Map Profile
Helping you buy right
EN
Developer profile · KPKT records

Oxley (Oxley Holdings Limited)

Last updated 28 Oct 2026
Who is Oxley?

Oxley Holdings Limited is a Singapore property group listed on the SGX Main Board (5UX). Its Malaysian company Oxley Rising Sdn Bhd has one housing project in the KPKT register: Oxley Towers KLCC, 857 serviced apartments, completed with a CCC dated 18 August 2025. The group was incorporated in Singapore in 2010.

  • 1 project in the KPKT register
  • 1 completed
  • None Sick or Abandoned

Has Oxley handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists one Oxley housing project in Malaysia: MENARA OXLEY (KPKT 19325-1) by OXLEY RISING SDN. BHD., 857 units, completed. It is not classed Sick or Abandoned.

The handover deadline under the first sale agreement (25 Jun 2018) was 25 Jun 2021, extended with KPKT approval by 48 months to 25 Jun 2025; the CCC is dated 18 Aug 2025; vacant possession is recorded on 22 Aug 2025 and 31 Oct 2025, 58 days and 128 days after the extended deadline †.

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
MENARA OXLEYKPKT 19325-1Oxley Towers @ KLCC · on PropertySifuKuala LumpurWP Kuala Lumpur85725 Jun 2025Extended 48 months from 25 Jun 20211st sale agreement 25 Jun 2018CCC 18 Aug 2025
Handover 22 Aug 2025 / 31 Oct 2025
58–128 days after †

† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

Oxley at a glance

ListedSingapore Exchange (SGX) Main Board · 5UX · Catalist from October 2010, Main Board from February 2013[2]
StartedIncorporated in Singapore on 16 March 2010[2]
Head officeSingapore[2]
LeadershipChing Chiat Kwong — Executive Chairman and CEO[1]
Low See Ching (Eric) — Executive Director and Deputy CEO[4]
Eddie Lim Chee Chong — Executive Director, Oxley Holdings (Malaysia) Sdn Bhd[11]
Companies in the KPKT registerOXLEY RISING SDN. BHD. KPKT 19325[3]
Websiteoxley.com.sg
Projects (company figure)52 launched and 50 completed across all its markets since March 2010 (stated August 2026)[1]
MarketsSingapore, UK, Ireland, Cambodia, Malaysia, China[1]
Plans for MalaysiaTo exit progressively once all existing projects are completed (Annual Report 2025)[11]

Oxley projects on sale on PropertySifu

Oxley Towers @ KLCC

City Centre, Kuala Lumpur · From RM1,600,000
KPKT 19325-1: Completed with CCC (18 Aug 2025)

Who is Oxley? The company behind the projects

Oxley Holdings Limited was incorporated in Singapore on 16 March 2010, listed on SGX Catalist in October 2010 and moved to the SGX Main Board in February 2013 [2]. Across all its markets, the company says it has launched 52 projects and completed 50 since 2010; it operates in six: Singapore, the UK, Ireland, Cambodia, Malaysia and China [1]. Those are group-wide figures — in Malaysia's KPKT register, the project above is the only one under an Oxley company. Its Executive Chairman and CEO is Ching Chiat Kwong [1].

In Malaysia, Oxley completed the purchase of a freehold site in the KLCC area in December 2014 [5]. Oxley Towers KLCC on that site has two hotel towers with residences, an office tower and a retail podium: Tower 1 holds the 226-room SO/ Kuala Lumpur Hotel and the 590-unit SO/ Kuala Lumpur Residences; Tower 2 holds the 198-room The Langham, Kuala Lumpur and the 267-unit Jewel Residences [4]. Tower 2 was first announced with Jumeirah as its hotel and residence brand [6]. Since January 2021, Pavilion Project Management has overseen the project's management, construction, sales and administration under a partnership with Oxley [7].

Oxley sold the office tower and four retail parcels to Alliance Bank Malaysia in October 2023 for about RM406 million [8]; the tower was handed over in early 2025 [9]. On 29 August 2025 Oxley announced that construction had been completed [10]. In July 2026 the Langham hotel floors were sold for RM250 million to Artisan Hospitality Sdn Bhd, in which Oxley Rising holds 70% [3].

Oxley's 2025 annual report says the group will progressively exit China, Cambodia and Malaysia once all existing projects are completed [11]. The same report lists Trinity Wellnessa (CCC on 25 July 2025) and Trinity Sensoria (completion expected in 2028), both in Ampang North, among its Malaysian projects [11]; KPKT registers Trinity Wellnessa under Trinity Wellnessa & Enlivea Development Sdn Bhd, so it is not counted in the table above.

