MK Land (M K Land Holdings Berhad)
M K Land Holdings Berhad is a Bursa Malaysia-listed property, leisure and solar-energy group with 56 housing projects in the KPKT register under nine subsidiaries: 43 completed, 9 under construction, 3 not yet started and 1 with its permit cancelled, none classed Sick or Abandoned. Listed since 1999, it builds townships in Selangor and Perak.
- 56 projects in the KPKT register
- 43 completed
- 9 under construction
- 3 not yet started
- 1 with the permit cancelled
- None Sick or Abandoned
Has MK Land handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 56 housing projects under 9 MK Land companies in 2 states: 43 completed, 9 under construction, 3 not yet started, 1 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 43 completed projects, 23 have both a handover deadline and a completion date in the register: 9 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 10 handed over or certified complete after that deadline (3 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 4 received the completion certificate before the deadline (handover date not recorded).
6 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 43
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN BUNGA RAYAKPKT 6822-24 | Hulu SelangorSelangor | 62 | 18 Apr 20261st sale agreement 18 Apr 2024 | CCC 15 Apr 2026 Handover 16 Apr 2026 | 2 days before |
| TAMAN MERU PERDANAKPKT 7670-22 | KintaPerak | 74 | 21 Mar 20261st sale agreement 21 Mar 2024 | CCC 29 Jan 2026 Handover 31 Jan 2026 | 49 days before |
| TAMAN BUNGA RAYAKPKT 6822-23 | Hulu SelangorSelangor | 114 | 29 Jan 20261st sale agreement 29 Jan 2024 | CCC 21 Jan 2026 Handover 21 Jan 2026 | 8 days before |
| TAMAN BUNGA RAYAKPKT 6822-22 | Hulu SelangorSelangor | 101 | 7 Nov 20251st sale agreement 7 Nov 2023 | CCC 30 Oct 2025 Handover 31 Oct 2025 | 7 days before |
| THE RAFFLESIAKPKT 7609-17 | PetalingSelangor | 24 | 4 Jul 20251st sale agreement 4 Jul 2023 | CCC 24 Jul 2025 Handover 24 Jul 2025 | 20 days after |
| TAMAN KLEBANG PUTRAKPKT 7670-21 | KintaPerak | 90 | 16 May 20251st sale agreement 16 May 2023 | CCC 9 May 2025 Handover 9 May 2025 | 7 days before |
| THE RAFFLESIAKPKT 7609-16 | PetalingSelangor | 24 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 30 Dec 2024 Handover 30 Dec 2024 | 30 days after |
| TAMAN RAIA PERDANAKPKT 19847-2 | KamparPerak | 117 | 18 Nov 20241st sale agreement 18 Nov 2022 | CCC 11 Dec 2024 Handover 12 Dec 2024 | 24 days after |
| TAMAN BUNGA RAYAKPKT 6822-21 | Hulu SelangorSelangor | 114 | 18 Oct 20241st sale agreement 18 Oct 2022 | CCC 20 Nov 2024 Handover 20 Nov 2024 | 33 days after |
| TAMAN BUNGA RAYAKPKT 6822-20 | Hulu SelangorSelangor | 126 | 17 Jun 20241st sale agreement 17 Jun 2022 | CCC 9 Aug 2024 Handover 9 Aug 2024 | 53 days after |
| TAMAN BUNGA RAYAKPKT 6822-19 | Hulu SelangorSelangor | 58 | 2 Aug 20241st sale agreement 2 Aug 2022 | CCC 24 Jul 2024 Handover 24 Jul 2024 | 9 days before |
