LBS Bina Group (LBS Bina Group Berhad)
LBS Bina Group Berhad is a Bursa Malaysia Main Market-listed developer with 182 housing projects in the KPKT register under 29 LBS companies in five states: 161 completed, 11 under construction, three not yet started and seven with permits cancelled. None is classed Sick or Abandoned; one is classed Late (Lewat). It was founded in the early 1960s.
- 182 projects in the KPKT register
- 161 completed
- 11 under construction (of which 1 Late)
- 3 not yet started
- 7 with the permit cancelled
- None Sick or Abandoned
Has LBS Bina Group handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 182 housing projects under 29 LBS Bina Group companies in 5 states: 161 completed, 11 under construction (of which 1 Late), 3 not yet started, 7 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 161 completed projects, 112 have both a handover deadline and a completion date in the register: 39 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 32 handed over or certified complete after that deadline (5 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 41 received the completion certificate before the deadline (handover date not recorded).
47 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 161
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IDAMAN SARIKPKT 30373-1 | SepangSelangor | 513 | 10 May 2027Extended 12 months from 10 May 20261st sale agreement 10 May 2023 | CCC 19 Aug 2026 Handover 24 Sep 2026 | 228 days before |
| BANDAR PUTERA INDAH (IMPERIAL GARDEN)KPKT 11018-3 | Batu PahatJohor | 30 | 11 Jul 20261st sale agreement 11 Jul 2024 | CCC 11 Jun 2026 Handover 12 Jun 2026 | 29 days before |
| PANGSAPURI KITA SEJATIKPKT 30027-1 | SepangSelangor | 1,054 | 13 Oct 2026Extended 12 months from 13 Oct 20251st sale agreement 13 Oct 2022 | CCC 28 Jan 2026 Handover 8 May 2026 | 158 days before |
| IDAMAN CAHAYA 1KPKT 30322-1 | PetalingSelangor | 568 | 23 Mar 2027Extended 12 months from 23 Mar 20261st sale agreement 23 Mar 2023 | CCC 19 Mar 2026 Handover 7 Apr 2026 | 350 days before |
| IDAMAN CAHAYA 2KPKT 30322-2 | PetalingSelangor | 872 | 6 Apr 20261st sale agreement 6 Apr 2023 | CCC 19 Mar 2026 Handover 7 Apr 2026 | 1 day after |
| PRESTIGE RESIDENCE (BLOCK B)KPKT 20162-2Prestige Residence · on PropertySifu | PetalingSelangor | 725 | 20 Mar 2027Extended 12 months from 20 Mar 20261st sale agreement 20 Mar 2023 | CCC 22 Oct 2025 Handover 28 Nov 2025 | 477 days before |
| TAMAN KINDING FLORAKPKT 19632-13 | KintaPerak | 32 | 21 Jun 20261st sale agreement 21 Jun 2024 | CCC 14 Oct 2025 Handover 14 Nov 2025 | 219 days before |
| PRESTIGE RESIDENCEKPKT 20162-1Prestige Residence · on PropertySifu | PetalingSelangor | 725 | 10 Oct 2025Extended 12 months from 10 Oct 20241st sale agreement 10 Oct 2021 | CCC 22 Oct 2025 | 12 days after |
| ASTELLA PHASE 1KPKT 11482-10D' Island Residences · on PropertySifu | SepangSelangor | 76 | 5 Sep 20251st sale agreement 5 Sep 2023 | CCC 2 Apr 2025 Handover 1 Oct 2025 | 26 days after |
| IDAMAN MELURKPKT 30136-1 | SepangSelangor | 1,448 | 11 Nov 2026Extended 12 months from 11 Nov 20251st sale agreement 11 Nov 2022 | CCC 16 Jun 2025 Handover 26 Jun 2025 | 503 days before |
| KITA MESRAKPKT 19533-4 | SepangSelangor | 646 | 11 Nov 2025Extended 12 months from 11 Nov 20241st sale agreement 11 Nov 2021 | CCC 15 May 2025 Handover 19 May 2025 | 176 days before |
| TAMAN KINDING FLORAKPKT 19632-11 | KintaPerak | 90 | 31 May 20251st sale agreement 31 May 2023 | CCC 27 Mar 2025 Handover 27 Mar 2025 | 65 days before |
Handed over or certified complete after the deadline — 12 most recent of 32
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IDAMAN CAHAYA 2KPKT 30322-2 | PetalingSelangor | 872 | 6 Apr 20261st sale agreement 6 Apr 2023 | CCC 19 Mar 2026 Handover 7 Apr 2026 | 1 day after |
| PRESTIGE RESIDENCEKPKT 20162-1Prestige Residence · on PropertySifu | PetalingSelangor | 725 | 10 Oct 2025Extended 12 months from 10 Oct 20241st sale agreement 10 Oct 2021 | CCC 22 Oct 2025 | 12 days after |
| ASTELLA PHASE 1KPKT 11482-10D' Island Residences · on PropertySifu | SepangSelangor | 76 | 5 Sep 20251st sale agreement 5 Sep 2023 | CCC 2 Apr 2025 Handover 1 Oct 2025 | 26 days after |
| TAMAN KINDING FLORAKPKT 19632-8 | KintaPerak | 84 | 29 Sep 20231st sale agreement 29 Sep 2021 | CCC 17 Nov 2023 Handover 17 Nov 2023 | 49 days after |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3 - PHASE 26)KPKT 7702-46 | Batu PahatJohor | 29 | 16 Jul 20231st sale agreement 16 Jul 2021 | CCC 31 Oct 2023 Handover 31 Oct 2023 | 107 days after |
| TAMAN KINDING FLORAKPKT 19632-6 | KintaPerak | 52 | 20 Mar 2023Extended 5 months from 20 Oct 20221st sale agreement 20 Oct 2020 | CCC 24 Mar 2023 Handover 24 Mar 2023 | 4 days after |
| BANDAR PUTERA INDAHKPKT 7702-36 | Batu PahatJohor | 40 | 1 Nov 2022Extended 5 months from 1 Jun 20221st sale agreement 1 Jun 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 44 days after † |
| BANDAR PUTERA INDAHKPKT 7702-39 | Batu PahatJohor | 38 | 17 Nov 2022Extended 5 months from 17 Jun 20221st sale agreement 17 Jun 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 28 days after † |
| BANDAR PUTERA INDAHKPKT 7702-43 | Batu PahatJohor | 56 | 14 Dec 2022Extended 5 months from 14 Jul 20221st sale agreement 14 Jul 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 1 day after † |
| KITA IMPIANKPKT 19533-3 | SepangSelangor | 964 | 14 May 20221st sale agreement 14 May 2019 | CCC 28 Jun 2022 Handover 30 Jun 2022 | 47 days after † |
| KITA BAYUKPKT 19533-1 | SepangSelangor | 1,077 | 30 Jul 20211st sale agreement 30 Jul 2018 | CCC 24 Dec 2021 | 147 days after † |
