Eupe (Eupe Corporation Berhad)
Eupe Corporation Berhad is a Bursa Malaysia Main Market-listed developer based in Sungai Petani, Kedah, with 63 housing projects in the KPKT register under seven Eupe companies: 59 completed, 2 under construction and 2 not started, none classed Sick or Abandoned. Most are landed homes in Kedah; since 2016 it has also built high-rise homes in the Klang Valley.
- 63 projects in the KPKT register
- 59 completed
- 2 under construction
- 2 not yet started
- None Sick or Abandoned
Has Eupe handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 63 housing projects under 7 Eupe companies in 3 states: 59 completed, 2 under construction, 2 not yet started. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 59 completed projects, 53 have both a handover deadline and a completion date in the register: 11 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 25 handed over or certified complete after that deadline (4 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 17 received the completion certificate before the deadline (handover date not recorded).
14 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 59
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| VILLA NATURAKPKT 3828-52 | Kuala MudaKedah | 102 | 30 Sep 20261st sale agreement 30 Sep 2024 | CCC 21 Apr 2026 Handover 22 Jun 2026 | 100 days before |
| VILLA NATURAKPKT 3828-51 | Kuala MudaKedah | 85 | 25 May 20261st sale agreement 25 May 2024 | CCC 21 Apr 2026 Handover 22 May 2026 | 3 days before |
| RESIDENSI ESTETIK 8 (EST8)KPKT 19122-2EST8 @ Seputeh · on PropertySifuEupe's 2026 annual report says EST8 @ Seputeh was completed in May 2026 and was being handed over to buyers. KPKT records the CCC for all three components on 19 May 2026 but no handover date.[1] | Kuala LumpurWP Kuala Lumpur | 821 | 18 Nov 2026Extended 24 months from 18 Nov 20241st sale agreement 18 Nov 2021 | CCC 19 May 2026 | CCC before deadline; handover not recorded |
| VILLA NATURAKPKT 3828-50 | Kuala MudaKedah | 59 | 30 Apr 20261st sale agreement 30 Apr 2024 | CCC 21 Apr 2026 Handover 27 Apr 2026 | 3 days before |
| CINTA SAYANG RESORT VILLAS 2KPKT 3828-53 | Kuala MudaKedah | 41 | 30 Nov 20261st sale agreement 30 Nov 2024 | CCC 2 Jan 2026 Handover 2 Feb 2026 | 301 days before |
| VILLA NATURAKPKT 3828-48 | Kuala MudaKedah | 66 | 31 Oct 20251st sale agreement 31 Oct 2023 | CCC 23 Oct 2025 Handover 23 Oct 2025 / 24 Oct 2025 | 7 days before |
| VILLA NATURAKPKT 3828-49 | Kuala MudaKedah | 65 | 23 Oct 20251st sale agreement 23 Oct 2023 | CCC 23 Oct 2025 Handover 23 Oct 2025 / 24 Oct 2025 | 1 day after |
| RESIDENSI HELIKSKPKT 30099-1 | PetalingSelangor | 500 | 18 Oct 20251st sale agreement 18 Oct 2022 | CCC 13 Oct 2025 Handover 16 Oct 2025 | 2 days before |
| VILLA NATURAKPKT 3828-47 | Kuala MudaKedah | 159 | 16 Jun 20251st sale agreement 16 Jun 2023 | CCC 18 Jun 2025 Handover 18 Jun 2025 | 2 days after |
| VILLA NATURAKPKT 3828-46 | Kuala MudaKedah | 171 | 8 Apr 20251st sale agreement 8 Apr 2023 | CCC 5 Jun 2025 Handover 5 Jun 2025 | 58 days after |
