Gamuda Land (Gamuda Berhad)
Gamuda Land is the property division of Bursa Malaysia-listed Gamuda Berhad, with 189 housing projects in the KPKT register under 12 Gamuda companies, three of them 50% joint ventures: 169 completed, 17 under construction (3 classed Sick, 2 Late), 2 not started and 1 with its permit cancelled; none is Abandoned. Its first township, Kota Kemuning, was launched in 1995.
- 189 projects in the KPKT register
- 169 completed
- 17 under construction (of which 3 Sick, 2 Late)
- 2 not yet started
- 1 with the permit cancelled
Has Gamuda Land handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 189 housing projects under 12 Gamuda Land companies in 3 states: 169 completed, 17 under construction (of which 3 Sick, 2 Late), 2 not yet started, 1 with the permit cancelled.
Of the 169 completed projects, 104 have both a handover deadline and a completion date in the register: 23 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 16 handed over or certified complete after that deadline (3 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 65 received the completion certificate before the deadline (handover date not recorded).
16 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 169
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| HORIZON HILLSKPKT 10316-53 | Johor BahruJohor | 25 | 21 Nov 20261st sale agreement 21 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 54 days before |
| HORIZON HILLSKPKT 10316-54 | Johor BahruJohor | 30 | 19 Nov 20261st sale agreement 19 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 52 days before |
| HORIZON HILLSKPKT 10316-55 | Johor BahruJohor | 32 | 21 Nov 20261st sale agreement 21 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 54 days before |
| HORIZON HILLSKPKT 10316-56 | Johor BahruJohor | 76 | 12 Nov 20261st sale agreement 12 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 45 days before |
| HORIZON HILLSKPKT 10316-57 | Johor BahruJohor | 26 | 25 Nov 20261st sale agreement 25 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 58 days before |
| HORIZON HILLSKPKT 10316-58 | Johor BahruJohor | 56 | 22 Nov 20261st sale agreement 22 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 55 days before |
| TAMAN KIAMBANGKPKT 19588-9 | Kuala LangatSelangor | 124 | 26 Feb 20271st sale agreement 26 Feb 2024 | CCC 25 Sep 2026 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-52 | Johor BahruJohor | 68 | 23 Jul 20261st sale agreement 23 Jul 2024 | CCC 15 Jul 2026 Handover 20 Jul 2026 | 3 days before |
| GAMUDA KEMUNINGKPKT 19085-5 | Kuala LangatSelangor | 368 | 4 Aug 20261st sale agreement 4 Aug 2023 | CCC 26 Jun 2026 | CCC before deadline; handover not recorded |
| TAMAN HIJAUANKPKT 19588-7 | Kuala LangatSelangor | 322 | 12 Mar 20261st sale agreement 12 Mar 2023 | CCC 17 Apr 2026 Handover 24 Apr 2026 / 30 Apr 2026 / 8 May 2026 | 43–57 days after |
| DANAU FLORAKPKT 19124-13 | GombakSelangor | 164 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 17 Mar 2026 Handover 15 Apr 2026 | 13 days before |
| HORIZON HILLSKPKT 10316-51 | Johor BahruJohor | 100 | 26 Jan 20261st sale agreement 26 Jan 2024 | CCC 16 Jan 2026 Handover 29 Jan 2026 | 3 days after |
Handed over or certified complete after the deadline — 12 most recent of 16
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN HIJAUANKPKT 19588-7 | Kuala LangatSelangor | 322 | 12 Mar 20261st sale agreement 12 Mar 2023 | CCC 17 Apr 2026 Handover 24 Apr 2026 / 30 Apr 2026 / 8 May 2026 | 43–57 days after |
| HORIZON HILLSKPKT 10316-51 | Johor BahruJohor | 100 | 26 Jan 20261st sale agreement 26 Jan 2024 | CCC 16 Jan 2026 Handover 29 Jan 2026 | 3 days after |
| TAMAN HIJAUANKPKT 19588-6 | Kuala LangatSelangor | 296 | 3 Jan 20261st sale agreement 3 Jan 2023 | CCC 22 Dec 2025 Handover 5 Jan 2026 | 2 days after |
| BANDAR GAMUDA COVEKPKT 19588-3 | Kuala LangatSelangor | 203 | 12 Feb 20241st sale agreement 12 Feb 2021 | CCC 26 Jun 2024 | 135 days after |
| PANGSAPURI MAYAKPKT 19588-2 | Kuala LangatSelangor | 972 | 29 Mar 2024Extended 15 months from 29 Dec 20221st sale agreement 29 Dec 2019 | CCC 2 Feb 2024 Handover 6 Mar 2024 / 14 May 2024 | 46 days after † |
| JADE HILLSKPKT 10709-19 | Hulu LangatSelangor | 28 | 31 Oct 2022Extended 5 months from 31 May 20221st sale agreement 31 May 2020 | CCC 24 Nov 2022 | 24 days after † |
| GAMUDA KEMUNINGKPKT 19085-1 | Kuala LangatSelangor | 279 | 26 Jul 20201st sale agreement 26 Jul 2017 | CCC 21 Sep 2020 | 57 days after † |
| HIGHPARK SUITESKPKT 13950-1HighPark Suites · on PropertySifu | PetalingSelangor | 512 | 25 May 2019Extended 12 months from 25 May 20181st sale agreement 25 May 2015 | CCC 30 Oct 2019 | 158 days after |
| KUNDANG ESTATESKPKT 14542-3 | GombakSelangor | 100 | 21 Mar 20191st sale agreement 21 Mar 2017 | CCC 12 Apr 2019 | 22 days after |
| KUNDANG ESTATESKPKT 14542-2 | GombakSelangor | 66 | 22 Mar 20191st sale agreement 22 Mar 2017 | CCC 31 Mar 2019 | 9 days after |
| JADE HILLSKPKT 10709-14 | Hulu LangatSelangor | 714 | 18 Jan 20191st sale agreement 18 Jan 2016 | CCC 28 Jan 2019 | 10 days after |
| IDAMAN LANTAS SND BHDKPKT 13061-1 | Kuala LumpurWP Kuala Lumpur | 793 | 20 Dec 20161st sale agreement 20 Dec 2013 | CCC 26 Dec 2017 | 371 days after |
