Gadang (Gadang Holdings Berhad)
Gadang Holdings Berhad is a Kuala Lumpur-based construction and property group listed on Bursa Malaysia's Main Market, with 31 housing projects in the KPKT register under 13 Gadang companies: 27 completed, 3 under construction (one of them, Residensi Hana, classed Late, or Lewat) and 1 not yet started; none is Sick or Abandoned. Its property arm is Gadang Land.
- 31 projects in the KPKT register
- 27 completed
- 3 under construction (of which 1 Late)
- 1 not yet started
- None Sick or Abandoned
Has Gadang handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 31 housing projects under 13 Gadang companies in 4 states: 27 completed, 3 under construction (of which 1 Late), 1 not yet started. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 27 completed projects, 17 have both a handover deadline and a completion date in the register: 4 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 6 handed over or certified complete after that deadline; 7 received the completion certificate before the deadline (handover date not recorded).
4 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 27
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| LAMAN CITRAKPKT 10372-5 | PontianJohor | 332 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 2 Jul 2026 Handover 6 Jul 2026 | 25 days before |
| LAMAN CITRAKPKT 10372-4 | PontianJohor | 262 | 27 Jun 20251st sale agreement 27 Jun 2023 | CCC 6 Jun 2025 Handover 11 Jun 2025 | 16 days before |
| TAMAN AKASIAKPKT 19959-2 | Hulu LangatSelangor | 162 | 25 Apr 20261st sale agreement 25 Apr 2023 | CCC 14 Apr 2025 Handover 28 Apr 2025 | 362 days before |
| CASSIA RESIDENCEKPKT 14016-6 | SepangSelangor | 300 | 23 Nov 20241st sale agreement 23 Nov 2021 | CCC 28 Jan 2025 Handover 28 Feb 2025 | 97 days after |
| TAMAN AKASIAKPKT 19959-1 | Hulu LangatSelangor | 152 | 21 Mar 2024Extended 5 months from 21 Oct 20231st sale agreement 21 Oct 2020 | CCC 11 Jun 2024 Handover 14 Jun 2024 | 85 days after |
| LAMAN CITRAKPKT 10372-3 | PontianJohor | 206 | 13 Dec 20231st sale agreement 13 Dec 2021 | CCC 25 Feb 2024 Handover 29 Feb 2024 | 78 days after |
| ELEGAN RESIDENSIKPKT 19544-2 | SepangSelangor | 134 | 2 Feb 20241st sale agreement 2 Feb 2021 | CCC 12 Oct 2023 Handover 15 Nov 2023 | 79 days before |
| MAPLE RESIDENCEKPKT 14016-5 | SepangSelangor | 146 | 30 Sep 20231st sale agreement 30 Sep 2020 | CCC 7 Nov 2022 | CCC before deadline; handover not recorded |
| RESIDENSI VYNE SUNGAI BESIKPKT 13074-3 | Kuala LumpurWP Kuala Lumpur | 152 | 14 Apr 2023Extended 11 months from 14 May 20221st sale agreement 14 May 2019 | CCC 5 Sep 2022 | CCC before deadline; handover not recorded |
| ELEGAN RESIDENSIKPKT 19544-1 | SepangSelangor | 270 | 22 Jul 2022Extended 6 months from 22 Jan 20221st sale agreement 22 Jan 2019 | CCC 16 Nov 2021 | CCC before deadline; handover not recorded |
| MAPLE RESIDENCEKPKT 14016-3 | SepangSelangor | 194 | 18 Jul 20201st sale agreement 18 Jul 2017 | CCC 9 Jan 2020 | CCC before deadline; handover not recorded |
| PR1MA TWO, LAMAN VIEW CYBERJAYAKPKT 14016-4 | SepangSelangor | 469 | 15 Jan 20211st sale agreement 15 Jan 2018 | CCC 17 Dec 2019 | CCC before deadline; handover not recorded |
Handed over or certified complete after the deadline (6)
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| CASSIA RESIDENCEKPKT 14016-6 | SepangSelangor | 300 | 23 Nov 20241st sale agreement 23 Nov 2021 | CCC 28 Jan 2025 Handover 28 Feb 2025 | 97 days after |
| TAMAN AKASIAKPKT 19959-1 | Hulu LangatSelangor | 152 | 21 Mar 2024Extended 5 months from 21 Oct 20231st sale agreement 21 Oct 2020 | CCC 11 Jun 2024 Handover 14 Jun 2024 | 85 days after |
