MKH (MKH Berhad)
MKH Berhad, a Kajang developer founded in 1979 and listed on Bursa Malaysia since 1995, has 86 housing projects in the KPKT register under 22 group companies: 76 completed, 7 under construction (one classed Late), 1 not started and 2 with the permit cancelled, none Sick or Abandoned. Its shares have been suspended since 16 October 2026 after Batu Kawan's takeover.
- 86 projects in the KPKT register
- 76 completed
- 7 under construction
- 1 not yet started
- 2 with the permit cancelled
- None Sick or Abandoned
Has MKH handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 86 housing projects under 22 MKH companies in 3 states: 76 completed, 7 under construction, 1 not yet started, 2 with the permit cancelled. 0 classed Sick (Sakit), 0 Abandoned (Terbengkalai), 1 Late (Lewat).
Of the 76 completed projects, 50 have both a handover deadline and a completion date in the register: 5 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 21 handed over or certified complete after that deadline; 24 received the completion certificate before the deadline (handover date not recorded).
19 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 76
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 507 | 15 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020 | CCC 19 Dec 2025 Handover 19 Dec 2025 | 34 days after |
| KAJANG 2 PRESINT 3 (AKINA)KPKT 30120-3 | Hulu LangatSelangor | 171 | 31 Jul 20251st sale agreement 31 Jul 2023 | CCC 11 Jul 2025 Handover 16 Jul 2025 | 15 days before |
| MIRAI RESIDENCESKPKT 19979-1 | Hulu LangatSelangor | 1,496 | 2 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020 | CCC 28 Feb 2025 Handover 4 Mar 2025 | 2 days after |
| KAJANG 2 PRESINT 3KPKT 30120-1 | Hulu LangatSelangor | 156 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| KAJANG 2 PRESINT 3KPKT 30120-2 | Hulu LangatSelangor | 120 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12 | Kuala SelangorSelangor | 241 | 27 Sep 20231st sale agreement 27 Sep 2021 | CCC 13 Mar 2024 Handover 13 Mar 2024 / 14 Mar 2024 | 168–169 days after |
| RESIDENSI PR1MA@KAJANGKPKT 11865-5 | Hulu LangatSelangor | 393 | 23 Apr 2024Extended 23 months from 23 May 20221st sale agreement 23 May 2019 | CCC 9 Feb 2024 Handover 11 Mar 2024 | 43 days before |
| NEXUS @ KAJANG STATIONKPKT 11865-6 | Hulu LangatSelangor | 393 | 27 Mar 2024Extended 21 months from 27 Jun 20221st sale agreement 27 Jun 2019 | CCC 9 Feb 2024 Handover 11 Mar 2024 | 16 days before |
| NEXUS @ KAJANG STATIONKPKT 11865-7 | Hulu LangatSelangor | 416 | 1 Jul 2024Extended 23 months from 1 Aug 20221st sale agreement 1 Aug 2019 | CCC 9 Feb 2024 Handover 11 Mar 2024 | 112 days before |
| MKH BOULEVARD IIKPKT 10332-2 | Hulu LangatSelangor | 604 | 29 Sep 2023Extended 23 months from 29 Oct 20211st sale agreement 29 Oct 2018 | CCC 4 Jul 2023 Handover 7 Jul 2023 | 84 days before |
| INSPIRASI MONT KIARAKPKT 19283-1 | Kuala LumpurWP Kuala Lumpur | 640 | 6 Mar 2023Extended 25 months from 6 Feb 20211st sale agreement 6 Feb 2018 | CCC 6 Jul 2022 | CCC before deadline; handover not recorded |
| KAJANG EAST-PRECINCT 1 (FASA 3A)KPKT 9531-10 | Hulu LangatSelangor | 40 | 15 Nov 2022Extended 5 months from 15 Jun 20221st sale agreement 15 Jun 2020 | CCC 4 Jul 2022 | CCC before deadline; handover not recorded |
Handed over or certified complete after the deadline — 12 most recent of 21
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 507 | 15 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020 | CCC 19 Dec 2025 Handover 19 Dec 2025 | 34 days after |
| MIRAI RESIDENCESKPKT 19979-1 | Hulu LangatSelangor | 1,496 | 2 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020 | CCC 28 Feb 2025 Handover 4 Mar 2025 | 2 days after |