Show all 16
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN HIJAUANKPKT 19588-7 | Kuala LangatSelangor | 322 | 12 Mar 20261st sale agreement 12 Mar 2023 | CCC 17 Apr 2026 Handover 24 Apr 2026 / 30 Apr 2026 / 8 May 2026 | 43–57 days after |
| HORIZON HILLSKPKT 10316-51 | Johor BahruJohor | 100 | 26 Jan 20261st sale agreement 26 Jan 2024 | CCC 16 Jan 2026 Handover 29 Jan 2026 | 3 days after |
| TAMAN HIJAUANKPKT 19588-6 | Kuala LangatSelangor | 296 | 3 Jan 20261st sale agreement 3 Jan 2023 | CCC 22 Dec 2025 Handover 5 Jan 2026 | 2 days after |
| BANDAR GAMUDA COVEKPKT 19588-3 | Kuala LangatSelangor | 203 | 12 Feb 20241st sale agreement 12 Feb 2021 | CCC 26 Jun 2024 | 135 days after |
| PANGSAPURI MAYAKPKT 19588-2 | Kuala LangatSelangor | 972 | 29 Mar 2024Extended 15 months from 29 Dec 20221st sale agreement 29 Dec 2019 | CCC 2 Feb 2024 Handover 6 Mar 2024 / 14 May 2024 | 46 days after † |
| JADE HILLSKPKT 10709-19 | Hulu LangatSelangor | 28 | 31 Oct 2022Extended 5 months from 31 May 20221st sale agreement 31 May 2020 | CCC 24 Nov 2022 | 24 days after † |
| GAMUDA KEMUNINGKPKT 19085-1 | Kuala LangatSelangor | 279 | 26 Jul 20201st sale agreement 26 Jul 2017 | CCC 21 Sep 2020 | 57 days after † |
| HIGHPARK SUITESKPKT 13950-1HighPark Suites · on PropertySifu | PetalingSelangor | 512 | 25 May 2019Extended 12 months from 25 May 20181st sale agreement 25 May 2015 | CCC 30 Oct 2019 | 158 days after |
| KUNDANG ESTATESKPKT 14542-3 | GombakSelangor | 100 | 21 Mar 20191st sale agreement 21 Mar 2017 | CCC 12 Apr 2019 | 22 days after |
| KUNDANG ESTATESKPKT 14542-2 | GombakSelangor | 66 | 22 Mar 20191st sale agreement 22 Mar 2017 | CCC 31 Mar 2019 | 9 days after |
| JADE HILLSKPKT 10709-14 | Hulu LangatSelangor | 714 | 18 Jan 20191st sale agreement 18 Jan 2016 | CCC 28 Jan 2019 | 10 days after |
| IDAMAN LANTAS SND BHDKPKT 13061-1 | Kuala LumpurWP Kuala Lumpur | 793 | 20 Dec 20161st sale agreement 20 Dec 2013 | CCC 26 Dec 2017 | 371 days after |
| JADE HILLSKPKT 10709-11 | Hulu LangatSelangor | 366 | 5 Apr 20161st sale agreement 5 Apr 2013 | CCC 2 Dec 2016 | 241 days after |
| JADE HILLSKPKT 10709-12 | Hulu LangatSelangor | 28 | 4 Apr 20161st sale agreement 4 Apr 2014 | CCC 28 Oct 2016 | 207 days after |
| HORIZON HILLSKPKT 10316-26 | Johor BahruJohor | 120 | 1 Aug 20151st sale agreement 1 Aug 2013 | CCC 13 Sep 2015 | 43 days after |
| HARUM INTISARI SDN BHDKPKT 8393-30 | KlangSelangor | 66 | 21 Mar 20151st sale agreement 21 Mar 2013 | CCC 20 Apr 2015 | 30 days after |
Show all 169 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| HORIZON HILLSKPKT 10316-53 | Johor BahruJohor | 25 | 21 Nov 20261st sale agreement 21 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 54 days before |
| HORIZON HILLSKPKT 10316-54 | Johor BahruJohor | 30 | 19 Nov 20261st sale agreement 19 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 52 days before |
| HORIZON HILLSKPKT 10316-55 | Johor BahruJohor | 32 | 21 Nov 20261st sale agreement 21 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 54 days before |
| HORIZON HILLSKPKT 10316-56 | Johor BahruJohor | 76 | 12 Nov 20261st sale agreement 12 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 45 days before |
| HORIZON HILLSKPKT 10316-57 | Johor BahruJohor | 26 | 25 Nov 20261st sale agreement 25 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 58 days before |
| HORIZON HILLSKPKT 10316-58 | Johor BahruJohor | 56 | 22 Nov 20261st sale agreement 22 Nov 2024 | CCC 15 Sep 2026 Handover 28 Sep 2026 | 55 days before |
| TAMAN KIAMBANGKPKT 19588-9 | Kuala LangatSelangor | 124 | 26 Feb 20271st sale agreement 26 Feb 2024 | CCC 25 Sep 2026 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-52 | Johor BahruJohor | 68 | 23 Jul 20261st sale agreement 23 Jul 2024 | CCC 15 Jul 2026 Handover 20 Jul 2026 | 3 days before |
| GAMUDA KEMUNINGKPKT 19085-5 | Kuala LangatSelangor | 368 | 4 Aug 20261st sale agreement 4 Aug 2023 | CCC 26 Jun 2026 | CCC before deadline; handover not recorded |
| TAMAN HIJAUANKPKT 19588-7 | Kuala LangatSelangor | 322 | 12 Mar 20261st sale agreement 12 Mar 2023 | CCC 17 Apr 2026 Handover 24 Apr 2026 / 30 Apr 2026 / 8 May 2026 | 43–57 days after |
| DANAU FLORAKPKT 19124-13 | GombakSelangor | 164 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 17 Mar 2026 Handover 15 Apr 2026 | 13 days before |
| HORIZON HILLSKPKT 10316-51 | Johor BahruJohor | 100 | 26 Jan 20261st sale agreement 26 Jan 2024 | CCC 16 Jan 2026 Handover 29 Jan 2026 | 3 days after |
| TAMAN HIJAUANKPKT 19588-6 | Kuala LangatSelangor | 296 | 3 Jan 20261st sale agreement 3 Jan 2023 | CCC 22 Dec 2025 Handover 5 Jan 2026 | 2 days after |
| DANAU FLORAKPKT 19124-12 | GombakSelangor | 270 | 11 Nov 20251st sale agreement 11 Nov 2022 | CCC 3 Sep 2025 Handover 15 Oct 2025 | 27 days before |
| GAMUDA KEMUNINGKPKT 19085-4 | Kuala LangatSelangor | 156 | 21 Feb 20261st sale agreement 21 Feb 2023 | CCC 9 Jun 2025 Handover 9 Sep 2025 | 165 days before |
| DANAU SIMFONIKPKT 19124-11 | GombakSelangor | 94 | 22 Jul 20251st sale agreement 22 Jul 2022 | CCC 17 Jul 2025 Handover 21 Jul 2025 | 1 day before |
