Kenting Development (Kenting Development Sdn Bhd)

Last updated 28 Oct 2026
Who is Kenting Development?

Kenting Development Sdn Bhd is a private developer with 41 housing projects in the KPKT register, all in Selangor: 30 completed and 11 under construction, none classed Sick or Abandoned. Most are small terraced-house schemes in Kuala Langat, Sepang and Klang districts, from 13 to 187 units each, including Taman Melati 4 and Taman Mutiara Salak.

  • 41 projects in the KPKT register
  • 30 completed
  • 11 under construction
  • None Sick or Abandoned

Has Kenting Development handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists 41 housing projects under 1 Kenting Development company in 1 state: 30 completed, 11 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).

Of the 30 completed projects, 30 have both a handover deadline and a completion date in the register: 18 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 5 handed over or certified complete after that deadline; 7 received the completion certificate before the deadline (handover date not recorded).

9 projects had the delivery period extended with KPKT approval.

Completed projects — the 12 most recent of 30

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN BENTARAKPKT 14366-30Kuala LangatSelangor4615 Oct 20261st sale agreement 15 Oct 2024CCC 23 Jul 2026
Handover 23 Jul 2026
84 days before
TAMAN SEMARANG INTANKPKT 14366-32SepangSelangor495 Feb 20271st sale agreement 5 Feb 2025CCC 1 Jul 2026
Handover 1 Jul 2026
219 days before
TAMAN GEMILANG 2KPKT 14366-31SepangSelangor2424 Feb 20271st sale agreement 24 Feb 2025CCC 28 Apr 2026
Handover 29 Apr 2026
301 days before
TAMAN MELATI 4KPKT 14366-27Taman Melati 4 · on PropertySifuKlangSelangor3216 Jul 20261st sale agreement 16 Jul 2024CCC 2 Dec 2025CCC before deadline; handover not recorded
TAMAN SEMARANG INTANKPKT 14366-25SepangSelangor2315 Nov 20251st sale agreement 15 Nov 2023CCC 3 Nov 2025
Handover 6 Nov 2025
9 days before
TAMAN SEMARANG INTANKPKT 14366-26SepangSelangor2430 May 20261st sale agreement 30 May 2024CCC 29 Sep 2025
Handover 29 Sep 2025
243 days before
TAMAN DATO' HARUN 7KPKT 14366-23KlangSelangor4417 Jul 20251st sale agreement 17 Jul 2023CCC 3 Jul 2025
Handover 3 Jul 2025
14 days before
TAMAN BENTARA @ JALAN PUYUHKPKT 14366-24Kuala LangatSelangor646 Jun 20251st sale agreement 6 Jun 2023CCC 19 Jun 2025
Handover 19 Jun 2025
13 days after
TAMAN IMPIAN CAHAYA 1KPKT 14366-19KlangSelangor136 Apr 20251st sale agreement 6 Apr 2023CCC 2 May 2025
Handover 2 May 2025
26 days after
TAMAN KHALID AL-WALID 2KPKT 14366-20KlangSelangor1310 Apr 20251st sale agreement 10 Apr 2023CCC 14 Mar 2025
Handover 14 Mar 2025
27 days before
TAMAN BENTARA - JALAN MERPATIKPKT 14366-22Kuala LangatSelangor2317 May 20251st sale agreement 17 May 2023CCC 25 Feb 2025
Handover 25 Feb 2025
81 days before
TAMAN SERI MAJUKPKT 14366-18Kuala LangatSelangor308 Sep 20251st sale agreement 8 Sep 2023CCC 24 Feb 2025
Handover 24 Feb 2025
196 days before

Handed over or certified complete after the deadline (5)

