EcoWorld (Eco World Development Group Berhad)
Eco World Development Group Berhad (EcoWorld) is a Bursa Malaysia-listed developer with 174 housing projects in the KPKT register: 116 completed, 47 under construction, 6 not yet started and 5 with permits cancelled, under 20 companies and joint ventures in Selangor, Johor, Penang and Kuala Lumpur, none classed Sick or Abandoned. It was Focal Aims Holdings until December 2013.
- 174 projects in the KPKT register
- 116 completed
- 47 under construction
- 6 not yet started
- 5 with the permit cancelled
- None Sick or Abandoned
Has EcoWorld handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 174 housing projects under 20 EcoWorld companies in 4 states: 116 completed, 47 under construction, 6 not yet started, 5 with the permit cancelled. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 116 completed projects, 111 have both a handover deadline and a completion date in the register: 41 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 14 handed over or certified complete after that deadline; 56 received the completion certificate before the deadline (handover date not recorded).
39 projects had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 116
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| EKOFLORA 4KPKT 14320-14 | Johor BahruJohor | 124 | 25 Nov 20261st sale agreement 25 Nov 2023 | CCC 20 Apr 2026 Handover 22 May 2026 | 187 days before |
| EKOTROPIKA 4KPKT 6443-23 | Johor BahruJohor | 50 | 19 Jan 20271st sale agreement 19 Jan 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 242 days before |
| EKOTROPIKA 4KPKT 6443-24 | Johor BahruJohor | 48 | 26 Feb 20271st sale agreement 26 Feb 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 280 days before |
| EKOTROPIKA 4KPKT 6443-25 | Johor BahruJohor | 80 | 2 Sep 20271st sale agreement 2 Sep 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 468 days before |
| EKOTROPIKA 4KPKT 6443-26 | Johor BahruJohor | 100 | 13 May 20271st sale agreement 13 May 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 356 days before |
| EKOTROPIKA 4KPKT 6443-20 | Johor BahruJohor | 164 | 28 Jun 20261st sale agreement 28 Jun 2023 | CCC 13 Mar 2026 Handover 8 May 2026 | 51 days before |
| EKOTROPIKA 4KPKT 6443-22 | Johor BahruJohor | 48 | 23 May 20261st sale agreement 23 May 2023 | CCC 13 Mar 2026 Handover 8 May 2026 | 15 days before |
| EKOFLORA 4KPKT 14320-15 | Johor BahruJohor | 88 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 20 Apr 2026 Handover 23 Apr 2026 | 5 days before |
| EKOFLORA 4KPKT 14320-16 | Johor BahruJohor | 136 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 20 Apr 2026 Handover 23 Apr 2026 | 5 days before |
| EKOTROPIKA 4KPKT 6443-21 | Johor BahruJohor | 50 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 13 Mar 2026 Handover 23 Apr 2026 | 5 days before |
| RESIDENSI SWNK HOUZEKPKT 14510-2 | Kuala LumpurWP Kuala Lumpur | 442 | 3 Dec 2026Extended 12 months from 3 Dec 20251st sale agreement 3 Dec 2022 | CCC 23 Feb 2026 Handover 31 Mar 2026 | 247 days before |
| HANAKPKT 14504-7 | PetalingSelangor | 500 | 11 Mar 20261st sale agreement 11 Mar 2023 | CCC 28 Nov 2025 Handover 26 Feb 2026 | 13 days before |
Handed over or certified complete after the deadline — 12 most recent of 14
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| THE PARQUE RESIDENCESKPKT 14050-8 | Kuala LangatSelangor | 401 | 30 Jul 20251st sale agreement 30 Jul 2022 | CCC 4 Jun 2025 Handover 29 Jul 2025 / 31 Dec 2025 | 154 days after |