| BANDAR GAMUDA COVEKPKT 19588-5 | Kuala LangatSelangor | 57 | 19 Sep 20251st sale agreement 19 Sep 2022 | CCC 8 Apr 2025 Handover 17 Jul 2025 | 64 days before |
| HORIZON HILLSKPKT 10316-50 | Johor BahruJohor | 105 | 25 Jul 20251st sale agreement 25 Jul 2023 | CCC 15 Dec 2024 Handover 23 Dec 2024 | 214 days before |
| HORIZON HILLSKPKT 10316-49 | Johor BahruJohor | 24 | 5 May 20251st sale agreement 5 May 2023 | CCC 9 Sep 2024 Handover 14 Oct 2024 | 203 days before |
| DANAU MENTARIKPKT 19124-10 | GombakSelangor | 211 | 26 Jul 2024Extended 5 months from 26 Feb 20241st sale agreement 26 Feb 2021 | CCC 4 Jul 2024 Handover 26 Jul 2024 | On the deadline |
| BANDAR GAMUDA COVEKPKT 19588-3 | Kuala LangatSelangor | 203 | 12 Feb 20241st sale agreement 12 Feb 2021 | CCC 26 Jun 2024 | 135 days after |
| BANDAR GAMUDA COVEKPKT 19588-4 | Kuala LangatSelangor | 251 | 27 Oct 20241st sale agreement 27 Oct 2021 | CCC 26 Jun 2024 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-23 | Hulu LangatSelangor | 19 | 25 Sep 20241st sale agreement 25 Sep 2022 | CCC 24 Jun 2024 | CCC before deadline; handover not recorded |
| DANAU MENTARIKPKT 19124-9 | GombakSelangor | 160 | 29 Jun 2024Extended 5 months from 29 Jan 20241st sale agreement 29 Jan 2021 | CCC 12 Jun 2024 | CCC before deadline; handover not recorded |
| PANGSAPURI MAYAKPKT 19588-2 | Kuala LangatSelangor | 972 | 29 Mar 2024Extended 15 months from 29 Dec 20221st sale agreement 29 Dec 2019 | CCC 2 Feb 2024 Handover 6 Mar 2024 / 14 May 2024 | 46 days after † |
| JADE HILLSKPKT 10709-22 | Hulu LangatSelangor | 44 | 18 Jun 20241st sale agreement 18 Jun 2022 | CCC 8 May 2024 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-21 | Hulu LangatSelangor | 18 | 17 Oct 2023Extended 5 months from 17 May 20231st sale agreement 17 May 2021 | CCC 26 Jul 2023 Handover 7 Sep 2023 | 40 days before |
| JADE HILLSKPKT 10709-20 | Hulu LangatSelangor | 91 | 28 Jul 2023Extended 5 months from 28 Feb 20231st sale agreement 28 Feb 2021 | CCC 24 Jul 2023 Handover 28 Jul 2023 | On the deadline |
| DANAU EMBUNKPKT 19124-8 | GombakSelangor | 285 | 22 Jun 2023Extended 11 months from 22 Jul 20221st sale agreement 22 Jul 2019 | CCC 25 May 2023 Handover 6 Jun 2023 | 16 days before |
| BANDAR GAMUDA COVEKPKT 19588-1 | Kuala LangatSelangor | 490 | 1 May 2023Extended 15 months from 31 Jan 20221st sale agreement 31 Jan 2019 | CCC 18 Apr 2023 Handover 19 Apr 2023 | 12 days before |
| DANAU EMBUNKPKT 19124-7 | GombakSelangor | 144 | 29 Mar 2023Extended 11 months from 29 Apr 20221st sale agreement 29 Apr 2019 | CCC 13 Mar 2023 | CCC before deadline; handover not recorded |
| GAMUDA KEMUNINGKPKT 19085-3 | Kuala LangatSelangor | 161 | 7 May 2023Extended 11 months from 7 Jun 20221st sale agreement 7 Jun 2019 | CCC 23 Dec 2022 Handover 20 Jan 2023 | 107 days before |
| GAIA RESIDENSIKPKT 19124-6 | GombakSelangor | 500 | 10 Jan 2023Extended 15 months from 10 Oct 20211st sale agreement 10 Oct 2018 | CCC 24 Nov 2022 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-19 | Hulu LangatSelangor | 28 | 31 Oct 2022Extended 5 months from 31 May 20221st sale agreement 31 May 2020 | CCC 24 Nov 2022 | 24 days after † |
| JADE HILLSKPKT 10709-18 | Hulu LangatSelangor | 104 | 1 Oct 2022Extended 11 months from 31 Oct 20211st sale agreement 31 Oct 2019 | CCC 4 Aug 2022 Handover 19 Aug 2022 | 43 days before |
| GAMUDA KEMUNINGKPKT 19085-2 | Kuala LangatSelangor | 596 | 21 Sep 2022Extended 15 months from 21 Jun 20211st sale agreement 21 Jun 2018 | CCC 1 Aug 2022 Handover 10 Aug 2022 | 42 days before |
| PANGSAPURI ARANDAKPKT 6784-61 | KlangSelangor | 458 | 1 Jul 20221st sale agreement 1 Jul 2019 | CCC 23 May 2022 Handover 8 Jun 2022 | 23 days before |
| GM RESIDENCEKPKT 19484-1 | KlangSelangor | 350 | 14 Mar 2022Extended 6 months from 14 Sep 20211st sale agreement 14 Sep 2018 | CCC 30 Aug 2021 | CCC before deadline; handover not recorded |
| GAMUDA GARDENSKPKT 19124-5 | GombakSelangor | 664 | 18 Oct 20211st sale agreement 18 Oct 2018 | CCC 18 Aug 2021 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-47 | Johor BahruJohor | 20 | 4 Feb 20231st sale agreement 4 Feb 2021 | CCC 2 May 2021 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-48 | Johor BahruJohor | 86 | 13 Mar 20221st sale agreement 13 Mar 2020 | CCC 23 Feb 2021 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-44 | Johor BahruJohor | 60 | 26 Apr 20211st sale agreement 26 Apr 2019 | CCC 16 Nov 2020 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-45 | Johor BahruJohor | 14 | 20 Sep 20211st sale agreement 20 Sep 2019 | CCC 16 Nov 2020 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-46 | Johor BahruJohor | 94 | 13 May 20211st sale agreement 13 May 2019 | CCC 10 Nov 2020 | CCC before deadline; handover not recorded |
| GAMUDA KEMUNINGKPKT 19085-1 | Kuala LangatSelangor | 279 | 26 Jul 20201st sale agreement 26 Jul 2017 | CCC 21 Sep 2020 | 57 days after † |
| GAMUDA GARDENSKPKT 19124-1 | GombakSelangor | 177 | 29 Sep 20201st sale agreement 29 Sep 2017 | CCC 18 Sep 2020 | CCC before deadline; handover not recorded |
| GAMUDA GARDENSKPKT 19124-2 | GombakSelangor | 134 | 16 Oct 20201st sale agreement 16 Oct 2017 | CCC 18 Sep 2020 | CCC before deadline; handover not recorded |