| BANDAR SERI ASTANA (ASTANA JAYA)KPKT 3828-45 | Kuala MudaKedah | 92 | 29 Nov 20241st sale agreement 29 Nov 2022 | CCC 9 Jan 2025 Handover 14 Jan 2025 | 46 days after |
| THE SOMERSET - COURTYARDKPKT 3828-43 | Kuala MudaKedah | 5 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 30 Oct 2024 Handover 5 Nov 2024 | 25 days before |
Handed over or certified complete after the deadline — 12 most recent of 25
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| VILLA NATURAKPKT 3828-49 | Kuala MudaKedah | 65 | 23 Oct 20251st sale agreement 23 Oct 2023 | CCC 23 Oct 2025 Handover 23 Oct 2025 / 24 Oct 2025 | 1 day after |
| VILLA NATURAKPKT 3828-47 | Kuala MudaKedah | 159 | 16 Jun 20251st sale agreement 16 Jun 2023 | CCC 18 Jun 2025 Handover 18 Jun 2025 | 2 days after |
| VILLA NATURAKPKT 3828-46 | Kuala MudaKedah | 171 | 8 Apr 20251st sale agreement 8 Apr 2023 | CCC 5 Jun 2025 Handover 5 Jun 2025 | 58 days after |
| BANDAR SERI ASTANA (ASTANA JAYA)KPKT 3828-45 | Kuala MudaKedah | 92 | 29 Nov 20241st sale agreement 29 Nov 2022 | CCC 9 Jan 2025 Handover 14 Jan 2025 | 46 days after |
| BANDAR SERI ASTANA FASA DKPKT 3828-19 | Kuala MudaKedah | 66 | 14 Jun 20191st sale agreement 14 Jun 2017 | CCC 23 May 2024 | 1,805 days after |
| BANDAR SERI ASTANAKPKT 3828-38 | Kuala MudaKedah | 7 | 11 Nov 20231st sale agreement 11 Nov 2021 | CCC 4 Feb 2024 Handover 7 Feb 2024 | 88 days after |
| BANDAR SERI ASTANAKPKT 3828-40 | Kuala MudaKedah | 6 | 10 Sep 20231st sale agreement 10 Sep 2021 | CCC 8 Nov 2023 Handover 14 Nov 2023 | 65 days after |
| TAMAN RIA VISTANAKPKT 11555-4 | KulimKedah | 72 | 7 Jun 2023Extended 5 months from 7 Jan 20231st sale agreement 7 Jan 2021 | CCC 30 Aug 2023 Handover 5 Sep 2023 | 90 days after |
| BANDAR SERI ASTANA D (PARK HOME)KPKT 3828-36 | Kuala MudaKedah | 52 | 3 Jul 2023Extended 5 months from 3 Feb 20231st sale agreement 3 Feb 2021 | CCC 9 Jul 2023 Handover 13 Jul 2023 | 10 days after |
| TAMAN RIA VISTANAKPKT 11555-2 | KulimKedah | 126 | 14 Dec 2022Extended 11 months from 14 Jan 20221st sale agreement 14 Jan 2020 | CCC 3 Jan 2023 | 20 days after † |
| TAMAN RIA VISTANAKPKT 11555-3 | KulimKedah | 56 | 29 Oct 2022Extended 5 months from 29 May 20221st sale agreement 29 May 2020 | CCC 7 Nov 2022 Handover 14 Nov 2022 | 16 days after † |
| PUNCAK SURYA - DARIAN (10 UNIT) & NERIS (32UNIT)KPKT 3828-23 | Kuala MudaKedah | 42 | 19 Apr 20201st sale agreement 19 Apr 2018 | CCC 5 Oct 2022 | 899 days after † |
Show all 25
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| VILLA NATURAKPKT 3828-49 | Kuala MudaKedah | 65 | 23 Oct 20251st sale agreement 23 Oct 2023 | CCC 23 Oct 2025 Handover 23 Oct 2025 / 24 Oct 2025 | 1 day after |
| VILLA NATURAKPKT 3828-47 | Kuala MudaKedah | 159 | 16 Jun 20251st sale agreement 16 Jun 2023 | CCC 18 Jun 2025 Handover 18 Jun 2025 | 2 days after |
| VILLA NATURAKPKT 3828-46 | Kuala MudaKedah | 171 | 8 Apr 20251st sale agreement 8 Apr 2023 | CCC 5 Jun 2025 Handover 5 Jun 2025 | 58 days after |
| BANDAR SERI ASTANA (ASTANA JAYA)KPKT 3828-45 | Kuala MudaKedah | 92 | 29 Nov 20241st sale agreement 29 Nov 2022 | CCC 9 Jan 2025 Handover 14 Jan 2025 | 46 days after |
