Lagenda Properties (Lagenda Properties Berhad)
Lagenda Properties Berhad is a Bursa Malaysia Main Market-listed developer of affordable landed townships, with 57 housing projects in the KPKT register under eight group companies: 33 completed, 22 under construction (1 classed Sick, 2 Late), 1 not yet started and 1 with its permit cancelled. None is Abandoned. Its townships began in Sitiawan, Perak.
- 57 projects in the KPKT register
- 33 completed
- 22 under construction (of which 1 Sick, 2 Late)
- 1 not yet started
- 1 with the permit cancelled
Has Lagenda Properties handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 57 housing projects under 8 Lagenda Properties companies in 6 states: 33 completed, 22 under construction (of which 1 Sick, 2 Late), 1 not yet started, 1 with the permit cancelled.
Of the 33 completed projects, 32 have both a handover deadline and a completion date in the register: 11 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 14 handed over or certified complete after that deadline (4 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 7 received the completion certificate before the deadline (handover date not recorded).
39 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 33
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-16 | ManjungPerak | 932 | 17 Mar 2026Extended 12 months from 17 Mar 20251st sale agreement 17 Mar 2023 | CCC 21 Sep 2026 Handover 21 Sep 2026 | 188 days after |
| DARULAMAN LAGENDAKPKT 30102-3 | Kuala MudaKedah | 636 | 25 Aug 2026Extended 12 months from 25 Aug 20251st sale agreement 25 Aug 2023 | CCC 11 Jun 2026 Handover 11 Jun 2026 | 75 days before |
| LAGENDA AMANKPKT 30377-1 | Batang PadangPerak | 1,449 | 10 Jan 2027Extended 12 months from 10 Jan 20261st sale agreement 10 Jan 2024 | CCC 21 May 2026 Handover 21 May 2026 | 234 days before |
| LAGENDA TELUK INTANKPKT 14283-17 | Hilir PerakPerak | 773 | 27 Mar 2026Extended 12 months from 27 Mar 20251st sale agreement 27 Mar 2023 | CCC 16 Jan 2026 Handover 20 Feb 2026 | 35 days before |
| DARULAMAN LAGENDA PHASE 2KPKT 30102-2 | Kuala MudaKedah | 1,131 | 28 Dec 2025Extended 12 months from 28 Dec 20241st sale agreement 28 Dec 2022 | CCC 29 Sep 2025 Handover 30 Sep 2025 | 89 days before |
| BIDORIA RESIDENSIKPKT 19950-2 | Batang PadangPerak | 56 | 19 Jul 20261st sale agreement 19 Jul 2024 | CCC 2 Sep 2025 Handover 3 Sep 2025 | 319 days before |
| LAGENDA TELUK INTANKPKT 14283-14 | Hilir PerakPerak | 1,098 | 18 Apr 2025Extended 12 months from 18 Apr 20241st sale agreement 18 Apr 2022 | CCC 26 Jun 2025 Handover 26 Jun 2025 | 69 days after |
| RESIDENSI LAGENDA TROPIKAKPKT 14283-13 | Batang PadangPerak | 1,783 | 5 May 2025Extended 12 months from 5 May 20241st sale agreement 5 May 2022 | CCC 28 Mar 2025 Handover 28 Mar 2025 | 38 days before |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-15 | ManjungPerak | 668 | 10 Jan 2025Extended 12 months from 10 Jan 20241st sale agreement 10 Jan 2022 | CCC 13 Dec 2024 Handover 13 Dec 2024 | 28 days before |
| DARULAMAN LAGENDAKPKT 30102-1 | Kuala MudaKedah | 282 | 7 Oct 20241st sale agreement 7 Oct 2022 | CCC 28 Oct 2024 Handover 28 Oct 2024 | 21 days after |
| TAMAN MULIAKPKT 11225-10 | ManjungPerak | 144 | 28 Jan 20251st sale agreement 28 Jan 2023 | CCC 4 Oct 2024 Handover 4 Oct 2024 | 116 days before |
| LAGENDA TELUK INTANKPKT 14283-10 | Hilir PerakPerak | 2,667 | 7 Jul 2024Extended 24 months from 7 Jul 20221st sale agreement 7 Jul 2020 | CCC 12 Aug 2024 Handover 12 Aug 2024 | 36 days after † |