| GAMUDA GARDENSKPKT 19124-3 | GombakSelangor | 125 | 24 Oct 20201st sale agreement 24 Oct 2017 | CCC 18 Sep 2020 | CCC before deadline; handover not recorded |
| GAMUDA GARDENSKPKT 19124-4 | GombakSelangor | 126 | 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 18 Sep 2020 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-17 | Hulu LangatSelangor | 16 | 30 Sep 20201st sale agreement 30 Sep 2018 | CCC 10 Dec 2019 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-42 | Johor BahruJohor | 61 | 8 Oct 20201st sale agreement 8 Oct 2018 | CCC 2 Dec 2019 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-43 | Johor BahruJohor | 62 | 8 Oct 20201st sale agreement 8 Oct 2018 | CCC 26 Nov 2019 | CCC before deadline; handover not recorded |
| HIGHPARK SUITESKPKT 13950-1HighPark Suites · on PropertySifu | PetalingSelangor | 512 | 25 May 2019Extended 12 months from 25 May 20181st sale agreement 25 May 2015 | CCC 30 Oct 2019 | 158 days after |
| HIGHPARK SUITESKPKT 13950-2HighPark Suites · on PropertySifu | PetalingSelangor | 512 | 29 May 20201st sale agreement 29 May 2017 | CCC 30 Oct 2019 | CCC before deadline; handover not recorded |
| KUNDANG ESTATESKPKT 14542-4 | GombakSelangor | 230 | 23 Sep 2021Extended 6 months from 23 Mar 20211st sale agreement 23 Mar 2018 | CCC 4 Oct 2019 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-16 | Hulu LangatSelangor | 81 | 11 Sep 20191st sale agreement 11 Sep 2017 | CCC 19 Jul 2019 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-38 | Johor BahruJohor | 62 | 22 May 20201st sale agreement 22 May 2018 | CCC 14 Apr 2019 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-41 | Johor BahruJohor | 133 | 15 Mar 20201st sale agreement 15 Mar 2018 | CCC 14 Apr 2019 | CCC before deadline; handover not recorded |
| KUNDANG ESTATESKPKT 14542-3 | GombakSelangor | 100 | 21 Mar 20191st sale agreement 21 Mar 2017 | CCC 12 Apr 2019 | 22 days after |
| KUNDANG ESTATESKPKT 14542-2 | GombakSelangor | 66 | 22 Mar 20191st sale agreement 22 Mar 2017 | CCC 31 Mar 2019 | 9 days after |
| JADE HILLSKPKT 10709-14 | Hulu LangatSelangor | 714 | 18 Jan 20191st sale agreement 18 Jan 2016 | CCC 28 Jan 2019 | 10 days after |
| JADE HILLSKPKT 10709-15 | Hulu LangatSelangor | 32 | 23 Jan 20191st sale agreement 23 Jan 2017 | CCC 4 Jan 2019 | CCC before deadline; handover not recorded |
| KUNDANG ESTATESKPKT 14542-1 | GombakSelangor | 56 | 28 Dec 20181st sale agreement 28 Dec 2016 | CCC 29 Nov 2018 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-39 | Johor BahruJohor | 113 | 20 Jun 20191st sale agreement 20 Jun 2017 | CCC 17 Oct 2018 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-40 | Johor BahruJohor | 115 | 8 Sep 20191st sale agreement 8 Sep 2017 | CCC 14 Oct 2018 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-37 | Johor BahruJohor | 25 | 13 Nov 20191st sale agreement 13 Nov 2017 | CCC 18 Sep 2018 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-13 | Hulu LangatSelangor | 16 | 29 Jul 20181st sale agreement 29 Jul 2016 | CCC 4 Jun 2018 | CCC before deadline; handover not recorded |
| IDAMAN LANTAS SND BHDKPKT 13061-1 | Kuala LumpurWP Kuala Lumpur | 793 | 20 Dec 20161st sale agreement 20 Dec 2013 | CCC 26 Dec 2017 | 371 days after |
| HARUM INTISARI SDN BHDKPKT 8393-34 | KlangSelangor | 306 | 18 Apr 20191st sale agreement 18 Apr 2016 | CCC 29 May 2017 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-11 | Hulu LangatSelangor | 366 | 5 Apr 20161st sale agreement 5 Apr 2013 | CCC 2 Dec 2016 | 241 days after |
| JADE HILLSKPKT 10709-12 | Hulu LangatSelangor | 28 | 4 Apr 20161st sale agreement 4 Apr 2014 | CCC 28 Oct 2016 | 207 days after |
| HORIZON HILLSKPKT 10316-21 | Johor BahruJohor | 356 | —1st sale agreement 18 Feb 2014 | CCC 27 Oct 2016 | — |
| HORIZON HILLSKPKT 10316-31 | Johor BahruJohor | 24 | 25 Feb 20171st sale agreement 25 Feb 2014 | CCC 27 Oct 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-27 | Johor BahruJohor | 15 | 21 Jul 20171st sale agreement 21 Jul 2015 | CCC 26 Sep 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-34 | Johor BahruJohor | 60 | 16 Oct 20161st sale agreement 16 Oct 2014 | CCC 10 Aug 2016 | CCC before deadline; handover not recorded |
| HARUM INTISARI SDN BHDKPKT 8393-33 | KlangSelangor | 171 | 11 Sep 20171st sale agreement 11 Sep 2015 | CCC 21 Jul 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-35 | Johor BahruJohor | 78 | 30 Apr 20161st sale agreement 30 Apr 2014 | CCC 27 Apr 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-20 | Johor BahruJohor | 27 | 3 Mar 20161st sale agreement 3 Mar 2014 | CCC 25 Feb 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-29 | Johor BahruJohor | 115 | 11 Apr 20161st sale agreement 11 Apr 2014 | CCC 18 Jan 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-30 | Johor BahruJohor | 121 | 20 Jan 20161st sale agreement 20 Jan 2014 | CCC 17 Jan 2016 | CCC before deadline; handover not recorded |