| ECO BOTANIC SDN. BHD.KPKT 14020-3 | Johor BahruJohor | 200 | 27 Nov 20241st sale agreement 27 Nov 2021 | CCC 12 Dec 2024 Handover 16 Dec 2024 | 19 days after |
| ECO BLOOMKPKT 14518-1 | Seberang Perai SelatanPulau Pinang | 490 | 11 Oct 20191st sale agreement 11 Oct 2016 | CCC 10 Mar 2020 | 151 days after |
| ECO SANCTUARYKPKT 14050-4 | Kuala LangatSelangor | 260 | 14 Oct 20191st sale agreement 14 Oct 2016 | CCC 18 Nov 2019 | 35 days after |
| ECO TERRACESKPKT 13968-1 | Daerah Timor LautPulau Pinang | 333 | 13 Jun 2019Extended 12 months from 13 Jun 20181st sale agreement 13 Jun 2015 | CCC 24 Jun 2019 | 11 days after |
| ECO MAJESTICKPKT 13544-5 | Hulu LangatSelangor | 482 | 10 Jan 20191st sale agreement 10 Jan 2016 | CCC 21 May 2019 | 131 days after |
| ECO SPRINGS DEVELOPMENT SDN BHD (FORMERLY KNOWN AS PROMOSI ETIKA SDN BHD)KPKT 13518-3 | Johor BahruJohor | 796 | 20 Sep 20171st sale agreement 20 Sep 2014 | CCC 17 Apr 2019 | 574 days after |
| ECO MAJESTICKPKT 13544-3 | Hulu LangatSelangor | 586 | 1 Dec 20171st sale agreement 1 Dec 2014 | CCC 9 Mar 2018 | 98 days after |
| ECOSKYKPKT 13307-1 | Kuala LumpurWP Kuala Lumpur | 975 | 21 Dec 20161st sale agreement 21 Dec 2013 | CCC 9 Mar 2018 | 443 days after |
| RAINFOREST DOUBLE STOREY CLUSTER HOME (CHERRYWOOD & TULIPWOOD)KPKT 6443-14 | Johor BahruJohor | 356 | 21 Jan 20171st sale agreement 21 Jan 2015 | CCC 9 Jan 2018 | 353 days after |
| ECONESTKPKT 13165-2 | Johor BahruJohor | 472 | 22 Dec 20161st sale agreement 22 Dec 2013 | CCC 14 Dec 2017 | 357 days after |
| ECO BOTANIC DEVELOPMENT SDN. BHD.KPKT 13165-4 | Johor BahruJohor | 400 | 20 Dec 20161st sale agreement 20 Dec 2014 | CCC 10 Sep 2017 | 264 days after |
Show all 14
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| THE PARQUE RESIDENCESKPKT 14050-8 | Kuala LangatSelangor | 401 | 30 Jul 20251st sale agreement 30 Jul 2022 | CCC 4 Jun 2025 Handover 29 Jul 2025 / 31 Dec 2025 | 154 days after |
| ECO BOTANIC SDN. BHD.KPKT 14020-3 | Johor BahruJohor | 200 | 27 Nov 20241st sale agreement 27 Nov 2021 | CCC 12 Dec 2024 Handover 16 Dec 2024 | 19 days after |
| ECO BLOOMKPKT 14518-1 | Seberang Perai SelatanPulau Pinang | 490 | 11 Oct 20191st sale agreement 11 Oct 2016 | CCC 10 Mar 2020 | 151 days after |
| ECO SANCTUARYKPKT 14050-4 | Kuala LangatSelangor | 260 | 14 Oct 20191st sale agreement 14 Oct 2016 | CCC 18 Nov 2019 | 35 days after |
| ECO TERRACESKPKT 13968-1 | Daerah Timor LautPulau Pinang | 333 | 13 Jun 2019Extended 12 months from 13 Jun 20181st sale agreement 13 Jun 2015 | CCC 24 Jun 2019 | 11 days after |
| ECO MAJESTICKPKT 13544-5 | Hulu LangatSelangor | 482 | 10 Jan 20191st sale agreement 10 Jan 2016 | CCC 21 May 2019 | 131 days after |
| ECO SPRINGS DEVELOPMENT SDN BHD (FORMERLY KNOWN AS PROMOSI ETIKA SDN BHD)KPKT 13518-3 | Johor BahruJohor | 796 | 20 Sep 20171st sale agreement 20 Sep 2014 | CCC 17 Apr 2019 | 574 days after |
| ECO MAJESTICKPKT 13544-3 | Hulu LangatSelangor | 586 | 1 Dec 20171st sale agreement 1 Dec 2014 | CCC 9 Mar 2018 | 98 days after |
| ECOSKYKPKT 13307-1 | Kuala LumpurWP Kuala Lumpur | 975 | 21 Dec 20161st sale agreement 21 Dec 2013 | CCC 9 Mar 2018 | 443 days after |
| RAINFOREST DOUBLE STOREY CLUSTER HOME (CHERRYWOOD & TULIPWOOD)KPKT 6443-14 | Johor BahruJohor | 356 | 21 Jan 20171st sale agreement 21 Jan 2015 | CCC 9 Jan 2018 | 353 days after |
| ECONESTKPKT 13165-2 | Johor BahruJohor | 472 | 22 Dec 20161st sale agreement 22 Dec 2013 | CCC 14 Dec 2017 | 357 days after |
