MKH (MKH Berhad)

Last updated 28 Oct 2026
Who is MKH?

MKH Berhad, a Kajang developer founded in 1979 and listed on Bursa Malaysia since 1995, has 86 housing projects in the KPKT register under 22 group companies: 76 completed, 7 under construction (one classed Late), 1 not started and 2 with the permit cancelled, none Sick or Abandoned. Its shares have been suspended since 16 October 2026 after Batu Kawan's takeover.

  • 86 projects in the KPKT register
  • 76 completed
  • 7 under construction
  • 1 not yet started
  • 2 with the permit cancelled
  • None Sick or Abandoned

Has MKH handed over on time? What the KPKT register shows

KPKT's TEDUH register (as at 27 Oct 2026) lists 86 housing projects under 22 MKH companies in 3 states: 76 completed, 7 under construction, 1 not yet started, 2 with the permit cancelled. 0 classed Sick (Sakit), 0 Abandoned (Terbengkalai), 1 Late (Lewat).

Of the 76 completed projects, 50 have both a handover deadline and a completion date in the register: 5 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 21 handed over or certified complete after that deadline; 24 received the completion certificate before the deadline (handover date not recorded).

19 projects had the delivery period extended with KPKT approval.

Completed projects — the 12 most recent of 76

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifuKuala LumpurWP Kuala Lumpur50715 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020CCC 19 Dec 2025
Handover 19 Dec 2025
34 days after
KAJANG 2 PRESINT 3 (AKINA)KPKT 30120-3Hulu LangatSelangor17131 Jul 20251st sale agreement 31 Jul 2023CCC 11 Jul 2025
Handover 16 Jul 2025
15 days before
MIRAI RESIDENCESKPKT 19979-1Hulu LangatSelangor1,4962 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020CCC 28 Feb 2025
Handover 4 Mar 2025
2 days after
KAJANG 2 PRESINT 3KPKT 30120-1Hulu LangatSelangor15619 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
KAJANG 2 PRESINT 3KPKT 30120-2Hulu LangatSelangor12019 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12Kuala SelangorSelangor24127 Sep 20231st sale agreement 27 Sep 2021CCC 13 Mar 2024
Handover 13 Mar 2024 / 14 Mar 2024
168–169 days after
RESIDENSI PR1MA@KAJANGKPKT 11865-5Hulu LangatSelangor39323 Apr 2024Extended 23 months from 23 May 20221st sale agreement 23 May 2019CCC 9 Feb 2024
Handover 11 Mar 2024
43 days before
NEXUS @ KAJANG STATIONKPKT 11865-6Hulu LangatSelangor39327 Mar 2024Extended 21 months from 27 Jun 20221st sale agreement 27 Jun 2019CCC 9 Feb 2024
Handover 11 Mar 2024
16 days before
NEXUS @ KAJANG STATIONKPKT 11865-7Hulu LangatSelangor4161 Jul 2024Extended 23 months from 1 Aug 20221st sale agreement 1 Aug 2019CCC 9 Feb 2024
Handover 11 Mar 2024
112 days before
MKH BOULEVARD IIKPKT 10332-2Hulu LangatSelangor60429 Sep 2023Extended 23 months from 29 Oct 20211st sale agreement 29 Oct 2018CCC 4 Jul 2023
Handover 7 Jul 2023
84 days before
INSPIRASI MONT KIARAKPKT 19283-1Kuala LumpurWP Kuala Lumpur6406 Mar 2023Extended 25 months from 6 Feb 20211st sale agreement 6 Feb 2018CCC 6 Jul 2022CCC before deadline; handover not recorded
KAJANG EAST-PRECINCT 1 (FASA 3A)KPKT 9531-10Hulu LangatSelangor4015 Nov 2022Extended 5 months from 15 Jun 20221st sale agreement 15 Jun 2020CCC 4 Jul 2022CCC before deadline; handover not recorded