| BANDAR PUTERA INDAHKPKT 7702-15 | Batu PahatJohor | 321 | 11 Jan 20191st sale agreement 11 Jan 2017 | CCC 23 Apr 2021 | 833 days after |
Show all 32
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IDAMAN CAHAYA 2KPKT 30322-2 | PetalingSelangor | 872 | 6 Apr 20261st sale agreement 6 Apr 2023 | CCC 19 Mar 2026 Handover 7 Apr 2026 | 1 day after |
| PRESTIGE RESIDENCEKPKT 20162-1Prestige Residence · on PropertySifu | PetalingSelangor | 725 | 10 Oct 2025Extended 12 months from 10 Oct 20241st sale agreement 10 Oct 2021 | CCC 22 Oct 2025 | 12 days after |
| ASTELLA PHASE 1KPKT 11482-10D' Island Residences · on PropertySifu | SepangSelangor | 76 | 5 Sep 20251st sale agreement 5 Sep 2023 | CCC 2 Apr 2025 Handover 1 Oct 2025 | 26 days after |
| TAMAN KINDING FLORAKPKT 19632-8 | KintaPerak | 84 | 29 Sep 20231st sale agreement 29 Sep 2021 | CCC 17 Nov 2023 Handover 17 Nov 2023 | 49 days after |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3 - PHASE 26)KPKT 7702-46 | Batu PahatJohor | 29 | 16 Jul 20231st sale agreement 16 Jul 2021 | CCC 31 Oct 2023 Handover 31 Oct 2023 | 107 days after |
| TAMAN KINDING FLORAKPKT 19632-6 | KintaPerak | 52 | 20 Mar 2023Extended 5 months from 20 Oct 20221st sale agreement 20 Oct 2020 | CCC 24 Mar 2023 Handover 24 Mar 2023 | 4 days after |
| BANDAR PUTERA INDAHKPKT 7702-36 | Batu PahatJohor | 40 | 1 Nov 2022Extended 5 months from 1 Jun 20221st sale agreement 1 Jun 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 44 days after † |
| BANDAR PUTERA INDAHKPKT 7702-39 | Batu PahatJohor | 38 | 17 Nov 2022Extended 5 months from 17 Jun 20221st sale agreement 17 Jun 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 28 days after † |
| BANDAR PUTERA INDAHKPKT 7702-43 | Batu PahatJohor | 56 | 14 Dec 2022Extended 5 months from 14 Jul 20221st sale agreement 14 Jul 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 1 day after † |
| KITA IMPIANKPKT 19533-3 | SepangSelangor | 964 | 14 May 20221st sale agreement 14 May 2019 | CCC 28 Jun 2022 Handover 30 Jun 2022 | 47 days after † |
| KITA BAYUKPKT 19533-1 | SepangSelangor | 1,077 | 30 Jul 20211st sale agreement 30 Jul 2018 | CCC 24 Dec 2021 | 147 days after † |
| BANDAR PUTERA INDAHKPKT 7702-15 | Batu PahatJohor | 321 | 11 Jan 20191st sale agreement 11 Jan 2017 | CCC 23 Apr 2021 | 833 days after |
| BANDAR PUTERA INDAHKPKT 6514-12 | Batu PahatJohor | 53 | 13 Apr 20051st sale agreement 13 Apr 2003 | CFO 11 Mar 2020 | 5,446 days after |
| BANDAR SAUJANA PUTRAKPKT 8945-7 | Kuala LangatSelangor | 898 | 2 Jan 20191st sale agreement 2 Jan 2016 | CCC 13 Mar 2019 | 70 days after |
| DESIRAN BAYUKPKT 7702-22 | SepangSelangor | 26 | 5 Feb 20181st sale agreement 5 Feb 2016 | CCC 28 Sep 2018 | 235 days after |
| D' ISLAND RESIDENCEKPKT 11482-2 | SepangSelangor | 74 | 24 Jul 20131st sale agreement 24 Jul 2011 | CCC 20 Apr 2018 | 1,731 days after |
| D' ISLAND RESIDENCESKPKT 11482-5 | SepangSelangor | 115 | 13 Dec 20131st sale agreement 13 Dec 2011 | CCC 16 Jan 2018 | 1,495 days after |
| BANDAR PUTERA INDAHKPKT 7702-16 | Batu PahatJohor | 44 | 6 Jun 20171st sale agreement 6 Jun 2015 | CCC 8 Jan 2018 | 216 days after |
| BANDAR SAUJANA PUTRAKPKT 8945-4 | Kuala LangatSelangor | 892 | 15 Dec 20171st sale agreement 15 Dec 2014 | CCC 21 Dec 2017 | 6 days after |
| BANDAR PUTERA INDAHKPKT 11018-2 | Batu PahatJohor | 34 | 15 Feb 20171st sale agreement 15 Feb 2015 | CCC 16 Nov 2017 | 274 days after |
| D' ISLAND RESIDENCEKPKT 11482-8 | SepangSelangor | 56 | 13 Jul 20171st sale agreement 13 Jul 2015 | CCC 28 Jul 2017 | 15 days after |
| D' ISLAND RESIDENCEKPKT 11482-6 | SepangSelangor | 86 | 2 Feb 20171st sale agreement 2 Feb 2015 | CCC 17 Mar 2017 | 43 days after |
| BANDAR PUTERA INDAHKPKT 7702-14 | Batu PahatJohor | 207 | 26 Mar 20161st sale agreement 26 Mar 2014 | CCC 14 Mar 2017 | 353 days after |
| BANDAR PUTERA INDAHKPKT 11018-1 | Batu PahatJohor | 218 | 2 Apr 20131st sale agreement 2 Apr 2011 | CFO 27 Dec 2016 | 1,365 days after |
| CAMERON GOLDEN HILLSKPKT 8752-9 | Cameron HighlandsPahang | 381 | 21 Aug 20161st sale agreement 21 Aug 2013 | CCC 8 Dec 2016 | 109 days after |
| CAMERON GOLDEN HILLSKPKT 8752-8 | Cameron HighlandsPahang | 46 | 16 Jun 20161st sale agreement 16 Jun 2014 | CCC 26 Sep 2016 | 102 days after |
| BANDAR PUTERA INDAHKPKT 7702-12 | Batu PahatJohor | 612 | 16 Dec 20151st sale agreement 16 Dec 2013 | CCC 29 Jun 2016 | 196 days after |
| BANDAR PUTERA INDAHKPKT 7702-11 | Batu PahatJohor | 166 | 19 Jun 20151st sale agreement 19 Jun 2013 | CCC 26 Aug 2015 | 68 days after |
| BANDAR SAUJANA PUTRAKPKT 11893-2 | Kuala LangatSelangor | 350 | 17 Oct 20141st sale agreement 17 Oct 2012 | CCC 17 Feb 2015 | 123 days after |
| BANDAR PUTERA INDAHKPKT 6514-18 | Batu PahatJohor | 268 | 18 Sep 20051st sale agreement 18 Sep 2003 | CFO 9 Nov 2014 | 3,339 days after |
| BANDAR PUTERA INDAHKPKT 6514-10 | Batu PahatJohor | 277 | 19 Nov 20031st sale agreement 19 Nov 2001 | CFO 5 Nov 2014 | 4,004 days after |
| BANDAR PUTERA INDAHKPKT 6514-17 | Batu PahatJohor | 80 | 12 Jul 20051st sale agreement 12 Jul 2003 | CFO 5 Aug 2014 | 3,311 days after |
Show all 161 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| IDAMAN SARIKPKT 30373-1 | SepangSelangor | 513 | 10 May 2027Extended 12 months from 10 May 20261st sale agreement 10 May 2023 | CCC 19 Aug 2026 Handover 24 Sep 2026 | 228 days before |
| BANDAR PUTERA INDAH (IMPERIAL GARDEN)KPKT 11018-3 | Batu PahatJohor | 30 | 11 Jul 20261st sale agreement 11 Jul 2024 | CCC 11 Jun 2026 Handover 12 Jun 2026 | 29 days before |
| PANGSAPURI KITA SEJATIKPKT 30027-1 | SepangSelangor | 1,054 | 13 Oct 2026Extended 12 months from 13 Oct 20251st sale agreement 13 Oct 2022 | CCC 28 Jan 2026 Handover 8 May 2026 | 158 days before |