| ECO BOTANIC DEVELOPMENT SDN. BHD.KPKT 13165-4 | Johor BahruJohor | 400 | 20 Dec 20161st sale agreement 20 Dec 2014 | CCC 10 Sep 2017 | 264 days after |
| KOTA MASAIKPKT 6443-12 | Johor BahruJohor | 360 | 1 Nov 20141st sale agreement 1 Nov 2012 | CCC 25 Aug 2015 | 297 days after |
| KOTA MASAIKPKT 6443-8 | Johor BahruJohor | 5,606 | 26 Nov 20131st sale agreement 26 Nov 2011 | CFO 26 Feb 2014 | 92 days after |
Show all 116 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| EKOFLORA 4KPKT 14320-14 | Johor BahruJohor | 124 | 25 Nov 20261st sale agreement 25 Nov 2023 | CCC 20 Apr 2026 Handover 22 May 2026 | 187 days before |
| EKOTROPIKA 4KPKT 6443-23 | Johor BahruJohor | 50 | 19 Jan 20271st sale agreement 19 Jan 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 242 days before |
| EKOTROPIKA 4KPKT 6443-24 | Johor BahruJohor | 48 | 26 Feb 20271st sale agreement 26 Feb 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 280 days before |
| EKOTROPIKA 4KPKT 6443-25 | Johor BahruJohor | 80 | 2 Sep 20271st sale agreement 2 Sep 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 468 days before |
| EKOTROPIKA 4KPKT 6443-26 | Johor BahruJohor | 100 | 13 May 20271st sale agreement 13 May 2024 | CCC 18 Mar 2026 Handover 22 May 2026 | 356 days before |
| EKOTROPIKA 4KPKT 6443-20 | Johor BahruJohor | 164 | 28 Jun 20261st sale agreement 28 Jun 2023 | CCC 13 Mar 2026 Handover 8 May 2026 | 51 days before |
| EKOTROPIKA 4KPKT 6443-22 | Johor BahruJohor | 48 | 23 May 20261st sale agreement 23 May 2023 | CCC 13 Mar 2026 Handover 8 May 2026 | 15 days before |
| EKOFLORA 4KPKT 14320-15 | Johor BahruJohor | 88 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 20 Apr 2026 Handover 23 Apr 2026 | 5 days before |
| EKOFLORA 4KPKT 14320-16 | Johor BahruJohor | 136 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 20 Apr 2026 Handover 23 Apr 2026 | 5 days before |
| EKOTROPIKA 4KPKT 6443-21 | Johor BahruJohor | 50 | 28 Apr 20261st sale agreement 28 Apr 2023 | CCC 13 Mar 2026 Handover 23 Apr 2026 | 5 days before |
| RESIDENSI SWNK HOUZEKPKT 14510-2 | Kuala LumpurWP Kuala Lumpur | 442 | 3 Dec 2026Extended 12 months from 3 Dec 20251st sale agreement 3 Dec 2022 | CCC 23 Feb 2026 Handover 31 Mar 2026 | 247 days before |
| HANAKPKT 14504-7 | PetalingSelangor | 500 | 11 Mar 20261st sale agreement 11 Mar 2023 | CCC 28 Nov 2025 Handover 26 Feb 2026 | 13 days before |
| CHEERYWOODKPKT 19150-14 | Hulu LangatSelangor | 162 | 21 Sep 20261st sale agreement 21 Sep 2023 | CCC 29 Jan 2026 | CCC before deadline; handover not recorded |
| CHEERYWOODKPKT 19150-13 | Hulu LangatSelangor | 68 | 16 Sep 20261st sale agreement 16 Sep 2023 | CCC 28 Jan 2026 | CCC before deadline; handover not recorded |
| THE PARQUE RESIDENCESKPKT 14050-8 | Kuala LangatSelangor | 401 | 30 Jul 20251st sale agreement 30 Jul 2022 | CCC 4 Jun 2025 Handover 29 Jul 2025 / 31 Dec 2025 | 154 days after |
| NORTON GARDENKPKT 14505-6 | Kuala SelangorSelangor | 376 | 18 Dec 20251st sale agreement 18 Dec 2022 | CCC 29 Jul 2025 Handover 22 Oct 2025 / 8 Dec 2025 | 10 days before |
| RESIDENSI BOTANI 3KPKT 19985-6 | Johor BahruJohor | 364 | 18 Nov 20251st sale agreement 18 Nov 2022 | CCC 12 Nov 2025 | CCC before deadline; handover not recorded |
| ECO HORIZON 1KPKT 19152-10 | Seberang Perai SelatanPulau Pinang | 70 | 21 May 20261st sale agreement 21 May 2023 | CCC 7 Oct 2025 Handover 3 Nov 2025 | 199 days before |
| BOHEMIAKPKT 14050-9 | Kuala LangatSelangor | 116 | 26 Nov 20251st sale agreement 26 Nov 2022 | CCC 19 Aug 2025 Handover 29 Aug 2025 | 89 days before |