Handed over or certified complete after the deadline — 12 most recent of 14
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-16 | ManjungPerak | 932 | 17 Mar 2026Extended 12 months from 17 Mar 20251st sale agreement 17 Mar 2023 | CCC 21 Sep 2026 Handover 21 Sep 2026 | 188 days after |
| LAGENDA TELUK INTANKPKT 14283-14 | Hilir PerakPerak | 1,098 | 18 Apr 2025Extended 12 months from 18 Apr 20241st sale agreement 18 Apr 2022 | CCC 26 Jun 2025 Handover 26 Jun 2025 | 69 days after |
| DARULAMAN LAGENDAKPKT 30102-1 | Kuala MudaKedah | 282 | 7 Oct 20241st sale agreement 7 Oct 2022 | CCC 28 Oct 2024 Handover 28 Oct 2024 | 21 days after |
| LAGENDA TELUK INTANKPKT 14283-10 | Hilir PerakPerak | 2,667 | 7 Jul 2024Extended 24 months from 7 Jul 20221st sale agreement 7 Jul 2020 | CCC 12 Aug 2024 Handover 12 Aug 2024 | 36 days after † |
| MAXITANAH SDN. BHD.KPKT 19950-1 | Batang PadangPerak | 397 | 26 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020 | CCC 29 Apr 2024 Handover 30 Apr 2024 | 401 days after |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-12 | ManjungPerak | 412 | 17 Sep 20231st sale agreement 17 Sep 2021 | CCC 22 Sep 2023 Handover 25 Sep 2023 | 8 days after |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-8 | ManjungPerak | 1,160 | 3 Feb 2023Extended 11 months from 3 Mar 20221st sale agreement 3 Mar 2020 | CCC 22 Jun 2023 | 139 days after † |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-7 | ManjungPerak | 1,243 | 16 Oct 2022Extended 17 months from 16 May 20211st sale agreement 16 May 2019 | CCC 15 Dec 2022 | 60 days after † |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-4 | ManjungPerak | 829 | 18 Oct 2020Extended 6 months from 18 Apr 20201st sale agreement 18 Apr 2018 | CCC 10 Mar 2021 | 143 days after † |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-3 | ManjungPerak | 1,492 | 14 Feb 20191st sale agreement 14 Feb 2017 | CCC 21 Feb 2020 | 372 days after |
| BANDAR BARU SETIAAWANKPKT 14283-1 | ManjungPerak | 1,147 | 7 Dec 20171st sale agreement 7 Dec 2015 | CCC 25 Apr 2019 | 504 days after |
| D LUX RESIDENSIKPKT 11225-6 | SerembanNegeri Sembilan | 16 | 13 Jun 20171st sale agreement 13 Jun 2015 | CCC 29 Jun 2018 | 381 days after |
Show all 14
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-16 | ManjungPerak | 932 | 17 Mar 2026Extended 12 months from 17 Mar 20251st sale agreement 17 Mar 2023 | CCC 21 Sep 2026 Handover 21 Sep 2026 | 188 days after |
| LAGENDA TELUK INTANKPKT 14283-14 | Hilir PerakPerak | 1,098 | 18 Apr 2025Extended 12 months from 18 Apr 20241st sale agreement 18 Apr 2022 | CCC 26 Jun 2025 Handover 26 Jun 2025 | 69 days after |
| DARULAMAN LAGENDAKPKT 30102-1 | Kuala MudaKedah | 282 | 7 Oct 20241st sale agreement 7 Oct 2022 | CCC 28 Oct 2024 Handover 28 Oct 2024 | 21 days after |
| LAGENDA TELUK INTANKPKT 14283-10 | Hilir PerakPerak | 2,667 | 7 Jul 2024Extended 24 months from 7 Jul 20221st sale agreement 7 Jul 2020 | CCC 12 Aug 2024 Handover 12 Aug 2024 | 36 days after † |