Handed over or certified complete after the deadline — 12 most recent of 21

Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifuKuala LumpurWP Kuala Lumpur50715 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020CCC 19 Dec 2025
Handover 19 Dec 2025
34 days after
MIRAI RESIDENCESKPKT 19979-1Hulu LangatSelangor1,4962 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020CCC 28 Feb 2025
Handover 4 Mar 2025
2 days after
KAJANG 2 PRESINT 3KPKT 30120-1Hulu LangatSelangor15619 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
KAJANG 2 PRESINT 3KPKT 30120-2Hulu LangatSelangor12019 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12Kuala SelangorSelangor24127 Sep 20231st sale agreement 27 Sep 2021CCC 13 Mar 2024
Handover 13 Mar 2024 / 14 Mar 2024
168–169 days after
HILLPARK RESIDENCEKPKT 11120-5Hulu LangatSelangor40213 Mar 2020Extended 6 months from 13 Sep 20191st sale agreement 13 Sep 2016CCC 13 Aug 2020153 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-11Kuala SelangorSelangor30118 Sep 20191st sale agreement 18 Sep 2017CCC 17 Oct 201929 days after
SAVILLE BANGSAR @ THE PARKKPKT 11868-1Kuala LumpurWP Kuala Lumpur42622 Mar 20151st sale agreement 22 Mar 2012CCC 15 Oct 20191,668 days after
SAVILLE@D'LAKEKPKT 14252-1Saville D'Lake · on PropertySifuSepangSelangor30518 Apr 20191st sale agreement 18 Apr 2016CCC 7 Aug 2019111 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-10Kuala SelangorSelangor38129 May 20191st sale agreement 29 May 2017CCC 8 Jul 201940 days after
SAVILLE CHERASKPKT 13982-1Saville @ Cheras · on PropertySifuHulu LangatSelangor35225 Jun 20181st sale agreement 25 Jun 2015CCC 19 Sep 201886 days after
SAVILLE@KAJANGKPKT 11398-4Hulu LangatSelangor57616 Jun 20171st sale agreement 16 Jun 2014CCC 15 Dec 2017182 days after
Show all 21
Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifuKuala LumpurWP Kuala Lumpur50715 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020CCC 19 Dec 2025
Handover 19 Dec 2025
34 days after
MIRAI RESIDENCESKPKT 19979-1Hulu LangatSelangor1,4962 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020CCC 28 Feb 2025
Handover 4 Mar 2025
2 days after
KAJANG 2 PRESINT 3KPKT 30120-1Hulu LangatSelangor15619 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
KAJANG 2 PRESINT 3KPKT 30120-2Hulu LangatSelangor12019 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12Kuala SelangorSelangor24127 Sep 20231st sale agreement 27 Sep 2021CCC 13 Mar 2024
Handover 13 Mar 2024 / 14 Mar 2024
168–169 days after
HILLPARK RESIDENCEKPKT 11120-5Hulu LangatSelangor40213 Mar 2020Extended 6 months from 13 Sep 20191st sale agreement 13 Sep 2016CCC 13 Aug 2020153 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-11Kuala SelangorSelangor30118 Sep 20191st sale agreement 18 Sep 2017CCC 17 Oct 201929 days after
SAVILLE BANGSAR @ THE PARKKPKT 11868-1Kuala LumpurWP Kuala Lumpur42622 Mar 20151st sale agreement 22 Mar 2012CCC 15 Oct 20191,668 days after
SAVILLE@D'LAKEKPKT 14252-1Saville D'Lake · on PropertySifuSepangSelangor30518 Apr 20191st sale agreement 18 Apr 2016CCC 7 Aug 2019111 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-10Kuala SelangorSelangor38129 May 20191st sale agreement 29 May 2017CCC 8 Jul 201940 days after
SAVILLE CHERASKPKT 13982-1Saville @ Cheras · on PropertySifuHulu LangatSelangor35225 Jun 20181st sale agreement 25 Jun 2015CCC 19 Sep 201886 days after
SAVILLE@KAJANGKPKT 11398-4Hulu LangatSelangor57616 Jun 20171st sale agreement 16 Jun 2014CCC 15 Dec 2017182 days after
KAJANG EASTKPKT 9531-6Hulu LangatSelangor22915 Sep 20171st sale agreement 15 Sep 2014CCC 24 Oct 201739 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-5Kuala SelangorSelangor38223 May 20171st sale agreement 23 May 2015CCC 19 Jul 201757 days after
HILLPARK3 (FASA 2)KPKT 11120-3Hulu LangatSelangor1069 Feb 20171st sale agreement 9 Feb 2015CFO 3 Mar 201722 days after
MKH BOULEVARDKPKT 10470-4Hulu LangatSelangor30830 May 20161st sale agreement 30 May 2013CCC 8 Aug 201670 days after
PELANGI HEIGHTS (SEMI-D & BUNGALOW)KPKT 8897-11SerembanNegeri Sembilan382 May 20161st sale agreement 2 May 2014CCC 3 Jun 201632 days after
HILLPARK, SHAH ALAMKPKT 12278-3Kuala SelangorSelangor23213 Feb 20161st sale agreement 13 Feb 2014CCC 9 Mar 201625 days after
PELANGI HEIGHTSKPKT 8897-10SerembanNegeri Sembilan4621 Oct 20151st sale agreement 21 Oct 2013CFO 25 Nov 201535 days after
PELANGI SERI ALAMKPKT 11865-3Kuala SelangorSelangor13112 Aug 20141st sale agreement 12 Aug 2012CCC 29 Oct 201478 days after
SRIJANG KEMAJUAN SDN BHDKPKT 11398-2Hulu LangatSelangor5230 Jun 20141st sale agreement 30 Jun 2012CCC 30 Sep 201492 days after
Show all 76 completed projects
Project (KPKT name)AreaUnitsHandover deadlineCCC / handoverAgainst deadline
