WCT (WCT Holdings Berhad)
WCT Holdings Berhad is a Bursa Malaysia Main Market-listed construction and property group with 56 housing projects in the KPKT register under ten WCT companies: 49 completed and 7 under construction, none classed Sick or Abandoned. Founded in 1981 as a building contractor and listed in 1995, it builds townships in Klang and high-rise homes in Kuala Lumpur and Johor.
- 56 projects in the KPKT register
- 49 completed
- 7 under construction
- None Sick or Abandoned
Has WCT handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 56 housing projects under 10 WCT companies in 3 states: 49 completed, 7 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 49 completed projects, 14 have both a handover deadline and a completion date in the register: 1 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 5 handed over or certified complete after that deadline; 8 received the completion certificate before the deadline (handover date not recorded).
10 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 49
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| PANGSAPURI ADENIAKPKT 9810-31 | KlangSelangor | 181 | 1 Aug 20251st sale agreement 1 Aug 2022 | CCC 9 Jul 2025 | CCC before deadline; handover not recorded |
| RESIDENSI MAPEL OUGKPKT 14379-2The Maple Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 940 | 8 Nov 2025Extended 23 months from 8 Dec 20231st sale agreement 8 Dec 2020 | CCC 30 May 2025 Handover 30 May 2025 | 162 days before |
| WCT HARTANAH JAYA SDN BHDKPKT 13569-1 | Johor BahruJohor | 263 | 28 Aug 2022Extended 11 months from 28 Sep 20211st sale agreement 28 Sep 2018 | CCC 8 Aug 2022 | CCC before deadline; handover not recorded |
| PANGSAPURI ARONIAKPKT 9810-30 | KlangSelangor | 320 | 18 Nov 2022Extended 6 months from 18 May 20221st sale agreement 18 May 2019 | CCC 16 Nov 2021 | CCC before deadline; handover not recorded |
| APARTMENT TRIFOLISKPKT 8128-26 | KlangSelangor | 372 | 10 Dec 20181st sale agreement 10 Dec 2015 | CCC 28 Nov 2018 | CCC before deadline; handover not recorded |
| JELAS PURI SDN. BHD.KPKT 13652-2 | PetalingSelangor | 229 | — | CCC 29 Oct 2018 | — |
| PANGSAPURI ASTERIA, BANDAR PARKLANDSKPKT 9810-29 | KlangSelangor | 321 | 13 Oct 20181st sale agreement 13 Oct 2015 | CCC 7 Jun 2018 | CCC before deadline; handover not recorded |
| PANGSAPURI AZARIA, BANDAR PARKLANDSKPKT 9810-28 | KlangSelangor | 240 | 3 Jun 20181st sale agreement 3 Jun 2015 | CCC 31 May 2018 | CCC before deadline; handover not recorded |
| THE LEAD RESIDENSIKPKT 8128-25 | KlangSelangor | 403 | 3 Dec 20171st sale agreement 3 Dec 2014 | CCC 5 Feb 2018 | 64 days after |
| THE AZURE @ PARADIGM PJKPKT 13652-1 | PetalingSelangor | 189 | 14 Aug 20171st sale agreement 14 Aug 2014 | CCC 16 Aug 2017 | 2 days after |
| LAMAN GREENVILLEKPKT 13492-1 | KlangSelangor | 266 | 12 May 20171st sale agreement 12 May 2014 | CCC 18 May 2017 | 6 days after |
| SKYZ JELUTONGKPKT 13439-1 | PetalingSelangor | 222 | 14 Apr 20171st sale agreement 14 Apr 2014 | CCC 13 Apr 2017 | CCC before deadline; handover not recorded |
