Lum Chang (Lum Chang Holdings Limited)
Lum Chang Holdings Limited is a Singapore construction and property group listed on the SGX Mainboard (L19). Its three wholly owned Malaysian companies, mainly Fabulous Range Sdn Bhd, have 20 housing projects in the KPKT register, all in Selangor: 19 completed and 1 under construction, none classed Sick or Abandoned, mostly Twin Palms phases in Sungai Long and Kemensah.
- 20 projects in the KPKT register
- 19 completed
- 1 under construction
- None Sick or Abandoned
Has Lum Chang handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 20 housing projects under 3 Lum Chang companies in 1 state: 19 completed, 1 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 19 completed projects, 13 have both a handover deadline and a completion date in the register: 2 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 6 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 5 received the completion certificate before the deadline (handover date not recorded).
3 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 19
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| INDICAKPKT 10443-14 | Hulu LangatSelangor | 34 | 8 Apr 20261st sale agreement 8 Apr 2024 | CCC 20 Apr 2026 | 12 days after |
| INDICA BUNGALOWKPKT 10443-13 | Hulu LangatSelangor | 24 | 27 May 20251st sale agreement 27 May 2023 | CCC 24 Apr 2025 Handover 25 Apr 2025 | 32 days before |
| FABULOUS RANGE SDN BHDKPKT 10443-12 | Hulu LangatSelangor | 24 | 1 Dec 20241st sale agreement 1 Dec 2022 | CCC 27 Nov 2024 Handover 27 Nov 2024 | 4 days before |
| WESTIARAKPKT 10443-8 | Hulu LangatSelangor | 19 | 26 Nov 2021Extended 12 months from 26 Nov 20201st sale agreement 26 Nov 2018 | CCC 17 May 2022 | 172 days after † |
| LATANIA PH4A2(A)KPKT 10443-10 | Hulu LangatSelangor | 16 | 7 Apr 2022Extended 6 months from 7 Oct 20211st sale agreement 7 Oct 2019 | CCC 12 Jan 2022 | CCC before deadline; handover not recorded |
| LATANIA PH4A2(B)KPKT 10443-11 | Hulu LangatSelangor | 5 | 11 Dec 2023Extended 6 months from 11 Jun 20231st sale agreement 11 Jun 2021 | CCC 12 Jan 2022 | CCC before deadline; handover not recorded |
| LATANIAKPKT 10443-7Twin Palms - Latania II · on PropertySifu | Hulu LangatSelangor | 28 | 3 Jul 20191st sale agreement 3 Jul 2017 | CCC 18 Dec 2019 | 168 days after |
| SUTERA BAYUKPKT 10443-9 | Hulu LangatSelangor | 130 | 18 Jul 20201st sale agreement 18 Jul 2017 | CCC 23 Oct 2019 | CCC before deadline; handover not recorded |
| CALYPSOKPKT 11062-3 | GombakSelangor | 45 | 10 Jan 20161st sale agreement 10 Jan 2014 | CCC 23 Dec 2015 | CCC before deadline; handover not recorded |
| FABULOUS RANGE SDN BHDKPKT 10443-5 | Hulu LangatSelangor | 28 | 8 Jul 20151st sale agreement 8 Jul 2013 | CCC 15 Dec 2015 | 160 days after |
| SIERRAKPKT 10443-6 | Hulu LangatSelangor | 37 | 11 Nov 20151st sale agreement 11 Nov 2013 | CCC 15 Dec 2015 | 34 days after |
| VENUS CAPITAL CORPORATION SDN BHDKPKT 11062-2 | GombakSelangor | 40 | 8 Apr 20141st sale agreement 8 Apr 2012 | CCC 11 Feb 2015 | 309 days after |
Handed over or certified complete after the deadline (6)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| INDICAKPKT 10443-14 | Hulu LangatSelangor | 34 | 8 Apr 20261st sale agreement 8 Apr 2024 | CCC 20 Apr 2026 | 12 days after |