RESIDENSI NEKSUS TAMAN PERTAMAKPKT 20010-1Nexus Residences · on PropertySifuKuala LumpurWP Kuala Lumpur50715 Nov 2025Extended 23 months from 15 Dec 20231st sale agreement 15 Dec 2020CCC 19 Dec 2025
Handover 19 Dec 2025
34 days after
KAJANG 2 PRESINT 3 (AKINA)KPKT 30120-3Hulu LangatSelangor17131 Jul 20251st sale agreement 31 Jul 2023CCC 11 Jul 2025
Handover 16 Jul 2025
15 days before
MIRAI RESIDENCESKPKT 19979-1Hulu LangatSelangor1,4962 Mar 2025Extended 17 months from 30 Sep 20231st sale agreement 30 Sep 2020CCC 28 Feb 2025
Handover 4 Mar 2025
2 days after
KAJANG 2 PRESINT 3KPKT 30120-1Hulu LangatSelangor15619 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
KAJANG 2 PRESINT 3KPKT 30120-2Hulu LangatSelangor12019 Sep 20241st sale agreement 19 Sep 2022CCC 18 Oct 2024
Handover 18 Oct 2024
29 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-12Kuala SelangorSelangor24127 Sep 20231st sale agreement 27 Sep 2021CCC 13 Mar 2024
Handover 13 Mar 2024 / 14 Mar 2024
168–169 days after
RESIDENSI PR1MA@KAJANGKPKT 11865-5Hulu LangatSelangor39323 Apr 2024Extended 23 months from 23 May 20221st sale agreement 23 May 2019CCC 9 Feb 2024
Handover 11 Mar 2024
43 days before
NEXUS @ KAJANG STATIONKPKT 11865-6Hulu LangatSelangor39327 Mar 2024Extended 21 months from 27 Jun 20221st sale agreement 27 Jun 2019CCC 9 Feb 2024
Handover 11 Mar 2024
16 days before
NEXUS @ KAJANG STATIONKPKT 11865-7Hulu LangatSelangor4161 Jul 2024Extended 23 months from 1 Aug 20221st sale agreement 1 Aug 2019CCC 9 Feb 2024
Handover 11 Mar 2024
112 days before
MKH BOULEVARD IIKPKT 10332-2Hulu LangatSelangor60429 Sep 2023Extended 23 months from 29 Oct 20211st sale agreement 29 Oct 2018CCC 4 Jul 2023
Handover 7 Jul 2023
84 days before
INSPIRASI MONT KIARAKPKT 19283-1Kuala LumpurWP Kuala Lumpur6406 Mar 2023Extended 25 months from 6 Feb 20211st sale agreement 6 Feb 2018CCC 6 Jul 2022CCC before deadline; handover not recorded
KAJANG EAST-PRECINCT 1 (FASA 3A)KPKT 9531-10Hulu LangatSelangor4015 Nov 2022Extended 5 months from 15 Jun 20221st sale agreement 15 Jun 2020CCC 4 Jul 2022CCC before deadline; handover not recorded
KAJANG EAST - PRECINT 1 (FASA 1)KPKT 9531-9Hulu LangatSelangor8028 Apr 2022Extended 11 months from 28 May 20211st sale agreement 28 May 2019CCC 18 Apr 2022CCC before deadline; handover not recorded
TR RESIDENSIKPKT 19049-1Kuala LumpurWP Kuala Lumpur64230 Dec 2021Extended 18 months from 30 Jun 20201st sale agreement 30 Jun 2017CCC 29 Jul 2021CCC before deadline; handover not recorded
KAJANG EAST - PRECINCT 1 (PHASE 4)KPKT 9531-7Hulu LangatSelangor8612 May 2021Extended 6 months from 12 Nov 20201st sale agreement 12 Nov 2018CCC 28 Apr 2021CCC before deadline; handover not recorded
KAJANG EAST - PRECINCT 1 (PHASE 2)KPKT 9531-8Hulu LangatSelangor13512 May 2021Extended 6 months from 12 Nov 20201st sale agreement 12 Nov 2018CCC 28 Apr 2021CCC before deadline; handover not recorded
KAJANG 2, PRESINT 2 (FASA 3)KPKT 19140-1Hulu LangatSelangor8819 Mar 2021Extended 18 months from 19 Sep 20191st sale agreement 19 Sep 2017CCC 8 Mar 2021CCC before deadline; handover not recorded
KAJANG 2, PRESINT 2 (FASA 4)KPKT 19140-2Hulu LangatSelangor9614 May 2021Extended 18 months from 14 Nov 20191st sale agreement 14 Nov 2017CCC 8 Mar 2021CCC before deadline; handover not recorded
HILLPARK RESIDENCEKPKT 11120-5Hulu LangatSelangor40213 Mar 2020Extended 6 months from 13 Sep 20191st sale agreement 13 Sep 2016CCC 13 Aug 2020153 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-11Kuala SelangorSelangor30118 Sep 20191st sale agreement 18 Sep 2017CCC 17 Oct 201929 days after
SAVILLE BANGSAR @ THE PARKKPKT 11868-1Kuala LumpurWP Kuala Lumpur42622 Mar 20151st sale agreement 22 Mar 2012CCC 15 Oct 20191,668 days after
SAVILLE@D'LAKEKPKT 14252-1Saville D'Lake · on PropertySifuSepangSelangor30518 Apr 20191st sale agreement 18 Apr 2016CCC 7 Aug 2019111 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-10Kuala SelangorSelangor38129 May 20191st sale agreement 29 May 2017CCC 8 Jul 201940 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-9Kuala SelangorSelangor13226 Apr 20191st sale agreement 26 Apr 2017CCC 30 Nov 2018CCC before deadline; handover not recorded
SAVILLE CHERASKPKT 13982-1Saville @ Cheras · on PropertySifuHulu LangatSelangor35225 Jun 20181st sale agreement 25 Jun 2015CCC 19 Sep 201886 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-6Kuala SelangorSelangor25716 Sep 20181st sale agreement 16 Sep 2016CCC 12 Sep 2018CCC before deadline; handover not recorded
HILLPARK 3 (FASA 1)KPKT 11120-4Hulu LangatSelangor1848 Jan 20181st sale agreement 8 Jan 2016CCC 19 Dec 2017CCC before deadline; handover not recorded
SAVILLE@KAJANGKPKT 11398-4Hulu LangatSelangor57616 Jun 20171st sale agreement 16 Jun 2014CCC 15 Dec 2017182 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-7Kuala SelangorSelangor23322 Mar 20181st sale agreement 22 Mar 2016CCC 8 Dec 2017CCC before deadline; handover not recorded