| IDAMAN CAHAYA 1KPKT 30322-1 | PetalingSelangor | 568 | 23 Mar 2027Extended 12 months from 23 Mar 20261st sale agreement 23 Mar 2023 | CCC 19 Mar 2026 Handover 7 Apr 2026 | 350 days before |
| IDAMAN CAHAYA 2KPKT 30322-2 | PetalingSelangor | 872 | 6 Apr 20261st sale agreement 6 Apr 2023 | CCC 19 Mar 2026 Handover 7 Apr 2026 | 1 day after |
| PRESTIGE RESIDENCE (BLOCK B)KPKT 20162-2Prestige Residence · on PropertySifu | PetalingSelangor | 725 | 20 Mar 2027Extended 12 months from 20 Mar 20261st sale agreement 20 Mar 2023 | CCC 22 Oct 2025 Handover 28 Nov 2025 | 477 days before |
| TAMAN KINDING FLORAKPKT 19632-13 | KintaPerak | 32 | 21 Jun 20261st sale agreement 21 Jun 2024 | CCC 14 Oct 2025 Handover 14 Nov 2025 | 219 days before |
| PRESTIGE RESIDENCEKPKT 20162-1Prestige Residence · on PropertySifu | PetalingSelangor | 725 | 10 Oct 2025Extended 12 months from 10 Oct 20241st sale agreement 10 Oct 2021 | CCC 22 Oct 2025 | 12 days after |
| ASTELLA PHASE 1KPKT 11482-10D' Island Residences · on PropertySifu | SepangSelangor | 76 | 5 Sep 20251st sale agreement 5 Sep 2023 | CCC 2 Apr 2025 Handover 1 Oct 2025 | 26 days after |
| IDAMAN MELURKPKT 30136-1 | SepangSelangor | 1,448 | 11 Nov 2026Extended 12 months from 11 Nov 20251st sale agreement 11 Nov 2022 | CCC 16 Jun 2025 Handover 26 Jun 2025 | 503 days before |
| KITA MESRAKPKT 19533-4 | SepangSelangor | 646 | 11 Nov 2025Extended 12 months from 11 Nov 20241st sale agreement 11 Nov 2021 | CCC 15 May 2025 Handover 19 May 2025 | 176 days before |
| TAMAN KINDING FLORAKPKT 19632-11 | KintaPerak | 90 | 31 May 20251st sale agreement 31 May 2023 | CCC 27 Mar 2025 Handover 27 Mar 2025 | 65 days before |
| TAMAN KINDING FLORAKPKT 19632-12 | KintaPerak | 62 | 31 May 20251st sale agreement 31 May 2023 | CCC 27 Mar 2025 Handover 27 Mar 2025 | 65 days before |
| SOMERHOMESKPKT 8752-13 | Cameron HighlandsPahang | 14 | 5 Jul 20251st sale agreement 5 Jul 2023 | CCC 13 Dec 2024 Handover 13 Dec 2024 | 204 days before |
| PANGSAPURI IDAMAN BSPKPKT 8695-13 | Kuala LangatSelangor | 1,312 | 8 Jul 2025Extended 12 months from 8 Jul 20241st sale agreement 8 Jul 2021 | CCC 15 Jul 2024 Handover 8 Aug 2024 | 334 days before |
| BANDAR PUTERA INDAHKPKT 7702-41 | Batu PahatJohor | 26 | 9 Jan 20251st sale agreement 9 Jan 2023 | CCC 27 Jun 2024 Handover 28 Jun 2024 | 195 days before |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3)KPKT 7702-47 | Batu PahatJohor | 26 | 5 Aug 20241st sale agreement 5 Aug 2022 | CCC 27 Jun 2024 Handover 28 Jun 2024 | 38 days before |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3 - PHASE 24)KPKT 7702-48 | Batu PahatJohor | 27 | 2 Aug 20241st sale agreement 2 Aug 2022 | CCC 27 Jun 2024 Handover 28 Jun 2024 | 35 days before |
| MELODI PERDANAKPKT 19183-12 | Kuala SelangorSelangor | 642 | 17 May 2026Extended 12 months from 17 May 20251st sale agreement 17 May 2022 | CCC 27 May 2024 Handover 13 Jun 2024 | 703 days before |
| KITA MEKARKPKT 19924-2 | SepangSelangor | 1,162 | 20 Mar 2025Extended 17 months from 20 Oct 20231st sale agreement 20 Oct 2020 | CCC 12 Mar 2024 Handover 29 Mar 2024 | 356 days before |
| RITMA PERDANAKPKT 19183-11 | Kuala SelangorSelangor | 1,151 | 12 Feb 2025Extended 17 months from 12 Sep 20231st sale agreement 12 Sep 2020 | CCC 1 Mar 2024 Handover 11 Mar 2024 | 338 days before |
| TAMAN KINDING FLORAKPKT 19632-10 | KintaPerak | 64 | 28 Apr 20241st sale agreement 28 Apr 2022 | CCC 13 Feb 2024 Handover 13 Feb 2024 | 75 days before |
| LAMAN BAYUKPKT 19398-3 | Batu PahatJohor | 62 | 16 Dec 20231st sale agreement 16 Dec 2021 | CCC 14 Dec 2023 Handover 14 Dec 2023 | 2 days before |
| LAMAN BAYUKPKT 19398-4 | Batu PahatJohor | 56 | 23 Jan 20241st sale agreement 23 Jan 2022 | CCC 14 Dec 2023 Handover 14 Dec 2023 | 40 days before |
| RESIDENSI BINTANG BUKIT JALILKPKT 19162-2 | Kuala LumpurWP Kuala Lumpur | 1,342 | 25 Jan 2024Extended 38 months from 25 Nov 20201st sale agreement 25 Nov 2017 | CCC 16 Nov 2023 Handover 4 Dec 2023 | 52 days before |
| TAMAN KINDING FLORAKPKT 19632-8 | KintaPerak | 84 | 29 Sep 20231st sale agreement 29 Sep 2021 | CCC 17 Nov 2023 Handover 17 Nov 2023 | 49 days after |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3 - PHASE 25)KPKT 7702-45 | Batu PahatJohor | 39 | 19 Nov 20231st sale agreement 19 Nov 2021 | CCC 16 Nov 2023 Handover 16 Nov 2023 | 3 days before |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3 - PHASE 26)KPKT 7702-46 | Batu PahatJohor | 29 | 16 Jul 20231st sale agreement 16 Jul 2021 | CCC 31 Oct 2023 Handover 31 Oct 2023 | 107 days after |
| MELODI PERDANAKPKT 19183-10 | Kuala SelangorSelangor | 878 | 12 Sep 2024Extended 23 months from 12 Oct 20221st sale agreement 12 Oct 2019 | CCC 4 Oct 2023 Handover 5 Oct 2023 | 343 days before |
| BANDAR PUTERA INDAH (EMERALD GARDEN 3 - PHASE 27)KPKT 7702-44 | Batu PahatJohor | 34 | 3 Oct 2023Extended 5 months from 3 May 20231st sale agreement 3 May 2021 | CCC 27 Sep 2023 Handover 27 Sep 2023 | 6 days before |
| KITA RIAKPKT 19924-1 | SepangSelangor | 812 | 1 Dec 2024Extended 17 months from 1 Jul 20231st sale agreement 1 Jul 2020 | CCC 15 Sep 2023 Handover 18 Sep 2023 | 440 days before |
| PPA1M MERCU JALILKPKT 19162-1 | Kuala LumpurWP Kuala Lumpur | 1,360 | 27 Sep 2023Extended 32 months from 27 Jan 20211st sale agreement 27 Jan 2018 | CCC 7 Sep 2023 Handover 7 Sep 2023 | 20 days before |
| TAMAN KINDING FLORAKPKT 19632-9 | KintaPerak | 32 | 6 Sep 20231st sale agreement 6 Sep 2021 | CCC 21 Jul 2023 Handover 21 Jul 2023 | 47 days before |
| BANDAR PUTERA INDAHKPKT 7702-40 | Batu PahatJohor | 24 | 22 Jun 2023Extended 5 months from 22 Jan 20231st sale agreement 22 Jan 2021 | CCC 22 Jun 2023 Handover 22 Jun 2023 | On the deadline |