| WESTIARAKPKT 10443-8 | Hulu LangatSelangor | 19 | 26 Nov 2021Extended 12 months from 26 Nov 20201st sale agreement 26 Nov 2018 | CCC 17 May 2022 | 172 days after † |
| LATANIAKPKT 10443-7Twin Palms - Latania II · on PropertySifu | Hulu LangatSelangor | 28 | 3 Jul 20191st sale agreement 3 Jul 2017 | CCC 18 Dec 2019 | 168 days after |
| FABULOUS RANGE SDN BHDKPKT 10443-5 | Hulu LangatSelangor | 28 | 8 Jul 20151st sale agreement 8 Jul 2013 | CCC 15 Dec 2015 | 160 days after |
| SIERRAKPKT 10443-6 | Hulu LangatSelangor | 37 | 11 Nov 20151st sale agreement 11 Nov 2013 | CCC 15 Dec 2015 | 34 days after |
| VENUS CAPITAL CORPORATION SDN BHDKPKT 11062-2 | GombakSelangor | 40 | 8 Apr 20141st sale agreement 8 Apr 2012 | CCC 11 Feb 2015 | 309 days after |
Show all 19 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| INDICAKPKT 10443-14 | Hulu LangatSelangor | 34 | 8 Apr 20261st sale agreement 8 Apr 2024 | CCC 20 Apr 2026 | 12 days after |
| INDICA BUNGALOWKPKT 10443-13 | Hulu LangatSelangor | 24 | 27 May 20251st sale agreement 27 May 2023 | CCC 24 Apr 2025 Handover 25 Apr 2025 | 32 days before |
| FABULOUS RANGE SDN BHDKPKT 10443-12 | Hulu LangatSelangor | 24 | 1 Dec 20241st sale agreement 1 Dec 2022 | CCC 27 Nov 2024 Handover 27 Nov 2024 | 4 days before |
| WESTIARAKPKT 10443-8 | Hulu LangatSelangor | 19 | 26 Nov 2021Extended 12 months from 26 Nov 20201st sale agreement 26 Nov 2018 | CCC 17 May 2022 | 172 days after † |
| LATANIA PH4A2(A)KPKT 10443-10 | Hulu LangatSelangor | 16 | 7 Apr 2022Extended 6 months from 7 Oct 20211st sale agreement 7 Oct 2019 | CCC 12 Jan 2022 | CCC before deadline; handover not recorded |
| LATANIA PH4A2(B)KPKT 10443-11 | Hulu LangatSelangor | 5 | 11 Dec 2023Extended 6 months from 11 Jun 20231st sale agreement 11 Jun 2021 | CCC 12 Jan 2022 | CCC before deadline; handover not recorded |
| LATANIAKPKT 10443-7Twin Palms - Latania II · on PropertySifu | Hulu LangatSelangor | 28 | 3 Jul 20191st sale agreement 3 Jul 2017 | CCC 18 Dec 2019 | 168 days after |
| SUTERA BAYUKPKT 10443-9 | Hulu LangatSelangor | 130 | 18 Jul 20201st sale agreement 18 Jul 2017 | CCC 23 Oct 2019 | CCC before deadline; handover not recorded |
| CALYPSOKPKT 11062-3 | GombakSelangor | 45 | 10 Jan 20161st sale agreement 10 Jan 2014 | CCC 23 Dec 2015 | CCC before deadline; handover not recorded |
| FABULOUS RANGE SDN BHDKPKT 10443-5 | Hulu LangatSelangor | 28 | 8 Jul 20151st sale agreement 8 Jul 2013 | CCC 15 Dec 2015 | 160 days after |
| SIERRAKPKT 10443-6 | Hulu LangatSelangor | 37 | 11 Nov 20151st sale agreement 11 Nov 2013 | CCC 15 Dec 2015 | 34 days after |
| VENUS CAPITAL CORPORATION SDN BHDKPKT 11062-2 | GombakSelangor | 40 | 8 Apr 20141st sale agreement 8 Apr 2012 | CCC 11 Feb 2015 | 309 days after |
| TWIN PALMS KEMENSAHKPKT 11062-1 | GombakSelangor | 42 | 5 Nov 20141st sale agreement 5 Nov 2012 | CCC 31 Oct 2014 | CCC before deadline; handover not recorded |
| FABULOUS RANGE SDN BHDKPKT 10443-4 | Hulu LangatSelangor | 46 | — | CCC 31 Mar 2014 | — |
| FABULOUS RANGE SDN BHDKPKT 10443-3 | Hulu LangatSelangor | 38 | — | CCC 15 Mar 2013 | — |
