Who is Monisprings Development?

Monisprings Development Sdn Bhd is a private Malaysian developer with two housing projects in the KPKT register, both completed and neither classed Sick or Abandoned, in Setapak, Kuala Lumpur: Residensi Berlian Setapak (228 units), certified complete 193 days after its deadline, and Residensi Berlian Setapak 2 (263 units), handed over 651 days before its extended deadline.

  • 2 projects in the KPKT register
  • 2 completed
  • None Sick or Abandoned

Has Monisprings Development handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists 2 housing projects under 1 Monisprings Development company in 1 state: 2 completed. None is classed Sick (Sakit) or Abandoned (Terbengkalai).

Of the 2 completed projects, 2 have both a handover deadline and a completion date in the register: 1 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 1 handed over or certified complete after that deadline.

1 project had the delivery period extended with KPKT approval.

Completed projects — most recent first

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
RESIDENSI BERLIAN SETAPAK 2KPKT 14634-2Berlian 2 Setapak · on PropertySifuKuala LumpurWP Kuala Lumpur26314 Jul 2027Extended 12 months from 14 Jul 20261st sale agreement 14 Jul 2023CCC 23 Sep 2025
Handover 1 Oct 2025
651 days before
RESIDENSI BERLIAN SETAPAKKPKT 14634-1Kuala LumpurWP Kuala Lumpur22813 Mar 20201st sale agreement 13 Mar 2017CCC 22 Sep 2020193 days after

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

Monisprings Development at a glance

ListedNot listed — Monisprings Development Sdn Bhd is a private limited company
Companies in the KPKT registerMONISPRINGS DEVELOPMENT SDN. BHD. KPKT 14634[1]
Projects (KPKT register)Two condominium towers in Setapak, Kuala Lumpur: 228 units (33 storeys) and 263 units (38 storeys)[1]
Parent groupNot found: no annual report, exchange filing or mainstream report names its shareholders or a parent group[2]

Monisprings Development projects on sale on PropertySifu

Berlian 2 Setapak

Setapak, Kuala Lumpur · From RM646,000
KPKT 14634-2: Completed with CCC (23 Sep 2025)
Completed Monisprings Development projects nearby (KPKT):
  • RESIDENSI BERLIAN SETAPAK — 0.4 km, 2020

Who is Monisprings Development? The company behind the projects

Monisprings Development Sdn Bhd is the developer that KPKT registers for two condominium towers in Setapak, Kuala Lumpur [1]. Residensi Berlian Setapak, 33 storeys and 228 units, received its CCC on 22 September 2020. Residensi Berlian Setapak 2, 38 storeys and 263 units, is the project sold on PropertySifu as Berlian 2 Setapak; its CCC is dated 23 September 2025 and vacant possession is recorded on 1 October 2025.

Monisprings is a private limited company. We found no stock-exchange listing, annual report, exchange filing or mainstream news report that names its shareholders or links it to another developer group; Platinum Victory's own list of completed projects, for example, does not include the Berlian towers [2]. This page therefore covers Monisprings on its own.

Frequently asked questions

Who developed Berlian 2 Setapak?

KPKT registers it under Monisprings Development Sdn Bhd (KPKT developer code 14634) as Residensi Berlian Setapak 2 (14634-2), 263 units [1].

Has Berlian 2 Setapak been completed and handed over?

Yes. KPKT records the first sale agreement on 14 July 2023 and a handover deadline of 14 July 2026, extended with approval by 12 months to 14 July 2027. The CCC is dated 23 September 2025 and vacant possession 1 October 2025, 651 days before the extended deadline.

Was the first Residensi Berlian Setapak handed over on time?

KPKT records the first sale agreement on 13 March 2017 and a handover deadline of 13 March 2020, with no extension. The CCC is dated 22 September 2020, 193 days after the deadline; the register does not record the handover date.

Is Berlian 2 Setapak a Platinum Victory project?

KPKT registers it under Monisprings Development Sdn Bhd. We found no annual report, exchange filing or mainstream news report linking Monisprings to Platinum Victory, and Platinum Victory's own list of completed projects does not include the Berlian towers [2].

Is Monisprings a listed company?

No stock-exchange listing was found. Monisprings Development Sdn Bhd is a private limited company.

Does Monisprings have any Sick or Abandoned projects?

No. As at 27 October 2026, both of its KPKT projects are completed, and neither is classed Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat).

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
  2. [1] TEDUH — housing developer and project records · Ministry of Local Government Development (KPKT) · accessed 28 Oct 2026
    https://teduh.kpkt.gov.my/
  3. [2] Our development — completed projects · Platinum Victory · accessed 28 Oct 2026
    https://www.platinumvictory.com/our-development/completed-project/

Last updated 28 Oct 2026