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN BENTARA @ JALAN PUYUHKPKT 14366-24Kuala LangatSelangor646 Jun 20251st sale agreement 6 Jun 2023CCC 19 Jun 2025
Handover 19 Jun 2025
13 days after
TAMAN IMPIAN CAHAYA 1KPKT 14366-19KlangSelangor136 Apr 20251st sale agreement 6 Apr 2023CCC 2 May 2025
Handover 2 May 2025
26 days after
TAMAN JENJAROM PERMAIKPKT 14366-13Kuala LangatSelangor2221 Oct 20231st sale agreement 21 Oct 2021CCC 25 Oct 2023
Handover 25 Oct 2023
4 days after
TAMAN JENJAROM PERMAIKPKT 14366-14Kuala LangatSelangor2921 Oct 20231st sale agreement 21 Oct 2021CCC 25 Oct 2023
Handover 25 Oct 2023
4 days after
TAMAN KEBUN SETAWAR 1KPKT 14366-12KlangSelangor444 Sep 2023Extended 5 months from 4 Apr 20231st sale agreement 4 Apr 2021CCC 5 Sep 2023
Handover 5 Sep 2023
1 day after
Show all 30 completed projects
Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
TAMAN BENTARAKPKT 14366-30Kuala LangatSelangor4615 Oct 20261st sale agreement 15 Oct 2024CCC 23 Jul 2026
Handover 23 Jul 2026
84 days before
TAMAN SEMARANG INTANKPKT 14366-32SepangSelangor495 Feb 20271st sale agreement 5 Feb 2025CCC 1 Jul 2026
Handover 1 Jul 2026
219 days before
TAMAN GEMILANG 2KPKT 14366-31SepangSelangor2424 Feb 20271st sale agreement 24 Feb 2025CCC 28 Apr 2026
Handover 29 Apr 2026
301 days before
TAMAN MELATI 4KPKT 14366-27Taman Melati 4 · on PropertySifuKlangSelangor3216 Jul 20261st sale agreement 16 Jul 2024CCC 2 Dec 2025CCC before deadline; handover not recorded
TAMAN SEMARANG INTANKPKT 14366-25SepangSelangor2315 Nov 20251st sale agreement 15 Nov 2023CCC 3 Nov 2025
Handover 6 Nov 2025
9 days before
TAMAN SEMARANG INTANKPKT 14366-26SepangSelangor2430 May 20261st sale agreement 30 May 2024CCC 29 Sep 2025
Handover 29 Sep 2025
243 days before
TAMAN DATO' HARUN 7KPKT 14366-23KlangSelangor4417 Jul 20251st sale agreement 17 Jul 2023CCC 3 Jul 2025
Handover 3 Jul 2025
14 days before
TAMAN BENTARA @ JALAN PUYUHKPKT 14366-24Kuala LangatSelangor646 Jun 20251st sale agreement 6 Jun 2023CCC 19 Jun 2025
Handover 19 Jun 2025
13 days after
TAMAN IMPIAN CAHAYA 1KPKT 14366-19KlangSelangor136 Apr 20251st sale agreement 6 Apr 2023CCC 2 May 2025
Handover 2 May 2025
26 days after
TAMAN KHALID AL-WALID 2KPKT 14366-20KlangSelangor1310 Apr 20251st sale agreement 10 Apr 2023CCC 14 Mar 2025
Handover 14 Mar 2025
27 days before
TAMAN BENTARA - JALAN MERPATIKPKT 14366-22Kuala LangatSelangor2317 May 20251st sale agreement 17 May 2023CCC 25 Feb 2025
Handover 25 Feb 2025
81 days before
TAMAN SERI MAJUKPKT 14366-18Kuala LangatSelangor308 Sep 20251st sale agreement 8 Sep 2023CCC 24 Feb 2025
Handover 24 Feb 2025
196 days before
TAMAN WIRA PERMAI 7KPKT 14366-16KlangSelangor264 Jul 20241st sale agreement 4 Jul 2022CCC 4 Jul 2024
Handover 4 Jul 2024
On the deadline
DESA SERI SETIAKPKT 14366-17SepangSelangor451 Nov 20241st sale agreement 1 Nov 2022CCC 27 Jun 2024
Handover 27 Jun 2024
127 days before
TAMAN SERI MENGKUANGKPKT 14366-21Kuala SelangorSelangor7927 Mar 20251st sale agreement 27 Mar 2023CCC 19 Jun 2024
Handover 19 Jun 2024
281 days before
TAMAN SEMARANG INTANKPKT 14366-15SepangSelangor5230 Dec 20231st sale agreement 30 Dec 2021CCC 27 Dec 2023
Handover 27 Dec 2023
3 days before
TAMAN JENJAROM PERMAIKPKT 14366-13Kuala LangatSelangor2221 Oct 20231st sale agreement 21 Oct 2021CCC 25 Oct 2023
Handover 25 Oct 2023
4 days after
TAMAN JENJAROM PERMAIKPKT 14366-14Kuala LangatSelangor2921 Oct 20231st sale agreement 21 Oct 2021CCC 25 Oct 2023
Handover 25 Oct 2023
4 days after
TAMAN KEBUN SETAWAR 1KPKT 14366-12KlangSelangor444 Sep 2023Extended 5 months from 4 Apr 20231st sale agreement 4 Apr 2021CCC 5 Sep 2023
Handover 5 Sep 2023
1 day after
TAMAN BENTARAKPKT 14366-11Kuala LangatSelangor3516 Sep 2023Extended 5 months from 16 Apr 20231st sale agreement 16 Apr 2021CCC 24 Aug 2023
Handover 24 Aug 2023
23 days before
TAMAN AMANAHKPKT 14366-10Kuala LangatSelangor381 Aug 2023Extended 5 months from 1 Mar 20231st sale agreement 1 Mar 2021CCC 7 Jul 2023
Handover 7 Jul 2023
25 days before
TAMAN LANGAT MURNIKPKT 14366-9Kuala LangatSelangor4216 Apr 2023Extended 5 months from 16 Nov 20221st sale agreement 16 Nov 2020CCC 22 Mar 2023
Handover 22 Mar 2023
25 days before
TAMAN BENTARAKPKT 14366-8Kuala LangatSelangor613 Feb 2023Extended 5 months from 3 Sep 20221st sale agreement 3 Sep 2020CCC 16 Dec 2022
Handover 16 Dec 2022
49 days before
TAMAN NAKHODAKPKT 14366-7Kuala LangatSelangor2829 Jul 20221st sale agreement 29 Jul 2020CCC 23 Jun 2022
Handover 24 Jun 2022
35 days before
TAMAN TULIP 4KPKT 14366-6KlangSelangor4522 May 2022Extended 6 months from 22 Nov 20211st sale agreement 22 Nov 2019CCC 25 Jan 2022CCC before deadline; handover not recorded
TAMAN BENTARAKPKT 14366-4Kuala LangatSelangor2212 May 2022Extended 6 months from 12 Nov 20211st sale agreement 12 Nov 2019CCC 30 Nov 2021CCC before deadline; handover not recorded
TAMAN BENTARAKPKT 14366-5Kuala LangatSelangor4412 May 2022Extended 6 months from 12 Nov 20211st sale agreement 12 Nov 2019CCC 23 Aug 2021CCC before deadline; handover not recorded
DESA SERI SETIAKPKT 14366-3SepangSelangor3017 Mar 2022Extended 6 months from 17 Sep 20211st sale agreement 17 Sep 2019CCC 15 Apr 2021CCC before deadline; handover not recorded
KENTING DEVELOPMENT SDN. BHDKPKT 14366-2Kuala LangatSelangor4623 Aug 20191st sale agreement 23 Aug 2017CCC 25 Mar 2019CCC before deadline; handover not recorded
KENTING DEVELOPMENT SDN BHDKPKT 14366-1Kuala LangatSelangor5323 Mar 20181st sale agreement 23 Mar 2016CCC 13 Mar 2018CCC before deadline; handover not recorded