| EKOFLORA 2KPKT 14320-12 | Johor BahruJohor | 44 | 14 Sep 20251st sale agreement 14 Sep 2022 | CCC 19 May 2025 Handover 13 Jun 2025 | 93 days before |
| EKOFLORA 2KPKT 14320-13 | Johor BahruJohor | 28 | 20 Apr 20261st sale agreement 20 Apr 2023 | CCC 13 May 2025 Handover 13 Jun 2025 | 311 days before |
| ECO SUMMER SDN BHDKPKT 14320-9 | Johor BahruJohor | 271 | 14 Feb 20261st sale agreement 14 Feb 2023 | CCC 14 Mar 2025 Handover 5 May 2025 | 285 days before |
| EMBERKPKT 14504-6 | PetalingSelangor | 376 | 15 May 20251st sale agreement 15 May 2022 | CCC 30 Apr 2025 | CCC before deadline; handover not recorded |
| EKOTROPIKA 3KPKT 6443-18 | Johor BahruJohor | 112 | 24 Jun 20251st sale agreement 24 Jun 2022 | CCC 27 Mar 2025 | CCC before deadline; handover not recorded |
| EKOTROPIKA 3KPKT 6443-19 | Johor BahruJohor | 204 | 13 Sep 20251st sale agreement 13 Sep 2022 | CCC 27 Mar 2025 | CCC before deadline; handover not recorded |
| EKOFLORA 3KPKT 14320-11 | Johor BahruJohor | 162 | 26 May 20251st sale agreement 26 May 2022 | CCC 20 Jan 2025 Handover 28 Feb 2025 | 87 days before |
| BIRCHPARKKPKT 19150-12 | Hulu LangatSelangor | 355 | 8 Jan 20261st sale agreement 8 Jan 2023 | CCC 7 Jan 2025 Handover 4 Feb 2025 | 338 days before |
| ECO BOTANIC SDN. BHD.KPKT 14020-3 | Johor BahruJohor | 200 | 27 Nov 20241st sale agreement 27 Nov 2021 | CCC 12 Dec 2024 Handover 16 Dec 2024 | 19 days after |
| EKOFLORA 2KPKT 14320-10 | Johor BahruJohor | 92 | 24 Feb 20251st sale agreement 24 Feb 2022 | CCC 24 Oct 2024 Handover 10 Dec 2024 | 76 days before |
| ECO HORIZON 2KPKT 19152-7 | Seberang Perai SelatanPulau Pinang | 235 | 24 Jun 20251st sale agreement 24 Jun 2022 | CCC 1 Nov 2024 Handover 2 Dec 2024 | 204 days before |
| ECO HORIZONKPKT 19152-8 | Seberang Perai SelatanPulau Pinang | 114 | 12 Nov 20251st sale agreement 12 Nov 2022 | CCC 1 Oct 2024 Handover 29 Oct 2024 | 379 days before |
| RESIDENSI BOTANI 2KPKT 19985-2 | Johor BahruJohor | 165 | 6 Sep 2024Extended 5 months from 6 Apr 20241st sale agreement 6 Apr 2021 | CCC 21 Aug 2024 Handover 29 Aug 2024 | 8 days before |
| RESIDENSI BOTANI 2KPKT 19985-3 | Johor BahruJohor | 94 | 7 Sep 2024Extended 5 months from 7 Apr 20241st sale agreement 7 Apr 2021 | CCC 21 Aug 2024 Handover 29 Aug 2024 | 9 days before |
| RESIDENSI BOTANI 2KPKT 19985-4 | Johor BahruJohor | 105 | 19 Nov 20241st sale agreement 19 Nov 2021 | CCC 21 Aug 2024 Handover 29 Aug 2024 | 82 days before |
| RESIDENSI BOTANI 2KPKT 19985-5 | Johor BahruJohor | 108 | 12 May 20251st sale agreement 12 May 2022 | CCC 21 Aug 2024 Handover 29 Aug 2024 | 256 days before |
| REGENT GARDENKPKT 14505-5 | Kuala SelangorSelangor | 154 | 11 Nov 20241st sale agreement 11 Nov 2021 | CCC 5 Aug 2024 Handover 20 Aug 2024 | 83 days before |
| ECO HORIZONKPKT 19152-5 | Seberang Perai SelatanPulau Pinang | 181 | 2 Nov 20241st sale agreement 2 Nov 2021 | CCC 30 May 2024 Handover 28 Jun 2024 | 127 days before |
| RESIDENSI BOTANI 1KPKT 19985-1 | Johor BahruJohor | 600 | 25 Aug 2024Extended 5 months from 25 Mar 20241st sale agreement 25 Mar 2021 | CCC 8 Feb 2024 Handover 18 Mar 2024 | 160 days before |
| ECO ARDENCEKPKT 14504-5 | PetalingSelangor | 1,728 | 26 Feb 2024Extended 5 months from 26 Sep 20231st sale agreement 26 Sep 2020 | CCC 9 Feb 2024 Handover 20 Feb 2024 / 25 Feb 2024 | 1 day before |
| ECO HORIZON SDN BHDKPKT 19152-4 | Seberang Perai SelatanPulau Pinang | 224 | 27 Aug 2024Extended 5 months from 27 Mar 20241st sale agreement 27 Mar 2021 | CCC 17 Jan 2024 Handover 5 Feb 2024 | 204 days before |