KAJANG EASTKPKT 9531-6Hulu LangatSelangor22915 Sep 20171st sale agreement 15 Sep 2014CCC 24 Oct 201739 days after
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-5Kuala SelangorSelangor38223 May 20171st sale agreement 23 May 2015CCC 19 Jul 201757 days after
PELANGI HEIGHTS - PHASE 1BKPKT 8897-15SerembanNegeri Sembilan1830 Sep 20181st sale agreement 30 Sep 2016CCC 10 Jun 2017CCC before deadline; handover not recorded
KAJANG EASTKPKT 9531-5Hulu LangatSelangor8915 May 20171st sale agreement 15 May 2015CCC 13 Apr 2017CCC before deadline; handover not recorded
PELANGI HEIGHTSKPKT 8897-13SerembanNegeri Sembilan7113 Mar 20171st sale agreement 13 Mar 2015CCC 10 Mar 2017CCC before deadline; handover not recorded
PELANGI HEIGHTSKPKT 8897-14SerembanNegeri Sembilan12214 Aug 20171st sale agreement 14 Aug 2015CCC 10 Mar 2017CCC before deadline; handover not recorded
HILLPARK3 (FASA 2)KPKT 11120-3Hulu LangatSelangor1069 Feb 20171st sale agreement 9 Feb 2015CFO 3 Mar 201722 days after
HILLPARK 3 - FASA 2(A)KPKT 11120-6Hulu LangatSelangor14—CFO 3 Mar 2017—
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-4Kuala SelangorSelangor2368 Feb 20171st sale agreement 8 Feb 2015CCC 3 Feb 2017CCC before deadline; handover not recorded
MKH BOULEVARDKPKT 10470-4Hulu LangatSelangor30830 May 20161st sale agreement 30 May 2013CCC 8 Aug 201670 days after
PELANGI HEIGHTS (SEMI-D & BUNGALOW)KPKT 8897-11SerembanNegeri Sembilan382 May 20161st sale agreement 2 May 2014CCC 3 Jun 201632 days after
PELANGI HEIGHTS (SEMI-D & BUNGALOW)KPKT 8897-12SerembanNegeri Sembilan453 Nov 20161st sale agreement 3 Nov 2014CCC 3 Jun 2016CCC before deadline; handover not recorded
HILLPARK SHAH ALAMKPKT 12278-1Kuala SelangorSelangor34317 May 20161st sale agreement 17 May 2014CCC 16 May 2016CCC before deadline; handover not recorded
HILLPARK, SHAH ALAMKPKT 12278-3Kuala SelangorSelangor23213 Feb 20161st sale agreement 13 Feb 2014CCC 9 Mar 201625 days after
KAJANG EASTKPKT 9531-4Hulu LangatSelangor11616 Dec 20151st sale agreement 16 Dec 2013CFO 15 Dec 2015CCC before deadline; handover not recorded
PELANGI HEIGHTSKPKT 8897-10SerembanNegeri Sembilan4621 Oct 20151st sale agreement 21 Oct 2013CFO 25 Nov 201535 days after
RESIDENSI WARNASARI 2KPKT 11865-4Kuala SelangorSelangor45011 Oct 20151st sale agreement 11 Oct 2012CCC 14 Sep 2015CCC before deadline; handover not recorded
HILLPARK, SHAH ALAMKPKT 12278-2Kuala SelangorSelangor31120 Aug 20151st sale agreement 20 Aug 2013CCC 19 Aug 2015CCC before deadline; handover not recorded
PELANGI SEMENYIH 2KPKT 11335-8Hulu LangatSelangor817 Apr 20151st sale agreement 17 Apr 2013CFO 6 Feb 2015CCC before deadline; handover not recorded
PELANGI SEMENYIH 2KPKT 11335-7Hulu LangatSelangor6215 Apr 20151st sale agreement 15 Apr 2013CFO 9 Jan 2015CCC before deadline; handover not recorded
PELANGI SERI ALAMKPKT 11865-3Kuala SelangorSelangor13112 Aug 20141st sale agreement 12 Aug 2012CCC 29 Oct 201478 days after
SRIJANG KEMAJUAN SDN BHDKPKT 11398-2Hulu LangatSelangor5230 Jun 20141st sale agreement 30 Jun 2012CCC 30 Sep 201492 days after
MEWAH 9 RESIDENCEKPKT 9531-3Hulu LangatSelangor120—CCC 18 Jul 2014—
PELANGI SERI ALAMKPKT 11865-2Kuala SelangorSelangor153—CCC 3 Apr 2014—
PELANGI SEMENYIH 2KPKT 11335-6Hulu LangatSelangor173—CFO 25 Mar 2014—
PELANGI SEMENYIH 2KPKT 11335-9Hulu LangatSelangor70—CFO 24 Jan 2014—
PELANGI SERI ALAMKPKT 11865-1Kuala SelangorSelangor114—CCC 27 Dec 2013—
SAVILLE @ MELAWATIKPKT 11367-1Kuala LumpurWP Kuala Lumpur0—CCC 27 Dec 2013—
PELANGI SEMENYIH 2KPKT 11335-5Hulu LangatSelangor66—CFO 18 Oct 2013—
PELANGI SEMENYIH 2KPKT 11335-3Hulu LangatSelangor166—CFO 10 May 2013—
PELANGI SEMENYIH 2KPKT 11335-4Hulu LangatSelangor40—CFO 10 May 2013—
KAJANG 2KPKT 11398-1Hulu LangatSelangor191—CCC 30 Apr 2013—
HILL PARK 2KPKT 11120-2Hulu LangatSelangor399—CCC 17 Jan 2013—
PELANGI SEMENYIH 2KPKT 11335-2Hulu LangatSelangor145—CCC 31 Dec 2012—
PELANGI SEMENYIH 2KPKT 11335-1Hulu LangatSelangor233—CCC 14 Sep 2012—
SENTOSA HEIGHTSKPKT 10470-2Hulu LangatSelangor55—CCC 20 Jul 2012—
HILL PARK HOMEKPKT 11120-1Hulu LangatSelangor272—CCC 9 Dec 2011—
ALIRAN PERKASA SDN. BHD.KPKT 9531-2Hulu LangatSelangor36—CFO 12 Jan 2011—
PELANGI SEMENYIHKPKT 8897-9Hulu LangatSelangor335—CCC 16 Nov 2010—
SENTOSA VILLA @ KAJANGKPKT 10470-1Hulu LangatSelangor73—CFO 2 Apr 2010—
PELANGI SEMENYIHKPKT 8897-7Hulu LangatSelangor256—CFO 14 Dec 2009—
ZEN PARK CHERASKPKT 10332-1Hulu LangatSelangor47—CFO 25 May 2009—
TAMAN BUKIT MEWAHKPKT 6029-2Hulu LangatSelangor34—CFO 26 Nov 2008—
TAMAN PELANGI SEMENYIHKPKT 8897-6Hulu LangatSelangor200—CFO 24 Sep 2008—
PELANGI SEMENYIH (FASA 5)KPKT 8897-5Hulu LangatSelangor153—CFO 6 Jul 2007—
TAMAN BUKIT MEWAHKPKT 9531-1Hulu LangatSelangor67—CFO 21 Dec 2006—
PELANGI SEMENYIH (FASA 4)KPKT 8897-4Hulu LangatSelangor184—CFO 19 Jan 2006—