Under construction

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
TAMAN LANGAT UTAMA 3KPKT 14366-29Kuala LangatSelangor40SmoothOn schedule5 Mar 20271st sale agreement 5 Mar 202590%
TAMAN BENTARAKPKT 14366-28Kuala LangatSelangor30SmoothOn schedule22 Mar 20271st sale agreement 22 Mar 202595%
TAMAN SIJANGKANG IDAMANKPKT 14366-34Kuala LangatSelangor27SmoothOn schedule16 Jun 20271st sale agreement 16 Jun 202580–86%
TAMAN SEMARANG INTANKPKT 14366-33SepangSelangor50SmoothOn schedule17 Jun 20271st sale agreement 17 Jun 202571–77%
TAMAN MUTIARA SALAKKPKT 14366-37Taman Mutiara Salak @ Salak Tinggi · on PropertySifuSepangSelangor40SmoothOn schedule28 Mar 20281st sale agreement 28 Mar 202658%
TAMAN LANGAT UTAMA 3KPKT 14366-38Selangor38SmoothOn schedule23 Apr 20281st sale agreement 23 Apr 202662–68%
TAMAN SEMARANG INTANKPKT 14366-40Selangor47SmoothOn schedule16 Jul 20281st sale agreement 16 Jul 202620–32%
DESA SALAK JAYAKPKT 14366-39Selangor48SmoothOn schedule10 Sep 20281st sale agreement 10 Sep 20265–12%
TAMAN LANGAT UTAMA 3KPKT 14366-36Kuala LangatSelangor29SmoothOn schedule19 Sep 20281st sale agreement 19 Sep 202635–40%
VISTA BAYUKPKT 14366-35Hulu LangatSelangor187SmoothOn schedule16 Feb 20291st sale agreement 16 Feb 202635%
TAMAN BAJURIKPKT 14366-41Selangor21SmoothOn schedule—24%