| ECO MAJESTICKPKT 13544-14 | Hulu LangatSelangor | 33 | 15 Dec 20241st sale agreement 15 Dec 2021 | CCC 23 Jan 2024 Handover 31 Jan 2024 | 319 days before |
| ECO SANCTUARYKPKT 14050-7 | Kuala LangatSelangor | 960 | 17 Mar 2024Extended 5 months from 17 Oct 20231st sale agreement 17 Oct 2020 | CCC 19 Jan 2024 Handover 24 Jan 2024 / 29 Jan 2024 | 48 days before |
| CHEERYWOODKPKT 19150-10 | Hulu LangatSelangor | 171 | 28 Dec 20241st sale agreement 28 Dec 2021 | CCC 16 Jan 2024 Handover 26 Jan 2024 | 337 days before |
| CHEERYWOODKPKT 19150-11 | Hulu LangatSelangor | 175 | 29 Dec 20241st sale agreement 29 Dec 2021 | CCC 16 Jan 2024 Handover 26 Jan 2024 | 338 days before |
| ECO MAJESTICKPKT 13544-13 | Hulu LangatSelangor | 116 | 16 Nov 20241st sale agreement 16 Nov 2021 | CCC 23 Jan 2024 | CCC before deadline; handover not recorded |
| ECO HORIZON 2KPKT 19152-6 | Seberang Perai SelatanPulau Pinang | 180 | 22 Jan 20241st sale agreement 22 Jan 2021 | CCC 17 Jan 2024 | CCC before deadline; handover not recorded |
| SENCILIAKPKT 14050-6 | Kuala LangatSelangor | 108 | 19 Feb 2024Extended 5 months from 19 Sep 20231st sale agreement 19 Sep 2020 | CCC 21 Aug 2023 Handover 25 Sep 2023 | 147 days before |
| REGENT GARDENKPKT 14505-4 | Kuala SelangorSelangor | 922 | 11 Sep 2023Extended 11 months from 11 Oct 20221st sale agreement 11 Oct 2019 | CCC 22 Jun 2023 Handover 7 Aug 2023 / 21 Aug 2023 / 4 Sep 2023 | 7 days before |
| ECO FORESTKPKT 19150-5 | Hulu LangatSelangor | 110 | 18 Jun 2023Extended 6 months from 18 Dec 20221st sale agreement 18 Dec 2019 | CCC 29 Mar 2023 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-6 | Hulu LangatSelangor | 92 | 29 Aug 20231st sale agreement 29 Aug 2020 | CCC 29 Mar 2023 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-7 | Hulu LangatSelangor | 162 | 20 Dec 20231st sale agreement 20 Dec 2020 | CCC 29 Mar 2023 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-8 | Hulu LangatSelangor | 100 | 27 Mar 20241st sale agreement 27 Mar 2021 | CCC 29 Mar 2023 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-9 | Hulu LangatSelangor | 66 | 27 Mar 20241st sale agreement 27 Mar 2021 | CCC 29 Mar 2023 | CCC before deadline; handover not recorded |
| CORAKPKT 14504-4 | PetalingSelangor | 250 | 24 Jul 2023Extended 11 months from 24 Aug 20221st sale agreement 24 Aug 2019 | CCC 14 Feb 2023 Handover 15 Mar 2023 | 131 days before |
| EKOTROPIKA 3KPKT 6443-17 | Johor BahruJohor | 300 | 20 Dec 2023Extended 5 months from 20 Jul 20231st sale agreement 20 Jul 2020 | CCC 16 Feb 2023 Handover 13 Mar 2023 | 282 days before |
| ECO MAJESTICKPKT 13544-12 | Hulu LangatSelangor | 176 | 25 Jul 20231st sale agreement 25 Jul 2020 | CCC 10 Nov 2022 | CCC before deadline; handover not recorded |
| BBCC DEVELOPMENT SDN BHDKPKT 14510-1 | Kuala LumpurWP Kuala Lumpur | 668 | 14 Jul 2022Extended 33 months from 14 Oct 20191st sale agreement 14 Oct 2016 | CCC 20 May 2022 Handover 24 Jan 2022 / 5 Jul 2022 | 9 days before |
| ECO SUMMER SDN BHDKPKT 14320-7 | Johor BahruJohor | 250 | 24 Feb 2023Extended 6 months from 24 Aug 20221st sale agreement 24 Aug 2019 | CCC 24 Feb 2022 | CCC before deadline; handover not recorded |
| EKOFLORA 3KPKT 14320-8 | Johor BahruJohor | 152 | 6 Jul 20231st sale agreement 6 Jul 2020 | CCC 24 Feb 2022 | CCC before deadline; handover not recorded |
| NARAKPKT 14504-3 | PetalingSelangor | 308 | 1 May 2022Extended 6 months from 31 Oct 20211st sale agreement 31 Oct 2018 | CCC 3 Dec 2021 | CCC before deadline; handover not recorded |
