Y&G (Y&G Corporation Bhd)
Y&G Corporation Bhd is a property developer listed on Bursa Malaysia's Main Market, with 17 housing projects in the KPKT register under nine Y&G companies: 11 completed and 6 under construction, none classed Sick, Abandoned or Late. Most are in Selangor, with others in Negeri Sembilan and Pahang; its managing director is Dato' Sri Yap Seng Yew.
- 17 projects in the KPKT register
- 11 completed
- 6 under construction
- None Sick or Abandoned
Has Y&G handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 17 housing projects under 9 Y&G companies in 3 states: 11 completed, 6 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 11 completed projects, 4 have both a handover deadline and a completion date in the register: 3 handed over or certified complete after that deadline; 1 received the completion certificate before the deadline (handover date not recorded).
7 projects had the delivery period extended with KPKT approval.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TRIFOLIA @ SG. JATI, KLANGKPKT 19107-1 | KlangSelangor | 586 | 15 Jul 2023Extended 11 months from 15 Aug 20221st sale agreement 15 Aug 2019 | CCC 28 Jun 2023 | CCC before deadline; handover not recorded |
| BANDAR SRI JAROMAS - PLUMERIAKPKT 11682-4 | Kuala LangatSelangor | 105 | 4 Oct 20181st sale agreement 4 Oct 2016 | CCC 3 Jan 2019 | 91 days after |
| BANDAR SRI JAROMAS - PLUMERIAKPKT 11682-5 | Kuala LangatSelangor | 163 | 10 Nov 20181st sale agreement 10 Nov 2016 | CCC 3 Jan 2019 | 54 days after |
| PANGSAPURI SUTRAVILLAKPKT 3730-2 | KuantanPahang | 520 | — | CCC 15 May 2018 | — |
| ALAMAIA HOMESKPKT 13434-1 | KlangSelangor | 20 | — | CCC 21 Aug 2017 | — |
| BANDAR SRI JAROMAS - ZINNIAKPKT 11682-3 | Selangor | 230 | — | CCC 10 Oct 2016 | — |
| BETA FAME DEVELOPMENT SDN. BHD.KPKT 11682-2 | Kuala LangatSelangor | 208 | — | CCC 6 Feb 2015 | — |
| BANDAR SERI JARUM MASKPKT 11682-1 | Kuala LangatSelangor | 78 | — | CCC 30 Jan 2015 | — |
| PANGSAPURI VILLAMASKPKT 11048-2 | KlangSelangor | 560 | 3 Jun 20141st sale agreement 3 Jun 2011 | CCC 9 Jan 2015 | 220 days after |
| LA VILLE CHERASKPKT 11048-1 | Hulu LangatSelangor | 259 | — | CCC 7 Sep 2012 | — |
| TAMAN MURNIMASKPKT 10979-1 | Kuala LangatSelangor | 527 | — | CCC 20 Mar 2012 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| HAMLET @ THE MEADOWSKPKT 30675-1 | Kuala SelangorSelangor | 219 | SmoothOn schedule | 5 Aug 2027Extended 12 months from 5 Aug 20261st sale agreement 5 Aug 2024 | 75–79% |
| HAMLET @ THE MEADOWSKPKT 30675-2 | Kuala SelangorSelangor | 167 | SmoothOn schedule | 3 Jan 2028Extended 12 months from 3 Jan 20271st sale agreement 3 Jan 2025 | 44–51% |
| HAMLET @ THE MEADOWSKPKT 30675-3 | Kuala SelangorSelangor | 74 | SmoothOn schedule | 15 Apr 2028Extended 12 months from 15 Apr 20271st sale agreement 15 Apr 2025 | 29–39% |
| TRIFOLIAKPKT 30503-1 | Port DicksonNegeri Sembilan | 204 | SmoothOn schedule | 15 Apr 2028Extended 12 months from 15 Apr 20271st sale agreement 15 Apr 2024 | 55–70% |
| TRIFOLIA 2KPKT 30503-2 | Port DicksonNegeri Sembilan | 354 | SmoothOn schedule | 11 Aug 2029Extended 6 months from 11 Feb 20291st sale agreement 11 Feb 2026 | 2–10% |
| ESTET KINDLEKPKT 30752-1Kindle Estate @ Rawang · on PropertySifu | GombakSelangor | 396 | SmoothOn schedule | 9 Mar 2030Extended 12 months from 9 Mar 20291st sale agreement 9 Mar 2026 | 8–12% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Y&G at a glance
| Listed | Bursa Malaysia Main Market · Y&G (7003)[1] |
|---|---|
| Started | Incorporated in 1965 (company registration no. 196501000612)[1] |
| Head office | PJ City Development, Seksyen 51A, Petaling Jaya, Selangor[1] |
| Leadership | Dato' Sri Yap Seng Yew — Managing Director (since 11 March 2005)[1] Datin Sri Gan Li Li — Deputy Managing Director[1] Lee Boon Hong @ Lee Boon Keong — Non-Independent Non-Executive Chairman[1] |
| Companies in the KPKT register | MAHA HARAPAN SDN. BHD. KPKT 30752[1] DUTA ASIANA SDN. BHD. KPKT 30675[1] MELATI PURNAMA SDN. BHD. KPKT 30503[1] TERAS ZAMAN SDN. BHD. KPKT 19107[1] BETA FAME DEVELOPMENT SDN. BHD. KPKT 11682[1] HALA KOTA DEVELOPMENT SDN. BHD. KPKT 11048[1] KUALITI KINTA SDN. BHD. KPKT 13434[1] MAGNA REMBANG SDN. BHD. KPKT 10979[1] BUMIDA ENGINEERING & CONSTRUCTION SDN.BHD. (98%) KPKT 3730[1] |