| CARNELIANKPKT 7670-20 | KintaPerak | 180 | — | CCC 28 Feb 2024 Handover 28 Feb 2024 | — |
Handed over or certified complete after the deadline (10)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| THE RAFFLESIAKPKT 7609-17 | PetalingSelangor | 24 | 4 Jul 20251st sale agreement 4 Jul 2023 | CCC 24 Jul 2025 Handover 24 Jul 2025 | 20 days after |
| THE RAFFLESIAKPKT 7609-16 | PetalingSelangor | 24 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 30 Dec 2024 Handover 30 Dec 2024 | 30 days after |
| TAMAN RAIA PERDANAKPKT 19847-2 | KamparPerak | 117 | 18 Nov 20241st sale agreement 18 Nov 2022 | CCC 11 Dec 2024 Handover 12 Dec 2024 | 24 days after |
| TAMAN BUNGA RAYAKPKT 6822-21 | Hulu SelangorSelangor | 114 | 18 Oct 20241st sale agreement 18 Oct 2022 | CCC 20 Nov 2024 Handover 20 Nov 2024 | 33 days after |
| TAMAN BUNGA RAYAKPKT 6822-20 | Hulu SelangorSelangor | 126 | 17 Jun 20241st sale agreement 17 Jun 2022 | CCC 9 Aug 2024 Handover 9 Aug 2024 | 53 days after |
| MEDAN PRESTASI SDN. BHD.KPKT 6822-15Suasana Damai · on PropertySifu | PetalingSelangor | 780 | 21 Jun 2021Extended 23 months from 21 Jul 20191st sale agreement 21 Jul 2016 | CCC 15 May 2023 Handover 24 Sep 2020 / 11 Oct 2021 / 16 May 2023 | 694 days after † |
| TAMAN BUNGA RAYAKPKT 6822-17 | Hulu SelangorSelangor | 419 | 22 Jan 2022Extended 11 months from 22 Feb 20211st sale agreement 22 Feb 2019 | CCC 22 Nov 2022 Handover 18 Mar 2021 / 27 Aug 2021 / 30 Nov 2021 / 22 Nov 2022 | 304 days after † |
| TAMAN KLEBANG PUTRAKPKT 7670-18 | KintaPerak | 242 | 21 Nov 2020Extended 6 months from 21 May 20201st sale agreement 21 May 2018 | CCC 13 Sep 2021 | 296 days after † |
| ARMANEE TERRACE BLOK BKPKT 7609-9 | PetalingSelangor | 518 | 19 Apr 20081st sale agreement 19 Apr 2005 | CFO 12 Aug 2015 | 2,671 days after |
| TAMAN KLEBANG PUTRAKPKT 7670-12 | KintaPerak | 275 | 29 Aug 20101st sale agreement 29 Aug 2008 | CFO 14 Dec 2010 | 107 days after |
Show all 43 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| TAMAN BUNGA RAYAKPKT 6822-24 | Hulu SelangorSelangor | 62 | 18 Apr 20261st sale agreement 18 Apr 2024 | CCC 15 Apr 2026 Handover 16 Apr 2026 | 2 days before |
| TAMAN MERU PERDANAKPKT 7670-22 | KintaPerak | 74 | 21 Mar 20261st sale agreement 21 Mar 2024 | CCC 29 Jan 2026 Handover 31 Jan 2026 | 49 days before |
| TAMAN BUNGA RAYAKPKT 6822-23 | Hulu SelangorSelangor | 114 | 29 Jan 20261st sale agreement 29 Jan 2024 | CCC 21 Jan 2026 Handover 21 Jan 2026 | 8 days before |
| TAMAN BUNGA RAYAKPKT 6822-22 | Hulu SelangorSelangor | 101 | 7 Nov 20251st sale agreement 7 Nov 2023 | CCC 30 Oct 2025 Handover 31 Oct 2025 | 7 days before |
| THE RAFFLESIAKPKT 7609-17 | PetalingSelangor | 24 | 4 Jul 20251st sale agreement 4 Jul 2023 | CCC 24 Jul 2025 Handover 24 Jul 2025 | 20 days after |