Under construction (7) and not yet started (1)

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
RESIDENSI TUN RAZAK 2KPKT 20082-1Kuala LumpurWP Kuala Lumpur918DelayLate14 Dec 2026Extended 24 months from 14 Dec 20241st sale agreement 14 Dec 202162–64%
ANNYA KAJANG 2 PRESINT 3KPKT 30120-4Hulu LangatSelangor171SmoothOn schedule7 Jul 20281st sale agreement 7 Jul 20265–17%
RESIDENSI NALURIKPKT 30750-1Residensi Naluri · on PropertySifuHulu LangatSelangor733SmoothOn schedule10 Jan 2029Extended 16 months from 10 Sep 20271st sale agreement 10 Sep 202425–26%
GAYA RESIDENCYKPKT 19979-2Hulu LangatSelangor494SmoothOn schedule18 Jan 2029Extended 16 months from 18 Sep 20271st sale agreement 18 Sep 202425%
RESIDENSI PINANGKPKT 12278-13Kuala SelangorSelangor177SmoothOn schedule14 Jun 20291st sale agreement 14 Jun 202661%
GAYA RESIDENCYKPKT 19979-3Hulu LangatSelangor494SmoothOn schedule18 Sep 20291st sale agreement 18 Sep 202620%
RESIDENSI NALURIKPKT 30750-2Hulu LangatSelangor720SmoothOn schedule28 Aug 2030Extended 16 months from 28 Apr 20291st sale agreement 28 Apr 202622%
KAJANG EAST - PRECINCT 1 (FASA 3B)KPKT 9531-11Hulu LangatSelangor27SmoothNot started—0%