| KAJANG 2 PRESINT 3KPKT 30120-1 | Hulu LangatSelangor | 156 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| KAJANG 2 PRESINT 3KPKT 30120-2 | Hulu LangatSelangor | 120 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12 | Kuala SelangorSelangor | 241 | 27 Sep 20231st sale agreement 27 Sep 2021 | CCC 13 Mar 2024 Handover 13 Mar 2024 / 14 Mar 2024 | 168–169 days after |
| HILLPARK RESIDENCEKPKT 11120-5 | Hulu LangatSelangor | 402 | 13 Mar 2020Extended 6 months from 13 Sep 20191st sale agreement 13 Sep 2016 | CCC 13 Aug 2020 | 153 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-11 | Kuala SelangorSelangor | 301 | 18 Sep 20191st sale agreement 18 Sep 2017 | CCC 17 Oct 2019 | 29 days after |
| SAVILLE BANGSAR @ THE PARKKPKT 11868-1 | Kuala LumpurWP Kuala Lumpur | 426 | 22 Mar 20151st sale agreement 22 Mar 2012 | CCC 15 Oct 2019 | 1,668 days after |
| SAVILLE@D'LAKEKPKT 14252-1Saville D'Lake · on PropertySifu | SepangSelangor | 305 | 18 Apr 20191st sale agreement 18 Apr 2016 | CCC 7 Aug 2019 | 111 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-10 | Kuala SelangorSelangor | 381 | 29 May 20191st sale agreement 29 May 2017 | CCC 8 Jul 2019 | 40 days after |
| SAVILLE CHERASKPKT 13982-1Saville @ Cheras · on PropertySifu | Hulu LangatSelangor | 352 | 25 Jun 20181st sale agreement 25 Jun 2015 | CCC 19 Sep 2018 | 86 days after |
| SAVILLE@KAJANGKPKT 11398-4 | Hulu LangatSelangor | 576 | 16 Jun 20171st sale agreement 16 Jun 2014 | CCC 15 Dec 2017 | 182 days after |
Show all 21
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 507 | 15 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020 | CCC 19 Dec 2025 Handover 19 Dec 2025 | 34 days after |
| MIRAI RESIDENCESKPKT 19979-1 | Hulu LangatSelangor | 1,496 | 2 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020 | CCC 28 Feb 2025 Handover 4 Mar 2025 | 2 days after |
| KAJANG 2 PRESINT 3KPKT 30120-1 | Hulu LangatSelangor | 156 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| KAJANG 2 PRESINT 3KPKT 30120-2 | Hulu LangatSelangor | 120 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12 | Kuala SelangorSelangor | 241 | 27 Sep 20231st sale agreement 27 Sep 2021 | CCC 13 Mar 2024 Handover 13 Mar 2024 / 14 Mar 2024 | 168–169 days after |
| HILLPARK RESIDENCEKPKT 11120-5 | Hulu LangatSelangor | 402 | 13 Mar 2020Extended 6 months from 13 Sep 20191st sale agreement 13 Sep 2016 | CCC 13 Aug 2020 | 153 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-11 | Kuala SelangorSelangor | 301 | 18 Sep 20191st sale agreement 18 Sep 2017 | CCC 17 Oct 2019 | 29 days after |
| SAVILLE BANGSAR @ THE PARKKPKT 11868-1 | Kuala LumpurWP Kuala Lumpur | 426 | 22 Mar 20151st sale agreement 22 Mar 2012 | CCC 15 Oct 2019 | 1,668 days after |
| SAVILLE@D'LAKEKPKT 14252-1Saville D'Lake · on PropertySifu | SepangSelangor | 305 | 18 Apr 20191st sale agreement 18 Apr 2016 | CCC 7 Aug 2019 | 111 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-10 | Kuala SelangorSelangor | 381 | 29 May 20191st sale agreement 29 May 2017 | CCC 8 Jul 2019 | 40 days after |
| SAVILLE CHERASKPKT 13982-1Saville @ Cheras · on PropertySifu | Hulu LangatSelangor | 352 | 25 Jun 20181st sale agreement 25 Jun 2015 | CCC 19 Sep 2018 | 86 days after |
| SAVILLE@KAJANGKPKT 11398-4 | Hulu LangatSelangor | 576 | 16 Jun 20171st sale agreement 16 Jun 2014 | CCC 15 Dec 2017 | 182 days after |
| KAJANG EASTKPKT 9531-6 | Hulu LangatSelangor | 229 | 15 Sep 20171st sale agreement 15 Sep 2014 | CCC 24 Oct 2017 | 39 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-5 | Kuala SelangorSelangor | 382 | 23 May 20171st sale agreement 23 May 2015 | CCC 19 Jul 2017 | 57 days after |
| HILLPARK3 (FASA 2)KPKT 11120-3 | Hulu LangatSelangor | 106 | 9 Feb 20171st sale agreement 9 Feb 2015 | CFO 3 Mar 2017 | 22 days after |