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

Kenting Development at a glance

ListedNo stock-exchange listing found — Kenting Development Sdn Bhd is a private limited company (Sdn Bhd)
Companies in the KPKT registerKENTING DEVELOPMENT SDN. BHD. KPKT 14366

Kenting Development projects on sale on PropertySifu

Taman Melati 4

Shah Alam, Selangor · From RM755,900
KPKT 14366-27: Completed with CCC (2 Dec 2025)
Completed Kenting Development projects nearby (KPKT):
  • TAMAN TULIP 4 — 1.8 km, 2022
  • TAMAN KHALID AL-WALID 2 — 2.0 km, 2025
  • TAMAN SERI MENGKUANG — 2.0 km, 2024

Taman Mutiara Salak @ Salak Tinggi

Sepang, Selangor · From RM580,500
KPKT 14366-37: On schedule · handover deadline 28 Mar 2028
Completed Kenting Development projects nearby (KPKT):
  • DESA SERI SETIA — 0.7 km, 2024
  • TAMAN GEMILANG 2 — 7.0 km, 2026
  • TAMAN LANGAT MURNI — 7.3 km, 2023

Who is Kenting Development? The company behind the projects

KPKT registers 41 housing projects under Kenting Development Sdn Bhd (developer code 14366), all in Selangor and most of them in Kuala Langat, Sepang and Klang districts. Most are terraced-house schemes, some with semi-detached or detached houses; the largest, VISTA BAYU in Hulu Langat (14366-35), has 187 apartment units and is under construction.

Its first completion in the register dates from 2018 and the most recent from July 2026. Of the two Kenting projects on PropertySifu, Taman Melati 4 in Shah Alam (14366-27, 32 terraced houses, registered in Klang district) received its CCC on 2 December 2025, and Taman Mutiara Salak in Sepang (14366-37, 40 houses) is under construction.

We found no annual report, official website or news report about Kenting Development Sdn Bhd; the project figures on this page come from its KPKT records.

Frequently asked questions

Who develops Taman Melati 4, and is it completed?

Kenting Development Sdn Bhd (KPKT developer code 14366). KPKT registers the project as TAMAN MELATI 4 (14366-27): 32 terraced houses in Shah Alam, registered in Klang district, Selangor. The first sale agreement was signed on 16 July 2024 and the handover deadline is 16 July 2026; the CCC is dated 2 December 2025, 226 days before that deadline. The register does not record the handover date.

Who develops Taman Mutiara Salak @ Salak Tinggi, and when is it due?

Kenting Development Sdn Bhd. KPKT registers it as TAMAN MUTIARA SALAK (14366-37): 40 semi-detached and terraced houses in Sepang district. The first sale agreement was signed on 28 March 2026, so the handover deadline under that agreement is 28 March 2028; no extension is recorded. The project is recorded as on schedule (Lancar), with reported construction progress of 58%.

Is Kenting Development a listed company?

No stock-exchange listing was found. Kenting Development Sdn Bhd is a private limited company (Sdn Bhd).

Does Kenting Development have any Sick or Abandoned projects?

No. As at 27 October 2026, the KPKT register classes none of the 41 Kenting Development projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat).

Were Kenting Development's completed projects handed over on time?

KPKT lists 30 completed Kenting projects. Comparing with the extended deadline where an extension was approved, 18 were handed over on or before their deadline and 5 after it, by 1 to 26 days. For the other 7, the CCC is dated before the deadline but the register does not record the handover date. 9 of the 41 projects have deadlines extended with approval, by 5 or 6 months each.

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.