | PetalingSelangor | 384 | SmoothOn schedule | 31 Aug 2029Extended 12 months from 31 Aug 20281st sale agreement 31 Aug 2025 | 25% |
| MYRA EMBUNKPKT 19355-7 | Selangor | 297 | SmoothOn schedule | 29 Jul 2030Extended 12 months from 29 Jul 20291st sale agreement 29 Jul 2026 | 5% |
| TAMAN DAHLIAKPKT 4625-8 | Selangor | 31 | Not startedNot started | — | 0% |
| DESA PINGGIRAN PUTRA PANGSAPURI 5 & 9 TINGKATKPKT 5534-12 | SepangSelangor | 195 | SmoothOn schedule | — | 84% |
| TAMAN SELASIHKPKT 2998-16 | KulimKedah | 117 | SmoothOn schedule | — | 3–78% |
| MYRA EMBUNKPKT 19355-6 | Selangor | 297 | SmoothOn schedule | —Extended 12 months (date not registered) | 5% |
| PANGSAPURI SAUJANA IDAMANKPKT 19355-8 | SepangSelangor | 286 | Not startedNot started | — | 0% |
| PANGSAPURI SAUJANA IDAMANKPKT 19355-9 | SepangSelangor | 286 | Not startedNot started | — | 0% |
| SERAI RESIDENSIKPKT 8502-11 | KulimKedah | 93 | SmoothOn schedule | — | 0–5% |
| SERAI RESIDENSIKPKT 8502-12 | KulimKedah | 144 | SmoothOn schedule | — | 5% |
| TAMAN BELIMBINGKPKT 7935-10 | Kedah | 14 | Not startedNot started | — | 0% |
| MYRA YARAKPKT 7935-9 | Selangor | 219 | Not startedNot started | —Extended 12 months (date not registered) | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
OIB Group at a glance
| Listed | Bursa Malaysia Main Market · OIB (5827) · listed on the KLSE Main Board on 18 October 1994[2][1] |
|---|---|
| Started | Incorporated in Malaysia on 3 August 1993[1] |
| Head office | Bandar Amanjaya, Sungai Petani, Kedah[3] |
| Leadership | DYTM Raja Puan Muda Kedah Che Puan Muda Zaheeda Binti Mohamad Ariff — Independent Non-Executive Chairman (since 18 March 2024)[2] Khoh Why Way — Executive Director and Chief Executive Officer (since 1 August 2025)[2] |
| Companies in the KPKT register | MYRA LAND SDN. BHD. (70%) KPKT 20164[9][7] OIB PROPERTIES (K) SDN. BHD. KPKT 2998[16] OIB PROPERTIES (CV) SDN. BHD. KPKT 5534[10][18] OIB PROPERTIES (PRV) SDN. BHD. KPKT 19355[11] OIB PROPERTIES (KV) SDN. BHD. KPKT 13769[17] OIB PROPERTIES (SW) SDN. BHD. KPKT 8502[17] OIB PROPERTIES (C) SDN. BHD. KPKT 5649[18] MYRA GARDENS SDN. BHD. KPKT 20014[12] MAXILUX PROPERTIES SDN BHD KPKT 4625[13] SMART BUDGET ECONOMY SDN. BHD. KPKT 7935[14][17] TOTAL MAJORITY SDN. BHD. KPKT 30962[15] |
| Website | oibgroup.com |
| Units handed over (company figure) | More than 31,400 units with vacant possession handed over[4] |
| Brands and regions | OIB in northern Peninsular Malaysia (mainly Kedah); the Myra brand in the Central region (Selangor)[5][6] |
| Group (company figure) | Oriental Interest Berhad and 20 subsidiaries: property development and construction, investment holding, hospitality and oil palm[1] |
| Myra Land Sdn Bhd (developer of Myra Senja) | 70% Oriental Interest; 30% Pesaka Saujana Properties Sdn Bhd[9] |
OIB Group projects on sale on PropertySifu
Who is OIB Group? The company behind the projects
Oriental Interest Berhad was incorporated on 3 August 1993 and listed on the Main Board of the Kuala Lumpur Stock Exchange on 18 October 1994 [1]; it trades on Bursa Malaysia's Main Market as OIB, stock code 5827 [2]. Its head office is in Bandar Amanjaya, Sungai Petani, Kedah [3]. The group says it has 20 subsidiaries in property development and construction, investment holding, hospitality and oil palm [1], and that it has handed over more than 31,400 units [4]. That is a group-wide company figure; the KPKT register counts each licensed phase as a separate housing project.
OIB builds in northern Peninsular Malaysia under its own name and in the Central region under the Myra brand [5], which belongs to OIB Marketing Sdn Bhd, a subsidiary of Oriental Interest Berhad [6]. The group lists Taman Serai Wangi, Taman Permaipura and SP Saujana Permai in Kedah, and Desa Pinggiran Putra, Myra Gardens and Myra Alam in Selangor, among its developments [4].
Myra Senja in Subang Bestari, listed on PropertySifu, and Myra Cove in Cyberjaya are developed by Myra Land Sdn Bhd under developer licence 20164 [7][8]. Oriental Interest owns 70% of Myra Land; the other 30% is held by Pesaka Saujana Properties Sdn Bhd [9]. In December 2025 Myra Land agreed to buy 68.12 acres in Bukit Raja, Selangor, for RM80.77 million [9].