Frequently asked questions

Is Oxley a listed company?

Yes. Oxley Holdings Limited is listed on the Main Board of the Singapore Exchange (stock code 5UX). It listed on SGX Catalist in October 2010 and moved to the Main Board in February 2013 [2].

Has Oxley Towers KLCC been completed and handed over?

Yes. The KPKT register records the project (KPKT code 19325-1, 857 serviced-apartment units) as completed, with a CCC dated 18 August 2025 and vacant possession dates of 22 August 2025 for the 590-unit tower and 31 October 2025 for the 267-unit tower.

Was Oxley Towers KLCC handed over late?

The KPKT register shows a handover deadline of 25 June 2021 under the first sale agreement (signed 25 June 2018), extended with approval by 48 months to 25 June 2025. The recorded vacant possession dates are 58 and 128 days after that extended deadline. Construction ran through 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether the deadline already reflects it.

Is Pavilion the developer of Oxley Towers KLCC?

No. The developer registered with KPKT is Oxley Rising Sdn Bhd, a wholly-owned Oxley subsidiary [3]. Under a 2021 partnership, Pavilion Project Management oversees the project's management, construction, sales and administration [7].

Who owns the office tower and the hotels at Oxley Towers KLCC?

The office tower was sold to Alliance Bank Malaysia under an agreement made in October 2023 [8]. The Langham hotel floors belong to Artisan Hospitality Sdn Bhd, held 70% by Oxley Rising and 30% by Kindway Express [3]. Oxley has said it will look to divest the hotel business when the right opportunity arises [10].

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
  2. [1] Oxley FY2026 results press release · Oxley Holdings Limited via SGX · 29 Aug 2026 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/8673OPU9GC91QBCY/902918_Oxley%20FY2026%20Press%20Release.pdf
  3. [2] Corporate information: Oxley Holdings Limited · Singapore Exchange (SGX) · 28 Oct 2026 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-information/2477
  4. [3] Completion of sale of 30% interest in luxury hotel at Oxley Towers KLCC · Oxley Holdings Limited via SGX · 29 Jul 2026 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/ZVU46FFL5OLUWMTB/897730_Completion%20of%20Sale.pdf
  5. [4] Oxley FY2026 corporate update · Oxley Holdings Limited via SGX · 29 Aug 2026 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/8673OPU9GC91QBCY/902919_Oxley%20FY2026%20Corporate%20Update.pdf
  6. [5] Oxley 2QFY15 results news release · Oxley Holdings Limited via SGX · 12 Feb 2015 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/CL03Z6L66MWJUFOZ/334797_Oxley2Q2015PR.pdf
  7. [6] Oxley corporate presentation (development portfolio, Malaysia) · Oxley Holdings Limited via SGX · 11 Nov 2016 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/OGKHITG0ANY3NJU0/429173_Oxley%20Corporate%20Presentation%20-11.11.16.pdf
  8. [7] Oxley enters strategic partnership with Pavilion for the development of Oxley Towers, Kuala Lumpur City Centre · Oxley Holdings Limited via SGX · 19 Jan 2021 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/JLRTJHFPNTWDM7HF/645450_PR%20Partnership%20with%20Pavilion.pdf
  9. [8] Oxley 1HFY2024 results press release · Oxley Holdings Limited via SGX · 8 Feb 2024 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/UV1FHJY3UDU41MOP/786455_Oxley%201H2024%20PR.pdf
  10. [9] Oxley secures 100-unit sales arrangement at SO/ Residences, KLCC · Oxley Holdings Limited via SGX · 2 Jun 2025 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/LQLIDBP8O8BFUEH3/847832_KLCC%20SoResidences.pdf
  11. [10] From vision to reality: Oxley celebrates the construction completion of Oxley Towers KLCC · Oxley Holdings Limited via SGX · 29 Aug 2025 · accessed 28 Oct 2026
    https://links.sgx.com/1.0.0/corporate-announcements/AGA3EJ1TDZE0TMP3/857808_Oxley%20KLCC%20PR.pdf
  12. [11] Oxley Holdings Limited Annual Report 2025 · Oxley Holdings Limited · 2025-10 · accessed 28 Oct 2026
    https://www.oxley.com.sg/download/annual-reports-and-related-documents/?wpdmdl=4443

Last updated 28 Oct 2026