| LAMAN CITRAKPKT 10372-3 | PontianJohor | 206 | 13 Dec 20231st sale agreement 13 Dec 2021 | CCC 25 Feb 2024 Handover 29 Feb 2024 | 78 days after |
| BANDAR PUNCAK SENAKPKT 9063-1 | Pokok Sena (daerah Kecil)Kedah | 218 | 12 Mar 20171st sale agreement 12 Mar 2015 | CCC 30 Aug 2018 | 536 days after |
| RESIDENSI VYNEKPKT 13074-2 | Kuala LumpurWP Kuala Lumpur | 304 | 23 Aug 20171st sale agreement 23 Aug 2014 | CCC 11 Dec 2017 | 110 days after |
| RESIDENSI VINEKPKT 13074-1 | Kuala LumpurWP Kuala Lumpur | 344 | 18 Dec 20161st sale agreement 18 Dec 2013 | CCC 19 Jul 2017 | 213 days after |
Show all 27 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| LAMAN CITRAKPKT 10372-5 | PontianJohor | 332 | 31 Jul 20261st sale agreement 31 Jul 2024 | CCC 2 Jul 2026 Handover 6 Jul 2026 | 25 days before |
| LAMAN CITRAKPKT 10372-4 | PontianJohor | 262 | 27 Jun 20251st sale agreement 27 Jun 2023 | CCC 6 Jun 2025 Handover 11 Jun 2025 | 16 days before |
| TAMAN AKASIAKPKT 19959-2 | Hulu LangatSelangor | 162 | 25 Apr 20261st sale agreement 25 Apr 2023 | CCC 14 Apr 2025 Handover 28 Apr 2025 | 362 days before |
| CASSIA RESIDENCEKPKT 14016-6 | SepangSelangor | 300 | 23 Nov 20241st sale agreement 23 Nov 2021 | CCC 28 Jan 2025 Handover 28 Feb 2025 | 97 days after |
| TAMAN AKASIAKPKT 19959-1 | Hulu LangatSelangor | 152 | 21 Mar 2024Extended 5 months from 21 Oct 20231st sale agreement 21 Oct 2020 | CCC 11 Jun 2024 Handover 14 Jun 2024 | 85 days after |
| LAMAN CITRAKPKT 10372-3 | PontianJohor | 206 | 13 Dec 20231st sale agreement 13 Dec 2021 | CCC 25 Feb 2024 Handover 29 Feb 2024 | 78 days after |
| ELEGAN RESIDENSIKPKT 19544-2 | SepangSelangor | 134 | 2 Feb 20241st sale agreement 2 Feb 2021 | CCC 12 Oct 2023 Handover 15 Nov 2023 | 79 days before |
| MAPLE RESIDENCEKPKT 14016-5 | SepangSelangor | 146 | 30 Sep 20231st sale agreement 30 Sep 2020 | CCC 7 Nov 2022 | CCC before deadline; handover not recorded |
| RESIDENSI VYNE SUNGAI BESIKPKT 13074-3 | Kuala LumpurWP Kuala Lumpur | 152 | 14 Apr 2023Extended 11 months from 14 May 20221st sale agreement 14 May 2019 | CCC 5 Sep 2022 | CCC before deadline; handover not recorded |
| ELEGAN RESIDENSIKPKT 19544-1 | SepangSelangor | 270 | 22 Jul 2022Extended 6 months from 22 Jan 20221st sale agreement 22 Jan 2019 | CCC 16 Nov 2021 | CCC before deadline; handover not recorded |
| MAPLE RESIDENCEKPKT 14016-3 | SepangSelangor | 194 | 18 Jul 20201st sale agreement 18 Jul 2017 | CCC 9 Jan 2020 | CCC before deadline; handover not recorded |
| PR1MA TWO, LAMAN VIEW CYBERJAYAKPKT 14016-4 | SepangSelangor | 469 | 15 Jan 20211st sale agreement 15 Jan 2018 | CCC 17 Dec 2019 | CCC before deadline; handover not recorded |
| BANDAR PUNCAK SENAKPKT 9063-1 | Pokok Sena (daerah Kecil)Kedah | 218 | 12 Mar 20171st sale agreement 12 Mar 2015 | CCC 30 Aug 2018 | 536 days after |
| PR1MA ONE @ LAMAN VIEWKPKT 14016-2 | SepangSelangor | 325 | 22 Dec 20181st sale agreement 22 Dec 2015 | CCC 2 Mar 2018 | CCC before deadline; handover not recorded |
| RESIDENSI VYNEKPKT 13074-2 | Kuala LumpurWP Kuala Lumpur | 304 | 23 Aug 20171st sale agreement 23 Aug 2014 | CCC 11 Dec 2017 | 110 days after |
| RESIDENSI VINEKPKT 13074-1 | Kuala LumpurWP Kuala Lumpur | 344 | 18 Dec 20161st sale agreement 18 Dec 2013 | CCC 19 Jul 2017 | 213 days after |
| LAMAN VIEWKPKT 14016-1 | SepangSelangor | 142 | 21 Oct 20171st sale agreement 21 Oct 2015 | CCC 25 May 2017 | CCC before deadline; handover not recorded |
| JENTAYU RESIDENSIKPKT 11357-1 | Johor BahruJohor | 512 | — | CCC 24 Jul 2014 | — |
| TAMAN PINGGIRAN PELANGI FASA 2KPKT 10423-2 | GombakSelangor | 257 | — | CFO 1 Nov 2011 | — |
| TAMAN PINGGIRAN PELANGI FASA 1KPKT 10423-1 | GombakSelangor | 166 | — | CFO 25 Jan 2010 | — |