| MAXITANAH SDN. BHD.KPKT 19950-1 | Batang PadangPerak | 397 | 26 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020 | CCC 29 Apr 2024 Handover 30 Apr 2024 | 401 days after |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-12 | ManjungPerak | 412 | 17 Sep 20231st sale agreement 17 Sep 2021 | CCC 22 Sep 2023 Handover 25 Sep 2023 | 8 days after |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-8 | ManjungPerak | 1,160 | 3 Feb 2023Extended 11 months from 3 Mar 20221st sale agreement 3 Mar 2020 | CCC 22 Jun 2023 | 139 days after † |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-7 | ManjungPerak | 1,243 | 16 Oct 2022Extended 17 months from 16 May 20211st sale agreement 16 May 2019 | CCC 15 Dec 2022 | 60 days after † |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-4 | ManjungPerak | 829 | 18 Oct 2020Extended 6 months from 18 Apr 20201st sale agreement 18 Apr 2018 | CCC 10 Mar 2021 | 143 days after † |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-3 | ManjungPerak | 1,492 | 14 Feb 20191st sale agreement 14 Feb 2017 | CCC 21 Feb 2020 | 372 days after |
| BANDAR BARU SETIAAWANKPKT 14283-1 | ManjungPerak | 1,147 | 7 Dec 20171st sale agreement 7 Dec 2015 | CCC 25 Apr 2019 | 504 days after |
| D LUX RESIDENSIKPKT 11225-6 | SerembanNegeri Sembilan | 16 | 13 Jun 20171st sale agreement 13 Jun 2015 | CCC 29 Jun 2018 | 381 days after |
| BLOSSOM EASTLAND SDN. BHD.KPKT 11225-7 | KintaPerak | 140 | 5 Jun 20171st sale agreement 5 Jun 2015 | CCC 12 Jun 2018 | 372 days after |
| BLOSSOM EASTLAND SDN. BHD.KPKT 11225-3 | SerembanNegeri Sembilan | 219 | 5 Dec 20151st sale agreement 5 Dec 2013 | CCC 21 Jan 2016 | 47 days after |
Show all 33 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-16 | ManjungPerak | 932 | 17 Mar 2026Extended 12 months from 17 Mar 20251st sale agreement 17 Mar 2023 | CCC 21 Sep 2026 Handover 21 Sep 2026 | 188 days after |
| DARULAMAN LAGENDAKPKT 30102-3 | Kuala MudaKedah | 636 | 25 Aug 2026Extended 12 months from 25 Aug 20251st sale agreement 25 Aug 2023 | CCC 11 Jun 2026 Handover 11 Jun 2026 | 75 days before |
| LAGENDA AMANKPKT 30377-1 | Batang PadangPerak | 1,449 | 10 Jan 2027Extended 12 months from 10 Jan 20261st sale agreement 10 Jan 2024 | CCC 21 May 2026 Handover 21 May 2026 | 234 days before |
| LAGENDA TELUK INTANKPKT 14283-17 | Hilir PerakPerak | 773 | 27 Mar 2026Extended 12 months from 27 Mar 20251st sale agreement 27 Mar 2023 | CCC 16 Jan 2026 Handover 20 Feb 2026 | 35 days before |
| DARULAMAN LAGENDA PHASE 2KPKT 30102-2 | Kuala MudaKedah | 1,131 | 28 Dec 2025Extended 12 months from 28 Dec 20241st sale agreement 28 Dec 2022 | CCC 29 Sep 2025 Handover 30 Sep 2025 | 89 days before |
| BIDORIA RESIDENSIKPKT 19950-2 | Batang PadangPerak | 56 | 19 Jul 20261st sale agreement 19 Jul 2024 | CCC 2 Sep 2025 Handover 3 Sep 2025 | 319 days before |
| LAGENDA TELUK INTANKPKT 14283-14 | Hilir PerakPerak | 1,098 | 18 Apr 2025Extended 12 months from 18 Apr 20241st sale agreement 18 Apr 2022 | CCC 26 Jun 2025 Handover 26 Jun 2025 | 69 days after |
| RESIDENSI LAGENDA TROPIKAKPKT 14283-13 | Batang PadangPerak | 1,783 | 5 May 2025Extended 12 months from 5 May 20241st sale agreement 5 May 2022 | CCC 28 Mar 2025 Handover 28 Mar 2025 | 38 days before |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-15 | ManjungPerak | 668 | 10 Jan 2025Extended 12 months from 10 Jan 20241st sale agreement 10 Jan 2022 | CCC 13 Dec 2024 Handover 13 Dec 2024 | 28 days before |
| DARULAMAN LAGENDAKPKT 30102-1 | Kuala MudaKedah | 282 | 7 Oct 20241st sale agreement 7 Oct 2022 | CCC 28 Oct 2024 Handover 28 Oct 2024 | 21 days after |
| TAMAN MULIAKPKT 11225-10 | ManjungPerak | 144 | 28 Jan 20251st sale agreement 28 Jan 2023 | CCC 4 Oct 2024 Handover 4 Oct 2024 | 116 days before |
| LAGENDA TELUK INTANKPKT 14283-10 | Hilir PerakPerak | 2,667 | 7 Jul 2024Extended 24 months from 7 Jul 20221st sale agreement 7 Jul 2020 | CCC 12 Aug 2024 Handover 12 Aug 2024 | 36 days after † |