| TAMAN KLEBANG PUTRAKPKT 7670-21 | KintaPerak | 90 | 16 May 20251st sale agreement 16 May 2023 | CCC 9 May 2025 Handover 9 May 2025 | 7 days before |
| THE RAFFLESIAKPKT 7609-16 | PetalingSelangor | 24 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 30 Dec 2024 Handover 30 Dec 2024 | 30 days after |
| TAMAN RAIA PERDANAKPKT 19847-2 | KamparPerak | 117 | 18 Nov 20241st sale agreement 18 Nov 2022 | CCC 11 Dec 2024 Handover 12 Dec 2024 | 24 days after |
| TAMAN BUNGA RAYAKPKT 6822-21 | Hulu SelangorSelangor | 114 | 18 Oct 20241st sale agreement 18 Oct 2022 | CCC 20 Nov 2024 Handover 20 Nov 2024 | 33 days after |
| TAMAN BUNGA RAYAKPKT 6822-20 | Hulu SelangorSelangor | 126 | 17 Jun 20241st sale agreement 17 Jun 2022 | CCC 9 Aug 2024 Handover 9 Aug 2024 | 53 days after |
| TAMAN BUNGA RAYAKPKT 6822-19 | Hulu SelangorSelangor | 58 | 2 Aug 20241st sale agreement 2 Aug 2022 | CCC 24 Jul 2024 Handover 24 Jul 2024 | 9 days before |
| CARNELIANKPKT 7670-20 | KintaPerak | 180 | — | CCC 28 Feb 2024 Handover 28 Feb 2024 | — |
| LUDISIAKPKT 7670-19 | KintaPerak | 128 | 30 Sep 2023Extended 5 months from 30 Apr 20231st sale agreement 30 Apr 2021 | CCC 10 Jul 2023 Handover 10 Jul 2023 | 82 days before |
| MEDAN PRESTASI SDN. BHD.KPKT 6822-15Suasana Damai · on PropertySifu | PetalingSelangor | 780 | 21 Jun 2021Extended 23 months from 21 Jul 20191st sale agreement 21 Jul 2016 | CCC 15 May 2023 Handover 24 Sep 2020 / 11 Oct 2021 / 16 May 2023 | 694 days after † |
| TAMAN BUNGA RAYAKPKT 6822-18 | Hulu SelangorSelangor | 66 | 2 Mar 2023Extended 5 months from 30 Sep 20221st sale agreement 30 Sep 2020 | CCC 28 Feb 2023 Handover 28 Feb 2023 | 2 days before |
| TAMAN BUNGA RAYAKPKT 6822-17 | Hulu SelangorSelangor | 419 | 22 Jan 2022Extended 11 months from 22 Feb 20211st sale agreement 22 Feb 2019 | CCC 22 Nov 2022 Handover 18 Mar 2021 / 27 Aug 2021 / 30 Nov 2021 / 22 Nov 2022 | 304 days after † |
| NALURI MAJUJAYA SDN. BHD.KPKT 19847-1 | KintaPerak | 135 | 22 Oct 2022Extended 5 months from 22 May 20221st sale agreement 22 May 2020 | CCC 18 Oct 2022 Handover 18 Oct 2022 | 4 days before |
| TAMAN KLEBANG PUTRAKPKT 7670-18 | KintaPerak | 242 | 21 Nov 2020Extended 6 months from 21 May 20201st sale agreement 21 May 2018 | CCC 13 Sep 2021 | 296 days after † |
| ZAMAN TELADAN SDN BHDKPKT 7670-17 | KintaPerak | 215 | 16 Feb 20181st sale agreement 16 Feb 2015 | CFO 9 Jan 2017 | CCC before deadline; handover not recorded |
| ARMANEE TERRACE BLOK BKPKT 7609-9 | PetalingSelangor | 518 | 19 Apr 20081st sale agreement 19 Apr 2005 | CFO 12 Aug 2015 | 2,671 days after |
| TAMAN KLEBANG PUTRAKPKT 7670-11 | KintaPerak | 400 | — | CFO 8 Dec 2014 | — |
| MERU PERDANA 2KPKT 7670-16 | KintaPerak | 146 | — | CFO 7 May 2014 | — |
| ONE DAMANSARAKPKT 6822-14 | PetalingSelangor | 899 | 5 Nov 20151st sale agreement 5 Nov 2012 | CFO 2 Apr 2013 | CCC before deadline; handover not recorded |
| MERU PERDANAKPKT 7670-14 | KintaPerak | 935 | — | CFO 7 Mar 2013 | — |