Permit cancelled or other KPKT status (2)

Project (KPKT name)AreaUnitsKPKT statusHandover deadlineProgress
BANDAR HILLPARK PUNCAK ALAMKPKT 12278-8Kuala SelangorSelangor396Permit cancelledPermit cancelled—0–20%
AURELIAKPKT 11398-3Hulu LangatSelangor149Permit cancelledPermit cancelled—0%

Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.

MKH at a glance

ListedBursa Malaysia Main Market · MKH (6114) · listed 1995 · trading suspended from 16 October 2026 after the Batu Kawan takeover; the offerors plan to withdraw the listing[5][4][9]
Started1979 in Kajang, Selangor, as Srijang Bena Sdn Bhd[5]
Head officeWisma MKH, Jalan Semenyih, Kajang, Selangor[4]
LeadershipTan Sri Dato' Chen Kooi Chiew @ Cheng Ngi Chong — Group Executive Chairman, 30 October 2006 – 19 August 2026 (director since 1979)[6]
Tan Sri Datuk Chen Lok Loi — Group Managing Director, 19 January 2005 – 19 August 2026[7]
Companies in the KPKT registerALIRAN PERKASA SDN. BHD. KPKT 9531[1]
GERAK TEGUH SDN. BHD. KPKT 8897[1]
MKH HEALTHCARE SDN. BHD. KPKT 11335[1]
METRO K.L. CITY SDN. BHD. KPKT 11865[1]
PETIK MEKAR SDN. BHD. KPKT 30120[1]
SRIJANG KEMAJUAN SDN. BHD. (99.99%) KPKT 11398[1]
MKH PROPERTY VENTURES SDN. BHD. (51%) KPKT 19979[1]
DANAU SAUJANA SDN. BHD. (65%) KPKT 30750[1]
STAND ALLIED CORPORATION SDN. BHD. KPKT 10332[1]
SURIA VILLA SDN. BHD. KPKT 19140[1]
ACHIEVE ACRES SDN. BHD. (85%) KPKT 14252[1]
MKH DEVELOPMENT SDN. BHD. KPKT 20010[1]
PERKASA BERNAS (M) SDN. BHD. KPKT 11367[1]
QUANTUM DENSITY SDN. BHD. (50.0004%) KPKT 20082[1]
SUMBER LENGKAP SDN. BHD. KPKT 6029[1]
TEMARA PEKELILING SDN. BHD. (50.4%) KPKT 19049[1]
VISTA HARUMAN DEVELOPMENT SDN. BHD. (55%) KPKT 13982[1]
KAJANG RESOURCES CORPORATION SDN.BHD. KPKT 11120[1]
SERBA SENTOSA SDN. BHD. KPKT 10470[1]
AMONA METRO DEVELOPMENT SDN. BHD. (60%) KPKT 11868[1]
ALIF MESRA SDN. BHD. (65%) KPKT 19283[1]
HILLPARK RESOURCES SDN. BHD. KPKT 12278[1]
Websitemkhberhad.com
Started1979 in Kajang, as Srijang Bena Sdn Bhd; renamed Metro Kajang Holdings Berhad on listing in 1995 and MKH Berhad in 2011[5]
Projects completed (company figure)More than 59 property projects (2025 annual report)[3]
Ownership96.73% held by Batu Kawan Bhd, its unit Whitmore Holdings and parties acting in concert when the RM2 offer closed on 8 October 2026[9]
Other businessesBuilding materials trading, property investment and, since 2008, oil palm plantations in East Kalimantan, Indonesia[5]