Handed over or certified complete after the deadline (5)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| THE LEAD RESIDENSIKPKT 8128-25 | KlangSelangor | 403 | 3 Dec 20171st sale agreement 3 Dec 2014 | CCC 5 Feb 2018 | 64 days after |
| THE AZURE @ PARADIGM PJKPKT 13652-1 | PetalingSelangor | 189 | 14 Aug 20171st sale agreement 14 Aug 2014 | CCC 16 Aug 2017 | 2 days after |
| LAMAN GREENVILLEKPKT 13492-1 | KlangSelangor | 266 | 12 May 20171st sale agreement 12 May 2014 | CCC 18 May 2017 | 6 days after |
| MEDINI SIGNATUREKPKT 11491-3 | Johor BahruJohor | 456 | 31 Jul 20161st sale agreement 31 Jul 2013 | CCC 15 Feb 2017 | 199 days after |
| 1 MEDINIKPKT 11491-1 | Johor BahruJohor | 662 | 6 Jan 20151st sale agreement 6 Jan 2012 | CCC 26 May 2015 | 140 days after |
Show all 49 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| PANGSAPURI ADENIAKPKT 9810-31 | KlangSelangor | 181 | 1 Aug 20251st sale agreement 1 Aug 2022 | CCC 9 Jul 2025 | CCC before deadline; handover not recorded |
| RESIDENSI MAPEL OUGKPKT 14379-2The Maple Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 940 | 8 Nov 2025Extended 23 months from 8 Dec 20231st sale agreement 8 Dec 2020 | CCC 30 May 2025 Handover 30 May 2025 | 162 days before |
| WCT HARTANAH JAYA SDN BHDKPKT 13569-1 | Johor BahruJohor | 263 | 28 Aug 2022Extended 11 months from 28 Sep 20211st sale agreement 28 Sep 2018 | CCC 8 Aug 2022 | CCC before deadline; handover not recorded |
| PANGSAPURI ARONIAKPKT 9810-30 | KlangSelangor | 320 | 18 Nov 2022Extended 6 months from 18 May 20221st sale agreement 18 May 2019 | CCC 16 Nov 2021 | CCC before deadline; handover not recorded |
| APARTMENT TRIFOLISKPKT 8128-26 | KlangSelangor | 372 | 10 Dec 20181st sale agreement 10 Dec 2015 | CCC 28 Nov 2018 | CCC before deadline; handover not recorded |
| JELAS PURI SDN. BHD.KPKT 13652-2 | PetalingSelangor | 229 | — | CCC 29 Oct 2018 | — |
| PANGSAPURI ASTERIA, BANDAR PARKLANDSKPKT 9810-29 | KlangSelangor | 321 | 13 Oct 20181st sale agreement 13 Oct 2015 | CCC 7 Jun 2018 | CCC before deadline; handover not recorded |
| PANGSAPURI AZARIA, BANDAR PARKLANDSKPKT 9810-28 | KlangSelangor | 240 | 3 Jun 20181st sale agreement 3 Jun 2015 | CCC 31 May 2018 | CCC before deadline; handover not recorded |
| THE LEAD RESIDENSIKPKT 8128-25 | KlangSelangor | 403 | 3 Dec 20171st sale agreement 3 Dec 2014 | CCC 5 Feb 2018 | 64 days after |
| THE AZURE @ PARADIGM PJKPKT 13652-1 | PetalingSelangor | 189 | 14 Aug 20171st sale agreement 14 Aug 2014 | CCC 16 Aug 2017 | 2 days after |
| LAMAN GREENVILLEKPKT 13492-1 | KlangSelangor | 266 | 12 May 20171st sale agreement 12 May 2014 | CCC 18 May 2017 | 6 days after |
| SKYZ JELUTONGKPKT 13439-1 | PetalingSelangor | 222 | 14 Apr 20171st sale agreement 14 Apr 2014 | CCC 13 Apr 2017 | CCC before deadline; handover not recorded |
| MEDINI SIGNATUREKPKT 11491-3 | Johor BahruJohor | 456 | 31 Jul 20161st sale agreement 31 Jul 2013 | CCC 15 Feb 2017 | 199 days after |
| BANDAR PARKLANDS, KLANG, A11KPKT 9810-27 | KlangSelangor | 400 | 7 Sep 20161st sale agreement 7 Sep 2013 | CCC 25 Jun 2015 | CCC before deadline; handover not recorded |
| 1 MEDINIKPKT 11491-1 | Johor BahruJohor | 662 | 6 Jan 20151st sale agreement 6 Jan 2012 | CCC 26 May 2015 | 140 days after |