| Website | ygcorp.com.my |
| Land bank | About 202 acres in 2025; purchases in Kuala Selangor and Sepang approved by shareholders in January 2026 add 548.35 acres[1] |
| New pipeline (company figure) | An estimated RM2 billion of gross development value from the Kuala Selangor and Sepang land, to be launched progressively from 2026[1] |
| Green rating (company statement) | Kindle Estate: provisional GreenRE Bronze (Annual Report 2025)[1] |
| Where it builds | Mainly Selangor; current projects also in Port Dickson, Negeri Sembilan[1] |
Y&G projects on sale on PropertySifu
Who is Y&G? The company behind the projects
Y&G Corporation Bhd is listed on the Main Market of Bursa Malaysia under the stock name Y&G, code 7003 [1]. Its company registration number, 196501000612, shows it was incorporated in 1965 [1]. Its principal place of business is in Seksyen 51A, Petaling Jaya, and its holding company is Kinta Aroma Sdn Bhd [1].
Managing director Dato' Sri Yap Seng Yew joined the board as an executive director on 20 December 2004 and became managing director on 11 March 2005; his wife, Datin Sri Gan Li Li, is deputy managing director, and their son Dato' Yap Jun Jien is an executive director [1]. The chairman is Lee Boon Hong @ Lee Boon Keong, a non-executive director [1].
Its completed developments, according to its website, include Bandar Sri Jaromas, a 133-acre township in Kuala Langat, the 586-unit Trifolia @ Sg. Jati apartments in Klang and Alamaia Homes in Kota Kemuning [2]. Under construction are Hamlet @ The Meadows in Kuala Selangor, 460 single-storey terrace houses, and Trifolia @ Port Dickson in Negeri Sembilan, 558 affordable townhouses; both were launched in 2024 [1].
Kindle Estate in Rawang went on sale in the first quarter of 2026. The company says it has two phases with 690 units on 41 acres of leasehold land and an estimated gross development value of RM347.4 million [1]. KPKT has so far registered 396 of those units (30752-1) under Maha Harapan Sdn Bhd, which the 2025 annual report lists as a wholly-owned subsidiary [1]. The company put its land bank at about 202 acres in 2025 and says land purchases in Kuala Selangor and Sepang, approved by shareholders in January 2026, add 548.35 acres [1].
Frequently asked questions
Is Y&G a listed company?
Yes. Y&G Corporation Bhd is listed on the Main Market of Bursa Malaysia under the stock name Y&G, stock code 7003 [1].
How many projects has Y&G completed?
In the KPKT register, 11 of the 17 housing projects under nine Y&G companies are completed, with 3,256 units. Only 4 of the 11 have both a handover deadline and a completion date recorded: for 3 of them the CCC is dated after the deadline (54, 91 and 220 days later), and 1 received the CCC 17 days before its extended deadline, with no handover date recorded.
Does Y&G have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 17 Y&G projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). All 6 projects under construction are recorded as on schedule (Lancar), and all 6 have handover deadlines extended with approval, by 6 to 12 months.
Which company develops Kindle Estate @ Rawang?
Maha Harapan Sdn Bhd (KPKT developer code 30752), which Y&G's 2025 annual report lists as a wholly-owned subsidiary [1]. KPKT registers the project as ESTET KINDLE (30752-1) with 396 units.
Has Kindle Estate's handover deadline been extended?
Yes, according to KPKT. The first sale agreement was signed on 9 March 2026, giving a handover deadline of 9 March 2029, extended with approval by 12 months to 9 March 2030. Reported construction progress ranges from 7.88% to 12.5% across components, and the project is recorded as on schedule (Lancar).
Where are Y&G's projects?
In the KPKT register: 14 in Selangor, 2 in Negeri Sembilan (Port Dickson) and 1 in Pahang (Kuantan).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Y&G Corporation Bhd Annual Report 2025 · Y&G Corporation Bhd · 28 Apr 2026 · accessed 28 Oct 2026
https://www.ygcorp.com.my/wp-content/uploads/2026/05/YG-Corporation_AR2025-Bursa-_compressed.pdf - [2] Our Developments · Y&G Corporation Bhd · accessed 28 Oct 2026
https://www.ygcorp.com.my/our-developments/
Last updated 28 Oct 2026