| BANDAR BOTANICKPKT 8393-32 | KlangSelangor | 64 | 29 Sep 20161st sale agreement 29 Sep 2014 | CCC 13 Jan 2016 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-28 | Johor BahruJohor | 101 | 7 Jan 20161st sale agreement 7 Jan 2014 | CCC 20 Oct 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-32 | Johor BahruJohor | 109 | 22 Oct 20161st sale agreement 22 Oct 2013 | CCC 20 Oct 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-26 | Johor BahruJohor | 120 | 1 Aug 20151st sale agreement 1 Aug 2013 | CCC 13 Sep 2015 | 43 days after |
| HORIZON HILLSKPKT 10316-19 | Johor BahruJohor | 42 | 20 Sep 20151st sale agreement 20 Sep 2013 | CCC 10 Sep 2015 | CCC before deadline; handover not recorded |
| JADE HILLSKPKT 10709-10 | Hulu LangatSelangor | 9 | 31 Oct 20151st sale agreement 31 Oct 2013 | CCC 16 Jul 2015 | CCC before deadline; handover not recorded |
| HARUM INTISARI SDN BHDKPKT 8393-28 | KlangSelangor | 37 | 5 Feb 20161st sale agreement 5 Feb 2014 | CCC 17 Jun 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-24 | Johor BahruJohor | 76 | 1 Jul 20151st sale agreement 1 Jul 2013 | CCC 11 Jun 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-25 | Johor BahruJohor | 112 | 13 Aug 20151st sale agreement 13 Aug 2013 | CCC 11 Jun 2015 | CCC before deadline; handover not recorded |
| HARUM INTISARI SDN BHDKPKT 8393-30 | KlangSelangor | 66 | 21 Mar 20151st sale agreement 21 Mar 2013 | CCC 20 Apr 2015 | 30 days after |
| BANDAR BOTANICKPKT 8393-31 | KlangSelangor | 8 | 29 Sep 20161st sale agreement 29 Sep 2014 | CCC 20 Apr 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-23 | Johor BahruJohor | 183 | 16 Apr 20151st sale agreement 16 Apr 2013 | CCC 9 Apr 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-17 | Johor BahruJohor | 7 | 11 Apr 20151st sale agreement 11 Apr 2013 | CCC 25 Mar 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-22 | Johor BahruJohor | 13 | 2 May 20151st sale agreement 2 May 2013 | CCC 25 Mar 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-18 | Johor BahruJohor | 104 | 25 Mar 20151st sale agreement 25 Mar 2013 | CCC 17 Mar 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-16 | Johor BahruJohor | 92 | 5 Feb 20151st sale agreement 5 Feb 2013 | CCC 5 Jan 2015 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-14 | Johor BahruJohor | 123 | 15 Jan 20151st sale agreement 15 Jan 2013 | CCC 24 Dec 2014 | CCC before deadline; handover not recorded |
| MADGE MANSIONSKPKT 11071-1 | Kuala LumpurWP Kuala Lumpur | 52 | 31 Jul 20151st sale agreement 31 Jul 2012 | CCC 22 Dec 2014 | CCC before deadline; handover not recorded |
| BANDAR BOTANICKPKT 8393-24 | KlangSelangor | 680 | 6 Mar 20151st sale agreement 6 Mar 2013 | CCC 27 Oct 2014 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-13 | Johor BahruJohor | 126 | 3 Sep 20141st sale agreement 3 Sep 2012 | CCC 26 Aug 2014 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-11 | Johor BahruJohor | 20 | 1 Oct 20141st sale agreement 1 Oct 2012 | CCC 18 Aug 2014 | CCC before deadline; handover not recorded |
| HARUM INTISARI SDN BHDKPKT 8393-27 | KlangSelangor | 35 | 13 Jul 20151st sale agreement 13 Jul 2013 | CCC 7 Aug 2014 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-12 | Johor BahruJohor | 24 | 25 Feb 20151st sale agreement 25 Feb 2013 | CCC 4 Aug 2014 | CCC before deadline; handover not recorded |
| HARUM INTISARI SDN BHDKPKT 8393-29 | KlangSelangor | 55 | 21 Jan 20151st sale agreement 21 Jan 2013 | CCC 25 Jul 2014 | CCC before deadline; handover not recorded |
| HORIZON HILLSKPKT 10316-8 | Johor BahruJohor | 88 | — | CCC 8 Jul 2014 | — |
| HORIZON HILLSKPKT 10316-5 | Johor BahruJohor | 240 | — | CCC 24 Feb 2014 | — |
| HARUM INTISARI SDN BHDKPKT 8393-25 | KlangSelangor | 27 | — | CCC 11 Feb 2014 | — |
| HARUM INTISARI SDN BHDKPKT 8393-26 | KlangSelangor | 60 | — | CCC 11 Feb 2014 | — |
| BANDAR BOTANICKPKT 8393-23 | KlangSelangor | 70 | — | CCC 29 Jan 2014 | — |
| HORIZON HILLS (FASA 1B1 & 1C)KPKT 10316-2 | Johor BahruJohor | 350 | — | CCC 16 Jan 2014 | — |
| HORIZON HILLSKPKT 10316-7 | Johor BahruJohor | 177 | — | CCC 13 Jan 2014 | — |
| HORIZON HILLSKPKT 10316-9 | Johor BahruJohor | 66 | — | CCC 30 Oct 2013 | — |
| JADE HILLSKPKT 10709-9 | Hulu LangatSelangor | 27 | — | CCC 23 Oct 2013 | — |
| HORIZON HILLSKPKT 10316-6 | Johor BahruJohor | 41 | — | CCC 30 Sep 2013 | — |
| HORIZON HILLSKPKT 10316-10 | Johor BahruJohor | 18 | — | CCC 24 Sep 2013 | — |
| JADE HILLSKPKT 10709-7 | Hulu LangatSelangor | 62 | — | CCC 19 Sep 2013 | — |
| BANDAR BOTANICKPKT 8393-22 | KlangSelangor | 240 | — | CCC 29 Jul 2013 | — |
| BANDAR BOTANICKPKT 8393-21 | KlangSelangor | 148 | — | CCC 24 Jul 2013 | — |
| JADE HILLSKPKT 10709-8 | Hulu LangatSelangor | 112 | — | CCC 4 Jun 2013 | — |
| BANDAR BOTANICKPKT 8393-18 | KlangSelangor | 104 | — | CCC 18 Apr 2013 | — |
| BANDAR BOTANICKPKT 8393-20 | KlangSelangor | 236 | — | CCC 25 Mar 2013 | — |
| LAGOON RESIDENCESKPKT 6784-59 | KlangSelangor | 56 | — | CCC 6 Nov 2012 | — |
| LAGOON SUITESKPKT 6784-60 | KlangSelangor | 176 | — | CCC 6 Nov 2012 | — |
| HORIZON HILL (2B (EXPAT VILLAGE)KPKT 10316-4 | Johor BahruJohor | 82 | — | CCC 25 Sep 2012 | — |
| RP9-3 LAGOON SUITESKPKT 6784-58 | KlangSelangor | 174 | — | CCC 6 Sep 2012 | — |
| BANDAR BOTANICKPKT 8393-17 | KlangSelangor | 169 | — | CCC 17 Jul 2012 | — |