Other Myra projects are registered under different companies: Myra Alam under OIB Properties (CV) Sdn Bhd [10], Myra Saujana under OIB Properties (PRV) Sdn Bhd [11], Myra Gardens under Myra Gardens Sdn Bhd [12], Myra Dahlia under Maxilux Properties Sdn Bhd [13], Myra Park under Smart Budget Economy Sdn Bhd [14] and Myra Tenuman under developer licence 30962 [15], which KPKT registers to Total Majority Sdn Bhd. OIB Properties (K) Sdn Bhd, which develops in Kedah, is wholly owned [16]; for the other companies we found no public source giving OIB's shareholding, so they are listed because the group's own websites name them as developers of its projects. The chairman is DYTM Raja Puan Muda Kedah Che Puan Muda Zaheeda Binti Mohamad Ariff, and Khoh Why Way has been executive director and chief executive officer since 1 August 2025 [2].
Frequently asked questions
Is the developer of Myra listed?
Myra is a brand of the Oriental Interest Berhad group [6], which is listed on Bursa Malaysia's Main Market as OIB, stock code 5827 [2]; it listed on the Main Board of the Kuala Lumpur Stock Exchange on 18 October 1994 [1]. Myra Senja's developer, Myra Land Sdn Bhd, is a private company 70% owned by Oriental Interest [9].
Which company develops Myra Senja, and has its deadline been extended?
Myra Land Sdn Bhd (KPKT developer code 20164) [7]. KPKT registers the project as 20164-3: 384 serviced apartments of up to 21 storeys, with the first sale agreement signed on 31 August 2025. Its handover deadline of 31 August 2028 has been extended with KPKT approval by 12 months, to 31 August 2029. It is recorded as on schedule (Lancar), with reported construction progress of 25%.
Has Myra Land completed a project before?
Yes, one. KPKT records the first phase of Myra Cove in Cyberjaya (20164-1, 279 units) with a first sale agreement on 15 April 2022 and a deadline of 15 April 2025, extended with approval by 12 months to 15 April 2026. The CCC is dated 3 December 2025 and vacant possession 5 January 2026, 100 days before the extended deadline. The second phase (20164-2, 421 units) is under construction, with a deadline of 28 November 2028 after a 12-month extension.
How many housing projects has the group completed?
In the KPKT register, 80 of the 109 housing projects under the 11 companies are completed. Of the 62 completed projects that have both a deadline and a completion date in the register, 17 were handed over on or before the deadline set by the first sale agreement (where KPKT approved an extension, the extended deadline is used), 23 were handed over or certified complete after that deadline — 4 of these were under construction during the 18 March–31 August 2020 movement control period — and 22 received the completion certificate before the deadline, with no handover date recorded. The group says it has handed over more than 31,400 units [4].
Does the group have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 109 projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). The 24 projects under construction are on schedule (Lancar), and 5 have not started (Belum Mula).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Corporate Profile · Oriental Interest Berhad (OIB Group) · accessed 28 Oct 2026
https://oibgroup.com/corporate-profile/ - [2] Corporate Information (stock code and Board of Directors) · Oriental Interest Berhad (OIB Group) · accessed 28 Oct 2026
https://oibgroup.com/corporate-information/ - [3] Keep in touch (head office) · Oriental Interest Berhad (OIB Group) · accessed 28 Oct 2026
https://oibgroup.com/keep-in-touch/ - [4] Property Development and General Construction · Oriental Interest Berhad (OIB Group) · accessed 28 Oct 2026
https://oibgroup.com/property-development-and-general-construction/ - [5] About us · Oriental Interest Berhad (OIB Group) · accessed 28 Oct 2026
https://oibgroup.com/about-us/ - [6] Myra — Corporate · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/corporate - [7] Myra Senja — official project page (developer and licence details) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myrasenja/ - [8] Myra Cove — official project page (developer and licence details) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myracove/ - [9] Oriental Interest to buy 68-acre Bukit Raja land for RM80.8m · The Edge Malaysia · 7 Jan 2026 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/788418 - [10] Myra Alam — Alea Residence, official project page (developer) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myraalam/alearesidence/ - [11] Myra Saujana — official project page (developer) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myrasaujana/ - [12] Myra Gardens — official project page (developer) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myragardens/ - [13] Myra Dahlia — official project page (developer) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myradahlia/ - [14] Myra Park — official project page (developer) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myrapark/ - [15] Myra Tenuman — official project page (developer licence) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes/myratenuman/ - [16] Oriental Interest buys 222 acres of land worth RM129 mil · EdgeProp (The Edge) · 24 May 2017 · accessed 28 Oct 2026
https://www.edgeprop.my/content/1141674/oriental-interest-buys-222-acres-land-worth-rm129-mil - [17] Projects · Oriental Interest Berhad (OIB Group) · accessed 28 Oct 2026
https://oibgroup.com/project/ - [18] Myra Homes (project list and locations) · OIB Marketing Sdn Bhd (Myra) · accessed 28 Oct 2026
https://www.myra.com.my/myra-homes.html
Last updated 28 Oct 2026