| MKH BOULEVARDKPKT 10470-4 | Hulu LangatSelangor | 308 | 30 May 20161st sale agreement 30 May 2013 | CCC 8 Aug 2016 | 70 days after |
| PELANGI HEIGHTS (SEMI-D & BUNGALOW)KPKT 8897-11 | SerembanNegeri Sembilan | 38 | 2 May 20161st sale agreement 2 May 2014 | CCC 3 Jun 2016 | 32 days after |
| HILLPARK, SHAH ALAMKPKT 12278-3 | Kuala SelangorSelangor | 232 | 13 Feb 20161st sale agreement 13 Feb 2014 | CCC 9 Mar 2016 | 25 days after |
| PELANGI HEIGHTSKPKT 8897-10 | SerembanNegeri Sembilan | 46 | 21 Oct 20151st sale agreement 21 Oct 2013 | CFO 25 Nov 2015 | 35 days after |
| PELANGI SERI ALAMKPKT 11865-3 | Kuala SelangorSelangor | 131 | 12 Aug 20141st sale agreement 12 Aug 2012 | CCC 29 Oct 2014 | 78 days after |
| SRIJANG KEMAJUAN SDN BHDKPKT 11398-2 | Hulu LangatSelangor | 52 | 30 Jun 20141st sale agreement 30 Jun 2012 | CCC 30 Sep 2014 | 92 days after |
Show all 76 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 507 | 15 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020 | CCC 19 Dec 2025 Handover 19 Dec 2025 | 34 days after |
| KAJANG 2 PRESINT 3 (AKINA)KPKT 30120-3 | Hulu LangatSelangor | 171 | 31 Jul 20251st sale agreement 31 Jul 2023 | CCC 11 Jul 2025 Handover 16 Jul 2025 | 15 days before |
| MIRAI RESIDENCESKPKT 19979-1 | Hulu LangatSelangor | 1,496 | 2 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020 | CCC 28 Feb 2025 Handover 4 Mar 2025 | 2 days after |
| KAJANG 2 PRESINT 3KPKT 30120-1 | Hulu LangatSelangor | 156 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| KAJANG 2 PRESINT 3KPKT 30120-2 | Hulu LangatSelangor | 120 | 19 Sep 20241st sale agreement 19 Sep 2022 | CCC 18 Oct 2024 Handover 18 Oct 2024 | 29 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12 | Kuala SelangorSelangor | 241 | 27 Sep 20231st sale agreement 27 Sep 2021 | CCC 13 Mar 2024 Handover 13 Mar 2024 / 14 Mar 2024 | 168–169 days after |
| RESIDENSI PR1MA@KAJANGKPKT 11865-5 | Hulu LangatSelangor | 393 | 23 Apr 2024Extended 23 months from 23 May 20221st sale agreement 23 May 2019 | CCC 9 Feb 2024 Handover 11 Mar 2024 | 43 days before |
| NEXUS @ KAJANG STATIONKPKT 11865-6 | Hulu LangatSelangor | 393 | 27 Mar 2024Extended 21 months from 27 Jun 20221st sale agreement 27 Jun 2019 | CCC 9 Feb 2024 Handover 11 Mar 2024 | 16 days before |
| NEXUS @ KAJANG STATIONKPKT 11865-7 | Hulu LangatSelangor | 416 | 1 Jul 2024Extended 23 months from 1 Aug 20221st sale agreement 1 Aug 2019 | CCC 9 Feb 2024 Handover 11 Mar 2024 | 112 days before |
| MKH BOULEVARD IIKPKT 10332-2 | Hulu LangatSelangor | 604 | 29 Sep 2023Extended 23 months from 29 Oct 20211st sale agreement 29 Oct 2018 | CCC 4 Jul 2023 Handover 7 Jul 2023 | 84 days before |
| INSPIRASI MONT KIARAKPKT 19283-1 | Kuala LumpurWP Kuala Lumpur | 640 | 6 Mar 2023Extended 25 months from 6 Feb 20211st sale agreement 6 Feb 2018 | CCC 6 Jul 2022 | CCC before deadline; handover not recorded |
| KAJANG EAST-PRECINCT 1 (FASA 3A)KPKT 9531-10 | Hulu LangatSelangor | 40 | 15 Nov 2022Extended 5 months from 15 Jun 20221st sale agreement 15 Jun 2020 | CCC 4 Jul 2022 | CCC before deadline; handover not recorded |
| KAJANG EAST - PRECINT 1 (FASA 1)KPKT 9531-9 | Hulu LangatSelangor | 80 | 28 Apr 2022Extended 11 months from 28 May 20211st sale agreement 28 May 2019 | CCC 18 Apr 2022 | CCC before deadline; handover not recorded |
| TR RESIDENSIKPKT 19049-1 | Kuala LumpurWP Kuala Lumpur | 642 | 30 Dec 2021Extended 18 months from 30 Jun 20201st sale agreement 30 Jun 2017 | CCC 29 Jul 2021 | CCC before deadline; handover not recorded |
| KAJANG EAST - PRECINCT 1 (PHASE 4)KPKT 9531-7 | Hulu LangatSelangor | 86 | 12 May 2021Extended 6 months from 12 Nov 20201st sale agreement 12 Nov 2018 | CCC 28 Apr 2021 | CCC before deadline; handover not recorded |