| BANDAR PARKLANDS, KLANG, C4KPKT 9810-26 | KlangSelangor | 76 | — | CCC 2 May 2014 | — |
| BANDAR PARKLANDS, KLANGKPKT 9810-14 | KlangSelangor | 480 | — | CCC 12 Mar 2014 | — |
| BANDAR PARKLANDS, KLANG, C10KPKT 9810-25 | KlangSelangor | 35 | — | CCC 21 Feb 2014 | — |
| BANDAR PARKLANDS, KLANG, C5KPKT 9810-23 | KlangSelangor | 103 | — | CCC 6 Nov 2013 | — |
| BANDAR PARKLANDS, KLANG, C3KPKT 9810-20 | KlangSelangor | 68 | — | CCC 31 Oct 2013 | — |
| BANDAR PARKLANDS, KLANG, C1KPKT 9810-24 | KlangSelangor | 68 | — | CCC 12 Oct 2013 | — |
| BANDAR PARKLANDS, KLANG, C7KPKT 9810-22 | KlangSelangor | 27 | — | CCC 7 Oct 2013 | — |
| BANDAR PARKLANDS KLANG C8KPKT 9810-19 | KlangSelangor | 76 | — | CCC 8 Jul 2013 | — |
| BANDAR PARKLANDS, KLANGKPKT 9810-18 | KlangSelangor | 36 | — | CCC 26 Apr 2013 | — |
| BANDAR PARKLANDS, KLANGKPKT 9810-17 | KlangSelangor | 103 | — | CCC 25 Apr 2013 | — |
| GEMILANG WARASKPKT 8128-24 | KlangSelangor | 86 | — | CCC 17 Apr 2013 | — |
| BANDAR PARKLANDS, KLANGKPKT 9810-16 | KlangSelangor | 56 | — | CCC 20 Feb 2013 | — |
| BANDAR PARKLANDS, KLANGKPKT 9810-15 | KlangSelangor | 48 | — | CCC 2 Aug 2012 | — |
| BANDAR PARKLANDS, KLANG FASA B10KPKT 9810-13 | KlangSelangor | 48 | — | CCC 17 Jul 2012 | — |
| BANDAR PARKLANDS, KLANG, B8KPKT 9810-12 | KlangSelangor | 76 | — | CCC 8 Nov 2011 | — |
| BANDAR PARKLANDS, KLANG B7KPKT 9810-11 | KlangSelangor | 84 | — | CCC 3 Nov 2011 | — |
| BANDAR PARKLANDS, KLANG B12KPKT 9810-10 | KlangSelangor | 72 | — | CCC 5 Jul 2011 | — |
| BANDAR PARKLANDS, KLANG FASA B5/B1KPKT 9810-8 | KlangSelangor | 161 | — | CCC 21 Feb 2011 | — |
| BANDAR PARKLANDS, KLANG(FASA B11)KPKT 9810-9 | KlangSelangor | 48 | — | CFO 6 Jan 2011 | — |
| BANDAR PARKLANDS, KLANG FASA A5KPKT 9810-7 | KlangSelangor | 102 | — | CCC 17 Aug 2010 | — |
| BANDAR PARKLANDS FASA B 13KPKT 9810-6 | KlangSelangor | 48 | — | CFO 18 Nov 2009 | — |
| BANDAR PARKLANDS FASA B14KPKT 9810-5 | KlangSelangor | 36 | — | CFO 1 Aug 2008 | — |
| BANDAR BUKIT TINGGI FASA 3D1KPKT 8128-22 | KlangSelangor | 176 | — | CFO 1 Aug 2008 | — |
| BANDAR BUKIT TINGGI, KLANGKPKT 8128-21 | KlangSelangor | 244 | — | CFO 18 Jan 2008 | — |
| BANDAR PARKLANDS B3 & B4KPKT 9810-4 | KlangSelangor | 120 | — | CFO 1 Nov 2007 | — |
| BANDAR PARKLANDS B2 & B6KPKT 9810-3 | KlangSelangor | 137 | — | CFO 5 Oct 2007 | — |
| BANDAR PARKLANDS A1 & A2KPKT 9810-1 | KlangSelangor | 158 | — | CFO 28 Sep 2007 | — |
| BANDAR PARKLANDS A3 & A4KPKT 9810-2 | KlangSelangor | 166 | — | CFO 28 Sep 2007 | — |
| BANDAR BUKIT TINGGIKPKT 8128-17 | KlangSelangor | 98 | — | CFO 14 Sep 2007 | — |
| BANDAR BUKIT TINGGI, KLANGKPKT 8128-20 | KlangSelangor | 159 | — | CFO 14 Sep 2007 | — |
| BANDAR BUKIT TINGGIKPKT 8128-18 | KlangSelangor | 160 | — | CFO 9 Feb 2007 | — |
| BANDAR BUKIT TINGGIKPKT 8128-19 | KlangSelangor | 195 | — | CFO 12 Jan 2007 | — |
| BANDAR BUKIT TINGGI, KLANGKPKT 8128-16 | KlangSelangor | 288 | — | CFO 12 Jan 2006 | — |
| BANDAR BUKIT TINGGIKPKT 8128-15 | KlangSelangor | 104 | — | CFO 19 Dec 2005 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| PAVILION MONT KIARAKPKT 30134-1Pavilion Mont Kiara · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 341 | SmoothOn schedule | 3 Aug 2027Extended 12 months from 3 Aug 20261st sale agreement 3 Aug 2023 | 62–89% |