| OPTI VEGA SDN. BHD.KPKT 20081-1 | Batang PadangPerak | 596 | 2 Aug 2024Extended 12 months from 2 Aug 20231st sale agreement 2 Aug 2021 | CCC 17 Jul 2024 Handover 18 Jul 2024 | 15 days before |
| MAXITANAH SDN. BHD.KPKT 19950-1 | Batang PadangPerak | 397 | 26 Mar 2023Extended 5 months from 26 Oct 20221st sale agreement 26 Oct 2020 | CCC 29 Apr 2024 Handover 30 Apr 2024 | 401 days after |
| TAMAN MULIAKPKT 11225-9 | ManjungPerak | 98 | 27 Aug 20241st sale agreement 27 Aug 2021 | CCC 8 Mar 2024 | CCC before deadline; handover not recorded |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-11 | ManjungPerak | 1,074 | 9 Mar 2024Extended 17 months from 9 Oct 20221st sale agreement 9 Oct 2020 | CCC 22 Sep 2023 Handover 25 Sep 2023 | 166 days before |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-12 | ManjungPerak | 412 | 17 Sep 20231st sale agreement 17 Sep 2021 | CCC 22 Sep 2023 Handover 25 Sep 2023 | 8 days after |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-8 | ManjungPerak | 1,160 | 3 Feb 2023Extended 11 months from 3 Mar 20221st sale agreement 3 Mar 2020 | CCC 22 Jun 2023 | 139 days after † |
| TARAF NUSANTARA SDN. BHD.KPKT 14283-9 | KintaPerak | 303 | 13 Mar 2023Extended 5 months from 13 Oct 20221st sale agreement 13 Oct 2020 | CCC 28 Feb 2023 Handover 3 Mar 2023 | 10 days before |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-7 | ManjungPerak | 1,243 | 16 Oct 2022Extended 17 months from 16 May 20211st sale agreement 16 May 2019 | CCC 15 Dec 2022 | 60 days after † |
| TARAF NUSANTARA SDN. BHD.KPKT 14283-6 | Hilir PerakPerak | 1,843 | 28 Jan 2023Extended 23 months from 28 Feb 20211st sale agreement 28 Feb 2019 | CCC 14 Sep 2022 | CCC before deadline; handover not recorded |
| DBE DEVELOPMENT SDN. BHD.KPKT 19599-1 | KintaPerak | 292 | 29 Jun 2022Extended 11 months from 29 Jul 20211st sale agreement 29 Jul 2019 | CCC 2 Mar 2022 | CCC before deadline; handover not recorded |
| BANDAR BARU SETIAAWAN PERDANAKPKT 14283-5 | ManjungPerak | 1,009 | 3 Apr 2022Extended 18 months from 3 Oct 20201st sale agreement 3 Oct 2018 | CCC 8 Nov 2021 | CCC before deadline; handover not recorded |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-4 | ManjungPerak | 829 | 18 Oct 2020Extended 6 months from 18 Apr 20201st sale agreement 18 Apr 2018 | CCC 10 Mar 2021 | 143 days after † |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-2 | ManjungPerak | 1,555 | 12 Apr 2020Extended 12 months from 12 Apr 20191st sale agreement 12 Apr 2017 | CCC 27 Feb 2020 | CCC before deadline; handover not recorded |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-3 | ManjungPerak | 1,492 | 14 Feb 20191st sale agreement 14 Feb 2017 | CCC 21 Feb 2020 | 372 days after |
| BANDAR BARU SETIAAWANKPKT 14283-1 | ManjungPerak | 1,147 | 7 Dec 20171st sale agreement 7 Dec 2015 | CCC 25 Apr 2019 | 504 days after |
| D LUX RESIDENSIKPKT 11225-6 | SerembanNegeri Sembilan | 16 | 13 Jun 20171st sale agreement 13 Jun 2015 | CCC 29 Jun 2018 | 381 days after |
| BLOSSOM EASTLAND SDN. BHD.KPKT 11225-7 | KintaPerak | 140 | 5 Jun 20171st sale agreement 5 Jun 2015 | CCC 12 Jun 2018 | 372 days after |
| BLOSSOM EASTLAND SDN. BHD.KPKT 11225-5 | ManjungPerak | 225 | 23 Mar 20181st sale agreement 23 Mar 2015 | CCC 30 May 2017 | CCC before deadline; handover not recorded |
| BLOSSOM EASTLAND SDN. BHD.KPKT 11225-3 | SerembanNegeri Sembilan | 219 | 5 Dec 20151st sale agreement 5 Dec 2013 | CCC 21 Jan 2016 | 47 days after |