| KAJANG EAST - PRECINCT 1 (PHASE 2)KPKT 9531-8 | Hulu LangatSelangor | 135 | 12 May 2021Extended 6 months from 12 Nov 20201st sale agreement 12 Nov 2018 | CCC 28 Apr 2021 | CCC before deadline; handover not recorded |
| KAJANG 2, PRESINT 2 (FASA 3)KPKT 19140-1 | Hulu LangatSelangor | 88 | 19 Mar 2021Extended 18 months from 19 Sep 20191st sale agreement 19 Sep 2017 | CCC 8 Mar 2021 | CCC before deadline; handover not recorded |
| KAJANG 2, PRESINT 2 (FASA 4)KPKT 19140-2 | Hulu LangatSelangor | 96 | 14 May 2021Extended 18 months from 14 Nov 20191st sale agreement 14 Nov 2017 | CCC 8 Mar 2021 | CCC before deadline; handover not recorded |
| HILLPARK RESIDENCEKPKT 11120-5 | Hulu LangatSelangor | 402 | 13 Mar 2020Extended 6 months from 13 Sep 20191st sale agreement 13 Sep 2016 | CCC 13 Aug 2020 | 153 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-11 | Kuala SelangorSelangor | 301 | 18 Sep 20191st sale agreement 18 Sep 2017 | CCC 17 Oct 2019 | 29 days after |
| SAVILLE BANGSAR @ THE PARKKPKT 11868-1 | Kuala LumpurWP Kuala Lumpur | 426 | 22 Mar 20151st sale agreement 22 Mar 2012 | CCC 15 Oct 2019 | 1,668 days after |
| SAVILLE@D'LAKEKPKT 14252-1Saville D'Lake · on PropertySifu | SepangSelangor | 305 | 18 Apr 20191st sale agreement 18 Apr 2016 | CCC 7 Aug 2019 | 111 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-10 | Kuala SelangorSelangor | 381 | 29 May 20191st sale agreement 29 May 2017 | CCC 8 Jul 2019 | 40 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-9 | Kuala SelangorSelangor | 132 | 26 Apr 20191st sale agreement 26 Apr 2017 | CCC 30 Nov 2018 | CCC before deadline; handover not recorded |
| SAVILLE CHERASKPKT 13982-1Saville @ Cheras · on PropertySifu | Hulu LangatSelangor | 352 | 25 Jun 20181st sale agreement 25 Jun 2015 | CCC 19 Sep 2018 | 86 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-6 | Kuala SelangorSelangor | 257 | 16 Sep 20181st sale agreement 16 Sep 2016 | CCC 12 Sep 2018 | CCC before deadline; handover not recorded |
| HILLPARK 3 (FASA 1)KPKT 11120-4 | Hulu LangatSelangor | 184 | 8 Jan 20181st sale agreement 8 Jan 2016 | CCC 19 Dec 2017 | CCC before deadline; handover not recorded |
| SAVILLE@KAJANGKPKT 11398-4 | Hulu LangatSelangor | 576 | 16 Jun 20171st sale agreement 16 Jun 2014 | CCC 15 Dec 2017 | 182 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-7 | Kuala SelangorSelangor | 233 | 22 Mar 20181st sale agreement 22 Mar 2016 | CCC 8 Dec 2017 | CCC before deadline; handover not recorded |
| KAJANG EASTKPKT 9531-6 | Hulu LangatSelangor | 229 | 15 Sep 20171st sale agreement 15 Sep 2014 | CCC 24 Oct 2017 | 39 days after |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-5 | Kuala SelangorSelangor | 382 | 23 May 20171st sale agreement 23 May 2015 | CCC 19 Jul 2017 | 57 days after |
| PELANGI HEIGHTS - PHASE 1BKPKT 8897-15 | SerembanNegeri Sembilan | 18 | 30 Sep 20181st sale agreement 30 Sep 2016 | CCC 10 Jun 2017 | CCC before deadline; handover not recorded |
| KAJANG EASTKPKT 9531-5 | Hulu LangatSelangor | 89 | 15 May 20171st sale agreement 15 May 2015 | CCC 13 Apr 2017 | CCC before deadline; handover not recorded |
| PELANGI HEIGHTSKPKT 8897-13 | SerembanNegeri Sembilan | 71 | 13 Mar 20171st sale agreement 13 Mar 2015 | CCC 10 Mar 2017 | CCC before deadline; handover not recorded |
| PELANGI HEIGHTSKPKT 8897-14 | SerembanNegeri Sembilan | 122 | 14 Aug 20171st sale agreement 14 Aug 2015 | CCC 10 Mar 2017 | CCC before deadline; handover not recorded |
| HILLPARK3 (FASA 2)KPKT 11120-3 | Hulu LangatSelangor | 106 | 9 Feb 20171st sale agreement 9 Feb 2015 | CFO 3 Mar 2017 | 22 days after |
| HILLPARK 3 - FASA 2(A)KPKT 11120-6 | Hulu LangatSelangor | 14 | — | CFO 3 Mar 2017 | — |