| BANDAR SERI ASTANA FASA DKPKT 3828-19 | Kuala MudaKedah | 66 | 14 Jun 20191st sale agreement 14 Jun 2017 | CCC 23 May 2024 | 1,805 days after |
| BANDAR SERI ASTANAKPKT 3828-38 | Kuala MudaKedah | 7 | 11 Nov 20231st sale agreement 11 Nov 2021 | CCC 4 Feb 2024 Handover 7 Feb 2024 | 88 days after |
| BANDAR SERI ASTANAKPKT 3828-40 | Kuala MudaKedah | 6 | 10 Sep 20231st sale agreement 10 Sep 2021 | CCC 8 Nov 2023 Handover 14 Nov 2023 | 65 days after |
| TAMAN RIA VISTANAKPKT 11555-4 | KulimKedah | 72 | 7 Jun 2023Extended 5 months from 7 Jan 20231st sale agreement 7 Jan 2021 | CCC 30 Aug 2023 Handover 5 Sep 2023 | 90 days after |
| BANDAR SERI ASTANA D (PARK HOME)KPKT 3828-36 | Kuala MudaKedah | 52 | 3 Jul 2023Extended 5 months from 3 Feb 20231st sale agreement 3 Feb 2021 | CCC 9 Jul 2023 Handover 13 Jul 2023 | 10 days after |
| TAMAN RIA VISTANAKPKT 11555-2 | KulimKedah | 126 | 14 Dec 2022Extended 11 months from 14 Jan 20221st sale agreement 14 Jan 2020 | CCC 3 Jan 2023 | 20 days after † |
| TAMAN RIA VISTANAKPKT 11555-3 | KulimKedah | 56 | 29 Oct 2022Extended 5 months from 29 May 20221st sale agreement 29 May 2020 | CCC 7 Nov 2022 Handover 14 Nov 2022 | 16 days after † |
| PUNCAK SURYA - DARIAN (10 UNIT) & NERIS (32UNIT)KPKT 3828-23 | Kuala MudaKedah | 42 | 19 Apr 20201st sale agreement 19 Apr 2018 | CCC 5 Oct 2022 | 899 days after † |
| PUNCAK SURYA -NERIS (36 UNIT)KPKT 3828-22 | Kuala MudaKedah | 35 | 3 Jul 2021Extended 6 months from 3 Jan 20211st sale agreement 3 Jan 2019 | CCC 15 Nov 2021 | 135 days after † |
| BANDAR SERI ASTANA FASA D 88KPKT 3828-21 | Kuala MudaKedah | 46 | 7 Nov 20191st sale agreement 7 Nov 2017 | CCC 6 Jan 2021 | 426 days after |
| ASTANA PARKHOMESKPKT 3828-12 | Kuala MudaKedah | 448 | 7 Jun 20131st sale agreement 7 Jun 2011 | CCC 5 Jan 2021 | 2,769 days after |
| RESORT VILLASKPKT 3828-15 | Kuala MudaKedah | 134 | 1 Jul 20161st sale agreement 1 Jul 2014 | CCC 28 Dec 2020 | 1,641 days after |
| NOVUMKPKT 14163-1 | Kuala LumpurWP Kuala Lumpur | 654 | 18 Feb 2020Extended 12 months from 18 Feb 20191st sale agreement 18 Feb 2016 | CCC 26 Jun 2020 | 129 days after |
| TAMAN KELISAKPKT 3828-16 | Kuala MudaKedah | 21 | 22 Feb 20191st sale agreement 22 Feb 2017 | CCC 6 Mar 2019 | 12 days after |
| SRI IORA 2KPKT 3828-17 | Kuala MudaKedah | 48 | 2 Mar 20191st sale agreement 2 Mar 2017 | CCC 6 Mar 2019 | 4 days after |
| EUPE KEMAJUAN SDN BHDKPKT 3828-13 | Kuala MudaKedah | 29 | 13 Sep 20151st sale agreement 13 Sep 2013 | CCC 29 Oct 2018 | 1,142 days after |
| TAMAN KELISA RIA IIKPKT 3828-6 | Kuala MudaKedah | 1,088 | 6 Aug 20051st sale agreement 6 Aug 2003 | CCC 26 Sep 2017 | 4,434 days after |
| MERA-LAND(MALAYSIA) SDN BHDKPKT 7348-4 | Kuala MudaKedah | 64 | 5 Mar 20171st sale agreement 5 Mar 2015 | CCC 6 Jun 2017 | 93 days after |
| TAMAN KELISA RIAKPKT 3828-14 | Kuala MudaKedah | 46 | 17 Dec 20161st sale agreement 17 Dec 2014 | CCC 8 Feb 2017 | 53 days after |
| BANDAR SERI ASTAN PARCEL EKPKT 3828-11 | Kuala MudaKedah | 951 | 2 Jun 20111st sale agreement 2 Jun 2009 | CCC 11 Dec 2016 | 2,019 days after |