| ADISONKPKT 30376-1 | Johor BahruJohor | 1,024 | SmoothOn schedule | 18 Mar 2028Extended 12 months from 18 Mar 20271st sale agreement 18 Mar 2024 | 57–76% |
| ADISONKPKT 30376-2 | Johor BahruJohor | 238 | SmoothOn schedule | 14 Dec 2028Extended 12 months from 14 Dec 20271st sale agreement 14 Dec 2024 | 56% |
| ADISONKPKT 30376-3 | Johor BahruJohor | 224 | SmoothOn schedule | 11 Jan 2029Extended 12 months from 11 Jan 20281st sale agreement 11 Jan 2025 | 58% |
| ADISONKPKT 30376-5 | Johor BahruJohor | 210 | SmoothOn schedule | 19 Mar 2029Extended 12 months from 19 Mar 20281st sale agreement 19 Mar 2025 | 40% |
| ADISONKPKT 30376-4 | Johor BahruJohor | 224 | SmoothOn schedule | 26 Apr 2029Extended 12 months from 26 Apr 20281st sale agreement 26 Apr 2025 | 39% |
| RESIDENSI ARASKPKT 14379-3Aras Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 1,272 | SmoothOn schedule | 7 Jan 2030Extended 18 months from 7 Jul 20281st sale agreement 7 Jul 2025 | 22% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
WCT at a glance
| Listed | Bursa Malaysia Main Market · WCT (9679) · WCT Berhad listed on 16 February 1995; listing moved to WCT Holdings Berhad on 8 July 2013[1] |
|---|---|
| Started | 14 January 1981, as WCT Earthworks & Building Contractors Sdn Bhd[1] |
| Head office | The Ascent, Paradigm, Kelana Jaya, Petaling Jaya, Selangor[1] |
| Leadership | Tan Sri Lim Siew Choon — Executive Chairman[1] Dato' Lee Tuck Fook — Group Managing Director[1] |
| Companies in the KPKT register | GABUNGAN EFEKTIF SDN. BHD. KPKT 9810[1] GEMILANG WARAS SDN. BHD. KPKT 8128[1] WCT GREEN SDN. BHD. KPKT 30376[1] WCT OUG DEVELOPMENT SDN. BHD. KPKT 14379[1] ONE MEDINI SDN. BHD. KPKT 11491[1] ATLANTA VILLA SDN. BHD. KPKT 13492[1] KEKAL KIRANA SDN. BHD. KPKT 30134[1] URBAN COURTYARD SDN. BHD. KPKT 13439[1] WCT HARTANAH JAYA SDN. BHD. KPKT 13569[1] JELAS PURI SDN. BHD. (70%) KPKT 13652[1] |
| Website | wct.com.my |
| Units delivered (company figure) | More than 19,000 residential and commercial units, worth RM7.4 billion in gross development value, since 1997 (Annual Report 2025)[1] |
| Land bank | About 185 acres in Malaysia (Annual Report 2025)[1] |
| Townships | Bandar Bukit Tinggi 1 & 2 and Bandar Parklands in Klang[1] |
| Where it builds (company statement) | Klang Valley, Johor and Sabah[1] |
| Construction record (company figure) | More than 400 infrastructure and building projects worth about RM40 billion completed (Annual Report 2025)[1] |
WCT projects on sale on PropertySifu
Who is WCT? The company behind the projects
WCT was established on 14 January 1981 as WCT Earthworks & Building Contractors Sdn Bhd and later renamed WCT Berhad. WCT Berhad listed on the Second Board of the then Kuala Lumpur Stock Exchange on 16 February 1995 and moved to the Main Market on 7 January 1999; on 8 July 2013 an internal reorganisation transferred the listing to WCT Holdings Berhad [1]. Its three core businesses are engineering and construction, property development, and property investment and management, and its registered office is at The Ascent, Paradigm in Kelana Jaya, Petaling Jaya [1].