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-4 | Kuala SelangorSelangor | 236 | 8 Feb 20171st sale agreement 8 Feb 2015 | CCC 3 Feb 2017 | CCC before deadline; handover not recorded |
| MKH BOULEVARDKPKT 10470-4 | Hulu LangatSelangor | 308 | 30 May 20161st sale agreement 30 May 2013 | CCC 8 Aug 2016 | 70 days after |
| PELANGI HEIGHTS (SEMI-D & BUNGALOW)KPKT 8897-11 | SerembanNegeri Sembilan | 38 | 2 May 20161st sale agreement 2 May 2014 | CCC 3 Jun 2016 | 32 days after |
| PELANGI HEIGHTS (SEMI-D & BUNGALOW)KPKT 8897-12 | SerembanNegeri Sembilan | 45 | 3 Nov 20161st sale agreement 3 Nov 2014 | CCC 3 Jun 2016 | CCC before deadline; handover not recorded |
| HILLPARK SHAH ALAMKPKT 12278-1 | Kuala SelangorSelangor | 343 | 17 May 20161st sale agreement 17 May 2014 | CCC 16 May 2016 | CCC before deadline; handover not recorded |
| HILLPARK, SHAH ALAMKPKT 12278-3 | Kuala SelangorSelangor | 232 | 13 Feb 20161st sale agreement 13 Feb 2014 | CCC 9 Mar 2016 | 25 days after |
| KAJANG EASTKPKT 9531-4 | Hulu LangatSelangor | 116 | 16 Dec 20151st sale agreement 16 Dec 2013 | CFO 15 Dec 2015 | CCC before deadline; handover not recorded |
| PELANGI HEIGHTSKPKT 8897-10 | SerembanNegeri Sembilan | 46 | 21 Oct 20151st sale agreement 21 Oct 2013 | CFO 25 Nov 2015 | 35 days after |
| RESIDENSI WARNASARI 2KPKT 11865-4 | Kuala SelangorSelangor | 450 | 11 Oct 20151st sale agreement 11 Oct 2012 | CCC 14 Sep 2015 | CCC before deadline; handover not recorded |
| HILLPARK, SHAH ALAMKPKT 12278-2 | Kuala SelangorSelangor | 311 | 20 Aug 20151st sale agreement 20 Aug 2013 | CCC 19 Aug 2015 | CCC before deadline; handover not recorded |
| PELANGI SEMENYIH 2KPKT 11335-8 | Hulu LangatSelangor | 8 | 17 Apr 20151st sale agreement 17 Apr 2013 | CFO 6 Feb 2015 | CCC before deadline; handover not recorded |
| PELANGI SEMENYIH 2KPKT 11335-7 | Hulu LangatSelangor | 62 | 15 Apr 20151st sale agreement 15 Apr 2013 | CFO 9 Jan 2015 | CCC before deadline; handover not recorded |
| PELANGI SERI ALAMKPKT 11865-3 | Kuala SelangorSelangor | 131 | 12 Aug 20141st sale agreement 12 Aug 2012 | CCC 29 Oct 2014 | 78 days after |
| SRIJANG KEMAJUAN SDN BHDKPKT 11398-2 | Hulu LangatSelangor | 52 | 30 Jun 20141st sale agreement 30 Jun 2012 | CCC 30 Sep 2014 | 92 days after |
| MEWAH 9 RESIDENCEKPKT 9531-3 | Hulu LangatSelangor | 120 | — | CCC 18 Jul 2014 | — |
| PELANGI SERI ALAMKPKT 11865-2 | Kuala SelangorSelangor | 153 | — | CCC 3 Apr 2014 | — |
| PELANGI SEMENYIH 2KPKT 11335-6 | Hulu LangatSelangor | 173 | — | CFO 25 Mar 2014 | — |
| PELANGI SEMENYIH 2KPKT 11335-9 | Hulu LangatSelangor | 70 | — | CFO 24 Jan 2014 | — |
| PELANGI SERI ALAMKPKT 11865-1 | Kuala SelangorSelangor | 114 | — | CCC 27 Dec 2013 | — |
| SAVILLE @ MELAWATIKPKT 11367-1 | Kuala LumpurWP Kuala Lumpur | 0 | — | CCC 27 Dec 2013 | — |
| PELANGI SEMENYIH 2KPKT 11335-5 | Hulu LangatSelangor | 66 | — | CFO 18 Oct 2013 | — |
| PELANGI SEMENYIH 2KPKT 11335-3 | Hulu LangatSelangor | 166 | — | CFO 10 May 2013 | — |
| PELANGI SEMENYIH 2KPKT 11335-4 | Hulu LangatSelangor | 40 | — | CFO 10 May 2013 | — |
| KAJANG 2KPKT 11398-1 | Hulu LangatSelangor | 191 | — | CCC 30 Apr 2013 | — |
| HILL PARK 2KPKT 11120-2 | Hulu LangatSelangor | 399 | — | CCC 17 Jan 2013 | — |
| PELANGI SEMENYIH 2KPKT 11335-2 | Hulu LangatSelangor | 145 | — | CCC 31 Dec 2012 | — |
| PELANGI SEMENYIH 2KPKT 11335-1 | Hulu LangatSelangor | 233 | — | CCC 14 Sep 2012 | — |
| SENTOSA HEIGHTSKPKT 10470-2 | Hulu LangatSelangor | 55 | — | CCC 20 Jul 2012 | — |
| HILL PARK HOMEKPKT 11120-1 | Hulu LangatSelangor | 272 | — | CCC 9 Dec 2011 | — |
| ALIRAN PERKASA SDN. BHD.KPKT 9531-2 | Hulu LangatSelangor | 36 | — | CFO 12 Jan 2011 | — |
| PELANGI SEMENYIHKPKT 8897-9 | Hulu LangatSelangor | 335 | — | CCC 16 Nov 2010 | — |
| SENTOSA VILLA @ KAJANGKPKT 10470-1 | Hulu LangatSelangor | 73 | — | CFO 2 Apr 2010 | — |