| TAMAN KINDING FLORAKPKT 19632-6 | KintaPerak | 52 | 20 Mar 2023Extended 5 months from 20 Oct 20221st sale agreement 20 Oct 2020 | CCC 24 Mar 2023 Handover 24 Mar 2023 | 4 days after |
| TAMAN KINDING FLORAKPKT 19632-7 | KintaPerak | 32 | 1 May 2023Extended 5 months from 1 Dec 20221st sale agreement 1 Dec 2020 | CCC 23 Feb 2023 Handover 23 Feb 2023 | 67 days before |
| BANDAR PUTERA INDAHKPKT 7702-36 | Batu PahatJohor | 40 | 1 Nov 2022Extended 5 months from 1 Jun 20221st sale agreement 1 Jun 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 44 days after † |
| BANDAR PUTERA INDAHKPKT 7702-39 | Batu PahatJohor | 38 | 17 Nov 2022Extended 5 months from 17 Jun 20221st sale agreement 17 Jun 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 28 days after † |
| BANDAR PUTERA INDAHKPKT 7702-43 | Batu PahatJohor | 56 | 14 Dec 2022Extended 5 months from 14 Jul 20221st sale agreement 14 Jul 2020 | CCC 15 Dec 2022 Handover 15 Dec 2022 | 1 day after † |
| TAMAN KINDING FLORAKPKT 19632-5 | KintaPerak | 64 | 22 Jan 2023Extended 15 months from 22 Oct 20211st sale agreement 22 Oct 2019 | CCC 29 Sep 2022 Handover 29 Sep 2022 | 115 days before |
| GENERASI SIMBOLIK SDN BHDKPKT 19632-1 | KintaPerak | 78 | 11 Sep 2022Extended 15 months from 11 Jun 20211st sale agreement 11 Jun 2019 | CCC 20 Jul 2022 Handover 21 Jul 2022 | 52 days before |
| TAMAN KINDING FLORAKPKT 19632-4 | KintaPerak | 52 | 10 Nov 2022Extended 5 months from 10 Jun 20221st sale agreement 10 Jun 2020 | CCC 20 Jul 2022 Handover 20 Jul 2022 / 21 Jul 2022 | 112 days before |
| BANDAR PUTERA INDAHKPKT 7702-37 | Batu PahatJohor | 46 | 2 Sep 2022Extended 10 months from 2 Nov 20211st sale agreement 2 Nov 2019 | CCC 21 Jul 2022 Handover 21 Jul 2022 | 43 days before |
| BANDAR PUTERA INDAHKPKT 7702-38 | Batu PahatJohor | 39 | 9 Nov 2022Extended 10 months from 9 Jan 20221st sale agreement 9 Jan 2020 | CCC 21 Jul 2022 Handover 21 Jul 2022 | 111 days before |
| KITA IMPIANKPKT 19533-3 | SepangSelangor | 964 | 14 May 20221st sale agreement 14 May 2019 | CCC 28 Jun 2022 Handover 30 Jun 2022 | 47 days after † |
| CAMERON GOLDEN HILLSKPKT 8752-12 | Cameron HighlandsPahang | 41 | 22 Dec 2022Extended 5 months from 22 Jul 20221st sale agreement 22 Jul 2020 | CCC 28 Jun 2022 Handover 28 Jun 2022 | 177 days before |
| SKYLAKE RESIDENCEKPKT 11482-9 | SepangSelangor | 746 | 18 Nov 2022Extended 27 months from 18 Aug 20201st sale agreement 18 Aug 2017 | CCC 10 Jun 2022 | CCC before deadline; handover not recorded |
| KITA HARMONIKPKT 19533-2 | SepangSelangor | 674 | 20 Apr 20221st sale agreement 20 Apr 2019 | CCC 8 Apr 2022 Handover 11 Apr 2022 | 9 days before |
| TAMAN KINDING FLORAKPKT 19632-2 | KintaPerak | 64 | 13 Feb 2022Extended 10 months from 13 Apr 20211st sale agreement 13 Apr 2019 | CCC 28 Jan 2022 Handover 28 Jan 2022 | 16 days before |
| TAMAN KINDING FLORAKPKT 19632-3 | KintaPerak | 48 | 16 May 2022Extended 10 months from 16 Jul 20211st sale agreement 16 Jul 2019 | CCC 28 Jan 2022 Handover 28 Jan 2022 | 108 days before |
| KITA BAYUKPKT 19533-1 | SepangSelangor | 1,077 | 30 Jul 20211st sale agreement 30 Jul 2018 | CCC 24 Dec 2021 | 147 days after † |
| LAMAN BAYUKPKT 19398-2 | Batu PahatJohor | 231 | 28 Nov 2021Extended 6 months from 28 May 20211st sale agreement 28 May 2019 | CCC 25 Oct 2021 | CCC before deadline; handover not recorded |
| RENTAK PERDANAKPKT 19183-8 | Kuala SelangorSelangor | 362 | 21 Jan 2022Extended 6 months from 21 Jul 20211st sale agreement 21 Jul 2018 | CCC 10 Sep 2021 | CCC before deadline; handover not recorded |
| RENTAK PERDANAKPKT 19183-9 | Kuala SelangorSelangor | 522 | 27 Aug 2022Extended 6 months from 27 Feb 20221st sale agreement 27 Feb 2019 | CCC 10 Sep 2021 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-15 | Batu PahatJohor | 321 | 11 Jan 20191st sale agreement 11 Jan 2017 | CCC 23 Apr 2021 | 833 days after |
| LAMAN BAYUKPKT 19398-1 | Batu PahatJohor | 134 | 17 May 2021Extended 6 months from 17 Nov 20201st sale agreement 17 Nov 2018 | CCC 18 Mar 2021 | CCC before deadline; handover not recorded |
| DELTA GALLERY SDN. BHD.KPKT 19145-1 | PetalingSelangor | 398 | 24 Sep 2021Extended 12 months from 24 Sep 20201st sale agreement 24 Sep 2017 | CCC 3 Dec 2020 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 6514-12 | Batu PahatJohor | 53 | 13 Apr 20051st sale agreement 13 Apr 2003 | CFO 11 Mar 2020 | 5,446 days after |
| IRAMA PERDANAKPKT 19183-1 | Kuala SelangorSelangor | 349 | 23 Oct 20201st sale agreement 23 Oct 2017 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| SIMFONI PERDANAKPKT 19183-2 | Kuala SelangorSelangor | 202 | 17 Dec 20201st sale agreement 17 Dec 2017 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| SIMFONI PERDANAKPKT 19183-3 | Kuala SelangorSelangor | 168 | 10 Oct 20201st sale agreement 10 Oct 2017 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| IRAMA PERDANAKPKT 19183-4 | Kuala SelangorSelangor | 324 | 4 Nov 20201st sale agreement 4 Nov 2017 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| SIMFONI PERDANAKPKT 19183-5 | Kuala SelangorSelangor | 98 | 15 Jul 20211st sale agreement 15 Jul 2018 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| SIMFONI PERDANAKPKT 19183-6 | Kuala SelangorSelangor | 340 | 11 Mar 20211st sale agreement 11 Mar 2018 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| SIMFONI PERDANAKPKT 19183-7 | Kuala SelangorSelangor | 172 | 25 Feb 20211st sale agreement 25 Feb 2018 | CCC 28 Jan 2020 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-31 | Batu PahatJohor | 29 | 10 Jun 20201st sale agreement 10 Jun 2018 | CCC 11 Dec 2019 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-33 | Batu PahatJohor | 32 | 14 Apr 20201st sale agreement 14 Apr 2018 | CCC 11 Dec 2019 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-28 | Batu PahatJohor | 34 | 10 Mar 20201st sale agreement 10 Mar 2018 | CCC 25 Nov 2019 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-35 | Batu PahatJohor | 30 | 10 Feb 20201st sale agreement 10 Feb 2018 | CCC 28 Oct 2019 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-34 | Batu PahatJohor | 30 | 27 Jan 20201st sale agreement 27 Jan 2018 | CCC 17 Oct 2019 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-32 | Batu PahatJohor | 45 | 28 Sep 20191st sale agreement 28 Sep 2017 | CCC 27 Sep 2019 | CCC before deadline; handover not recorded |