| METROPOLITAN SQUAREKPKT 7609-11 | PetalingSelangor | 537 | — | CCC 20 Jul 2012 | — |
| FAIRWAY HEIGHTSKPKT 9386-2 | Larut & MatangPerak | 76 | — | CFO 25 Jan 2012 | — |
| TAMAN KLEBANG PUTRAKPKT 7670-12 | KintaPerak | 275 | 29 Aug 20101st sale agreement 29 Aug 2008 | CFO 14 Dec 2010 | 107 days after |
| TAMAN BUNGA RAYAKPKT 9230-1 | Hulu SelangorSelangor | 2,724 | — | CFO 28 Jul 2010 | — |
| METROPOLITAN SQUAREKPKT 7609-8 | PetalingSelangor | 670 | 28 Nov 20141st sale agreement 28 Nov 2011 | CFO 27 Feb 2009 | CCC before deadline; handover not recorded |
| BANDAR TASIK BUKIT MERAHKPKT 6656-3 | KerianPerak | 156 | — | CFO 26 Feb 2009 | — |
| BANDAR TASIK BUKIT MERAHKPKT 6656-4 | KerianPerak | 372 | — | CFO 26 Feb 2009 | — |
| METROPOLITAN SQUAREKPKT 7609-7 | PetalingSelangor | 837 | — | CFO 24 Apr 2008 | — |
| TAMAN BUNGA RAYAKPKT 6822-4 | Hulu SelangorSelangor | 1,950 | — | CFO 20 Apr 2008 | — |
| CYBERIA CRESCENT 2KPKT 7586-3 | SepangSelangor | 164 | — | CFO 6 Dec 2007 | — |
| CYBERIA CRESCENTKPKT 7586-2 | SepangSelangor | 209 | — | CFO 26 Oct 2007 | — |
| FLORA DAMANSARA - BANDAR DAMANSARA PERDANAKPKT 7609-4 | PetalingSelangor | 3,608 | — | CFO 15 May 2007 | — |
| TAMAN KLEBANG PUTRAKPKT 7670-10 | KintaPerak | 79 | — | CFO 30 Mar 2007 | — |
| BANDAR LEMBAH BERIAHKPKT 8110-5 | KerianPerak | 293 | 16 Nov 20091st sale agreement 16 Nov 2007 | CFO 18 Jan 2007 | CCC before deadline; handover not recorded |
| FAIRWAY HEIGHTSKPKT 9386-1 | Larut & MatangPerak | 30 | — | CFO 28 Jul 2006 | — |
| TAMAN BUNGA RAYAKPKT 6822-11 | Hulu SelangorSelangor | 2,100 | — | CFO 24 Jul 2006 | — |
| TAMAN KLEBANG PUTRAKPKT 7670-13 | KintaPerak | 73 | — | CFO 15 May 2006 | — |
| TAMAN KLEBANG PUTRAKPKT 7670-7 | KintaPerak | 305 | 3 Nov 20151st sale agreement 3 Nov 2013 | — | — |
| ARMANEEKPKT 6822-8 | PetalingSelangor | 1,915 | — | — | — |
Under construction (9) and not yet started (3)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| THE RAFFLESIA - BANDAR DAMANSARA PERDANAKPKT 7609-10 | PetalingSelangor | 460 | SmoothOn schedule | 30 Dec 20141st sale agreement 30 Dec 2012 | 0–100% |
| TAMAN KLEBANG PUTRA 2KPKT 7670-15 | KintaPerak | 610 | Not startedNot started | 18 Feb 20161st sale agreement 18 Feb 2013 | 0–100% |
| TAMAN KLEBANG PUTRA 3KPKT 7670-23 | KintaPerak | 48 | SmoothOn schedule | 31 Jan 20271st sale agreement 31 Jan 2025 | 94% |
| THE RAFFLESIA @ HILL 4KPKT 7609-18 | PetalingSelangor | 22 | SmoothOn schedule | 17 May 20271st sale agreement 17 May 2025 | 96% |
| TAMAN TEJA PERDANAKPKT 19847-3 | KamparPerak | 56 | SmoothOn schedule | 9 Jun 20271st sale agreement 9 Jun 2025 | 92% |
| TAMAN BUNGA RAYAKPKT 6822-25 | Ulu SelangorSelangor | 108 | SmoothOn schedule | 20 Nov 20271st sale agreement 20 Nov 2025 | 64% |
| TAMAN RAIA PERDANAKPKT 19847-4 | KamparPerak | 54 | SmoothOn schedule | 30 Mar 20281st sale agreement 30 Mar 2026 | 44% |