| PELANGI SEMENYIHKPKT 8897-7 | Hulu LangatSelangor | 256 | — | CFO 14 Dec 2009 | — |
| ZEN PARK CHERASKPKT 10332-1 | Hulu LangatSelangor | 47 | — | CFO 25 May 2009 | — |
| TAMAN BUKIT MEWAHKPKT 6029-2 | Hulu LangatSelangor | 34 | — | CFO 26 Nov 2008 | — |
| TAMAN PELANGI SEMENYIHKPKT 8897-6 | Hulu LangatSelangor | 200 | — | CFO 24 Sep 2008 | — |
| PELANGI SEMENYIH (FASA 5)KPKT 8897-5 | Hulu LangatSelangor | 153 | — | CFO 6 Jul 2007 | — |
| TAMAN BUKIT MEWAHKPKT 9531-1 | Hulu LangatSelangor | 67 | — | CFO 21 Dec 2006 | — |
| PELANGI SEMENYIH (FASA 4)KPKT 8897-4 | Hulu LangatSelangor | 184 | — | CFO 19 Jan 2006 | — |
Under construction (7) and not yet started (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI TUN RAZAK 2KPKT 20082-1 | Kuala LumpurWP Kuala Lumpur | 918 | DelayLate | 14 Dec 2026Extended 24 months from 14 Dec 20241st sale agreement 14 Dec 2021 | 62–64% |
| ANNYA KAJANG 2 PRESINT 3KPKT 30120-4 | Hulu LangatSelangor | 171 | SmoothOn schedule | 7 Jul 20281st sale agreement 7 Jul 2026 | 5–17% |
| RESIDENSI NALURIKPKT 30750-1Residensi Naluri · on PropertySifu | Hulu LangatSelangor | 733 | SmoothOn schedule | 10 Jan 2029Extended 16 months from 10 Sep 20271st sale agreement 10 Sep 2024 | 25–26% |
| GAYA RESIDENCYKPKT 19979-2 | Hulu LangatSelangor | 494 | SmoothOn schedule | 18 Jan 2029Extended 16 months from 18 Sep 20271st sale agreement 18 Sep 2024 | 25% |
| RESIDENSI PINANGKPKT 12278-13 | Kuala SelangorSelangor | 177 | SmoothOn schedule | 14 Jun 20291st sale agreement 14 Jun 2026 | 61% |
| GAYA RESIDENCYKPKT 19979-3 | Hulu LangatSelangor | 494 | SmoothOn schedule | 18 Sep 20291st sale agreement 18 Sep 2026 | 20% |
| RESIDENSI NALURIKPKT 30750-2 | Hulu LangatSelangor | 720 | SmoothOn schedule | 28 Aug 2030Extended 16 months from 28 Apr 20291st sale agreement 28 Apr 2026 | 22% |
| KAJANG EAST - PRECINCT 1 (FASA 3B)KPKT 9531-11 | Hulu LangatSelangor | 27 | SmoothNot started | — | 0% |
Permit cancelled or other KPKT status (2)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| BANDAR HILLPARK PUNCAK ALAMKPKT 12278-8 | Kuala SelangorSelangor | 396 | Permit cancelledPermit cancelled | — | 0–20% |
| AURELIAKPKT 11398-3 | Hulu LangatSelangor | 149 | Permit cancelledPermit cancelled | — | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
MKH at a glance
| Listed | Bursa Malaysia Main Market · MKH (6114) · listed 1995 · trading suspended from 16 October 2026 after the Batu Kawan takeover; the offerors plan to withdraw the listing[5][4][9] |
|---|---|
| Started | 1979 in Kajang, Selangor, as Srijang Bena Sdn Bhd[5] |
| Head office | Wisma MKH, Jalan Semenyih, Kajang, Selangor[4] |
| Leadership | Tan Sri Dato' Chen Kooi Chiew @ Cheng Ngi Chong — Group Executive Chairman, 30 October 2006 – 19 August 2026 (director since 1979)[6] Tan Sri Datuk Chen Lok Loi — Group Managing Director, 19 January 2005 – 19 August 2026[7] |
| Companies in the KPKT register | ALIRAN PERKASA SDN. BHD. KPKT 9531[1] GERAK TEGUH SDN. BHD. KPKT 8897[1] MKH HEALTHCARE SDN. BHD. KPKT 11335[1] METRO K.L. CITY SDN. BHD. KPKT 11865[1] PETIK MEKAR SDN. BHD. KPKT 30120[1] SRIJANG KEMAJUAN SDN. BHD. (99.99%) KPKT 11398[1] MKH PROPERTY VENTURES SDN. BHD. (51%) KPKT 19979[1] DANAU SAUJANA SDN. BHD. (65%) KPKT 30750[1] STAND ALLIED CORPORATION SDN. BHD. KPKT 10332[1] SURIA VILLA SDN. BHD. KPKT 19140[1] ACHIEVE ACRES SDN. BHD. (85%) KPKT 14252[1] MKH DEVELOPMENT SDN. BHD. KPKT 20010[1] PERKASA BERNAS (M) SDN. BHD. KPKT 11367[1] QUANTUM DENSITY SDN. BHD. (50.0004%) KPKT 20082[1] SUMBER LENGKAP SDN. BHD. KPKT 6029[1] TEMARA PEKELILING SDN. BHD. (50.4%) KPKT 19049[1] VISTA HARUMAN DEVELOPMENT SDN. BHD. (55%) KPKT 13982[1] KAJANG RESOURCES CORPORATION SDN.BHD. KPKT 11120[1] SERBA SENTOSA SDN. BHD. KPKT 10470[1] AMONA METRO DEVELOPMENT SDN. BHD. (60%) KPKT 11868[1] ALIF MESRA SDN. BHD. (65%) KPKT 19283[1] HILLPARK RESOURCES SDN. BHD. KPKT 12278[1] |