| CINTA SAYANG RESORT HOMESKPKT 10559-1 | Kuala MudaKedah | 332 | 6 Jun 20121st sale agreement 6 Jun 2010 | CCC 19 Oct 2016 | 1,596 days after |
Show all 59 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| VILLA NATURAKPKT 3828-52 | Kuala MudaKedah | 102 | 30 Sep 20261st sale agreement 30 Sep 2024 | CCC 21 Apr 2026 Handover 22 Jun 2026 | 100 days before |
| VILLA NATURAKPKT 3828-51 | Kuala MudaKedah | 85 | 25 May 20261st sale agreement 25 May 2024 | CCC 21 Apr 2026 Handover 22 May 2026 | 3 days before |
| RESIDENSI ESTETIK 8 (EST8)KPKT 19122-2EST8 @ Seputeh · on PropertySifuEupe's 2026 annual report says EST8 @ Seputeh was completed in May 2026 and was being handed over to buyers. KPKT records the CCC for all three components on 19 May 2026 but no handover date.[1] | Kuala LumpurWP Kuala Lumpur | 821 | 18 Nov 2026Extended 24 months from 18 Nov 20241st sale agreement 18 Nov 2021 | CCC 19 May 2026 | CCC before deadline; handover not recorded |
| VILLA NATURAKPKT 3828-50 | Kuala MudaKedah | 59 | 30 Apr 20261st sale agreement 30 Apr 2024 | CCC 21 Apr 2026 Handover 27 Apr 2026 | 3 days before |
| CINTA SAYANG RESORT VILLAS 2KPKT 3828-53 | Kuala MudaKedah | 41 | 30 Nov 20261st sale agreement 30 Nov 2024 | CCC 2 Jan 2026 Handover 2 Feb 2026 | 301 days before |
| VILLA NATURAKPKT 3828-48 | Kuala MudaKedah | 66 | 31 Oct 20251st sale agreement 31 Oct 2023 | CCC 23 Oct 2025 Handover 23 Oct 2025 / 24 Oct 2025 | 7 days before |
| VILLA NATURAKPKT 3828-49 | Kuala MudaKedah | 65 | 23 Oct 20251st sale agreement 23 Oct 2023 | CCC 23 Oct 2025 Handover 23 Oct 2025 / 24 Oct 2025 | 1 day after |
| RESIDENSI HELIKSKPKT 30099-1 | PetalingSelangor | 500 | 18 Oct 20251st sale agreement 18 Oct 2022 | CCC 13 Oct 2025 Handover 16 Oct 2025 | 2 days before |
| VILLA NATURAKPKT 3828-47 | Kuala MudaKedah | 159 | 16 Jun 20251st sale agreement 16 Jun 2023 | CCC 18 Jun 2025 Handover 18 Jun 2025 | 2 days after |
| VILLA NATURAKPKT 3828-46 | Kuala MudaKedah | 171 | 8 Apr 20251st sale agreement 8 Apr 2023 | CCC 5 Jun 2025 Handover 5 Jun 2025 | 58 days after |
| BANDAR SERI ASTANA (ASTANA JAYA)KPKT 3828-45 | Kuala MudaKedah | 92 | 29 Nov 20241st sale agreement 29 Nov 2022 | CCC 9 Jan 2025 Handover 14 Jan 2025 | 46 days after |
| THE SOMERSET - COURTYARDKPKT 3828-43 | Kuala MudaKedah | 5 | 30 Nov 20241st sale agreement 30 Nov 2022 | CCC 30 Oct 2024 Handover 5 Nov 2024 | 25 days before |
| BANDAR SERI ASTANA (ASTANA JAYA)KPKT 3828-44 | Kuala MudaKedah | 124 | 17 Sep 20241st sale agreement 17 Sep 2022 | CCC 15 Sep 2024 Handover 16 Sep 2024 | 1 day before |
| BANDAR SERI ASTANA FASA DKPKT 3828-19 | Kuala MudaKedah | 66 | 14 Jun 20191st sale agreement 14 Jun 2017 | CCC 23 May 2024 | 1,805 days after |
| BANDAR SERI ASTANAKPKT 3828-38 | Kuala MudaKedah | 7 | 11 Nov 20231st sale agreement 11 Nov 2021 | CCC 4 Feb 2024 Handover 7 Feb 2024 | 88 days after |
| CSRV LUXURY BUNGALOWKPKT 3828-41 | Kuala MudaKedah | 13 | — | CCC 22 Jan 2024 Handover 16 Feb 2024 | — |
| BANDAR SERI ASTANAKPKT 3828-40 | Kuala MudaKedah | 6 | 10 Sep 20231st sale agreement 10 Sep 2021 | CCC 8 Nov 2023 Handover 14 Nov 2023 | 65 days after |