The company says that since 1997 it has delivered more than 19,000 residential and commercial units worth RM7.4 billion in gross development value across the Klang Valley, Sabah and Johor, and that its land bank in Malaysia is about 185 acres [1]. Its townships include Bandar Bukit Tinggi 1 & 2 and Bandar Parklands in Klang [1]. Those are company figures that include commercial units; the KPKT register counts only projects licensed as housing, so WCT's malls, offices and hotels are not in the table above.
Property development is run by WCT Land Sdn Bhd. The Maple Residences and Aras Residences, in the 63-acre WCity OUG in Kuala Lumpur, are developed by WCT OUG Development Sdn Bhd, which WCT Land holds through WCT Premier Development Sdn Bhd [1]. The Maple Residences was completed and handed over in 2025; Aras Residences has two towers with a gross development value of RM1.03 billion, and its 636-unit Tower A was launched in the third quarter of 2025 [1]. Pavilion Mont' Kiara, launched in August 2023 with 336 high-rise units and five villas, is developed by Kekal Kirana Sdn Bhd, wholly owned by WCT Land, and is targeted for completion by the third quarter of 2027 [1]. KPKT also registers two completed Petaling Jaya projects, including The Azure @ Paradigm PJ, under Jelas Puri Sdn Bhd, a joint venture in which WCT Land holds 70% [1].
The executive chairman is Tan Sri Lim Siew Choon, a major shareholder of WCT who also chairs Pavilion REIT Management Sdn Bhd, the manager of Pavilion REIT; the group managing director is Dato' Lee Tuck Fook [1].
Frequently asked questions
Is WCT a listed company?
Yes. WCT Holdings Berhad trades on Bursa Malaysia's Main Market as WCT (stock code 9679). Its predecessor, WCT Berhad, first listed on 16 February 1995, and the listing moved to WCT Holdings Berhad on 8 July 2013 [1].
How many projects has WCT completed?
In the KPKT register, 49 of the 56 housing projects under ten WCT companies are completed, with 9,406 units; the other 7 are under construction. The company says it has delivered more than 19,000 residential and commercial units since 1997 [1]; that wider figure includes commercial units.
Does WCT have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 56 WCT projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat); all 7 projects under construction are recorded as on schedule (Lancar).
Has WCT handed over its projects on time?
The register has full dates for 14 of the 49 completed projects; the other 35, mostly older phases of the Klang townships, have no sale-agreement date. Against the deadline (the extended deadline where an extension was approved), The Maple Residences was handed over 162 days early; 8 projects received the CCC before the deadline but have no handover date registered; and 5 received the CCC after the deadline: Medini Signature by 199 days, 1 Medini by 140, The Lead Residensi by 64, Laman Greenville by 6 and The Azure @ Paradigm PJ by 2.
Which company develops The Maple Residences and Aras Residences?
WCT OUG Development Sdn Bhd (KPKT developer code 14379), held 100% through WCT Land [1]. KPKT records The Maple Residences (14379-2, 940 units) with a deadline of 8 December 2023, extended with approval by 23 months to 8 November 2025; the CCC and handover are both dated 30 May 2025. Aras Residences (14379-3) is registered with 1,272 units across its two towers; the first sale agreement was signed on 7 July 2025, and the deadline of 7 July 2028 was extended by 18 months to 7 January 2030. Reported construction progress is 22.5%.
Is Pavilion Mont' Kiara a WCT project or a Pavilion Group project?
It is developed by Kekal Kirana Sdn Bhd (KPKT developer code 30134), a wholly owned subsidiary of WCT Land [1]. WCT's executive chairman, Tan Sri Lim Siew Choon, also chairs Pavilion REIT Management Sdn Bhd [1]. KPKT registers 341 units (30134-1); the first sale agreement was signed on 3 August 2023, and the deadline of 3 August 2026 was extended with approval by 12 months to 3 August 2027. Reported construction progress is 62.5% to 89.35% across its components.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] WCT Holdings Berhad Annual Report 2025 · WCT Holdings Berhad · 23 Apr 2026 · accessed 28 Oct 2026
https://www.wct.com.my/annual/wct_annual_2025.pdf
Last updated 28 Oct 2026