| TAMAN KLEBANG PUTRA 3KPKT 7670-24 | Perak | 69 | SmoothOn schedule | 8 Jun 20281st sale agreement 8 Jun 2026 | 52% |
| TAMAN BUNGA RAYAKPKT 6822-26 | Ulu SelangorSelangor | 96 | SmoothOn schedule | 20 Jun 20281st sale agreement 20 Jun 2026 | 23% |
| TAMAN BUNGA RAYAKPKT 6822-27 | Ulu SelangorSelangor | 162 | SmoothOn schedule | 17 Aug 20281st sale agreement 17 Aug 2026 | 0% |
| TAMAN BUNGA RAYAKPKT 6822-28 | Hulu SelangorSelangor | 147 | Not startedNot started | — | 0% |
| TAMAN RAIA PERDANAKPKT 19847-5 | KamparPerak | 80 | Not startedNot started | — | 0% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| CYBERIA CRESCENT 3KPKT 7586-4 | SepangSelangor | 186 | Permit cancelledPermit cancelled | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
MK Land at a glance
| Listed | Bursa Malaysia Main Market · MKLAND (8893) · listed 27 August 1999[1] |
|---|---|
| Started | Incorporated in Malaysia in 1978 (company registration no. 197801003984)[1] |
| Head office | Bandar Damansara Perdana, Petaling Jaya, Selangor[1] |
| Leadership | Felina binti Mustapha Kamal — Executive Chairman (since 29 August 2017)[1] |
| Companies in the KPKT register | MEDAN PRESTASI SDN. BHD. KPKT 6822[1] ZAMAN TELADAN SDN. BHD. KPKT 7670[1] SAUJANA TRIANGLE SDN. BHD. KPKT 7609[1] NALURI MAJUJAYA SDN. BHD. (85%) KPKT 19847[1] PARAMODEN SDN. BHD. KPKT 7586[1] DOMINANT STAR SDN. BHD. KPKT 9386[1] VIBRANT LEISURE SDN. BHD. KPKT 6656[1] CENTRALPOLITAN DEVELOPMENT SDN. BHD. KPKT 9230[1] MK DEVELOPMENT SDN. BHD. KPKT 8110[1] |
| Website | mkland.com.my |
| Businesses | Property; leisure (Bukit Merah Laketown Resort in Perak, Ombak Villa Langkawi); renewable energy (a 10.95MWac solar plant in Kerian, Perak)[1] |
| Property share of revenue (company figure) | RM151.2 million of RM177.0 million (about 85.4%) in the year to 30 June 2026[1] |
| Townships named in the annual report | Damansara Perdana and Damansara Damai (Petaling Jaya); Taman Bunga Raya (Bukit Beruntung, Selangor); Meru Perdana and Klebang Putra (Ipoh); Raia Perdana and Teja Perdana (Simpang Pulai, Perak)[1] |
| Largest land parcel (company figure) | 1,316.88 acres in Kerian, Perak, held for a proposed mixed development and resort (30 June 2026)[1] |
MK Land projects on sale on PropertySifu
Suasana Damai
- ONE DAMANSARA — 0.4 km, 2013
- THE RAFFLESIA — 2.4 km, 2025
- THE RAFFLESIA — 2.4 km, 2024
Who is MK Land? The company behind the projects
M K Land Holdings Berhad was incorporated in Malaysia in 1978, as its company registration number shows, and made its debut on the Main Board of the Kuala Lumpur Stock Exchange — today Bursa Malaysia's Main Market — on 27 August 1999; it trades as MKLAND, stock code 8893 [1]. Its co-founder, the late Tan Sri Mustapha Kamal Abu Bakar, was behind Damansara Perdana and several other townships in Selangor [2]. The registered office and principal place of business are in Bandar Damansara Perdana, Petaling Jaya [1].