MKH projects on sale on PropertySifu

Nexus Residences

Cheras, Kuala Lumpur · From RM492,000
KPKT 20010-1: Completed with CCC (19 Dec 2025)
Completed MKH projects nearby (KPKT):
  • SAVILLE CHERAS — 7.3 km, 2018
  • TR RESIDENSI — 7.8 km, 2021
  • SAVILLE BANGSAR @ THE PARK — 7.9 km, 2019

Residensi Naluri

Cheras, Selangor · From RM250,000
KPKT 30750-1: On schedule · handover deadline 10 Jan 2029
Completed MKH projects nearby (KPKT):
  • SAVILLE CHERAS — 1.1 km, 2018
  • MKH BOULEVARD — 7.1 km, 2016
  • MKH BOULEVARD II — 7.4 km, 2023

Saville @ Cheras

Cheras, Selangor · From RM690,000
KPKT 13982-1: Completed with CCC (19 Sep 2018)
Completed MKH projects nearby (KPKT):
  • RESIDENSI NEKSUS TAMAN PERTAMA — 7.3 km, 2025

Saville D'Lake

Puchong, Kuala Lumpur · From RM471,000
KPKT 14252-1: Completed with CCC (7 Aug 2019)

Who is MKH? The company behind the projects

MKH started in Kajang in 1979 as Srijang Bena Sdn Bhd, building its first residential township that year, its first high-rise in 1993 and Kajang's first shopping complex in 1994 [5]. On its listing on the Main Market of Bursa Malaysia in 1995 it became Metro Kajang Holdings Berhad, and it was renamed MKH Berhad in 2011 [5]; its stock name is MKH and its code 6114 [4]. The registered office is at Wisma MKH in Kajang [4]. Besides property development, MKH trades building materials, holds investment properties and, since 2008, runs oil palm plantations in East Kalimantan, Indonesia [5].

MKH says it has completed more than 59 property projects (2025 annual report) [3]. That is the company's own count; the KPKT register lists each licensed phase separately, which gives the 86 projects under 22 MKH companies above. Several of these companies are not wholly owned: the 2025 annual report gives MKH 65% of Danau Saujana, 55% of Vista Haruman Development, 85% of Achieve Acres, 51% of MKH Property Ventures, and about 50% of Quantum Density and Temara Pekeliling [1].

Of the MKH projects on PropertySifu, Nexus Residences in Cheras is developed by MKH Development Sdn Bhd, Residensi Naluri by Danau Saujana Sdn Bhd, Saville @ Cheras by Vista Haruman Development Sdn Bhd and Saville D'Lake by Achieve Acres Sdn Bhd [1]. Jernih Residence in Kajang is a separate case: its developer, Daksina Harta Sdn Bhd, was set up in 2018 as a joint venture in which Sunway holds 60% and MKH 40% [12], and MKH's 2025 annual report lists it as a 40% associate [2]; it is not counted in the table above.

In 2026 Batu Kawan Bhd, through its wholly owned Whitmore Holdings, agreed to buy a combined 47.7% of MKH at RM2 a share from Chen Choy & Sons Realty Sdn Bhd and related parties [10], which led to a general offer for the remaining shares. When the offer closed on 8 October 2026 the offerors held 96.73%; trading in MKH shares was suspended from 16 October 2026, and the offerors said they would take steps to withdraw MKH's listing [9]. Group Executive Chairman Tan Sri Dato' Chen Kooi Chiew @ Cheng Ngi Chong, a director since 1979, and Group Managing Director Tan Sri Datuk Chen Lok Loi resigned on 19 August 2026 ahead of the offer's first closing date [6][7]; the same day Lee Wen Ling, managing director of KLK Land, joined the board as a non-executive director [8].

Frequently asked questions

Is MKH a listed company?

MKH Berhad has been listed on the Main Market of Bursa Malaysia since 1995 (stock code 6114) [5][4]. After Batu Kawan's takeover offer closed on 8 October 2026 with the offerors holding 96.73%, trading in its shares was suspended from 16 October 2026, and the offerors said they would take steps to withdraw the listing [9].

Does MKH have any Sick or Abandoned projects?

No. As at 27 October 2026, the KPKT register classes none of MKH's 86 projects as Sick (Sakit) or Abandoned (Terbengkalai). One is classed Late (Lewat): RESIDENSI TUN RAZAK 2 in Kuala Lumpur (KPKT 20082-1, 918 units, Quantum Density Sdn Bhd), which MKH's annual report calls TR2 Residence [13]. Its first sale agreement was signed on 14 December 2021; the deadline of 14 December 2024 was extended with approval by 24 months to 14 December 2026, and reported construction progress is 61.75–64.2%. Two other projects are recorded with the permit cancelled.

Was Nexus Residences in Cheras handed over on time?

KPKT registers it as RESIDENSI NEKSUS TAMAN PERTAMA (20010-1, 507 units, MKH Development Sdn Bhd). The first sale agreement was signed on 15 December 2020 and the deadline of 15 December 2023 was extended with approval by 23 months to 15 November 2025. The CCC and vacant possession are both dated 19 December 2025, 34 days after the extended deadline.