| BANDAR SAUJANA PUTRAKPKT 8945-7 | Kuala LangatSelangor | 898 | 2 Jan 20191st sale agreement 2 Jan 2016 | CCC 13 Mar 2019 | 70 days after |
| DESIRAN BAYUKPKT 7702-29 | SepangSelangor | 81 | 28 Jul 20191st sale agreement 28 Jul 2017 | CCC 28 Nov 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-30 | SepangSelangor | 30 | 28 Jul 20191st sale agreement 28 Jul 2017 | CCC 28 Nov 2018 | CCC before deadline; handover not recorded |
| CAMERON GOLDEN HILLSKPKT 8752-11 | Cameron HighlandsPahang | 77 | 2 Jun 20191st sale agreement 2 Jun 2017 | CCC 23 Nov 2018 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-23 | Batu PahatJohor | 30 | 7 Feb 20191st sale agreement 7 Feb 2017 | CCC 16 Oct 2018 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-24 | Batu PahatJohor | 44 | 7 Feb 20191st sale agreement 7 Feb 2017 | CCC 16 Oct 2018 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-25 | Batu PahatJohor | 44 | 27 Feb 20191st sale agreement 27 Feb 2017 | CCC 16 Oct 2018 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-26 | Batu PahatJohor | 23 | 1 Mar 20191st sale agreement 1 Mar 2017 | CCC 16 Oct 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-20 | SepangSelangor | 34 | 20 Nov 20181st sale agreement 20 Nov 2016 | CCC 28 Sep 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-22 | SepangSelangor | 26 | 5 Feb 20181st sale agreement 5 Feb 2016 | CCC 28 Sep 2018 | 235 days after |
| MIDHILLSKPKT 8938-5 | BentongPahang | 167 | 15 Aug 20201st sale agreement 15 Aug 2017 | CCC 7 Sep 2018 | CCC before deadline; handover not recorded |
| BANDAR SAUJANA PUTRAKPKT 8945-6 | Kuala LangatSelangor | 534 | 9 Jun 20191st sale agreement 9 Jun 2016 | CCC 21 Aug 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-18 | SepangSelangor | 64 | 27 Oct 20181st sale agreement 27 Oct 2016 | CCC 16 Aug 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-19 | SepangSelangor | 26 | 29 Sep 20181st sale agreement 29 Sep 2016 | CCC 16 Aug 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-17 | SepangSelangor | 318 | 6 Aug 20181st sale agreement 6 Aug 2016 | CCC 12 Jun 2018 | CCC before deadline; handover not recorded |
| DESIRAN BAYUKPKT 7702-27 | SepangSelangor | 12 | 7 Mar 20191st sale agreement 7 Mar 2017 | CCC 12 Jun 2018 | CCC before deadline; handover not recorded |
| MIDHILLSKPKT 8938-4 | BentongPahang | 251 | 3 May 20201st sale agreement 3 May 2017 | CCC 31 May 2018 | CCC before deadline; handover not recorded |
| D' ISLAND RESIDENCEKPKT 11482-2 | SepangSelangor | 74 | 24 Jul 20131st sale agreement 24 Jul 2011 | CCC 20 Apr 2018 | 1,731 days after |
| D' ISLAND RESIDENCESKPKT 11482-5 | SepangSelangor | 115 | 13 Dec 20131st sale agreement 13 Dec 2011 | CCC 16 Jan 2018 | 1,495 days after |
| BANDAR PUTERA INDAHKPKT 7702-16 | Batu PahatJohor | 44 | 6 Jun 20171st sale agreement 6 Jun 2015 | CCC 8 Jan 2018 | 216 days after |
| D' ISLAND RESIDENCEKPKT 11482-7 | SepangSelangor | 352 | 11 Jun 20181st sale agreement 11 Jun 2015 | CCC 29 Dec 2017 | CCC before deadline; handover not recorded |
| BANDAR SAUJANA PUTRAKPKT 8945-4 | Kuala LangatSelangor | 892 | 15 Dec 20171st sale agreement 15 Dec 2014 | CCC 21 Dec 2017 | 6 days after |
| BANDAR SAUJANA PUTRAKPKT 8945-5 | Kuala LangatSelangor | 278 | 5 May 20181st sale agreement 5 May 2015 | CCC 21 Dec 2017 | CCC before deadline; handover not recorded |
| MIDHILLSKPKT 8938-3 | BentongPahang | 192 | 24 Dec 20171st sale agreement 24 Dec 2014 | CCC 27 Nov 2017 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 11018-2 | Batu PahatJohor | 34 | 15 Feb 20171st sale agreement 15 Feb 2015 | CCC 16 Nov 2017 | 274 days after |
| D' ISLAND RESIDENCEKPKT 11482-8 | SepangSelangor | 56 | 13 Jul 20171st sale agreement 13 Jul 2015 | CCC 28 Jul 2017 | 15 days after |
| D' ISLAND RESIDENCEKPKT 11482-6 | SepangSelangor | 86 | 2 Feb 20171st sale agreement 2 Feb 2015 | CCC 17 Mar 2017 | 43 days after |
| BANDAR PUTERA INDAHKPKT 7702-14 | Batu PahatJohor | 207 | 26 Mar 20161st sale agreement 26 Mar 2014 | CCC 14 Mar 2017 | 353 days after |
| BANDAR PUTERA INDAHKPKT 11018-1 | Batu PahatJohor | 218 | 2 Apr 20131st sale agreement 2 Apr 2011 | CFO 27 Dec 2016 | 1,365 days after |
| CAMERON GOLDEN HILLSKPKT 8752-9 | Cameron HighlandsPahang | 381 | 21 Aug 20161st sale agreement 21 Aug 2013 | CCC 8 Dec 2016 | 109 days after |
| SINARAN RESTU SDN. BHD.KPKT 7400-16 | KintaPerak | 11 | 9 Jan 20171st sale agreement 9 Jan 2015 | CCC 22 Nov 2016 | CCC before deadline; handover not recorded |
| CAMERON GOLDEN HILLSKPKT 8752-8 | Cameron HighlandsPahang | 46 | 16 Jun 20161st sale agreement 16 Jun 2014 | CCC 26 Sep 2016 | 102 days after |
| BANDAR PUTERA INDAHKPKT 7702-12 | Batu PahatJohor | 612 | 16 Dec 20151st sale agreement 16 Dec 2013 | CCC 29 Jun 2016 | 196 days after |
| BANDAR SAUJANA PUTRAKPKT 8945-3 | Kuala LangatSelangor | 689 | 9 Jan 20161st sale agreement 9 Jan 2013 | CCC 12 Nov 2015 | CCC before deadline; handover not recorded |