| BLOSSOM EASTLAND SDN. BHD.KPKT 11225-4 | ManjungPerak | 19 | 25 Feb 20161st sale agreement 25 Feb 2014 | CCC 8 Jan 2016 | CCC before deadline; handover not recorded |
| PT 6407-6506KPKT 11225-1 | ManjungPerak | 265 | — | CCC 12 Jul 2013 | — |
Under construction (22) and not yet started (1) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| LAGENDA SURIAKPKT 30223-1 | MersingJohor | 608 | SickSick | 26 Oct 2026Extended 12 months from 26 Oct 20251st sale agreement 26 Oct 2023 | 91% |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-19 | ManjungPerak | 664 | SmoothOn schedule | 28 Nov 2026Extended 12 months from 28 Nov 20251st sale agreement 28 Nov 2023 | 96% |
| PUNCAK WARISANKPKT 20081-2 | Kota TinggiJohor | 639 | DelayLate | 17 Feb 2027Extended 12 months from 17 Feb 20261st sale agreement 17 Feb 2024 | 74–75% |
| LAGENDA SURIAKPKT 30223-2 | MersingJohor | 359 | SmoothOn schedule | 6 May 2027Extended 12 months from 6 May 20261st sale agreement 6 May 2024 | 79–87% |
| LAGENDA ARDEAKPKT 11225-11 | Hulu SelangorSelangor | 831 | SmoothOn schedule | 25 May 2027Extended 12 months from 25 May 20261st sale agreement 25 May 2024 | 82–86% |
| DARULAMAN LAGENDAKPKT 30102-4 | Kuala MudaKedah | 398 | SmoothOn schedule | 8 Oct 20271st sale agreement 8 Oct 2025 | 86% |
| LAGENDA ARDEAKPKT 11225-13Lagenda Ardea · on PropertySifu | Hulu SelangorSelangor | 818 | SmoothOn schedule | 16 Oct 2027Extended 12 months from 16 Oct 20261st sale agreement 16 Oct 2024 | 68–78% |
| LA INDERAKPKT 19599-2 | KuantanPahang | 1,009 | SmoothOn schedule | 17 Mar 2028Extended 12 months from 17 Mar 20271st sale agreement 17 Mar 2025 | 51% |
| TAMAN PUNCAK WARISANKPKT 20081-3 | Johor | 104 | SmoothOn schedule | 31 Mar 20281st sale agreement 31 Mar 2026 | 49% |
| SETIA RESIDEN @ AURORAKPKT 11225-14 | ManjungPerak | 75 | SmoothOn schedule | 5 May 20281st sale agreement 5 May 2026 | 35–42% |
| LA' LUMIEREKPKT 30223-3 | KulaiJohor | 893 | SmoothOn schedule | 3 Jun 2028Extended 12 months from 3 Jun 20271st sale agreement 3 Jun 2025 | 43% |
| LAGENDA TELUK INTANKPKT 14283-20 | Hilir PerakPerak | 980 | DelayLate | 13 Jun 2028Extended 12 months from 13 Jun 20271st sale agreement 13 Jun 2025 | 10–19% |
Show all 23 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| LAGENDA SURIAKPKT 30223-1 | MersingJohor | 608 | SickSick | 26 Oct 2026Extended 12 months from 26 Oct 20251st sale agreement 26 Oct 2023 | 91% |
| BANDAR BARU SETIA AWAN PERDANAKPKT 14283-19 | ManjungPerak | 664 | SmoothOn schedule | 28 Nov 2026Extended 12 months from 28 Nov 20251st sale agreement 28 Nov 2023 | 96% |
| PUNCAK WARISANKPKT 20081-2 | Kota TinggiJohor | 639 | DelayLate | 17 Feb 2027Extended 12 months from 17 Feb 20261st sale agreement 17 Feb 2024 | 74–75% |
| LAGENDA SURIAKPKT 30223-2 | MersingJohor | 359 | SmoothOn schedule | 6 May 2027Extended 12 months from 6 May 20261st sale agreement 6 May 2024 | 79–87% |
| LAGENDA ARDEAKPKT 11225-11 | Hulu SelangorSelangor | 831 | SmoothOn schedule | 25 May 2027Extended 12 months from 25 May 20261st sale agreement 25 May 2024 | 82–86% |
| DARULAMAN LAGENDAKPKT 30102-4 | Kuala MudaKedah | 398 | SmoothOn schedule | 8 Oct 20271st sale agreement 8 Oct 2025 | 86% |
| LAGENDA ARDEAKPKT 11225-13Lagenda Ardea · on PropertySifu | Hulu SelangorSelangor | 818 | SmoothOn schedule | 16 Oct 2027Extended 12 months from 16 Oct 20261st sale agreement 16 Oct 2024 | 68–78% |