| TWIN PALMS FASA 2AKPKT 10443-2 | Hulu LangatSelangor | 41 | — | CCC 2 Aug 2012 | — |
| TWIN PALMS 1A,1B,2A,2B,3A,3B,4A, 4B,5&6KPKT 10443-1 | Hulu LangatSelangor | 186 | — | CFO 13 Aug 2010 | — |
| SURIA 618KPKT 3552-4 | PetalingSelangor | 66 | — | CFO 20 Mar 2007 | — |
| LAMAN SERIKPKT 3552-3 | PetalingSelangor | 112 | — | CFO 21 Jun 2006 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| SUTERA EMBUNKPKT 10443-15 | Hulu LangatSelangor | 236 | SmoothOn schedule | 5 Jul 20281st sale agreement 5 Jul 2025 | 98% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Lum Chang at a glance
| Listed | Singapore Exchange (SGX) Mainboard · L19 · listed 28 December 1984[2][3] |
|---|---|
| Started | Began as a sole proprietorship in the 1940s; Lum Chang Holdings Limited was incorporated in Singapore on 18 September 1982[1][2] |
| Head office | Singapore[2] |
| Leadership | Raymond Lum Kwan Sung — Executive Chairman since 1984; Non-Executive Chairman from 1 January 2027[1] David Lum Kok Seng — Managing Director[1] Cham Kooi Joo — Managing Director, Malaysia (since 2016)[1] |
| Companies in the KPKT register | FABULOUS RANGE SDN. BHD. KPKT 10443[1] NEXUS SDN. BHD. KPKT 3552[1] VENUS CAPITAL CORPORATION SDN. BHD. KPKT 11062[1] |
| Website | lumchang.com.sg |
| Twin Palms Sungai Long (company figure) | 126-acre freehold gated estate in Bandar Sungai Long, Kajang: 579 homes (bungalows, semi-detached and superlink houses) and nine shop lots (Annual Report 2026)[1] |
| Affordable housing | Rumah Selangorku at Twin Palms Sungai Long: 236 homes, launched in July 2025[1] |
| Business | Construction, property development and investment, conservation and interior finishing; property in Singapore, Malaysia and the United Kingdom[1] |
Lum Chang projects on sale on PropertySifu
Who is Lum Chang? The company behind the projects
Lum Chang began as a sole proprietorship in the 1940s and describes itself as a construction firm listed on the Singapore Exchange that has expanded into property development, investment, conservation and interior finishing [1]. Lum Chang Holdings Limited was incorporated in Singapore on 18 September 1982 and listed on 28 December 1984 [2]; it trades on the SGX Mainboard under the symbol L19 [3]. Raymond Lum Kwan Sung has been executive chairman since 1984 and is due to become non-executive chairman on 1 January 2027; David Lum Kok Seng is managing director [1]. The group's property business spans Singapore, Malaysia and the United Kingdom [1]; the KPKT register below covers only its housing projects in Malaysia.
In Malaysia the group develops through Fabulous Range Sdn Bhd, a wholly owned subsidiary; its Malaysian property operations are led by Cham Kooi Joo, who joined Lum Chang Malaysia in 2002 and became managing director in 2016 [1]. The main project is Twin Palms Sungai Long, a 126-acre freehold gated estate in Bandar Sungai Long, Kajang, with 579 homes — bungalows, semi-detached and superlink houses — and nine shop lots [1]. KPKT registers 15 projects under Fabulous Range (KPKT 10443-1 to 10443-15), all in Hulu Langat district, with phase names such as TWIN PALMS, SIERRA, LATANIA, WESTIARA and INDICA; the group completed 34 Indica bungalows in April 2026 [1].