The group has three businesses: property; leisure, with Bukit Merah Laketown Resort in Perak and Ombak Villa Langkawi; and renewable energy, including a 10.95MWac solar plant in Kerian, Perak [1]. Property is the main one — it contributed RM151.2 million of the group's RM177.0 million revenue in the year to 30 June 2026, the company says [1]. The annual report names its residential townships as Damansara Perdana and Damansara Damai in Petaling Jaya, Taman Bunga Raya in Bukit Beruntung, Meru Perdana and Klebang Putra in Ipoh, and Raia Perdana and Teja Perdana in Simpang Pulai, Perak [1].
The KPKT records on this page cover nine MK Land subsidiaries listed in the 2026 annual report: eight wholly owned, and Naluri Majujaya Sdn Bhd, 85% owned [1]. Suasana Damai, the Damansara Damai project on PropertySifu, is registered with KPKT as a 780-unit project (6822-15) under Medan Prestasi Sdn Bhd, a wholly-owned subsidiary [1]. The resorts and solar plants are not housing projects, so they are not in the KPKT records.
The executive chairman is Felina binti Mustapha Kamal, in the role since 29 August 2017 and on the board since 19 January 2007 [1].
Frequently asked questions
Is MK Land a listed company?
Yes. M K Land Holdings Berhad has been listed since 27 August 1999 and trades on Bursa Malaysia's Main Market as MKLAND, stock code 8893 [1].
How many projects has MK Land completed?
The KPKT register lists 56 housing projects under nine MK Land subsidiaries: 43 completed, 9 under construction, 3 not yet started and 1 with its permit cancelled. 30 are in Selangor and 26 in Perak.
Does MK Land have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 56 MK Land projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat).
Which company develops Suasana Damai?
Medan Prestasi Sdn Bhd (KPKT developer code 6822), a wholly-owned subsidiary of M K Land Holdings Berhad according to its 2026 annual report [1]. KPKT registers the project as 6822-15, with 780 units.
Was Suasana Damai handed over on time?
KPKT records the first sale agreement on 21 July 2016 and a handover deadline of 21 July 2019, extended with approval by 23 months to 21 June 2021. The project has three 260-unit blocks, handed over on 24 September 2020 (270 days before the extended deadline), 11 October 2021 (112 days after it) and 16 May 2023 (694 days after it); the last CCC is dated 15 May 2023. Construction ran through 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether the deadline already reflects it.
Does MK Land usually hand over before the deadline?
Of the 43 completed projects, 23 have dates that can be compared with a deadline (an approved extension is counted at the extended deadline): 9 were handed over on or before it, 10 after it (3 of them with construction during the 18 March–31 August 2020 period excluded by Act 829), and 4 received the completion certificate before the deadline with no handover date recorded. The other 20 have no comparable dates in the register.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] M K Land Holdings Berhad Annual Report 2026 (financial year ended 30 June 2026) · M K Land Holdings Berhad · 22 Oct 2026 · accessed 28 Oct 2026