| TIJANAKPKT 3828-42 | Kuala MudaKedah | 9 | — | CCC 6 Nov 2023 Handover 29 Nov 2023 | — |
| BANDAR SERI ASTANAKPKT 3828-39 | Kuala MudaKedah | 27 | 30 Sep 20231st sale agreement 30 Sep 2021 | CCC 16 Aug 2023 Handover 12 Sep 2023 | 18 days before |
| TAMAN RIA VISTANAKPKT 11555-4 | KulimKedah | 72 | 7 Jun 2023Extended 5 months from 7 Jan 20231st sale agreement 7 Jan 2021 | CCC 30 Aug 2023 Handover 5 Sep 2023 | 90 days after |
| BANDAR SERI ASTANA D (PARK HOME)KPKT 3828-36 | Kuala MudaKedah | 52 | 3 Jul 2023Extended 5 months from 3 Feb 20231st sale agreement 3 Feb 2021 | CCC 9 Jul 2023 Handover 13 Jul 2023 | 10 days after |
| CINTA SAYANG RESORT VILLASKPKT 3828-34 | Kuala MudaKedah | 16 | 22 Apr 20231st sale agreement 22 Apr 2021 | CCC 4 Apr 2023 Handover 12 Apr 2023 | 10 days before |
| TAMAN RIA VISTANAKPKT 11555-2 | KulimKedah | 126 | 14 Dec 2022Extended 11 months from 14 Jan 20221st sale agreement 14 Jan 2020 | CCC 3 Jan 2023 | 20 days after † |
| TAMAN RIA VISTANAKPKT 11555-3 | KulimKedah | 56 | 29 Oct 2022Extended 5 months from 29 May 20221st sale agreement 29 May 2020 | CCC 7 Nov 2022 Handover 14 Nov 2022 | 16 days after † |
| PUNCAK SURYA - DARIAN (10 UNIT) & NERIS (32UNIT)KPKT 3828-23 | Kuala MudaKedah | 42 | 19 Apr 20201st sale agreement 19 Apr 2018 | CCC 5 Oct 2022 | 899 days after † |
| BANDAR SERI ASTANAKPKT 3828-33 | Kuala MudaKedah | 60 | 18 Nov 2022Extended 5 months from 18 Jun 20221st sale agreement 18 Jun 2020 | CCC 12 Jun 2022 Handover 15 Jun 2022 | 156 days before |
| RESIDENSI PARC 3KPKT 19122-1 | Kuala LumpurWP Kuala Lumpur | 793 | 28 Nov 2022Extended 23 months from 28 Dec 20201st sale agreement 28 Dec 2017 | CCC 2 Dec 2021 | CCC before deadline; handover not recorded |
| BANDAR SERI ASTANA D (PARK HOMES)KPKT 3828-30 | Kuala MudaKedah | 6 | 24 Jan 2022Extended 6 months from 24 Jul 20211st sale agreement 24 Jul 2019 | CCC 1 Dec 2021 | CCC before deadline; handover not recorded |
| BANDAR SERI ASTANA FASA DKPKT 3828-31 | Kuala MudaKedah | 42 | 22 Jan 2022Extended 6 months from 22 Jul 20211st sale agreement 22 Jul 2019 | CCC 1 Dec 2021 | CCC before deadline; handover not recorded |
| BANDAR SERI ASTANA FASA DKPKT 3828-35 | Kuala MudaKedah | 7 | 9 Feb 20231st sale agreement 9 Feb 2021 | CCC 1 Dec 2021 | CCC before deadline; handover not recorded |
| BANDAR SERI ASTANAKPKT 3828-37 | Kuala MudaKedah | 8 | 26 Mar 20231st sale agreement 26 Mar 2021 | CCC 30 Nov 2021 | CCC before deadline; handover not recorded |
| PUNCAK SURYA -NERIS (36 UNIT)KPKT 3828-22 | Kuala MudaKedah | 35 | 3 Jul 2021Extended 6 months from 3 Jan 20211st sale agreement 3 Jan 2019 | CCC 15 Nov 2021 | 135 days after † |
| PUNCAK SURYA - NERISSA (22 UNIT)KPKT 3828-24 | Kuala MudaKedah | 22 | 18 Mar 2022Extended 6 months from 18 Sep 20211st sale agreement 18 Sep 2019 | CCC 15 Nov 2021 | CCC before deadline; handover not recorded |
| PUNCAK SURYA - NEYAZA (2 UNIT) & NERISSA (24 UNIT)KPKT 3828-25 | Kuala MudaKedah | 26 | 31 Dec 20221st sale agreement 31 Dec 2020 | CCC 15 Nov 2021 | CCC before deadline; handover not recorded |
