Mahajaya (Mahajaya Berhad)
Mahajaya is a Kuala Lumpur property group, active since the 1970s according to the company and not listed today, with 18 housing projects in the KPKT register under five group companies: 17 completed and 1 under construction, none classed Sick or Abandoned. It developed the Bandar Damai Perdana township in Cheras, where The Courtyard @ Cheras was completed in 2026.
- 18 projects in the KPKT register
- 17 completed
- 1 under construction
- None Sick or Abandoned
Has Mahajaya handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 18 housing projects under 5 Mahajaya companies in 3 states: 17 completed, 1 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 17 completed projects, 10 have both a handover deadline and a completion date in the register: 2 handed over on or before the deadline; 4 handed over or certified complete after that deadline; 4 received the completion certificate before the deadline (handover date not recorded).
No project has a KPKT-approved extension of the delivery period.
Completed projects — the 12 most recent of 17
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| THE COURTYARD @ CHERASKPKT 4900-16The Courtyard · on PropertySifu | Hulu LangatSelangor | 62 | 24 Apr 20261st sale agreement 24 Apr 2024 | CCC 12 Feb 2026 Handover 23 Feb 2026 | 60 days before |
| RESIDENSI 118, TAMAN DAMAI UTAMAKPKT 4900-15 | PetalingSelangor | 118 | 26 Aug 20231st sale agreement 26 Aug 2021 | CCC 12 Apr 2023 Handover 5 May 2023 | 113 days before |
| D' INFINITI IIKPKT 5167-8 | Hulu LangatSelangor | 139 | 11 Jul 20201st sale agreement 11 Jul 2017 | CCC 25 Mar 2019 | CCC before deadline; handover not recorded |
| SALAK PARK SDN. BHD.KPKT 13535-1 | Kuala LumpurWP Kuala Lumpur | 33 | 8 Jul 20171st sale agreement 8 Jul 2015 | CCC 13 Jan 2017 | CCC before deadline; handover not recorded |
| MEDAN DAMAI SDN BHDKPKT 4900-14 | Hulu LangatSelangor | 132 | 21 Jul 20161st sale agreement 21 Jul 2014 | CCC 2 Dec 2016 | 134 days after |
| TAMAN ALAM INDAHKPKT 3888-6 | KlangSelangor | 65 | 9 Jun 20161st sale agreement 9 Jun 2014 | CCC 22 Mar 2016 | CCC before deadline; handover not recorded |
| MEDAN DAMAI SDN BHDKPKT 4900-12 | Hulu LangatSelangor | 386 | 2 Jan 20141st sale agreement 2 Jan 2012 | CCC 2 Jan 2015 | 365 days after |
| TAMAN ALAM INDAHKPKT 3888-5 | KlangSelangor | 426 | 7 Feb 20141st sale agreement 7 Feb 2012 | CCC 26 Nov 2014 | 292 days after |
| PT 75591KPKT 4900-13 | PetalingSelangor | 629 | 11 Jun 20151st sale agreement 11 Jun 2012 | CCC 24 Oct 2014 | CCC before deadline; handover not recorded |
| BANDAR DAMAI PERDANAKPKT 4900-8 | Hulu LangatSelangor | 76 | — | CCC 27 Mar 2014 | — |
| BANDAR DAMAI PERDANA 2KPKT 4900-7 | Hulu LangatSelangor | 649 | 22 Aug 20051st sale agreement 22 Aug 2003 | CFO 14 Jan 2013 | 2,702 days after |
| BANDAR DAMAI PERDANAKPKT 4900-11 | Hulu LangatSelangor | 249 | — | CCC 29 Mar 2012 | — |
Handed over or certified complete after the deadline (4)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| MEDAN DAMAI SDN BHDKPKT 4900-14 | Hulu LangatSelangor | 132 | 21 Jul 20161st sale agreement 21 Jul 2014 | CCC 2 Dec 2016 | 134 days after |
| MEDAN DAMAI SDN BHDKPKT 4900-12 | Hulu LangatSelangor | 386 | 2 Jan 20141st sale agreement 2 Jan 2012 | CCC 2 Jan 2015 | 365 days after |
| TAMAN ALAM INDAHKPKT 3888-5 | KlangSelangor | 426 | 7 Feb 20141st sale agreement 7 Feb 2012 | CCC 26 Nov 2014 | 292 days after |
| BANDAR DAMAI PERDANA 2KPKT 4900-7 | Hulu LangatSelangor | 649 | 22 Aug 20051st sale agreement 22 Aug 2003 | CFO 14 Jan 2013 | 2,702 days after |
Show all 17 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| THE COURTYARD @ CHERASKPKT 4900-16The Courtyard · on PropertySifu | Hulu LangatSelangor | 62 | 24 Apr 20261st sale agreement 24 Apr 2024 | CCC 12 Feb 2026 Handover 23 Feb 2026 | 60 days before |
| RESIDENSI 118, TAMAN DAMAI UTAMAKPKT 4900-15 | PetalingSelangor | 118 | 26 Aug 20231st sale agreement 26 Aug 2021 | CCC 12 Apr 2023 Handover 5 May 2023 | 113 days before |