Were Saville @ Cheras and Saville D'Lake completed on time?

According to KPKT: Saville @ Cheras (13982-1, 352 units) had its first sale agreement on 25 June 2015 and a deadline of 25 June 2018 with no approved extension; its CCC is dated 19 September 2018, 86 days after the deadline. Saville D'Lake (14252-1, 305 units) had its first sale agreement on 18 April 2016 and a deadline of 18 April 2019 with no extension; its CCC is dated 7 August 2019, 111 days after the deadline. The register does not record their handover dates.

Who develops Residensi Naluri, and has its deadline been extended?

Danau Saujana Sdn Bhd (KPKT developer code 30750), 65% owned by MKH according to its 2025 annual report [1]. KPKT records two phases, both on schedule (Lancar): 30750-1 (733 units, first sale agreement 10 September 2024) with a deadline of 10 September 2027 extended by 16 months to 10 January 2029 and reported progress of 24.79–26.15%; and 30750-2 (720 units, first sale agreement 28 April 2026) with a deadline of 28 April 2029 extended by 16 months to 28 August 2030 and progress of 21.96–22.43%.

Is Jernih Residence in Kajang an MKH project?

It is a joint venture. The developer, Daksina Harta Sdn Bhd, was set up in 2018 with Sunway holding 60% and MKH 40% through their subsidiaries [12]; MKH's 2025 annual report lists it as a 40% associate [2]. Because MKH does not control that company, its KPKT record is not included in the MKH table on this page.

Sources and how we checked

  1. Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
  2. [1] MKH Berhad Annual Report 2025 — Note 16 Investment in subsidiaries · MKH Berhad · accessed 28 Oct 2026
    https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/228
  3. [2] MKH Berhad Annual Report 2025 — Note 17 Investment in associates · MKH Berhad · accessed 28 Oct 2026
    https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/243
  4. [3] MKH Berhad Annual Report 2025 — MKH At A Glance · MKH Berhad · accessed 28 Oct 2026
    https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/20
  5. [4] MKH Berhad Annual Report 2025 — Corporate Information · MKH Berhad · accessed 28 Oct 2026
    https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/115
  6. [5] About Us · MKH Berhad · accessed 28 Oct 2026
    https://www.mkhberhad.com/about-us/
  7. [6] MKH Berhad — Change in Boardroom: Tan Sri Dato' Chen Kooi Chiew @ Cheng Ngi Chong (resignation) · MKH Berhad via Bursa Malaysia · 19 Aug 2026 · accessed 28 Oct 2026
    https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3696249
  8. [7] MKH Berhad — Change in Boardroom: Tan Sri Datuk Chen Lok Loi (resignation) · MKH Berhad via Bursa Malaysia · 19 Aug 2026 · accessed 28 Oct 2026
    https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3696250
  9. [8] MKH Berhad — Change in Boardroom: Lee Wen Ling (appointment) · MKH Berhad via Bursa Malaysia · 19 Aug 2026 · accessed 28 Oct 2026
    https://www.bursamalaysia.com/market_information/announcements/company_announcement/announcement_details?ann_id=3696253
  10. [9] Batu Kawan secures 96.73% stake in MKH as takeover offer closes · The Star · 8 Oct 2026 · accessed 28 Oct 2026
    https://www.thestar.com.my/business/business-news/2026/10/08/batu-kawan-secures-9673-stake-in-mkh-as-takeover-offer-closes
  11. [10] Batu Kawan斥5.5亿收购美景将触MGO · The Edge 中文 · accessed 28 Oct 2026
    https://theedgemalaysia.com/node/804352
  12. [11] 每股66.26仙现金 峇都加湾全面献购MKH油棕 · 中国报 China Press · 27 Aug 2026 · accessed 28 Oct 2026
    https://www.chinapress.com.my/20260827/%E6%AF%8F%E8%82%A166-26%E4%BB%99%E7%8E%B0%E9%87%91-%E5%B3%87%E9%83%BD%E5%8A%A0%E6%B9%BE%E5%85%A8%E9%9D%A2%E7%8C%AE%E8%B4%ADmkh%E6%B2%B9%E6%A3%95/
  13. [12] Sunway partners MKH for RM540m mixed development project in Kajang · New Straits Times · 26 Oct 2018 · accessed 28 Oct 2026
    https://www.nst.com.my/amp/business/home/2018/10/425298/sunway-partners-mkh-rm540m-mixed-development-project-kajang
  14. [13] MKH Berhad Annual Report 2025 — Management Discussion and Analysis (Prospects) · MKH Berhad · accessed 28 Oct 2026
    https://www.insage.com.my/interactiveAR/MKH/interactiveAR2025/47

Last updated 28 Oct 2026