Sick & Abandoned Housing Projects in Kedah (2026)

Official KPKT status (TEDUH) · updated 2026-08-29
13 Sick 5 Abandoned 10 Late 28 total
As at 2026-08-29, KPKT records 13 Sick, 5 Abandoned and 10 Late housing projects in Kedah — all 28 listed in full below. Statuses are quoted directly from the KPKT TEDUH register, unamended. Check the project or developer name before you buy.

What do these statuses mean?

Sick
“Sick” (registry term: Sakit) — a project delayed by more than 30% against its expected progress schedule, or whose Sale & Purchase Agreement period has expired.
Abandoned
“Abandoned” (registry term: Terbengkalai) — an incomplete project with no significant site activity for 6 consecutive months; or a winding-up petition filed (S.218 Companies Act); or the company under a Receiver & Manager; or the developer admitting inability in writing — and confirmed by the Minister under S.11(1)(c) of Act 118.
Late
“Late” (registry term: Lewat) — TEDUH status for a project behind schedule that has not yet met the sick-project definition.

Definitions: National Housing Department — Sick Projects · Abandoned Projects

Full list (28 projects)

ProjectDistrictDeveloperKPKT statusSold / Total unitsPermit valid until
BANDAR SRI AMPANGKota SetarPERTAMA PERDAGANGAN SDN. BHD.Abandoned114 / 1142007-07-06
KIM LONG CREDIT DEVELOPMENT SDN. BHD.KulimKIM LONG CREDIT DEVELOPMENT SDN. BHD.Abandoned14 / 142022-03-11
VIRTUE PLUS SDN BHDKota SetarVIRTUE PLUS SDN. BHD.Abandoned5 / 52020-01-24
TAMAN SENTOSALangkawiWELDTECH ENGINEERING (M) SDN. BHDAbandoned5 / 52015-04-30
TAMAN TUNKU YAACOBKota SetarQUANTUM DEVELOPER LINES SDN. BHD.Abandoned4 / 42013-01-05
TAMAN SEJAHTERASikREXHILL SDN. BHD.Sick3042012-11-20
BANDAR PERMATA LUNASKulimGOLDEN BLUECHIP SDN. BHD.Sick157 / 2142027-05-12
AERA GARDENSKuala MudaHENG GUAN DEVELOPMENT SDN. BHD.Sick111 / 1132027-01-22
ST HAN DEVELOPMENT SDN BHDPokok Sena (daerah Kecil)ST HAN DEVELOPMENT SDN. BHD.Sick36 / 452027-03-21
LOT 463Kota SetarEVERISE ACRES HOLDINGS SDN. BHD.Sick442008-11-01
TAMAN KERANJI IIYanKOTA JELITA SDN. BHD.Sick26 / 402026-10-26
TAMAN CAHAYA INTAN 2Bandar BaharuPAKATAN SAKSAMA SDN. BHD.
Group: SUNNY TRIUMPH DEVELOPMENT SDN. BHD.
Sick31 / 382027-01-29
TAMAN MINANG SARIKota SetarTH GRAND PROPERTIES SDN. BHD.Sick22 / 302026-11-25
TAMAN KEKWAKuala MudaIRAMA JAYA DEVELOPMENT SDN. BHD.
Group: IRAMAJAYAGROUP (iramajayagroup.com)
Sick20 / 302026-11-07
TAMAN KERIANG INDAH BANDAR CHANGLUNKubang PasuYAKIN BINAJAYA SDN. BHD.Sick19 / 272025-11-16
LOT PT 1419PendangLAM CHAN CHOON BINA SDN. BHD.Sick212006-08-18
TAMAN GUNUNG TAHANKota SetarGOLDEN VISION POWER SDN. BHD.Sick9 / 202026-04-22
TAMAN DERMAGA JAYAKota SetarIRAMA CERIA DEVELOPMENT SDN. BHD.Sick14 / 162027-06-14
RESIDENSI AKASIAKota SetarSUNGGUH KEMAJUAN SDN. BHD.
Group: SUNGGUHKEMAJUAN (sungguhkemajuan.com.my)
Late56 / 1262027-04-27
LUMINA BEDONGKuala MudaSELETAR SDN. BHD.
Group: PPB (ppb.com.my)
Late96 / 1252027-08-22
SP SAUJANA PERMAIKuala MudaOIB PROPERTIES (K) SDN. BHD.
Group: OIBGROUP (oibgroup.com)
Late112 / 1252026-11-26
TAMAN AZALEAPendangBDB LAND SDN. BHD.
Group: BDB (bdb.com.my)
Late2 / 942027-06-24
TAMAN SURYALangkawiKAWALAN JAYA SDN. BHD.
Group: DSR (dsr.com.my)
Late7 / 542027-01-21
TAMAN KERIANG PERMAIKubang PasuPRIMAHILL SDN. BHD.Late18 / 412026-09-26
TAMAN DAHLIAPendangTIMELESS CENTURY SDN. BHD.Late18 / 302027-03-17
TAMAN DESA DAHLIABalingMERGER TREND SDN. BHD.Late27 / 292026-09-01
TAMAN HARMONISikTH GRAND PROPERTIES SDN. BHD.Late6 / 202027-03-12
TAMAN CERMAIKubang PasuSBLE ENTERPRISE SDN. BHD.
Group: SENIMAS VENTURE SDN. BHD.
Late15 / 202027-07-07
Unit data refreshes on TEDUH's per-state review cycle; the “sold” figure is KPKT's latest record, not necessarily today's.

Frequently asked questions

How many distressed housing projects are in Kedah?

As at 2026-08-29: 13 Sick, 5 Abandoned, 10 Late (official KPKT TEDUH record).

Does this list include projects that have been rehabilitated?

No. It shows the current TEDUH status; a project that recovers and receives its CCC drops off the list at the next update.

Can units in a sick project still be sold?

Yes — sick status does not stop sales. That is exactly why it pays to check this list and confirm the APDL status with the developer and your financier before signing anything.

How do I check my own project's status?

Search the project name in the table above, or check directly at teduh.kpkt.gov.my. This list is compiled from that same official register, just easier to search.

Status changed? Get monthly updates
Data source: TEDUH, Ministry of Housing and Local Government (KPKT) — teduh.kpkt.gov.my, data as at 2026-08-29. Used under the Government Open Data Terms of Use 1.0. Analysis by Affirm Plus Research. Project statuses are quoted exactly as recorded by KPKT, unamended.
PropertySifu does not represent any project on these distressed lists. Sabah/Sarawak/WP Labuan are not covered by TEDUH (East Malaysian housing development falls under state legislation).