| LA INDERAKPKT 19599-2 | KuantanPahang | 1,009 | SmoothOn schedule | 17 Mar 2028Extended 12 months from 17 Mar 20271st sale agreement 17 Mar 2025 | 51% |
| TAMAN PUNCAK WARISANKPKT 20081-3 | Johor | 104 | SmoothOn schedule | 31 Mar 20281st sale agreement 31 Mar 2026 | 49% |
| SETIA RESIDEN @ AURORAKPKT 11225-14 | ManjungPerak | 75 | SmoothOn schedule | 5 May 20281st sale agreement 5 May 2026 | 35–42% |
| LA' LUMIEREKPKT 30223-3 | KulaiJohor | 893 | SmoothOn schedule | 3 Jun 2028Extended 12 months from 3 Jun 20271st sale agreement 3 Jun 2025 | 43% |
| LAGENDA TELUK INTANKPKT 14283-20 | Hilir PerakPerak | 980 | DelayLate | 13 Jun 2028Extended 12 months from 13 Jun 20271st sale agreement 13 Jun 2025 | 10–19% |
| SAMUDRA@LAGENDA SURIAKPKT 30223-5 | MersingJohor | 1,379 | SmoothOn schedule | 28 Oct 2028Extended 12 months from 28 Oct 20271st sale agreement 28 Oct 2025 | 8–46% |
| LAGENDA DAMAIKPKT 19599-3 | Batang PadangPerak | 936 | SmoothOn schedule | 12 Nov 2028Extended 12 months from 12 Nov 20271st sale agreement 12 Nov 2025 | 17% |
| LA' LUMIE'REKPKT 30223-4 | KulaiJohor | 1,918 | SmoothOn schedule | 26 Nov 2028Extended 12 months from 26 Nov 20271st sale agreement 26 Nov 2025 | 5–16% |
| LAGENDA ARDEAKPKT 11225-12 | Hulu SelangorSelangor | 691 | SmoothOn schedule | 26 Dec 2028Extended 12 months from 26 Dec 20271st sale agreement 26 Dec 2025 | 39–67% |
| PALMA 1B@LA INDERAKPKT 19599-5 | KuantanPahang | 379 | SmoothOn schedule | 31 Mar 2029Extended 12 months from 31 Mar 20281st sale agreement 31 Mar 2026 | 16% |
| LEXA@LA'LUMIE'REKPKT 30223-6 | KulaiJohor | 800 | SmoothOn schedule | 24 May 2029Extended 12 months from 24 May 20281st sale agreement 24 May 2026 | 12% |
| LA'INDERA@TIARAKPKT 19599-6 | KuantanPahang | 1,540 | SmoothOn schedule | 2 Sep 2029Extended 12 months from 2 Sep 20281st sale agreement 2 Sep 2026 | 3% |
| LA' AVIERA@SERENAKPKT 11225-15 | Kuala MudaKedah | 1,056 | Not startedNot started | — | 0% |
| RHEA@LA' LUMIEREKPKT 30223-7 | KulaiJohor | 2,013 | SmoothOn schedule | —Extended 12 months (date not registered) | 3% |
| LAGENDA DAMAIKPKT 19599-4 | Batang PadangPerak | 954 | SmoothOn schedule | —Extended 12 months (date not registered) | 4–6% |
| BANDAR BARU SETIAWAN PERDANAKPKT 14283-18 | ManjungPerak | 1,048 | SmoothOn schedule | —Extended 12 months (date not registered) | 7% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN PERMAI JAYA 2KPKT 11225-8 | ManjungPerak | 19 | Permit cancelledPermit cancelled | — | 5% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Lagenda Properties at a glance
| Listed | Bursa Malaysia Main Market · LAGENDA (7179) · renamed from D.B.E. Gurney Resources Berhad on 16 July 2020[1][2] |
|---|---|
| Started | Early 2018 in Sitiawan, Perak — the company's account of when its affordable-housing business began[2][6] |
| Head office | Seri Manjung, Perak (principal place of business); branch office in Petaling Jaya, Selangor[1] |
| Leadership | Dato' Doh Jee Ming — Managing Director and major shareholder[1] Admiral Tan Sri Dato' Seri Panglima Dr. Ahmad Kamarulzaman bin Hj. Ahmad Badaruddin (Retired) — Independent Non-Executive Chairman[1] |
| Companies in the KPKT register | BLOSSOM EASTLAND SDN. BHD. KPKT 11225[1] TARAF NUSANTARA SDN. BHD. KPKT 14283[1] MAXITANAH SDN. BHD. KPKT 19950[1] OPTI VEGA SDN. BHD. KPKT 20081[1] LAGENDA TAPAH SDN. BHD. KPKT 30377[1] LPB DEVELOPMENT SDN. BHD. KPKT 19599[1] LAGENDA MERSING SDN. BHD. (70%) KPKT 30223[1] BDB LAGENDA SDN. BHD. (50%) KPKT 30102[1][2] |
| Website | lagendaproperties.com |