| D' INFINITI IIKPKT 5167-8 | Hulu LangatSelangor | 139 | 11 Jul 20201st sale agreement 11 Jul 2017 | CCC 25 Mar 2019 | CCC before deadline; handover not recorded |
| SALAK PARK SDN. BHD.KPKT 13535-1 | Kuala LumpurWP Kuala Lumpur | 33 | 8 Jul 20171st sale agreement 8 Jul 2015 | CCC 13 Jan 2017 | CCC before deadline; handover not recorded |
| MEDAN DAMAI SDN BHDKPKT 4900-14 | Hulu LangatSelangor | 132 | 21 Jul 20161st sale agreement 21 Jul 2014 | CCC 2 Dec 2016 | 134 days after |
| TAMAN ALAM INDAHKPKT 3888-6 | KlangSelangor | 65 | 9 Jun 20161st sale agreement 9 Jun 2014 | CCC 22 Mar 2016 | CCC before deadline; handover not recorded |
| MEDAN DAMAI SDN BHDKPKT 4900-12 | Hulu LangatSelangor | 386 | 2 Jan 20141st sale agreement 2 Jan 2012 | CCC 2 Jan 2015 | 365 days after |
| TAMAN ALAM INDAHKPKT 3888-5 | KlangSelangor | 426 | 7 Feb 20141st sale agreement 7 Feb 2012 | CCC 26 Nov 2014 | 292 days after |
| PT 75591KPKT 4900-13 | PetalingSelangor | 629 | 11 Jun 20151st sale agreement 11 Jun 2012 | CCC 24 Oct 2014 | CCC before deadline; handover not recorded |
| BANDAR DAMAI PERDANAKPKT 4900-8 | Hulu LangatSelangor | 76 | — | CCC 27 Mar 2014 | — |
| BANDAR DAMAI PERDANA 2KPKT 4900-7 | Hulu LangatSelangor | 649 | 22 Aug 20051st sale agreement 22 Aug 2003 | CFO 14 Jan 2013 | 2,702 days after |
| BANDAR DAMAI PERDANAKPKT 4900-11 | Hulu LangatSelangor | 249 | — | CCC 29 Mar 2012 | — |
| BANDAR DAMAI PERDANAKPKT 4900-10 | Hulu LangatSelangor | 73 | — | CFO 29 Jan 2010 | — |
| TAMAN KUALA JAYAKPKT 5167-7 | Alor GajahMelaka | 22 | — | CFO 28 May 2009 | — |
| TAMAN TANJUNG JAYAKPKT 5167-6 | Melaka TengahMelaka | 50 | — | CFO 11 May 2009 | — |
| TAMAN KOTA LAKSAMANAKPKT 5167-5 | Melaka TengahMelaka | 30 | — | CFO 10 Feb 2009 | — |
| TAMAN DESA PETALINGKPKT 2109-3 | Kuala LumpurWP Kuala Lumpur | 715 | — | CFO 18 Dec 2003 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| ALUNAN DAMAI, DESA VISTAKPKT 4900-17 | Selangor | 96 | SmoothOn schedule | — | 12% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Mahajaya at a glance
| Listed | Not listed today — Mahajaya was listed on the Main Board of the then Kuala Lumpur Stock Exchange in April 2004, according to the company and The Star; no current listing was found[3][4] |
|---|---|
| Started | In the 1970s, according to the company; founded by Dato' Tan Leong Min[1][2] |
| Head office | Wisma Mahajaya, Taman Desa Petaling, Kuala Lumpur[1] |
| Leadership | Ben Tan — Managing Director (since 2018)[3] Dato' Tan Leong Min — Founder[2] |
| Companies in the KPKT register | MEDAN DAMAI SDN. BHD. KPKT 4900[1][5] MAHAJAYA PROPERTY SDN. BHD. KPKT 5167[2] JIWA PROPERTY SDN. BHD. KPKT 3888[2] SALAK PARK SDN. BHD. KPKT 13535[1][2] SALAK PARK DEVELOPMENT SDN. BHD KPKT 2109[2] |
| Website | mahajaya.com |
| Main townships | Bandar Damai Perdana, Cheras (Hulu Langat, Selangor), since 1996; Taman Damai Utama, Puchong[2][1] |
| Stock-exchange history | Quoted on the Kuala Lumpur Stock Exchange Main Board from 27 April 2004 after a reverse takeover of Hotline Furniture Bhd[4][3] |
| Where it has built (company list) | Kuala Lumpur, Selangor, Melaka, Negeri Sembilan and Johor Bahru[2] |
| Project now selling (company) | Alunan Damai, Taman Desa Vista, Salak Tinggi: 96 double-storey terrace homes on Malay reserve land[1] |
Mahajaya projects on sale on PropertySifu
The Courtyard
- BANDAR DAMAI PERDANA 2 — 0.8 km, 2013
- D' INFINITI II — 1.0 km, 2019
- SALAK PARK SDN. BHD. — 5.8 km, 2017
Who is Mahajaya? The company behind the projects
Mahajaya is a property group founded by Dato' Tan Leong Min; the company says it has developed property since the 1970s, in Kuala Lumpur, Selangor, Johor Bahru and Melaka [2][1]. Its website is run under Mahajaya Berhad and also names Medan Damai Sdn Bhd and Salak Park Sdn Bhd [1]. The Star reported in April 2004 that Mahajaya would be quoted on the Main Board on 27 April after a reverse takeover of Hotline Furniture Bhd [4], and the company says it listed that year [3]; no current listing was found. Its office is in Taman Desa Petaling, Kuala Lumpur [1], and its managing director since 2018 is Ben Tan [3].