| ECO SUMMER SDN BHDKPKT 14320-6 | Johor BahruJohor | 543 | 2 May 2023Extended 6 months from 2 Nov 20221st sale agreement 2 Nov 2019 | CCC 17 Oct 2021 | CCC before deadline; handover not recorded |
| ECO GRANDEURKPKT 14505-3 | Kuala SelangorSelangor | 361 | 7 Apr 2022Extended 6 months from 7 Oct 20211st sale agreement 7 Oct 2018 | CCC 15 Oct 2021 | CCC before deadline; handover not recorded |
| ECO SUMMER SDN BHDKPKT 14320-4 | Johor BahruJohor | 18 | 28 Apr 2022Extended 6 months from 28 Oct 20211st sale agreement 28 Oct 2018 | CCC 31 Mar 2021 | CCC before deadline; handover not recorded |
| ECO SUMMER SDN BHDKPKT 14320-5 | Johor BahruJohor | 12 | 28 Apr 2022Extended 6 months from 28 Oct 20211st sale agreement 28 Oct 2018 | CCC 31 Mar 2021 | CCC before deadline; handover not recorded |
| ECO HORIZONKPKT 19152-1 | Seberang Perai SelatanPulau Pinang | 280 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 11 Jan 2021 | CCC before deadline; handover not recorded |
| ECO HORIZONKPKT 19152-2 | Seberang Perai SelatanPulau Pinang | 424 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 11 Jan 2021 | CCC before deadline; handover not recorded |
| ECO SUMMER SDN BHDKPKT 14320-2 | Johor BahruJohor | 84 | 14 Oct 2022Extended 18 months from 14 Apr 20211st sale agreement 14 Apr 2018 | CCC 9 Dec 2020 | CCC before deadline; handover not recorded |
| ECO MAJESTICKPKT 13544-10 | Hulu LangatSelangor | 79 | 23 Jan 20211st sale agreement 23 Jan 2018 | CCC 8 Dec 2020 | CCC before deadline; handover not recorded |
| ECO MAJESTICKPKT 13544-8 | Hulu LangatSelangor | 144 | 24 Jan 20211st sale agreement 24 Jan 2018 | CCC 8 Dec 2020 | CCC before deadline; handover not recorded |
| ECO ARDENCEKPKT 14504-2 | PetalingSelangor | 259 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 27 Nov 2020 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-1 | Hulu LangatSelangor | 94 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 23 Oct 2020 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-2 | Hulu LangatSelangor | 212 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 23 Oct 2020 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-3 | Hulu SelangorSelangor | 149 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 23 Oct 2020 | CCC before deadline; handover not recorded |
| ECO FORESTKPKT 19150-4 | Hulu LangatSelangor | 230 | 1 May 2021Extended 6 months from 31 Oct 20201st sale agreement 31 Oct 2017 | CCC 23 Oct 2020 | CCC before deadline; handover not recorded |
| ECO BOTANIC SDN. BHD.KPKT 14020-4 | Johor BahruJohor | 12 | 24 Oct 20221st sale agreement 24 Oct 2019 | CCC 15 Jun 2020 | CCC before deadline; handover not recorded |
| ECO BLOOMKPKT 14518-1 | Seberang Perai SelatanPulau Pinang | 490 | 11 Oct 20191st sale agreement 11 Oct 2016 | CCC 10 Mar 2020 | 151 days after |
| ECO SANCTUARYKPKT 14050-4 | Kuala LangatSelangor | 260 | 14 Oct 20191st sale agreement 14 Oct 2016 | CCC 18 Nov 2019 | 35 days after |
| AERESKPKT 14504-1 | PetalingSelangor | 432 | 31 Oct 20191st sale agreement 31 Oct 2016 | CCC 17 Oct 2019 | CCC before deadline; handover not recorded |
| ECO GRANDEURKPKT 14505-1 | Kuala SelangorSelangor | 1,012 | 31 Oct 20191st sale agreement 31 Oct 2016 | CCC 17 Sep 2019 | CCC before deadline; handover not recorded |
| ECO GRANDEURKPKT 14505-2 | Kuala SelangorSelangor | 812 | 10 Nov 20191st sale agreement 10 Nov 2016 | CCC 17 Sep 2019 | CCC before deadline; handover not recorded |
| ECO TERRACESKPKT 13968-1 | Daerah Timor LautPulau Pinang | 333 | 13 Jun 2019Extended 12 months from 13 Jun 20181st sale agreement 13 Jun 2015 | CCC 24 Jun 2019 | 11 days after |