| JADE HILLSKPKT 10709-6 | Hulu LangatSelangor | 20 | — | CCC 5 Jul 2012 | — |
| BANDAR BOTANICKPKT 8393-16 | KlangSelangor | 174 | — | CCC 3 Jul 2012 | — |
| BANDAR BOTANICKPKT 8393-15 | KlangSelangor | 227 | — | CCC 11 Jun 2012 | — |
| BANDAR BOTANICKPKT 8393-19 | KlangSelangor | 10 | — | CCC 11 Jun 2012 | — |
| JADE HILLSKPKT 10709-4 | Hulu LangatSelangor | 20 | — | CCC 6 Jun 2012 | — |
| VALENCIA DEVELOPMENT SDN BHDKPKT 8318-17 | GombakSelangor | 66 | — | CCC 1 Jun 2012 | — |
| HORIZON HILLS 1B(SOUTHERN GOLF)KPKT 10316-3 | Johor BahruJohor | 237 | — | CCC 8 May 2012 | — |
| JADE HILLSKPKT 10709-5 | Hulu LangatSelangor | 23 | — | CCC 26 Apr 2012 | — |
| VALENCIA DEVELOPMENT SDN BHDKPKT 8318-16 | GombakSelangor | 13 | — | CCC 19 Apr 2012 | — |
| BANDAR BOTANIC FASA 15CKPKT 8393-10 | KlangSelangor | 58 | — | CFO 28 Dec 2011 | — |
| JADE HILLSKPKT 10709-3 | Hulu LangatSelangor | 37 | — | CCC 19 Oct 2011 | — |
| BANDAR BOTANICKPKT 8393-14 | KlangSelangor | 150 | — | CCC 7 Sep 2011 | — |
| HARUM INTISARIKPKT 8393-13 | PetalingSelangor | 179 | — | CCC 5 Sep 2011 | — |
| JADE HILLSKPKT 10709-2 | Hulu LangatSelangor | 41 | — | CCC 12 Jul 2011 | — |
| VALENCIAKPKT 8318-14 | GombakSelangor | 45 | — | CCC 7 Jul 2011 | — |
| LAGOON VILLASKPKT 6784-52 | KlangSelangor | 125 | — | CFO 4 Jul 2011 | — |
| 92203KPKT 6784-57 | KlangSelangor | 14 | — | CCC 6 Sep 2010 | — |
| -KPKT 6784-55 | KlangSelangor | 24 | — | CFO 19 Jul 2010 | — |
| JADE HILLSKPKT 10709-1 | Hulu LangatSelangor | 90 | 2 Jan 20111st sale agreement 2 Jan 2009 | CCC 14 Jun 2010 | CCC before deadline; handover not recorded |
| VALENCIA - THE PAVILLANSKPKT 8318-13 | GombakSelangor | 32 | — | CCC 13 Apr 2010 | — |
| LOT91971 RP5CKPKT 6784-54 | KlangSelangor | 25 | — | CFO 18 Jan 2010 | — |
| BANDAR BOTANICKPKT 8393-8 | KlangSelangor | 500 | — | CFO 24 Dec 2009 | — |
| LAGOON TERRACESKPKT 6784-50 | KlangSelangor | 383 | — | CFO 7 Dec 2009 | — |
| LAKESIDE TERRACES 2KPKT 6784-51 | KlangSelangor | 117 | — | CFO 25 Nov 2009 | — |
| HARUM INTISARI SDN BHDKPKT 8393-12 | PetalingSelangor | 14 | — | CCC 19 Nov 2009 | — |
| BANDAR BOTANIC FASA 19KPKT 8393-11 | KlangSelangor | 182 | — | CFO 2 Nov 2009 | — |
| HORIZON HILLS (FASA 1A)KPKT 10316-1 | Johor BahruJohor | 475 | — | CCC 19 Oct 2009 | — |
| VALENCIA - URBAN VILLASKPKT 8318-12 | GombakSelangor | 55 | — | CCC 7 Oct 2009 | — |
| VALENCIA FASA 4DKPKT 8318-9 | GombakSelangor | 45 | — | CFO 29 Jun 2009 | — |
| LOT 70822 & 99628KPKT 6784-53 | KlangSelangor | 20 | — | CFO 12 May 2009 | — |
| VALENCIAKPKT 8318-10 | GombakSelangor | 18 | — | CFO 15 Aug 2008 | — |
| VALENCIAKPKT 8318-11 | GombakSelangor | 28 | — | CFO 24 Apr 2008 | — |
| BANDAR BOTANICKPKT 8393-9 | KlangSelangor | 15 | — | CFO 7 Mar 2008 | — |
| KOTA KEMUNING HILLSKPKT 6784-47 | KlangSelangor | 142 | — | CFO 7 Nov 2007 | — |
| VALENCIA FASA 4BKPKT 8318-6 | GombakSelangor | 12 | — | CFO 12 Sep 2007 | — |
| VALENCIA FASA 2GKPKT 8318-7 | GombakSelangor | 21 | — | CFO 27 Jul 2007 | — |
| VALENCIA FASA 3CKPKT 8318-8 | GombakSelangor | 28 | — | CFO 27 Jul 2007 | — |
| LAKESIDE TERRACESKPKT 6784-49 | KlangSelangor | 125 | — | CFO 9 Feb 2007 | — |
| MERANTI TERRACEKPKT 6784-44 | KlangSelangor | 162 | — | CFO 2 Jun 2006 | — |
| CANAL GARDENSKPKT 6784-48 | KlangSelangor | 602 | — | CFO 2 Jun 2006 | — |
| RANDA APARTMENTKPKT 6784-45 | KlangSelangor | 340 | — | CFO 26 Jan 2006 | — |
| THE LAKES CONDOKPKT 6784-43 | KlangSelangor | 160 | — | CFO 25 Jan 2006 | — |
| BANDAR BOTANICKPKT 8393-7 | KlangSelangor | 680 | — | CFO 28 Jul 2005 | — |
Under construction (17) and not yet started (2) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN BAYU RIMBA, BANDAR GAMUDA COVEKPKT 19588-8 | Kuala LangatSelangor | 300 | SickSick | 27 Sep 20261st sale agreement 27 Sep 2023 | 98% |
| KIRANAKPKT 14542-5 | GombakSelangor | 215 | SickSick | 25 Oct 20261st sale agreement 25 Oct 2024 | 96% |
| KIRANAKPKT 14542-6 | GombakSelangor | 286 | SickSick | 25 Oct 20261st sale agreement 25 Oct 2024 | 96% |
| QUAYSIDE PLAZAKPKT 19085-6 | Kuala LangatSelangor | 465 | SmoothOn schedule | 31 Jan 20271st sale agreement 31 Jan 2024 | 93–98% |
| HORIZON HILLSKPKT 10316-59 | Johor | 85 | SmoothOn schedule | 18 Feb 20271st sale agreement 18 Feb 2025 | 98% |
| TAMAN BAYU RIMBAKPKT 19588-10 | Kuala LangatSelangor | 324 | DelayLate | 29 Apr 20271st sale agreement 29 Apr 2024 | 23–70% |
| PANGSAPURI RIMBA UTARA RESIDENSIKPKT 19588-11 | Kuala LangatSelangor | 462 | DelayLate | 29 Apr 20271st sale agreement 29 Apr 2024 | 67–75% |
| HORIZON HILLSKPKT 10316-60 | Johor | 52 | SmoothOn schedule | 21 May 20271st sale agreement 21 May 2025 | 88–89% |
| HORIZON HILLSKPKT 10316-61 | Johor | 54 | SmoothOn schedule | 26 Oct 20271st sale agreement 26 Oct 2025 | 56–57% |
| TAMAN CENGKIHKPKT 19588-13 | Kuala LangatSelangor | 242 | SmoothOn schedule | 28 Jan 20281st sale agreement 28 Jan 2025 | 55–56% |
| HORIZON HILLSKPKT 10316-62 | Johor | 54 | SmoothOn schedule | 2 May 20281st sale agreement 2 May 2026 | 23–35% |
| DANAU CENGKIHKPKT 19124-14 | GombakSelangor | 172 | SmoothOn schedule | 14 May 20281st sale agreement 14 May 2025 | 50–65% |