| Homes delivered (company figure) | About 30,000 homes as of 2025; target of more than 35,000 affordable homes by 2030[1] |
| Land bank | About 4,300 acres of undeveloped land at 31 December 2025, with an estimated remaining GDV of RM11.0 billion[1] |
| States | Perak, Johor, Kedah, Selangor, Pahang, Negeri Sembilan[1] |
| Award | Bandar Baru Setia Awan Perdana (Phase 1A): a winner in the Affordable Urban Housing category, The Edge Malaysia Property Excellence Awards 2022[5] |
| Joint venture (Lagenda Ardea) | With Kumpulan Hartanah Selangor Bhd, wholly owned by the Selangor government, as landowner; Lagenda is the developer[3] |
Lagenda Properties projects on sale on PropertySifu
Who is Lagenda Properties? The company behind the projects
Lagenda Properties Berhad is listed on the Main Market of Bursa Malaysia under the stock name LAGENDA (code 7179) [1]. The listed company was previously D.B.E. Gurney Resources Berhad and took its current name on 16 July 2020 [2]. On 12 August 2020 it completed the purchase of Blossom Eastland Sdn Bhd from Doh Properties Holdings Sdn Bhd, together with Rantau Urusan (M) Sdn Bhd and Yik Wang Trading Sdn Bhd from members of the Doh family [2]. The company says it began building affordable homes in early 2018, starting in Sitiawan, Perak [2][6]. Blossom Eastland's own projects go back further: its earliest completion certificate in the KPKT register is dated 2013.
The managing director and major shareholder is Dato' Doh Jee Ming, and the independent non-executive chairman is Admiral Tan Sri Dato' Seri Panglima Dr. Ahmad Kamarulzaman bin Hj. Ahmad Badaruddin (Retired) [1]. The principal place of business is in Seri Manjung, Perak, with a branch office in Petaling Jaya, Selangor [1]. The company says it had delivered about 30,000 homes by 2025 and aims to provide more than 35,000 affordable homes by 2030; at 31 December 2025 it held about 4,300 acres of undeveloped land [1]. These are group-wide figures: the KPKT register covers housing-licensed projects only, and the 33 completed projects under the eight companies on this page total 25,953 units.
Most of the group's KPKT projects are registered under two wholly owned subsidiaries, Taraf Nusantara Sdn Bhd (Bandar Baru Setia Awan Perdana in Manjung and Lagenda Teluk Intan) and Blossom Eastland [1]. Lagenda holds 70% of the ownership and 99.9% of the voting rights in Lagenda Mersing Sdn Bhd, which registers Lagenda Suria in Mersing and La' Lumière in Kulai, Johor [1]. Darulaman Lagenda in Sungai Petani, Kedah, is developed by BDB Lagenda Sdn Bhd, set up in 2021 in a joint venture with BDB Land, a Bina Darulaman Berhad subsidiary [2]; Lagenda holds 50% but accounts for it as a wholly owned subsidiary under development rights agreements [1].
Lagenda Ardea, the project listed on PropertySifu, is in Bernam Jaya, Hulu Selangor. In 2022 Blossom Eastland entered a joint venture with Kumpulan Hartanah Selangor Bhd (KHSB), wholly owned by the Selangor government, to develop a 191-acre plot, with Lagenda as developer and KHSB as landowner [3]. The company plans 2,340 single-storey terrace homes in three phases [1]; construction started in May 2024, and the homes are part of the Selangor government's Rumah Selangorku housing scheme [4]. KPKT registers the three phases as 11225-11 (831 units), 11225-13 (818 units) and 11225-12 (691 units), all on schedule (Lancar).
Frequently asked questions
Is Lagenda Properties a listed company?
Which company develops Lagenda Ardea?