| TAMAN SERI BUKIT SEGAMBUTKPKT 10372-1 | Kuala LumpurWP Kuala Lumpur | 31 | — | CFO 30 Dec 2009 | — |
| AMAN COURTKPKT 9326-3 | GombakSelangor | 48 | — | CFO 9 Jul 2009 | — |
| PANGSAPURI SRI IXORAKPKT 9313-1 | PetalingSelangor | 600 | — | CFO 12 Jun 2008 | — |
| MANDY COURTKPKT 8688-2 | Kuala LumpurWP Kuala Lumpur | 88 | — | CFO 13 May 2008 | — |
| SERI AMAN HEIGHTSKPKT 9326-1 | GombakSelangor | 78 | — | CFO 21 Mar 2007 | — |
| PRIMA IMPIANKPKT 3574-2 | Kuala LumpurWP Kuala Lumpur | 160 | — | CFO 29 Jun 2006 | — |
| MANDY VILLAKPKT 8688-1 | Kuala LumpurWP Kuala Lumpur | 288 | — | CFO 16 Jan 2006 | — |
Under construction (3) and not yet started (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN AKASIAKPKT 19959-3Zinnia Residence · on PropertySifu | Hulu LangatSelangor | 149 | SmoothOn schedule | 28 Mar 20271st sale agreement 28 Mar 2025 | 75–80% |
| RESIDENSI HANAKPKT 13074-4Residensi Hana · on PropertySifu | Kuala LumpurWP Kuala Lumpur | 299 | DelayLate | 9 Apr 20271st sale agreement 9 Apr 2024 | 88% |
| LAMAN CITRAKPKT 10372-6 | PontianJohor | 136 | SmoothOn schedule | 17 Apr 20281st sale agreement 17 Apr 2026 | 47–50% |
| LAMAN WARINGINKPKT 31038-1 | Selangor | 398 | Not startedNot started | —Extended 6 months (date not registered) | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Gadang at a glance
| Listed | Bursa Malaysia Main Market · GADANG (9261) · listed on the Second Board 2 September 1994, Main Board from 24 December 2007[1] |
|---|---|
| Started | Incorporated in Malaysia on 6 October 1993 as Lai Sing Holdings Berhad; renamed Gadang after a 1997 change of control[1] |
| Head office | Sri Damansara, Kuala Lumpur[1] |
| Leadership | Dato' Dr Tan Yew Chong — Independent Non-Executive Chairman (since 1 December 2025)[1] Tan Sri Dato' Kok Onn — Group Managing Director[1] |
| Companies in the KPKT register | HILLSTRAND DEVELOPMENT SDN. BHD. KPKT 14016[1] SPLENDID PAVILION SDN. BHD. KPKT 10372[1] NATURAL DOMAIN SDN. BHD. KPKT 13074[1] CRIMSON VILLA SDN. BHD. KPKT 19959[1] DAMAI KLASIK SDN BHD. KPKT 9326[1] MANDY CORPORATION SDN. BHD. KPKT 8688[1] NOBLE PARADISE SDN. BHD. KPKT 10423[1] TEMA WARISAN SDN. BHD. KPKT 19544[1] ACHWELL PROPERTY SDN. BHD. KPKT 11357[1] ELEGANCE SONATA SDN. BHD. KPKT 31038[1] SAMA PESONA SDN. BHD. KPKT 9313[1] CAMAR AJAIB SDN. BHD. KPKT 9063[1] HARTA SEGAMBUT SDN. BHD. KPKT 3574[2] |
| Website | gadang.com.my |
| Land bank (company figure) | 100 acres with an estimated gross development value of RM1.1 billion, as at 31 May 2026[1] |
| Property arm | Gadang Land Sdn Bhd, set up on 25 July 1996; its first project was 30 semi-detached factories in Shah Alam[2] |
| Other businesses | Earthworks and civil engineering construction, water concessions in Indonesia, a solar plant in Tawau, Sabah, and mechanical and electrical services[1] |
| Green rating | Residensi Hana: GBI Certified, certificate GBI-RNC-0240(P), valid 13 September 2024 to 12 September 2027[3] |
Gadang projects on sale on PropertySifu
Zinnia Residence
- TAMAN AKASIA — 0.3 km, 2025
- TAMAN AKASIA — 0.3 km, 2024
Who is Gadang? The company behind the projects
Gadang Holdings Berhad was incorporated on 6 October 1993 as Lai Sing Holdings Berhad and listed on the Second Board of what is now Bursa Malaysia on 2 September 1994, in the construction sector [1]. In 1997 Tan Sri Dato' Kok Onn, now the group managing director, became its major shareholder, took over its operations and renamed it Gadang; the company moved to the Main Board, now the Main Market, on 24 December 2007 [1]. Besides construction and property, the group runs water concessions in Indonesia and a solar plant in Tawau, Sabah [1].