Show all 19 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN BAYU RIMBA, BANDAR GAMUDA COVEKPKT 19588-8 | Kuala LangatSelangor | 300 | SickSick | 27 Sep 20261st sale agreement 27 Sep 2023 | 98% |
| KIRANAKPKT 14542-5 | GombakSelangor | 215 | SickSick | 25 Oct 20261st sale agreement 25 Oct 2024 | 96% |
| KIRANAKPKT 14542-6 | GombakSelangor | 286 | SickSick | 25 Oct 20261st sale agreement 25 Oct 2024 | 96% |
| QUAYSIDE PLAZAKPKT 19085-6 | Kuala LangatSelangor | 465 | SmoothOn schedule | 31 Jan 20271st sale agreement 31 Jan 2024 | 93–98% |
| HORIZON HILLSKPKT 10316-59 | Johor | 85 | SmoothOn schedule | 18 Feb 20271st sale agreement 18 Feb 2025 | 98% |
| TAMAN BAYU RIMBAKPKT 19588-10 | Kuala LangatSelangor | 324 | DelayLate | 29 Apr 20271st sale agreement 29 Apr 2024 | 23–70% |
| PANGSAPURI RIMBA UTARA RESIDENSIKPKT 19588-11 | Kuala LangatSelangor | 462 | DelayLate | 29 Apr 20271st sale agreement 29 Apr 2024 | 67–75% |
| HORIZON HILLSKPKT 10316-60 | Johor | 52 | SmoothOn schedule | 21 May 20271st sale agreement 21 May 2025 | 88–89% |
| HORIZON HILLSKPKT 10316-61 | Johor | 54 | SmoothOn schedule | 26 Oct 20271st sale agreement 26 Oct 2025 | 56–57% |
| TAMAN CENGKIHKPKT 19588-13 | Kuala LangatSelangor | 242 | SmoothOn schedule | 28 Jan 20281st sale agreement 28 Jan 2025 | 55–56% |
| HORIZON HILLSKPKT 10316-62 | Johor | 54 | SmoothOn schedule | 2 May 20281st sale agreement 2 May 2026 | 23–35% |
| DANAU CENGKIHKPKT 19124-14 | GombakSelangor | 172 | SmoothOn schedule | 14 May 20281st sale agreement 14 May 2025 | 50–65% |
| AMBANG RESIDENSIKPKT 19484-2 | KlangSelangor | 618 | SmoothOn schedule | 29 Aug 20281st sale agreement 29 Aug 2025 | 20% |
| HORIZON HILLSKPKT 10316-63 | Johor | 74 | SmoothOn schedule | 19 Sep 20281st sale agreement 19 Sep 2026 | 20–22% |
| DANAU SUTERAKPKT 19124-15 | GombakSelangor | 237 | SmoothOn schedule | 5 Dec 20281st sale agreement 5 Dec 2025 | 45–48% |
| GAMUDA KEMUNING 25.7KPKT 19085-7 | Kuala LangatSelangor | 300 | SmoothOn schedule | 25 Jan 20291st sale agreement 25 Jan 2026 | 16–54% |
| TAMAN KIAMBANGKPKT 19588-14 | Kuala LangatSelangor | 34 | SmoothOn schedule | 25 Jun 20291st sale agreement 25 Jun 2026 | 66–75% |
| HORIZON HILLSKPKT 10316-33 | Johor BahruJohor | 68 | Not startedNot started | — | 0% |
| HORIZON HILLSKPKT 10316-36 | Johor BahruJohor | 105 | Not startedNot started | — | 0% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN KIAMBANGKPKT 19588-12 | Kuala LangatSelangor | 50 | Permit cancelledPermit cancelled | — | 2–12% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Gamuda Land at a glance
| Listed | Bursa Malaysia Main Market · GAMUDA (5398) · listed 10 August 1992 (Gamuda Berhad)[2][6][7] |
|---|---|
| Started | 6 October 1976 in Ipoh, Perak (Gamuda Berhad); Gamuda Land's first township, Kota Kemuning, in 1995[2] |
| Head office | Menara Gamuda, Bandar Damansara Perdana, Petaling Jaya, Selangor[1] |
| Leadership | Tan Sri Dato' Setia Haji Ambrin bin Buang — Independent Non-Executive Chairman, Gamuda Berhad[4] Dato' Lin Yun Ling — Group Managing Director (on the board as managing director since 10 February 1981)[4] Gim Teck Yew — Chief Executive Officer, Gamuda Land (since 2025)[5] |
| Companies in the KPKT register | GAMUDA LAND (BOTANIC) SDN. BHD. KPKT 8393[1] GAMUDA LAND (BOTANIC) SDN. BHD. KPKT 14542[1] BANDAR SERAI DEVELOPMENT SDN. BHD. KPKT 19124[1] GAMUDA LAND (T12) SDN. BHD. KPKT 19588[1] VALENCIA DEVELOPMENT SDN. BHD KPKT 8318[1] GAMUDA LAND (KEMUNING) SDN. BHD. KPKT 19085[1] HIGHPARK DEVELOPMENT SDN. BHD. KPKT 13950[1] IDAMAN ROBERTSON SDN. BHD. KPKT 13061[1] JADE HOMES SDN. BHD. KPKT 10709[1] MADGE MANSIONS SDN. BHD. KPKT 11071[1] HORIZON HILLS DEVELOPMENT SDN. BHD. (50%) KPKT 10316[1][9] HICOM-GAMUDA DEVELOPMENT SDN. BHD. (50%) KPKT 6784[1] GAMUDA GM KLANG SDN. BHD. (50%) KPKT 19484[1] |
| Website | gamudaland.com.my |
| Property since | 1995, with the 1,854-acre Kota Kemuning township in Selangor[2] |
| Land bank (company figure) | 2,414 acres in total, with RM61 billion of remaining gross development value across Malaysia, Vietnam, Australia and the UK (Integrated Report 2025)[3] |
| Townships in Malaysia | Kota Kemuning (1995), Valencia (2000), Bandar Botanic (2001), Horizon Hills (2007), Jade Hills (2008), Gamuda Gardens and twentyfive.7 (2017), Gamuda Cove (2018)[2] |
| Joint ventures counted here | Horizon Hills Development (50:50 with UEM Sunrise), Hicom-Gamuda Development (Kota Kemuning, 50%), Gamuda GM Klang (50%)[1][9] |
Gamuda Land projects on sale on PropertySifu
Who is Gamuda Land? The company behind the projects
Gamuda Berhad was incorporated as a private limited company in Ipoh, Perak, on 6 October 1976, and was listed on the Main Board of the Kuala Lumpur Stock Exchange, now Bursa Malaysia, on 10 August 1992 [2]. It is an engineering, property and infrastructure group whose registered office and principal place of business is Menara Gamuda in Bandar Damansara Perdana, Petaling Jaya [1]. Dato' Lin Yun Ling, on the board as managing director since 10 February 1981, is the Group Managing Director, and the chairman is Tan Sri Dato' Setia Haji Ambrin bin Buang [4]. Gim Teck Yew became chief executive officer of Gamuda Land in 2025 [5].