| CAMERON GOLDEN HILLSKPKT 8752-7 | Cameron HighlandsPahang | 156 | —1st sale agreement 26 Oct 2011 | CCC 5 Nov 2015 | — |
| TAMAN ROYAL LILYKPKT 8719-6 | Cameron HighlandsPahang | 44 | 21 Mar 20161st sale agreement 21 Mar 2013 | CCC 18 Sep 2015 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7702-11 | Batu PahatJohor | 166 | 19 Jun 20151st sale agreement 19 Jun 2013 | CCC 26 Aug 2015 | 68 days after |
| BANDAR SAUJANA PUTRAKPKT 11893-2 | Kuala LangatSelangor | 350 | 17 Oct 20141st sale agreement 17 Oct 2012 | CCC 17 Feb 2015 | 123 days after |
| BANDAR SAUJANA PUTRAKPKT 11893-3 | Kuala LangatSelangor | 16 | 29 Jun 20151st sale agreement 29 Jun 2013 | CCC 19 Dec 2014 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 6514-18 | Batu PahatJohor | 268 | 18 Sep 20051st sale agreement 18 Sep 2003 | CFO 9 Nov 2014 | 3,339 days after |
| BANDAR PUTERA INDAHKPKT 6514-10 | Batu PahatJohor | 277 | 19 Nov 20031st sale agreement 19 Nov 2001 | CFO 5 Nov 2014 | 4,004 days after |
| BANDAR PUTERA INDAHKPKT 6514-13 | Batu PahatJohor | 100 | —1st sale agreement 12 Feb 2003 | CFO 5 Nov 2014 | — |
| BANDAR SAUJANA PUTRAKPKT 11893-1 | Kuala LangatSelangor | 368 | —1st sale agreement 7 Mar 2012 | CCC 29 Aug 2014 | — |
| BANDAR PUTERA INDAHKPKT 6514-17 | Batu PahatJohor | 80 | 12 Jul 20051st sale agreement 12 Jul 2003 | CFO 5 Aug 2014 | 3,311 days after |
| SERIBU BAIDURI SDN BHDKPKT 8695-10 | Kuala LangatSelangor | 536 | — | CCC 9 May 2014 | — |
| THE LAKE RESIDENCEKPKT 11482-3 | SepangSelangor | 299 | — | CCC 9 Dec 2013 | — |
| TAMAN GOLDEN HILLSKPKT 8752-6 | Cameron HighlandsPahang | 153 | — | CCC 26 Sep 2013 | — |
| TAMAN TASIK PUCHONGKPKT 9337-2 | SepangSelangor | 234 | — | CCC 2 Aug 2013 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-1 | Kuala LangatSelangor | 590 | — | CFO 2 Jul 2013 | — |
| BANDAR SAUJANA PUTRA (FASA 1)KPKT 8695-2 | Kuala LangatSelangor | 480 | — | CFO 14 Jun 2013 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-10 | Kuala LangatSelangor | 109 | — | CCC 8 May 2013 | — |
| D' ISLAND RESIDENCEKPKT 11482-1 | SepangSelangor | 122 | — | CCC 16 Apr 2013 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-12 | Kuala LangatSelangor | 150 | — | CCC 8 Apr 2013 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-11 | Kuala LangatSelangor | 178 | — | CCC 29 Mar 2013 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-13 | Kuala LangatSelangor | 288 | — | CCC 2 Nov 2012 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-14 | Kuala LangatSelangor | 44 | — | CCC 17 Aug 2012 | — |
| BANDAR SAUJANA PUTRAKPKT 8695-9 | Kuala LangatSelangor | 194 | — | CFO 15 May 2012 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-9 | Kuala LangatSelangor | 88 | — | CCC 4 May 2012 | — |
| TAMAN ROYAL LILYKPKT 8719-1 | Cameron HighlandsPahang | 56 | — | CCC 9 Jan 2012 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-8 | Kuala LangatSelangor | 346 | — | CFO 29 Nov 2011 | — |
| BANDAR SAUJANA PUTRAKPKT 8945-1 | Kuala LangatSelangor | 544 | — | CFO 31 Jan 2011 | — |
| BNDAR SAUJANA PUTRAKPKT 8944-7 | Kuala LangatSelangor | 200 | — | CFO 26 Jan 2011 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-6 | Kuala LangatSelangor | 220 | — | CFO 12 Jan 2011 | — |
| BANDAR SAUJANA PUTRAKPKT 8944-4 | Kuala LangatSelangor | 168 | — | CFO 19 Oct 2010 | — |
| BANDAR SAUJANA PUTRA (FASA 1)KPKT 8695-1 | Kuala LangatSelangor | 240 | — | CFO 30 Aug 2010 | — |
| BANDAR SAUJANA PUTRA (FASA 2)KPKT 8695-3 | Kuala LangatSelangor | 240 | — | CFO 30 Aug 2010 | — |
| BANDAR SAUJANA PUTRAKPKT 8695-5 | Kuala LangatSelangor | 320 | — | CFO 30 Aug 2010 | — |
| BANDAR SAUJANA PUTRAKPKT 8945-2 | Kuala LangatSelangor | 436 | — | CFO 1 Mar 2010 | — |
| TAMAN TASIK PUCHONGKPKT 9337-1 | SepangSelangor | 245 | — | CFO 18 Feb 2010 | — |
| BANDAR SAUJANA PUTRAKPKT 8695-7 | Kuala LangatSelangor | 372 | — | CFO 9 Dec 2009 | — |
| BANDAR SAUJANA PUTRAKPKT 8695-8 | Kuala LangatSelangor | 408 | — | CFO 15 Oct 2009 | — |
| AZAM PERSPEKTIF SDN BHDKPKT 9337-3 | SepangSelangor | 330 | — | CCC 5 May 2009 | — |
| PUNCAK JELAPANG MAJUKPKT 7400-8 | KintaPerak | 37 | — | CFO 19 Feb 2009 | — |
| TAMAN BERCHAM TROPICANAKPKT 7400-15 | KintaPerak | 48 | — | CFO 22 Jan 2009 | — |
| TAMAN PINGGIRAN USJKPKT 6514-15 | PetalingSelangor | 312 | — | CFO 15 Dec 2008 | — |
| BANDAR SAUJANA PUTRA (FASA 3)KPKT 8695-6 | Kuala LangatSelangor | 480 | — | CFO 12 Nov 2008 | — |
| BANDAR SAUJANA PUTRA (FASA 2)KPKT 8695-4 | Kuala LangatSelangor | 480 | — | CFO 27 May 2008 | — |
| TAMAN BERCHAM TROPICANAKPKT 7400-14 | KintaPerak | 28 | — | CFO 31 Dec 2007 | — |
| PUNCAK JELAPANG MAJUKPKT 7400-13 | KintaPerak | 44 | — | CFO 31 Dec 2006 | — |
| TAMAN BUKIT SERDANGKPKT 8938-2 | PetalingSelangor | 840 | — | CFO 21 Nov 2006 | — |
| TAMAN BUKIT SERDANGKPKT 8938-1 | PetalingSelangor | 183 | — | CFO 11 Aug 2006 | — |
| TAMAN ROYAL LILYKPKT 8719-3 | Cameron HighlandsPahang | 56 | — | CFO 7 Apr 2006 | — |
| TAMAN ROYAL LILYKPKT 8719-4 | Cameron HighlandsPahang | 80 | — | CFO 7 Apr 2006 | — |
| TAMAN ROYAL LILYKPKT 8719-5 | Cameron HighlandsPahang | 240 | — | CFO 7 Apr 2006 | — |
| TAMAN ROYAL LILYKPKT 8719-2 | Cameron HighlandsPahang | 120 | — | CFO 29 Dec 2005 | — |
| PANGSAPURI SERI SETIAKPKT 7906-1 | PetalingSelangor | 164 | — | CFO 1 Dec 2005 | — |
| TAMAN BALAKONG JAYAKPKT 6514-6 | PetalingSelangor | 660 | — | CFO 30 Mar 2005 | — |
| TAMAN BALAKONG JAYAKPKT 6514-7 | Hulu LangatSelangor | 120 | — | CFO 29 Oct 2004 | — |
| TAMAN PINGGIRAN PUTRA, SEKSYEN 2KPKT 7702-6 | PetalingSelangor | 998 | — | CFO 31 Mar 2004 | — |
| DESIRAN BAYUKPKT 7702-21 | SepangSelangor | 14 | 10 Jul 20191st sale agreement 10 Jul 2017 | — | — |