| Website | mkhberhad.com |
| Started | 1979 in Kajang, as Srijang Bena Sdn Bhd; renamed Metro Kajang Holdings Berhad on listing in 1995 and MKH Berhad in 2011[5] |
| Projects completed (company figure) | More than 59 property projects (2025 annual report)[3] |
| Ownership | 96.73% held by Batu Kawan Bhd, its unit Whitmore Holdings and parties acting in concert when the RM2 offer closed on 8 October 2026[9] |
| Other businesses | Building materials trading, property investment and, since 2008, oil palm plantations in East Kalimantan, Indonesia[5] |
MKH projects on sale on PropertySifu
Nexus Residences
- SAVILLE CHERAS — 7.3 km, 2018
- TR RESIDENSI — 7.8 km, 2021
- SAVILLE BANGSAR @ THE PARK — 7.9 km, 2019
Residensi Naluri
- SAVILLE CHERAS — 1.1 km, 2018
- MKH BOULEVARD — 7.1 km, 2016
- MKH BOULEVARD II — 7.4 km, 2023
Who is MKH? The company behind the projects
MKH started in Kajang in 1979 as Srijang Bena Sdn Bhd, building its first residential township that year, its first high-rise in 1993 and Kajang's first shopping complex in 1994 [5]. On its listing on the Main Market of Bursa Malaysia in 1995 it became Metro Kajang Holdings Berhad, and it was renamed MKH Berhad in 2011 [5]; its stock name is MKH and its code 6114 [4]. The registered office is at Wisma MKH in Kajang [4]. Besides property development, MKH trades building materials, holds investment properties and, since 2008, runs oil palm plantations in East Kalimantan, Indonesia [5].
MKH says it has completed more than 59 property projects (2025 annual report) [3]. That is the company's own count; the KPKT register lists each licensed phase separately, which gives the 86 projects under 22 MKH companies above. Several of these companies are not wholly owned: the 2025 annual report gives MKH 65% of Danau Saujana, 55% of Vista Haruman Development, 85% of Achieve Acres, 51% of MKH Property Ventures, and about 50% of Quantum Density and Temara Pekeliling [1].
Of the MKH projects on PropertySifu, Nexus Residences in Cheras is developed by MKH Development Sdn Bhd, Residensi Naluri by Danau Saujana Sdn Bhd, Saville @ Cheras by Vista Haruman Development Sdn Bhd and Saville D'Lake by Achieve Acres Sdn Bhd [1]. Jernih Residence in Kajang is a separate case: its developer, Daksina Harta Sdn Bhd, was set up in 2018 as a joint venture in which Sunway holds 60% and MKH 40% [12], and MKH's 2025 annual report lists it as a 40% associate [2]; it is not counted in the table above.
In 2026 Batu Kawan Bhd, through its wholly owned Whitmore Holdings, agreed to buy a combined 47.7% of MKH at RM2 a share from Chen Choy & Sons Realty Sdn Bhd and related parties [10], which led to a general offer for the remaining shares. When the offer closed on 8 October 2026 the offerors held 96.73%; trading in MKH shares was suspended from 16 October 2026, and the offerors said they would take steps to withdraw MKH's listing [9]. Group Executive Chairman Tan Sri Dato' Chen Kooi Chiew @ Cheng Ngi Chong, a director since 1979, and Group Managing Director Tan Sri Datuk Chen Lok Loi resigned on 19 August 2026 ahead of the offer's first closing date [6][7]; the same day Lee Wen Ling, managing director of KLK Land, joined the board as a non-executive director [8].
Frequently asked questions
Is MKH a listed company?
MKH Berhad has been listed on the Main Market of Bursa Malaysia since 1995 (stock code 6114) [5][4]. After Batu Kawan's takeover offer closed on 8 October 2026 with the offerors holding 96.73%, trading in its shares was suspended from 16 October 2026, and the offerors said they would take steps to withdraw the listing [9].