| ECO MAJESTICKPKT 13544-7 | Hulu LangatSelangor | 900 | 5 Aug 20191st sale agreement 5 Aug 2016 | CCC 28 May 2019 | CCC before deadline; handover not recorded |
| MILLSGATE DOUBLE STOREY TERRACE HOMEKPKT 6443-16 | Johor BahruJohor | 638 | 29 May 20191st sale agreement 29 May 2016 | CCC 23 May 2019 | CCC before deadline; handover not recorded |
| ECO MAJESTICKPKT 13544-5 | Hulu LangatSelangor | 482 | 10 Jan 20191st sale agreement 10 Jan 2016 | CCC 21 May 2019 | 131 days after |
| ECO SPRINGS DEVELOPMENT SDN BHD (FORMERLY KNOWN AS PROMOSI ETIKA SDN BHD)KPKT 13518-3 | Johor BahruJohor | 796 | 20 Sep 20171st sale agreement 20 Sep 2014 | CCC 17 Apr 2019 | 574 days after |
| ECO MAJESTICKPKT 13544-6 | Hulu LangatSelangor | 750 | 22 Feb 20191st sale agreement 22 Feb 2016 | CCC 29 Nov 2018 | CCC before deadline; handover not recorded |
| ECO SANCTUARYKPKT 14050-3 | Kuala LangatSelangor | 594 | 5 Dec 20181st sale agreement 5 Dec 2015 | CCC 22 Nov 2018 | CCC before deadline; handover not recorded |
| ECO MAJESTICKPKT 13544-4 | Hulu LangatSelangor | 870 | 25 Feb 20191st sale agreement 25 Feb 2016 | CCC 17 Oct 2018 | CCC before deadline; handover not recorded |
| ECO MEADOWSKPKT 14145-1 | Seberang Perai SelatanPulau Pinang | 375 | 24 Oct 20181st sale agreement 24 Oct 2015 | CCC 6 Sep 2018 | CCC before deadline; handover not recorded |
| ECO BOTANIC SDN. BHD.KPKT 14020-1 | Johor BahruJohor | 308 | 20 Aug 20181st sale agreement 20 Aug 2015 | CCC 13 Aug 2018 | CCC before deadline; handover not recorded |
| ECO BOTANIC SDN. BHD.KPKT 14020-2 | Johor BahruJohor | 24 | 4 Dec 20181st sale agreement 4 Dec 2015 | CCC 13 Aug 2018 | CCC before deadline; handover not recorded |
| GREENSGATE DOUBLE STOREY TERRACE HOUSEKPKT 6443-15 | Johor BahruJohor | 558 | 30 May 20181st sale agreement 30 May 2015 | CCC 27 May 2018 | CCC before deadline; handover not recorded |
| ECO SANCTUARYKPKT 14050-1 | Kuala LangatSelangor | 353 | 28 Jun 20181st sale agreement 28 Jun 2015 | CCC 3 May 2018 | CCC before deadline; handover not recorded |
| ECO SANCTUARYKPKT 14050-2 | Kuala LangatSelangor | 358 | 30 Jun 20181st sale agreement 30 Jun 2015 | CCC 3 May 2018 | CCC before deadline; handover not recorded |
| ECO MAJESTICKPKT 13544-3 | Hulu LangatSelangor | 586 | 1 Dec 20171st sale agreement 1 Dec 2014 | CCC 9 Mar 2018 | 98 days after |
| ECOSKYKPKT 13307-1 | Kuala LumpurWP Kuala Lumpur | 975 | 21 Dec 20161st sale agreement 21 Dec 2013 | CCC 9 Mar 2018 | 443 days after |
| LAMAN INDAH 2KPKT 14320-1 | Johor BahruJohor | 146 | 15 Nov 20181st sale agreement 15 Nov 2016 | CCC 15 Feb 2018 | CCC before deadline; handover not recorded |
| RAINFOREST DOUBLE STOREY CLUSTER HOME (CHERRYWOOD & TULIPWOOD)KPKT 6443-14 | Johor BahruJohor | 356 | 21 Jan 20171st sale agreement 21 Jan 2015 | CCC 9 Jan 2018 | 353 days after |
| ECONESTKPKT 13165-2 | Johor BahruJohor | 472 | 22 Dec 20161st sale agreement 22 Dec 2013 | CCC 14 Dec 2017 | 357 days after |
| ECO BOTANIC DEVELOPMENT SDN. BHD.KPKT 13165-4 | Johor BahruJohor | 400 | 20 Dec 20161st sale agreement 20 Dec 2014 | CCC 10 Sep 2017 | 264 days after |
| ECO MAJESTICKPKT 13544-2 | Hulu LangatSelangor | 576 | 12 Jul 20171st sale agreement 12 Jul 2014 | CCC 22 Jun 2017 | CCC before deadline; handover not recorded |
| ECO SRPINGS DEVELOPMENT SDN BHD (FORMERLY KNOWN AS PROMOSI ETIKA SDN BHD)KPKT 13518-1 | Johor BahruJohor | 459 | 25 May 20171st sale agreement 25 May 2014 | CCC 24 May 2017 | CCC before deadline; handover not recorded |