| BANDAR SERI ASTANA FASA D 88KPKT 3828-21 | Kuala MudaKedah | 46 | 7 Nov 20191st sale agreement 7 Nov 2017 | CCC 6 Jan 2021 | 426 days after |
| ASTANA PARKHOMESKPKT 3828-12 | Kuala MudaKedah | 448 | 7 Jun 20131st sale agreement 7 Jun 2011 | CCC 5 Jan 2021 | 2,769 days after |
| BANDAR SERI ASTANA FASA DKPKT 3828-20 | Kuala MudaKedah | 7 | 17 Apr 2021Extended 6 months from 17 Oct 20201st sale agreement 17 Oct 2018 | CCC 5 Jan 2021 | CCC before deadline; handover not recorded |
| BANDAR SERI ASTANA FASA D,PARK HOMES A(P4-A)KPKT 3828-29 | Kuala MudaKedah | 9 | 5 Sep 20211st sale agreement 5 Sep 2019 | CCC 5 Jan 2021 | CCC before deadline; handover not recorded |
| RESORT VILLASKPKT 3828-15 | Kuala MudaKedah | 134 | 1 Jul 20161st sale agreement 1 Jul 2014 | CCC 28 Dec 2020 | 1,641 days after |
| CINTA SAYANG RESORT VILLAS - 1SZL(1)KPKT 3828-27 | Kuala MudaKedah | 19 | 19 Mar 2021Extended 6 months from 19 Sep 20201st sale agreement 19 Sep 2018 | CCC 28 Dec 2020 | CCC before deadline; handover not recorded |
| CINTA SAYANG RESORT VILLAS -1SZL(2)KPKT 3828-28 | Kuala MudaKedah | 10 | 13 Feb 20211st sale agreement 13 Feb 2019 | CCC 28 Dec 2020 | CCC before deadline; handover not recorded |
| CINTA SAYANG RESORT VILLAS-1SZL(3)KPKT 3828-32 | Kuala MudaKedah | 6 | 7 Jul 20221st sale agreement 7 Jul 2020 | CCC 28 Dec 2020 | CCC before deadline; handover not recorded |
| NOVUMKPKT 14163-1 | Kuala LumpurWP Kuala Lumpur | 654 | 18 Feb 2020Extended 12 months from 18 Feb 20191st sale agreement 18 Feb 2016 | CCC 26 Jun 2020 | 129 days after |
| 10 UNIT TERES 2.5 TINGKATKPKT 3828-26 | Kuala MudaKedah | 10 | 3 Aug 20201st sale agreement 3 Aug 2018 | CCC 6 Nov 2019 | CCC before deadline; handover not recorded |
| ASTANA B(1)KPKT 3828-18 | Kuala MudaKedah | 54 | 14 Apr 20191st sale agreement 14 Apr 2017 | CCC 14 Apr 2019 | CCC before deadline; handover not recorded |
| TAMAN KELISAKPKT 3828-16 | Kuala MudaKedah | 21 | 22 Feb 20191st sale agreement 22 Feb 2017 | CCC 6 Mar 2019 | 12 days after |
| SRI IORA 2KPKT 3828-17 | Kuala MudaKedah | 48 | 2 Mar 20191st sale agreement 2 Mar 2017 | CCC 6 Mar 2019 | 4 days after |
| EUPE KEMAJUAN SDN BHDKPKT 3828-13 | Kuala MudaKedah | 29 | 13 Sep 20151st sale agreement 13 Sep 2013 | CCC 29 Oct 2018 | 1,142 days after |
| TAMAN KELISA RIA IIKPKT 3828-6 | Kuala MudaKedah | 1,088 | 6 Aug 20051st sale agreement 6 Aug 2003 | CCC 26 Sep 2017 | 4,434 days after |
| MERA-LAND(MALAYSIA) SDN BHDKPKT 7348-4 | Kuala MudaKedah | 64 | 5 Mar 20171st sale agreement 5 Mar 2015 | CCC 6 Jun 2017 | 93 days after |
| TAMAN KELISA RIAKPKT 3828-14 | Kuala MudaKedah | 46 | 17 Dec 20161st sale agreement 17 Dec 2014 | CCC 8 Feb 2017 | 53 days after |
| BANDAR SERI ASTAN PARCEL EKPKT 3828-11 | Kuala MudaKedah | 951 | 2 Jun 20111st sale agreement 2 Jun 2009 | CCC 11 Dec 2016 | 2,019 days after |
| CINTA SAYANG RESORT HOMESKPKT 10559-1 | Kuala MudaKedah | 332 | 6 Jun 20121st sale agreement 6 Jun 2010 | CCC 19 Oct 2016 | 1,596 days after |
| TAMAN RIA MESRA IIKPKT 7348-3 | Kuala MudaKedah | 632 | 21 Nov 20141st sale agreement 21 Nov 2012 | CCC 22 May 2014 | CCC before deadline; handover not recorded |