Its property arm, Gadang Land Sdn Bhd, was set up on 25 July 1996; its first project was 30 semi-detached factories in Shah Alam [2]. The company says the property division had a land bank of 100 acres, with an estimated gross development value of RM1.1 billion, at 31 May 2026 [1]. Twelve of the 13 companies counted here are wholly owned subsidiaries listed in the 2026 annual report [1]; the thirteenth, Harta Segambut Sdn Bhd, registered Prima Impian in Segambut, which Gadang Land lists among its completed projects [2].
Residensi Hana in Sungai Besi, Kuala Lumpur, is developed by Natural Domain Sdn Bhd [1], which also registered the three completed projects next to it, Residensi Vine, Residensi Vyne and Residensi Vyne Sungai Besi; the building holds a GBI Certified rating [3]. Zinnia Residence in Semenyih is registered with KPKT as Taman Akasia (19959-3) under Crimson Villa Sdn Bhd [1]. Laman Waringin in Kwasa Damansara is registered but not yet started; the annual report records a development rights agreement with Kwasa Development (3) Sdn Bhd over 24.08 acres in Mukim Sungai Buloh [1].
The chairman is Dato' Dr Tan Yew Chong, who succeeded Tan Sri Dato' Seri Dr Mohamed Ismail Merican on 1 December 2025, and the group managing director is Tan Sri Dato' Kok Onn [1].
Frequently asked questions
Is Gadang a listed company?
Yes. Gadang Holdings Berhad trades on Bursa Malaysia's Main Market as GADANG, stock code 9261. It was listed on the Second Board on 2 September 1994 and moved to the Main Board on 24 December 2007 [1].
Does Gadang have any Sick or Abandoned projects?
No. As at 27 October 2026, none of the 31 projects under the 13 Gadang companies is classed Sick (Sakit) or Abandoned (Terbengkalai). One project under construction, Residensi Hana, is classed Late (Lewat).
Which company develops Residensi Hana, and is it on schedule?
Residensi Hana is registered with KPKT as 13074-4 under Natural Domain Sdn Bhd, a wholly owned Gadang subsidiary [1]: 299 serviced apartments in a 31-storey block. KPKT classes it Late (Lewat), with reported construction progress of 87.5%. Its handover deadline under the first sale agreement (9 April 2024) is 9 April 2027, with no approved extension recorded.
Which company develops Zinnia Residence in Semenyih?
Crimson Villa Sdn Bhd (KPKT developer code 19959), a wholly owned Gadang subsidiary [1]. KPKT registers Zinnia Residence as Taman Akasia, 19959-3: 149 terrace houses, on schedule (Lancar), with reported progress of 75–80% and a handover deadline of 28 March 2027 under the first sale agreement. The two earlier Taman Akasia phases are completed: 19959-1 was handed over on 14 June 2024, 85 days after its deadline as extended by 5 months, and 19959-2 on 28 April 2025, 362 days before its deadline.
How many homes has Gadang completed?
In the KPKT register, the 27 completed projects under the 13 Gadang companies have 6,340 approved units, out of 7,322 across all 31 projects. They are in Selangor, Kuala Lumpur, Johor and Kedah.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Gadang Holdings Berhad Annual Report 2026 (financial year ended 31 May 2026) · Gadang Holdings Berhad · 23 Sep 2026 · accessed 28 Oct 2026
https://www.gadang.com.my/wp-content/uploads/2026/09/GADANG-Annual-Report-2026.pdf - [2] Gadang Land — corporate profile and projects · Gadang Land Sdn Bhd · accessed 28 Oct 2026
https://www.gadangland.com.my/ - [3] GBI directory: Residensi Hana, Sungai Besi · Green Building Index · accessed 28 Oct 2026
https://gallery.greenbuildingindex.org/en/directory/residensi-hana-sungai-besi
Last updated 28 Oct 2026