Under construction (11) and not yet started (3) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| PANGSAPURI SAUJANA INDAHKPKT 19398-5 | Johor BahruJohor | 595 | DelayLate | 21 Mar 2027Extended 12 months from 21 Mar 20261st sale agreement 21 Mar 2023 | 90% |
| KITA BESTARIKPKT 19533-5 | SepangSelangor | 817 | SmoothOn schedule | 21 Mar 2027Extended 12 months from 21 Mar 20261st sale agreement 21 Mar 2023 | 97% |
| PANGSAPURI SKYRIAKPKT 11482-12 | SepangSelangor | 608 | SmoothOn schedule | 10 May 2028Extended 12 months from 10 May 20271st sale agreement 10 May 2024 | 64% |
| PANGSAPURI SAUJANA INDAHKPKT 19398-6 | Johor BahruJohor | 393 | SmoothOn schedule | 29 May 2028Extended 12 months from 29 May 20271st sale agreement 29 May 2024 | 86% |
| BANDAR PUTERA INDAH (SAPPHIRE GARDEN)KPKT 11018-4 | Batu PahatJohor | 33 | SmoothOn schedule | 19 Jun 20281st sale agreement 19 Jun 2026 | 98% |
| PANGSAPURI IDAMAN PERDANAKPKT 19183-13 | Kuala SelangorSelangor | 1,048 | SmoothOn schedule | 5 Aug 2028Extended 12 months from 5 Aug 20271st sale agreement 5 Aug 2024 | 97% |
| CENTRUM IRISKPKT 30401-1 | Cameron HighlandsPahang | 705 | SmoothOn schedule | 20 Jan 2029Extended 12 months from 20 Jan 20281st sale agreement 20 Jan 2025 | 31% |
| RESIDENSI STARLIGHTKPKT 31059-1 | Pahang | 270 | SmoothOn schedule | 29 Jul 20291st sale agreement 29 Jul 2026 | 5% |
| IDAMAN CAHAYA 3KPKT 30322-3 | PetalingSelangor | 413 | SmoothOn schedule | 22 Jun 2030Extended 12 months from 22 Jun 20291st sale agreement 22 Jun 2026 | 20% |
| AULICAKPKT 11482-11 | SepangSelangor | 79 | SmoothOn schedule | —Extended 12 months (date not registered) | 66–96% |
| BANDAR SAUJANA PUTRAKPKT 8944-5 | Kuala LangatSelangor | 220 | SmoothOn schedule | — | 0–98% |
| PANGSAPURI KITA SERIKPKT 19924-3 | Selangor | 1,171 | SmoothNot started | —Extended 12 months (date not registered) | 0% |
Show all 14 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| PANGSAPURI SAUJANA INDAHKPKT 19398-5 | Johor BahruJohor | 595 | DelayLate | 21 Mar 2027Extended 12 months from 21 Mar 20261st sale agreement 21 Mar 2023 | 90% |
| KITA BESTARIKPKT 19533-5 | SepangSelangor | 817 | SmoothOn schedule | 21 Mar 2027Extended 12 months from 21 Mar 20261st sale agreement 21 Mar 2023 | 97% |
| PANGSAPURI SKYRIAKPKT 11482-12 | SepangSelangor | 608 | SmoothOn schedule | 10 May 2028Extended 12 months from 10 May 20271st sale agreement 10 May 2024 | 64% |
| PANGSAPURI SAUJANA INDAHKPKT 19398-6 | Johor BahruJohor | 393 | SmoothOn schedule | 29 May 2028Extended 12 months from 29 May 20271st sale agreement 29 May 2024 | 86% |
| BANDAR PUTERA INDAH (SAPPHIRE GARDEN)KPKT 11018-4 | Batu PahatJohor | 33 | SmoothOn schedule | 19 Jun 20281st sale agreement 19 Jun 2026 | 98% |
| PANGSAPURI IDAMAN PERDANAKPKT 19183-13 | Kuala SelangorSelangor | 1,048 | SmoothOn schedule | 5 Aug 2028Extended 12 months from 5 Aug 20271st sale agreement 5 Aug 2024 | 97% |
| CENTRUM IRISKPKT 30401-1 | Cameron HighlandsPahang | 705 | SmoothOn schedule | 20 Jan 2029Extended 12 months from 20 Jan 20281st sale agreement 20 Jan 2025 | 31% |
| RESIDENSI STARLIGHTKPKT 31059-1 | Pahang | 270 | SmoothOn schedule | 29 Jul 20291st sale agreement 29 Jul 2026 | 5% |
| IDAMAN CAHAYA 3KPKT 30322-3 | PetalingSelangor | 413 | SmoothOn schedule | 22 Jun 2030Extended 12 months from 22 Jun 20291st sale agreement 22 Jun 2026 | 20% |
| AULICAKPKT 11482-11 | SepangSelangor | 79 | SmoothOn schedule | —Extended 12 months (date not registered) | 66–96% |
| BANDAR SAUJANA PUTRAKPKT 8944-5 | Kuala LangatSelangor | 220 | SmoothOn schedule | — | 0–98% |
| PANGSAPURI KITA SERIKPKT 19924-3 | Selangor | 1,171 | SmoothNot started | —Extended 12 months (date not registered) | 0% |
| BANDAR PUTERA INDAHKPKT 7702-42 | Batu PahatJohor | 27 | SmoothNot started | — | 0% |
| PANGSAPURI IDAMAN KITAKPKT 19533-6 | Selangor | 1,242 | SmoothNot started | —Extended 12 months (date not registered) | 0% |
Permit cancelled or other KPKT status (7)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| D' ISLAND RESIDENCEKPKT 11482-4 | SepangSelangor | 82 | Permit cancelledPermit cancelled | — | 0% |
| CAMERON HOLDEN HILLSKPKT 8752-10 | Cameron HighlandsPahang | 30 | Permit cancelledPermit cancelled | — | 2% |
| BAYU HILLSKPKT 30092-1 | BentongPahang | 642 | Permit cancelledPermit cancelled | —Extended 12 months (date not registered) | 21% |
| BANDAR PUTERA INDAHKPKT 6514-14 | Batu PahatJohor | 242 | Permit cancelledPermit cancelled | — | 88% |
| BANDAR PUTERA INDAHKPKT 7702-13 | Batu PahatJohor | 483 | Permit cancelledPermit cancelled | — | 0% |
| BSP 6KPKT 8695-11 | Kuala LangatSelangor | 684 | Permit cancelledPermit cancelled | — | 0% |
| BSP BAYUAN MASKPKT 8695-12 | Kuala LangatSelangor | 304 | Permit cancelledPermit cancelled | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
LBS Bina Group at a glance
| Listed | Bursa Malaysia Main Market · LBS (5789) · listed January 2002[1] |
|---|---|
| Started | Early 1960s in Petaling Jaya, by the late Dato' Seri Lim Bock Seng; incorporated as LBS Bina Holdings Sdn Bhd in 1982[1] |
| Head office | Sungai Way, Petaling Jaya, Selangor[1] |
| Leadership | Tan Sri Dato' Sri Ir. (Dr.) Lim Hock San — Group Executive Chairman (since 1 March 2021; managing director from 6 December 2001)[1] Datuk Wira Lim Hock Guan — Group Managing Director and Chief Executive Officer (since 14 January 2022)[1] |