| TAMAN RIA, PADANG SERAIKPKT 11555-1 | KulimKedah | 71 | — | CCC 12 Feb 2014 | — |
| TAMAN RIA MESRA IIKPKT 7348-2 | Kuala MudaKedah | 950 | — | CFO 20 Jun 2013 | — |
| SKY RESIDENCESKPKT 3828-10 | Kuala MudaKedah | 88 | 3 Sep 20111st sale agreement 3 Sep 2008 | CCC 29 Jun 2010 | CCC before deadline; handover not recorded |
| SERI ASTANA PARCEL CKPKT 3828-9 | Kuala MudaKedah | 633 | — | CFO 31 Dec 2009 | — |
| TAMAN KELISA RIAKPKT 3828-5 | Kuala MudaKedah | 1,542 | — | CFO 5 Jan 2005 | — |
Under construction (2) and not yet started (2)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN KELISA RIA IIIKPKT 3828-54 | Kuala MudaKedah | 35 | SmoothOn schedule | 10 Sep 20281st sale agreement 10 Sep 2026 | 5% |
| BANDAR SERI ASTANA (CALISTA)KPKT 3828-55 | Kuala MudaKedah | 49 | SmoothOn schedule | 29 Sep 20281st sale agreement 29 Sep 2026 | 5% |
| SERI ASTANA PARCEL AKPKT 3828-7 | Kuala MudaKedah | 1,488 | Not startedNot started | — | 0–95% |
| SERI ASTANA PARCEL BKPKT 3828-8 | Kuala MudaKedah | 1,057 | Not startedNot started | — | 0–95% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Eupe at a glance
| Listed | Bursa Malaysia Main Market · EUPE (6815) · listed since 1997[1][2] |
|---|---|
| Started | 1986 in Kedah, founded by Dato' Paduka Beh Heng Seong and Dato' Wira Tajudin bin Haji Hashim (company's account)[2] |
| Head office | Wisma Ria, Taman Ria, Sungai Petani, Kedah[1] |
| Leadership | Alfian bin Tan Sri Mohamed Basir — Independent Non-Executive Chairman[1] Dato' Beh Huck Lee — Group Managing Director (since 1 July 1997)[1] |
| Companies in the KPKT register | EUPE KEMAJUAN SDN. BHD KPKT 3828[1] ESTEEM GLORY SDN. BHD. KPKT 11555[1] MERA-LAND (MALAYSIA) SDN. BHD. KPKT 7348[1] EUPE DEVELOPMENT SDN. BHD. (60%) KPKT 10559[1] EUPE PJ SOUTH DEVELOPMENT SDN. BHD. KPKT 30099[1] TITIAN SAMA SDN. BHD. (70%) KPKT 19122[1] EUPE BANGSAR SOUTH DEVELOPMENT (JV) SDN. BHD. (50%) KPKT 14163[1] |
| Website | eupe.com.my |
| Homes built (company figure) | More than 25,000 homes since 1986[3] |
| First project | Taman Ria, Sungai Petani, with 3,376 homes[2] |
| Where it builds | Landed and township developments around Sungai Petani, Kedah; high-rise homes in the Klang Valley since 2016[1][2] |
| Award | Parc3 @ KL South: World Gold Winner, Residential (High Rise), FIABCI World Prix d'Excellence Awards 2024[4] |
Eupe projects on sale on PropertySifu
EST8 @ Seputeh
- NOVUM — 0.5 km, 2020
- RESIDENSI HELIKS — 6.5 km, 2025
- RESIDENSI PARC 3 — 6.7 km, 2021
Who is Eupe? The company behind the projects
Eupe says it started operations in 1986, when Dato' Paduka Beh Heng Seong and Dato' Wira Tajudin bin Haji Hashim founded the company to build townships in Kedah; its first project, Taman Ria in Sungai Petani, involved 3,376 homes [2]. Eupe Corporation Berhad has been listed on the Main Market of Bursa Malaysia since 1997 [2] and trades as EUPE, stock code 6815; its registered office is at Wisma Ria, Taman Ria, Sungai Petani [1]. The Group Managing Director is Dato' Beh Huck Lee, in the role since 1 July 1997, and the chairman is Alfian bin Tan Sri Mohamed Basir [1].