Its main township is Bandar Damai Perdana in Cheras, in Selangor's Hulu Langat district, where the company lists link houses, superlink homes, semi-detached houses, bungalows and shop offices from 1996 onwards [2]. KPKT registers the township's phases under Medan Damai Sdn Bhd, except D' Infiniti II (2019), which is under Mahajaya Property Sdn Bhd. The Courtyard @ Cheras, the project on PropertySifu, is 62 double-storey superlink homes in Bandar Damai Perdana [5]; KPKT registers it as THE COURTYARD @ CHERAS (4900-16).
The company also lists 118 Residence (2021) in Taman Damai Utama, Puchong; Taman Alam Indah in Section 33, Shah Alam (2014 and 2016); Residensi Gembira 33 in Kuchai Lama (2017); the Amadesa condominium in Desa Petaling (2003); and link houses in Kota Laksamana, Melaka (2009) [2]. In the KPKT register, Taman Alam Indah is under Jiwa Property Sdn Bhd, a 33-unit terrace project in Kuala Lumpur completed in January 2017 is under Salak Park Sdn Bhd, a 715-unit condominium in Taman Desa Petaling completed in December 2003 is under Salak Park Development Sdn Bhd, and the Melaka projects are under Mahajaya Property. Its current project, Alunan Damai in Taman Desa Vista, Salak Tinggi, is 96 double-storey terrace homes on Malay reserve land [1].
The KPKT register only includes projects licensed as housing and only the five companies above are counted; projects the company lists in Bangsar, Port Dickson and Johor Bahru are not registered under them [2].
Frequently asked questions
Is Mahajaya a listed company?
Not today, as far as we could find. The Star reported in April 2004 that Mahajaya would be quoted on the Main Board of the Kuala Lumpur Stock Exchange on 27 April after a reverse takeover of Hotline Furniture Bhd [4], and the company says it listed in 2004 [3]; no current listing was found. The companies registered with KPKT are private limited companies (Sdn Bhd).
Which company developed The Courtyard @ Cheras?
Medan Damai Sdn Bhd (KPKT developer code 4900), one of the companies named on Mahajaya's website [1]. KPKT registers the project as THE COURTYARD @ CHERAS (4900-16), 62 terrace houses in Hulu Langat, Selangor.
Was The Courtyard @ Cheras handed over on time?
Yes, according to KPKT. The first sale agreement was signed on 24 April 2024 and the handover deadline was 24 April 2026, with no extension. The CCC is dated 12 February 2026 and vacant possession 23 February 2026, 60 days before the deadline.
Does Mahajaya have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 18 projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat), and none has an approved extension recorded. The one under construction, ALUNAN DAMAI, DESA VISTA (4900-17, 96 terrace houses), is on schedule (Lancar) at 12% reported progress.
Has Mahajaya handed over its projects by the deadline?
Of the 17 completed projects, 10 have both a deadline and a completion date in the KPKT register: 2 were handed over before the deadline (The Courtyard @ Cheras and RESIDENSI 118, TAMAN DAMAI UTAMA), 4 received the CCC before it with no handover date recorded, and 4 have a completion date after it. For phased projects the register compares the date of the last component with the deadline under the first sale agreement, so later buyers' deadlines are not reflected: BANDAR DAMAI PERDANA 2 (4900-7) shows 2,702 days after its August 2005 deadline because its last 7 bungalows were certified in January 2013, while its earliest component, 246 terrace houses, received its CFO on 9 November 2004. The other three later ones are 4900-12 (365 days), 3888-5 (292 days) and 4900-14 (134 days).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Mahajaya — home page (projects, group companies, office) · Mahajaya Berhad · accessed 28 Oct 2026
https://www.mahajaya.com/ - [2] About Us (founder and project milestones) · Mahajaya Berhad · accessed 28 Oct 2026
https://www.mahajaya.com/about-us/ - [3] Our People (managing director's profile) · Mahajaya Berhad · accessed 28 Oct 2026
https://www.mahajaya.com/our-people/ - [4] Mahajaya not raising prices (The Star, reproduced by the National House Buyers Association) · The Star · 21 Apr 2004 · accessed 28 Oct 2026
https://www.hba.org.my/news/2004/404/mahajaya.htm - [5] The Courtyard · Mahajaya Berhad · accessed 28 Oct 2026
https://www.mahajaya.com/project-development/the-courtyard/
Last updated 28 Oct 2026