| Companies in the KPKT register | ASTANA MODAL (M) SDN. BHD. KPKT 11482[1] AZAM PERSPEKTIF SDN. BHD. KPKT 9337[1] CASA INSPIRASI SDN. BHD. (69%) KPKT 30401[1] CERGAS ASAL (M) SDN. BHD. KPKT 8752[1] DELTA GALLERY SDN. BHD. (57.88%) KPKT 19145[1] EQUAL SIGN SDN. BHD. KPKT 8938[1] GENERASI SIMBOLIK SDN. BHD. KPKT 19632[1] IDAMAN AKTIF SDN. BHD. (57.88%) KPKT 30373[1] IDAMAN KUKUH SDN. BHD. (57.88%) KPKT 30322[1] IDAMAN LIVING SDN. BHD. (57.88%) KPKT 30136[1] JATIDIRI GIGIH SDN. BHD. KPKT 8944[1] JAUHARI UNGGUL SDN. BHD. KPKT 11893[1] JOHAN ANGGUN SDN. BHD. (85%) KPKT 30092[1] KEMUDI EHSAN SDN. BHD. KPKT 19183[1] KILATLIMA SDN. BHD. KPKT 7906[1] KITA SEJATI SDN. BHD. KPKT 30027[1] KOLEKSI SIGMA SDN. BHD. (85%) KPKT 19924[1] LBS BINA HOLDINGS SDN. BHD. KPKT 6514[1] MAYANG JELATEK SDN. BHD. (51%) KPKT 8719[1] MITC SDN. BHD. KPKT 11018[1] MULTI COURT DEVELOPERS SDN. BHD. (57.88%) KPKT 19398[1] PELANGI HOMES SDN. BHD. KPKT 7702[1] PUNCAK GAMA SDN. BHD. KPKT 19162[1] SELOKA SINARAN SDN. BHD. KPKT 19533[1] SERIBU BAIDURI SDN. BHD. KPKT 8695[1] SINARAN KENCANA SDN. BHD. (57.88%) KPKT 31059[1] SINARAN RESTU SDN. BHD. KPKT 7400[1] UTUH ASPIRASI SDN. BHD. KPKT 20162[1] UTUH SEJAGAT SDN. BHD. KPKT 8945[1] |
| Website | lbs.com.my |
| Homes delivered (company figure) | More than 57,000 homes, as of 31 January 2026[1] |
| Land bank | 3,918 acres, as at 15 April 2026[1] |
| Ongoing development value (company figure) | RM4.2 billion at the end of 2025[1] |
| Townships | KITA @ Cybersouth, LBS Alam Perdana, Bandar Saujana Putra, Rimbawan[1] |
| Listed subsidiary | MGB Berhad, majority-owned (57.88% effective interest at 31 December 2025)[1] |
LBS Bina Group projects on sale on PropertySifu
D' Island Residences
- D' ISLAND RESIDENCE — 0.6 km, 2018
- D' ISLAND RESIDENCES — 0.8 km, 2018
- DESIRAN BAYU — 1.3 km, —
Prestige Residence
- DELTA GALLERY SDN. BHD. — 0.2 km, 2020
- RESIDENSI BINTANG BUKIT JALIL — 4.2 km, 2023
- PPA1M MERCU JALIL — 4.3 km, 2023
Who is LBS Bina Group? The company behind the projects
LBS was founded in Petaling Jaya in the early 1960s by the late Dato' Seri Lim Bock Seng, who started a sand and stone business with two lorries; the business was incorporated as LBS Bina Holdings Sdn Bhd in 1982 [1]. LBS Bina Group Berhad was listed on the Main Market of Bursa Malaysia in January 2002 and trades under stock code 5789 [1]. Its headquarters is in Sungai Way, Petaling Jaya [1].
The company says it had delivered more than 57,000 homes as of 31 January 2026, and that its land bank stood at 3,918 acres as at 15 April 2026 [1]. Its townships include KITA @ Cybersouth, LBS Alam Perdana, Bandar Saujana Putra and Rimbawan [1]. These are group-wide figures; the KPKT register counts only projects licensed as housing, and many older records carry no handover dates, so the 161 completed projects above add up to 45,267 units, fewer than the company's total.
Six of the 29 companies belong to MGB Berhad, LBS's majority-owned listed subsidiary, in which the group had a 57.88% effective interest at 31 December 2025 [1]. Of the other 23, 19 are wholly owned; LBS holds 85% of Johan Anggun Sdn Bhd and Koleksi Sigma Sdn Bhd, 69% of Casa Inspirasi Sdn Bhd and 51% of Mayang Jelatek Sdn Bhd [1].
Both LBS projects on PropertySifu are by wholly owned subsidiaries [1]. KPKT registers the phases of D' Island Residence in Puchong (Sepang district, Selangor), a 175-acre lakeside development [1], under Astana Modal (M) Sdn Bhd (licence 11482), and Prestige Residence in Seri Kembangan, two 29-storey towers [1], under Utuh Aspirasi Sdn Bhd (licence 20162). Tan Sri Dato' Sri Ir. (Dr.) Lim Hock San, managing director from 6 December 2001, has been Group Executive Chairman since 1 March 2021; Datuk Wira Lim Hock Guan has been Group Managing Director and Chief Executive Officer since 14 January 2022 [1].
Frequently asked questions
Is LBS a listed company?
Yes. LBS Bina Group Berhad has been listed on the Main Market of Bursa Malaysia since January 2002; its stock code is 5789 [1].
How many homes has LBS completed?
LBS says it had delivered more than 57,000 homes as of 31 January 2026 [1]. In the KPKT register, 161 of the 182 housing projects under the 29 LBS companies are completed, with 45,267 units; the register counts only housing-licensed projects.
Does LBS have any Sick, Abandoned or Late projects?
As at 27 October 2026, KPKT classes none of the 182 projects as Sick (Sakit) or Abandoned (Terbengkalai). One is classed Late (Lewat): 19398-5, 595 serviced apartments in Johor Bahru under Multi Court Developers Sdn Bhd, an MGB Berhad company; its first sale agreement was signed on 21 March 2023, the deadline of 21 March 2026 was extended with approval by 12 months to 21 March 2027, and reported progress is 90%. Seven projects are recorded with their permits cancelled.
Was D' Island Residences handed over on time?
The PropertySifu listing's permit is for KPKT project 11482-10 (registered as Astella Phase 1, 76 terrace houses, Astana Modal (M) Sdn Bhd). Its first sale agreement was signed on 5 September 2023, giving a handover deadline of 5 September 2025, with no approved extension. The CCC is dated 2 April 2025 and vacant possession is recorded on 1 October 2025, 26 days after the deadline.
Was Prestige Residence handed over on time?
KPKT registers Prestige Residence as two projects under Utuh Aspirasi Sdn Bhd, 725 units each. 20162-1: first sale agreement 10 October 2021, deadline 10 October 2024, extended with approval by 12 months to 10 October 2025; the CCC is dated 22 October 2025, 12 days after the extended deadline, and the handover date is not recorded. 20162-2 (Block B): first sale agreement 20 March 2023, deadline 20 March 2026, extended by 12 months to 20 March 2027; the CCC is dated 22 October 2025 and vacant possession is recorded on 28 November 2025, before the original deadline.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.