Premier Consortium (Premier Consortium Sdn Bhd)
Premier Consortium Sdn Bhd is a privately held Malaysian developer with three housing projects in the KPKT register: two completed and one under construction, none classed Sick or Abandoned. They are Aman Heights in Petaling, Selangor, completed in 2014, and two phases of Residensi KLIA in Negeri Sembilan: the first completed in 2024, the second listed on PropertySifu.
- 3 projects in the KPKT register
- 2 completed
- 1 under construction
- None Sick or Abandoned
Has Premier Consortium handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 3 housing projects under 1 Premier Consortium company in 2 states: 2 completed, 1 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 2 completed projects, 1 has both a handover deadline and a completion date in the register: 1 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†).
1 project had the delivery period extended with KPKT approval.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI KLIAKPKT 9948-2 | SerembanNegeri Sembilan | 306 | 28 Nov 2022Extended 23 months from 28 Dec 20201st sale agreement 28 Dec 2017 | CCC 26 Feb 2024 | 455 days after † |
| AMAN HEIGHTSKPKT 9948-1 | PetalingSelangor | 798 | — | CCC 11 Sep 2014 | — |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI KLIAKPKT 9948-3Residensi KLIA · on PropertySifu | SerembanNegeri Sembilan | 306 | SmoothOn schedule | 21 Jun 20271st sale agreement 21 Jun 2024 | 74% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Premier Consortium at a glance
| Listed | Not listed — Premier Consortium Sdn Bhd is a private limited company (Sdn Bhd) |
|---|---|
| Started | Incorporated in 2004, according to its StarProperty developer profile[1] |
| Head office | Cheras, Kuala Lumpur[1] |
| Companies in the KPKT register | PREMIER CONSORTIUM SDN. BHD. KPKT 9948[1] |
| Business | Property development and turnkey design and construction[1] |
| Projects in the KPKT register | Aman Heights, Petaling, Selangor (798 units); Residensi KLIA, Seremban district, Negeri Sembilan, two phases of 306 units each[2] |
Premier Consortium projects on sale on PropertySifu
Who is Premier Consortium? The company behind the projects
Premier Consortium Sdn Bhd is a private company incorporated in 2004 whose core business is property development and turnkey design and construction, according to its developer profile on StarProperty, which gives an office in Cheras, Kuala Lumpur [1]. No stock-exchange listing was found, and no public source naming its directors was found.
The KPKT register lists three housing projects under the company. Aman Heights in Petaling, Selangor (798 units) received its CCC on 11 September 2014. Residensi KLIA, which StarProperty places in Nilai [1], is registered in the Seremban district of Negeri Sembilan in two phases of 306 serviced apartments: the first received its CCC on 26 February 2024, and the second, listed on PropertySifu, is under construction.
Frequently asked questions
Is Premier Consortium a listed company?
No stock-exchange listing was found. Premier Consortium Sdn Bhd is a private limited company, incorporated in 2004 according to its StarProperty developer profile [1].
Which company develops Residensi KLIA, and when is the handover deadline?
Premier Consortium Sdn Bhd (KPKT developer code 9948). KPKT registers the phase listed on PropertySifu as 9948-3: 306 serviced apartments of up to 26 storeys, with the first sale agreement signed on 21 June 2024 and a handover deadline of 21 June 2027; no extension is registered. It is recorded as on schedule (Lancar), with reported construction progress of 74%.
Was the first phase of Residensi KLIA completed on time?
KPKT records phase 1 (9948-2, 306 serviced apartments) with a first sale agreement on 28 December 2017 and a handover deadline of 28 December 2020, extended with approval by 23 months to 28 November 2022. The CCC is dated 26 February 2024, 455 days after the extended deadline; the register does not record the handover date. Construction ran through 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether the deadline already reflects it.
Does Premier Consortium have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of its three projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). Aman Heights (9948-1) and Residensi KLIA phase 1 (9948-2) are completed, and phase 2 (9948-3) is on schedule (Lancar).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Premier Consortium Sdn Bhd — developer profile · StarProperty (Star Media Group) · accessed 28 Oct 2026
https://www.starproperty.my/developer/221/premier-consortium-sdn-bhd - [2] TEDUH register: projects 9948-1, 9948-2 and 9948-3 (Premier Consortium Sdn Bhd) · Kementerian Perumahan dan Kerajaan Tempatan (KPKT) · 27 Oct 2026 · accessed 28 Oct 2026
https://teduh.kpkt.gov.my/
Last updated 28 Oct 2026