Blossom Eastland Sdn Bhd (KPKT developer code 11225), a wholly owned subsidiary according to Lagenda's 2025 annual report [1]. The land belongs to Kumpulan Hartanah Selangor Bhd (KHSB), wholly owned by the Selangor government; under their 2022 joint venture, Lagenda is the developer and KHSB the landowner [3].
Has Lagenda Ardea's handover deadline been extended?
Yes, according to KPKT. The registration PropertySifu lists (11225-13, 818 terrace houses, first sale agreement 16 October 2024) had a deadline of 16 October 2026, extended with approval by 12 months to 16 October 2027; reported progress is 68–78%. The other two: 11225-11 (831 houses) from 25 May 2026 extended by 12 months to 25 May 2027, 82–86%; 11225-12 (691 houses) from 26 December 2027 extended by 12 months to 26 December 2028, 39–67%. All three are recorded as on schedule (Lancar).
Does Lagenda have any Sick or Abandoned projects?
None is Abandoned. As at 27 October 2026, KPKT classes 1 of the 57 projects as Sick (Sakit): Lagenda Suria (30223-1, 608 terrace houses in Mersing, Johor, under Lagenda Mersing Sdn Bhd), first sale agreement 26 October 2023, deadline 26 October 2025 extended with approval by 12 months to 26 October 2026, reported progress 91%. 2 are classed Late (Lewat): Puncak Warisan (20081-2, 639 terrace houses in Kota Tinggi, Johor, under Opti Vega Sdn Bhd), deadline extended by 12 months to 17 February 2027, progress 74–75%; and a Lagenda Teluk Intan phase (14283-20, 980 units, under Taraf Nusantara Sdn Bhd), deadline extended by 12 months to 13 June 2028, progress 10–19%. One more registration (11225-8, 19 terrace houses in Manjung) has its permit cancelled.
How many Lagenda projects have been completed, and were they handed over on time?
In the KPKT register, 33 of the 57 projects are completed. Of the 32 completed projects with both a deadline and a completion date: 11 were handed over on or before the deadline (where an extension was approved, the extended deadline is used); 14 have a handover or CCC date after the deadline, 4 of them with construction spanning the 18 March–31 August 2020 movement control period; and 7 received the CCC before the deadline, with no handover date registered. The remaining completed project does not have both dates registered. The company says it had delivered about 30,000 homes by 2025 [1].
Are all companies with "Lagenda" in their name part of this group?
No. The KPKT register has many developer companies with "Lagenda" in their name. This page counts only the eight companies that Lagenda Properties' 2025 annual report lists as subsidiaries and that are registered with KPKT [1]; the projects of other similarly named companies are not included.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Lagenda Properties Berhad Annual Report 2025 (corporate structure p.4, corporate information p.5, MD&A pp.20–25, sustainability pp.43 and 52, note 12 pp.178–180) · Lagenda Properties Berhad · 30 Apr 2026 · accessed 28 Oct 2026
https://lagendaproperties.com/wp-content/uploads/2026/05/Annual-Report-Year-2025.pdf - [2] Lagenda Properties Berhad Annual Report 2020 (About Lagenda p.2, additional compliance information pp.54–55, directors' report p.65, note 37) · Lagenda Properties Berhad · 2021-04 · accessed 28 Oct 2026
https://lagendaproperties.com/wp-content/uploads/2023/07/Annual-Report-Year-2020.pdf - [3] Lagenda and Selangor govt to jointly develop large-scale affordable township · The Edge Malaysia (CEO Morning Brief) · 6 Sep 2022 · accessed 28 Oct 2026
https://ceomorningbrief.theedgemalaysia.com/article/2022/0439/Home/11/635305 - [4] Lagenda Properties kicks off construction of first large-scale landed Rumah Selangorku project · New Straits Times · 5 May 2024 · accessed 28 Oct 2026
https://nst.com.my/amp/business/corporate/2024/05/1046463/%C2%A0lagenda-properties-kicks-construction-first-large-scale-landed - [5] S P Setia takes No 1 spot at The Edge Malaysia Top Property Developers Awards 2022 (Property Excellence Awards results) · The Edge Malaysia (EdgeProp.my) · 7 Nov 2022 · accessed 28 Oct 2026
https://www.edgeprop.my/content/1904200/s-p-setia-takes-no-1-spot-edge-malaysia-top-property-developers-awards-2022 - [6] Our Story · Lagenda Properties Berhad · accessed 28 Oct 2026
https://lagendaproperties.com/about-us/our-story/
Last updated 28 Oct 2026