Gamuda Land launched its first integrated township, the 1,854-acre Kota Kemuning in Selangor, in 1995 [2]. Its later Malaysian townships include Valencia in Sungai Buloh (2000), Bandar Botanic in Klang (2001), Horizon Hills in Iskandar Puteri, Johor (2007), Jade Hills in Kajang (2008), Gamuda Gardens in Sungai Buloh and twentyfive.7 in Kota Kemuning (both 2017) and Gamuda Cove in the southern Klang Valley (2018) [2]. The company says its total land bank was 2,414 acres, with RM61 billion of remaining gross development value across Malaysia, Vietnam, Australia and the UK, in its 2025 integrated report [3]. These are group-wide figures; the KPKT register used here has no Sabah or overseas records, so Bukit Bantayan Residences in Kota Kinabalu and the overseas projects are not in the table above.
According to Gamuda's 2025 annual report, Gamuda Land (Botanic), Valencia Development, Jade Homes, Madge Mansions, Highpark Development, Idaman Robertson, Gamuda Land (Kemuning), Bandar Serai Development (Gamuda Gardens) and Gamuda Land (T12) (Gamuda Cove) are wholly owned [1]. Three of the companies counted here are 50% joint ventures: Horizon Hills Development, shared 50:50 with UEM Sunrise [1][9]; Hicom-Gamuda Development, which develops Kota Kemuning; and Gamuda GM Klang, which develops a wholesale hub at GM Klang Wholesale City in Bandar Botanic [1]. Horizon Hills is counted on this page and not on the UEM Sunrise page.
HighPark Suites in Kelana Jaya, Petaling Jaya, was launched in 2015 [2]. It is developed by Highpark Development Sdn Bhd, a wholly owned Gamuda subsidiary [1].
Frequently asked questions
Is Gamuda Land a listed company?
Gamuda Land is the property division of Gamuda Berhad, which has been listed since 10 August 1992 and trades on Bursa Malaysia's Main Market under stock code 5398 [2][6]. The housing projects on this page are registered under Gamuda subsidiaries and joint-venture companies, not under a separately listed Gamuda Land.
How many housing projects has Gamuda completed, and were they handed over on time?
In the KPKT register, 169 of the 189 housing projects under 12 Gamuda companies are completed. Of the 104 completed projects that have both a deadline and a completion date in the register, 23 were handed over on or before the deadline (for projects with an approved extension, the extended deadline), 16 were handed over or certified complete after it — 3 of these were under construction during the 18 March–31 August 2020 movement control period — and 65 received the completion certificate before the deadline, with no handover date recorded. The other 65 completed projects have no deadline or completion date to compare.
Does Gamuda have any Sick, Late or Abandoned projects?
None is classed Abandoned (Terbengkalai). As at 27 October 2026, the KPKT register classes 3 of the 17 projects under construction as Sick (Sakit): two Kirana registrations by Gamuda Land (Botanic), 14542-5 and 14542-6 (215 and 286 terrace houses, first sale agreements 25 October 2024, deadline 25 October 2026, reported progress 95.5%), and 19588-8 by Gamuda Land (T12) in Gamuda Cove (300 terrace houses, first sale agreement 27 September 2023, deadline 27 September 2026, reported progress 97.5%). Two more, 19588-10 and 19588-11 (324 and 462 units, deadline 29 April 2027), are classed Late (Lewat). One registration, 19588-12, has the status Permit Telah Dibatalkan (permit cancelled), and two Horizon Hills registrations, 10316-33 and 10316-36, are not yet started (Belum Mula).
Which company develops HighPark Suites, and was it handed over on time?
Highpark Development Sdn Bhd (KPKT developer code 13950), wholly owned by Gamuda according to its 2025 annual report [1]. KPKT registers two phases of 512 units each. 13950-1 (first sale agreement 25 May 2015) had a deadline of 25 May 2018, extended with approval by 12 months to 25 May 2019; its CCC is dated 30 October 2019, 158 days after the extended deadline. 13950-2 (first sale agreement 29 May 2017) had a deadline of 29 May 2020 and received its CCC on the same date, 30 October 2019, 212 days before the deadline. The register does not record handover dates for either phase.
Is Horizon Hills a Gamuda project?
Yes, as a joint venture. Horizon Hills Development Sdn Bhd is owned 50:50 by Gamuda and UEM Sunrise [1][9], and Gamuda Land launched the 1,228-acre township in Iskandar Puteri, Johor, in 2007 [2]. This page counts its 62 KPKT registrations — 55 completed, 5 under construction and 2 not started — under Gamuda; the UEM Sunrise page does not count them, so they are not counted twice.
Are Gamuda's projects in Sabah and overseas in this record?
No. The KPKT register used here has no Sabah or overseas records, so Bukit Bantayan Residences in Kota Kinabalu — Gamuda Land's entry into East Malaysia in 2016 [2] — and its projects in Vietnam, Singapore, Australia and the UK [1] are not in the table. The 2,414-acre land bank the company reports covers Malaysia, Vietnam, Australia and the UK [3].
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Gamuda Berhad Integrated Report 2025 — Financial Statements (note 1, corporate information; note 17, subsidiaries, printed pp. 233–234; note 19, joint arrangements, printed pp. 248–250) · Gamuda Berhad · 15 Oct 2025 · accessed 28 Oct 2026
https://gamuda.listedcompany.com/misc/Finanacial_Statements_2025.pdf - [2] Milestones · Gamuda Berhad · accessed 28 Oct 2026
https://gamuda.com/who-we-are/milestones/ - [3] Gamuda Berhad Integrated Report 2025 — Overview (Who we are; business highlights) · Gamuda Berhad · 2025-11 · accessed 28 Oct 2026
https://gamuda.listedcompany.com/misc/Gamuda_2025_Overview.pdf - [4] The Gamuda Board of Directors · Gamuda Berhad · accessed 28 Oct 2026
https://gamuda.com/who-we-are/board-of-directors/ - [5] Senior Management · Gamuda Berhad · accessed 28 Oct 2026
https://gamuda.com/who-we-are/senior-management/ - [6] Stock Information (Bursa symbol 5398) · Gamuda Berhad Investor Relations · accessed 28 Oct 2026
https://gamuda.listedcompany.com/stock_information.html - [7] 金务大年度净利连续第二年突破10亿 订单总额达610亿 · The Edge Malaysia(中文) · 29 Sep 2026 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/819829 - [8] 连5年刷新纪录 金务大全年净赚10.5亿 · 中国报 · 29 Sep 2026 · accessed 28 Oct 2026
https://www.chinapress.com.my/20260929/%E8%BF%9E5%E5%B9%B4%E5%88%B7%E6%96%B0%E7%BA%AA%E5%BD%95-%E9%87%91%E5%8A%A1%E5%A4%A7%E5%85%A8%E5%B9%B4%E5%87%80%E8%B5%9A10-5%E4%BA%BF/ - [9] UEM Sunrise Berhad Integrated Annual Report 2025 (active JVs and associates: Horizon Hills Development Sdn Bhd) · UEM Sunrise Berhad · 2026-04 · accessed 28 Oct 2026
https://www.uemsunrise.com/storage/files/spread-uem-sunrise-iar2025-xWmUKaNr.pdf#page=7
Last updated 28 Oct 2026