Does MKH have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of MKH's 86 projects as Sick (Sakit) or Abandoned (Terbengkalai). One is classed Late (Lewat): RESIDENSI TUN RAZAK 2 in Kuala Lumpur (KPKT 20082-1, 918 units, Quantum Density Sdn Bhd), which MKH's annual report calls TR2 Residence [13]. Its first sale agreement was signed on 14 December 2021; the deadline of 14 December 2024 was extended with approval by 24 months to 14 December 2026, and reported construction progress is 61.75–64.2%. Two other projects are recorded with the permit cancelled.
Was Nexus Residences in Cheras handed over on time?
KPKT registers it as RESIDENSI NEKSUS TAMAN PERTAMA (20010-1, 507 units, MKH Development Sdn Bhd). The first sale agreement was signed on 15 December 2020 and the deadline of 15 December 2023 was extended with approval by 23 months to 15 November 2025. The CCC and vacant possession are both dated 19 December 2025, 34 days after the extended deadline.
Were Saville @ Cheras and Saville D'Lake completed on time?
According to KPKT: Saville @ Cheras (13982-1, 352 units) had its first sale agreement on 25 June 2015 and a deadline of 25 June 2018 with no approved extension; its CCC is dated 19 September 2018, 86 days after the deadline. Saville D'Lake (14252-1, 305 units) had its first sale agreement on 18 April 2016 and a deadline of 18 April 2019 with no extension; its CCC is dated 7 August 2019, 111 days after the deadline. The register does not record their handover dates.
Who develops Residensi Naluri, and has its deadline been extended?
Danau Saujana Sdn Bhd (KPKT developer code 30750), 65% owned by MKH according to its 2025 annual report [1]. KPKT records two phases, both on schedule (Lancar): 30750-1 (733 units, first sale agreement 10 September 2024) with a deadline of 10 September 2027 extended by 16 months to 10 January 2029 and reported progress of 24.79–26.15%; and 30750-2 (720 units, first sale agreement 28 April 2026) with a deadline of 28 April 2029 extended by 16 months to 28 August 2030 and progress of 21.96–22.43%.
Is Jernih Residence in Kajang an MKH project?
It is a joint venture. The developer, Daksina Harta Sdn Bhd, was set up in 2018 with Sunway holding 60% and MKH 40% through their subsidiaries [12]; MKH's 2025 annual report lists it as a 40% associate [2]. Because MKH does not control that company, its KPKT record is not included in the MKH table on this page.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] MKH Berhad Annual Report 2025 — Note 16 Investment in subsidiaries · MKH Berhad · accessed 28 Oct 2026
https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/228 - [2] MKH Berhad Annual Report 2025 — Note 17 Investment in associates · MKH Berhad · accessed 28 Oct 2026
https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/243 - [3] MKH Berhad Annual Report 2025 — MKH At A Glance · MKH Berhad · accessed 28 Oct 2026
https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/20 - [4] MKH Berhad Annual Report 2025 — Corporate Information · MKH Berhad · accessed 28 Oct 2026
https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/115 - [5] About Us · MKH Berhad · accessed 28 Oct 2026
https://www.mkhberhad.com/about-us/ - [6] MKH Berhad — Change in Boardroom: Tan Sri Dato' Chen Kooi Chiew @ Cheng Ngi Chong (resignation) · MKH Berhad via Bursa Malaysia · 19 Aug 2026 · accessed 28 Oct 2026
https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3696249 - [7] MKH Berhad — Change in Boardroom: Tan Sri Datuk Chen Lok Loi (resignation) · MKH Berhad via Bursa Malaysia · 19 Aug 2026 · accessed 28 Oct 2026
https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3696250 - [8] MKH Berhad — Change in Boardroom: Lee Wen Ling (appointment) · MKH Berhad via Bursa Malaysia · 19 Aug 2026 · accessed 28 Oct 2026
https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3696253 - [9] Batu Kawan secures 96.73% stake in MKH as takeover offer closes · The Star · 8 Oct 2026 · accessed 28 Oct 2026
https://www.thestar.com.my/business/business-news/2026/10/08/batu-kawan-secures-9673-stake-in-mkh-as-takeover-offer-closes - [10] Batu Kawan斥5.5亿收购美景将触MGO · The Edge 中文 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/804352 - [11] 每股66.26仙现金 峇都加湾全面献购MKH油棕 · 中国报 China Press · 27 Aug 2026 · accessed 28 Oct 2026
https://www.chinapress.com.my/20260827/%E6%AF%8F%E8%82%A166-26%E4%BB%99%E7%8E%B0%E9%87%91-%E5%B3%87%E9%83%BD%E5%8A%A0%E6%B9%BE%E5%85%A8%E9%9D%A2%E7%8C%AE%E8%B4%ADmkh%E6%B2%B9%E6%A3%95/ - [12] Sunway partners MKH for RM540m mixed development project in Kajang · New Straits Times · 26 Oct 2018 · accessed 28 Oct 2026
https://www.nst.com.my/amp/business/home/2018/10/425298/sunway-partners-mkh-rm540m-mixed-development-project-kajang - [13] MKH Berhad Annual Report 2025 — Management Discussion and Analysis (Prospects) · MKH Berhad · accessed 28 Oct 2026
https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/47
Last updated 28 Oct 2026