The company says it has built more than 25,000 homes since 1986 [3]. That is the company's own count; the KPKT register covers only projects licensed as housing, and 59 of the 63 registrations above are in Kedah. In 2016 Eupe began developing high-rise homes in Kuala Lumpur [2]. KPKT registers four Klang Valley projects: Novum in Bangsar South (14163-1, 654 units), Parc3 (19122-1, 793 units) and EST8 in Seputeh (19122-2, 821 units) in Kuala Lumpur, and Helix2 in Petaling Jaya (30099-1, 500 units), which was handed over to buyers in October 2025 [1]. FIABCI named Parc3 @ KL South a World Gold Winner in the residential high-rise category of its World Prix d'Excellence Awards 2024 [4].
According to the 2026 annual report, the Kedah projects are developed by Eupe Kemajuan, Esteem Glory and Mera-Land (Malaysia), all wholly owned, and by Eupe Development, 60% owned [1]. In the Klang Valley, Eupe PJ South Development is wholly owned, the group has a 70% effective interest in Titian Sama, and Eupe Bangsar South Development (JV) is 50% owned [1]. EST8 @ Seputeh, the project on PropertySifu, is registered under Titian Sama Sdn Bhd (KPKT developer code 19122).
Frequently asked questions
Is Eupe a listed company?
Which company develops EST8 @ Seputeh?
Titian Sama Sdn Bhd (KPKT developer code 19122), a subsidiary of Eupe Kemajuan in which the Eupe group has a 70% effective interest, according to the 2026 annual report [1]. The same company registered Parc3 (19122-1).
Has EST8 @ Seputeh been completed, and was its deadline extended?
KPKT records EST8 (19122-2, 821 suites in three components) as completed. The first sale agreement was signed on 18 November 2021, and the handover deadline of 18 November 2024 was extended with approval by 24 months to 18 November 2026. The CCC for all three components is dated 19 May 2026, 183 days before the extended deadline; the register does not record the handover date.
Does Eupe have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 63 Eupe projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). The 2 projects under construction, 3828-54 and 3828-55 in Kedah (35 and 49 houses, first sale agreements in September 2026), are on schedule (Lancar). Two large registrations, 3828-7 and 3828-8 (Seri Astana parcels A and B, 1,488 and 1,057 units), are recorded as not started (Belum Mula), although some of their components show 95% reported progress.
How many housing projects has Eupe completed, and were they handed over on time?
In the KPKT register, 59 of the 63 Eupe housing projects are completed. Of the 53 completed projects that have both a deadline and a completion date, 11 were handed over on or before the deadline (for projects with an approved extension, the extended deadline), 25 were handed over or certified complete after it — 4 of these were under construction during the 18 March–31 August 2020 movement control period — and 17 received the completion certificate before the deadline, with no handover date recorded. In several large Kedah registrations the last completion certificate is dated years after the deadline set by the first sale agreement, for example 3828-6 (1,088 houses; deadline 6 August 2005; last CCC 26 September 2017); buyers who signed later in the same registration had later deadlines.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Eupe Corporation Berhad Annual Report 2026 (corporate information p.4; management discussion and analysis pp.7–9; note 8, subsidiaries, pp.186–187) · Eupe Corporation Berhad · 2026-06 · accessed 28 Oct 2026
https://www.eupe.com.my/sites/default/files/node/annual-report/files/2026-06/ECB_Annual%20Report%202026_full.pdf - [2] Historical timeline · Eupe Corporation Berhad · 13 Sep 2022 · accessed 28 Oct 2026
https://www.eupe.com.my/historical-timeline - [3] Eupe Corporation Berhad — home page (about us) · Eupe Corporation Berhad · accessed 28 Oct 2026
https://www.eupe.com.my/ - [4] Celebrating Excellence and Innovation in Real Estate: Highlights From The FIABCI World Prix d'Excellence Awards 2024 · FIABCI · 30 May 2024 · accessed 28 Oct 2026
https://fiabci.org/en/news-room/view/471
Last updated 28 Oct 2026