Next to the estate, Rumah Selangorku at Twin Palms Sungai Long is an affordable-housing project of 236 homes launched in July 2025 [1]; KPKT registers a 236-unit project named SUTERA EMBUN under Fabulous Range, still under construction. The other 5 of the 20 records belong to two dormant subsidiaries [1]: Venus Capital Corporation Sdn Bhd registered three bungalow projects in Gombak district (KPKT 11062-1 to 11062-3), including TWIN PALMS KEMENSAH, with CCCs in 2014 and 2015, and Nexus Sdn Bhd registered two terraced-house projects in Petaling district, LAMAN SERI and SURIA 618 (KPKT 3552-3 and 3552-4), completed in 2006 and 2007.
Frequently asked questions
Is Lum Chang a listed company?
Which company develops Twin Palms - Latania II?
Fabulous Range Sdn Bhd (KPKT developer code 10443), wholly owned by Lum Chang Holdings [1]. KPKT registers 15 projects under Fabulous Range (10443-1 to 10443-15), all in Hulu Langat district, Selangor; three have LATANIA in the registered name: 10443-7 (28 units, CCC on 18 December 2019), 10443-10 (16 units) and 10443-11 (5 units), the last two with CCCs on 12 January 2022.
Does Lum Chang have any Sick or Abandoned projects in Malaysia?
No. As at 27 October 2026, none of the 20 projects under the three Lum Chang companies in the KPKT register is classed Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). The one under construction, SUTERA EMBUN (10443-15, 236 units), is recorded as on schedule (Lancar) with reported construction progress of 98%; its first sale agreement was signed on 5 July 2025 and its handover deadline is 5 July 2028.
Were the Twin Palms phases handed over on time?
KPKT lists 19 completed projects under the three Lum Chang companies; 13 have dates that can be compared with a deadline (the extended deadline where an extension was approved). Two were handed over before the deadline: a 24-unit phase registered under the company's own name (10443-12, 4 days before) and INDICA BUNGALOW (10443-13, 32 days before). Five received their CCC before the deadline, with no handover date recorded. Six received their CCC after the deadline, by 12 to 309 days, with no handover date recorded: INDICA (10443-14, 12 days), SIERRA (10443-6, 34), a 28-bungalow phase registered under the company's own name (10443-5, 160), LATANIA (10443-7, 168), WESTIARA (10443-8, 172) and a 40-bungalow project in Gombak registered under Venus Capital Corporation's own name (11062-2, 309). WESTIARA was under construction during 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether its deadline already reflects it. The other 6, completed between 2006 and 2014, have no deadline in the register.
Has KPKT approved any deadline extensions for these projects?
Yes, for 3 of the 20: WESTIARA (10443-8, 19 bungalows), by 12 months to 26 November 2021; and LATANIA PH4A2(A) and LATANIA PH4A2(B) (10443-10 and 10443-11), by 6 months each, to 7 April 2022 and 11 December 2023. Both Latania phases received their CCC on 12 January 2022, before those extended deadlines; their handover dates are not recorded.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Lum Chang Holdings Limited Annual Report 2026 · Lum Chang Holdings Limited · 1 Oct 2026 · accessed 28 Oct 2026
https://investor.lumchang.com.sg/newsroom/20261001_173520_L19_92KZ8BWGUMRHIHHC.1.pdf - [2] Corporate information: Lum Chang Holdings Limited · Singapore Exchange (SGX) · accessed 28 Oct 2026
https://links.sgx.com/1.0.0/corporate-information/1049 - [3] Stock information · Lum Chang Holdings Limited · accessed 28 Oct 2026
https://investor.lumchang.com.sg/stock_fundamentals.html
Last updated 28 Oct 2026