| ECO SPRINGS DEVELOPMENT SDN BHD (FORMERLY KNOWN AS PROMOSI ETIKA SDN BHD)KPKT 13518-2 | Johor BahruJohor | 460 | 25 May 20171st sale agreement 25 May 2014 | CCC 24 May 2017 | CCC before deadline; handover not recorded |
| KOTA MASAIKPKT 6443-7 | Johor BahruJohor | 1,075 | 15 Jul 20171st sale agreement 15 Jul 2015 | CFO 4 Apr 2017 | CCC before deadline; handover not recorded |
| ECO MAJESTICKPKT 13544-1 | Hulu LangatSelangor | 612 | 14 Jun 20171st sale agreement 14 Jun 2014 | CCC 17 Mar 2017 | CCC before deadline; handover not recorded |
| RAINFOREST DOUBLE STOREY CLUSTER HOMEKPKT 6443-13 | Johor BahruJohor | 144 | 25 Nov 20161st sale agreement 25 Nov 2014 | CCC 31 Oct 2016 | CCC before deadline; handover not recorded |
| ECO BOTANICKPKT 13165-1 | Johor BahruJohor | 624 | 22 Sep 20161st sale agreement 22 Sep 2013 | CCC 7 Sep 2016 | CCC before deadline; handover not recorded |
| KOTA MASAIKPKT 6443-12 | Johor BahruJohor | 360 | 1 Nov 20141st sale agreement 1 Nov 2012 | CCC 25 Aug 2015 | 297 days after |
| KOTA MASAIKPKT 6443-6 | Johor BahruJohor | 879 | 17 May 20151st sale agreement 17 May 2013 | CFO 15 Jan 2015 | CCC before deadline; handover not recorded |
| KOTA MASAIKPKT 6443-9 | Johor BahruJohor | 970 | 4 Jun 20151st sale agreement 4 Jun 2013 | CFO 29 Oct 2014 | CCC before deadline; handover not recorded |
| KOTA MASAIKPKT 6443-8 | Johor BahruJohor | 5,606 | 26 Nov 20131st sale agreement 26 Nov 2011 | CFO 26 Feb 2014 | 92 days after |
| SAUJANA O-LOTKPKT 10192-3 | PetalingSelangor | 41 | — | CCC 13 Dec 2013 | — |
| SAUJANA O-LOTKPKT 10192-2 | PetalingSelangor | 48 | — | CCC 20 Sep 2012 | — |
| SAUJANA O-LOTKPKT 10192-1 | PetalingSelangor | 48 | — | CFO 22 Oct 2008 | — |
| KOTA MASAIKPKT 6443-11 | Johor BahruJohor | 470 | — | CFO 6 Nov 2007 | — |
| PANGSAPURI PERKHIDMATAN CERIAKPKT 19152-11 | Seberang Perai SelatanPulau Pinang | 1,302 | 23 Sep 2027Extended 12 months from 23 Sep 20261st sale agreement 23 Sep 2023 | — | — |
Under construction (47) and not yet started (6) — first 12 by deadline
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| WELLINGTON GARDENKPKT 14505-7 | Kuala SelangorSelangor | 605 | SmoothOn schedule | 18 Nov 20261st sale agreement 18 Nov 2023 | 98% |
| RESIDENSI BOTANI 3KPKT 19985-7 | Johor BahruJohor | 112 | SmoothOn schedule | 21 Dec 20261st sale agreement 21 Dec 2023 | 98% |
| RESIDENSI BOTANI 3KPKT 19985-8 | Johor BahruJohor | 128 | SmoothOn schedule | 21 Jan 20271st sale agreement 21 Jan 2024 | 98% |
| LAMAN INDAH 3KPKT 6443-27 | Johor BahruJohor | 280 | SmoothOn schedule | 13 Jun 20271st sale agreement 13 Jun 2025 | 80% |
| ECO HORIZON 1KPKT 19152-9 | Seberang Perai SelatanPulau Pinang | 112 | SmoothOn schedule | 20 Jul 20271st sale agreement 20 Jul 2024 | 75% |
| RESIDENSI KOMERSIAL BOTANI SAYANGKPKT 14020-5 | Johor BahruJohor | 383 | SmoothOn schedule | 10 Oct 2027Extended 12 months from 10 Oct 20261st sale agreement 10 Oct 2023 | 98% |
| EKOFLORA 4KPKT 14320-19 | Johor BahruJohor | 132 | SmoothOn schedule | 27 Nov 20271st sale agreement 27 Nov 2024 | 72% |
| PRESINT 2KPKT 14020-6 | Johor BahruJohor | 76 | SmoothOn schedule | 30 Dec 20271st sale agreement 30 Dec 2024 | 72% |
| LAMAN INDAH 3KPKT 6443-28 | Johor BahruJohor | 282 | SmoothOn schedule | 3 Mar 20281st sale agreement 3 Mar 2026 | 50% |
| EKOFLORA 4KPKT 14320-20 | Johor BahruJohor | 32 | SmoothOn schedule | 7 Mar 20281st sale agreement 7 Mar 2025 | 72% |
| FLORA SANTAIKPKT 14320-18 | Johor BahruJohor | 460 | SmoothOn schedule | 8 Mar 2028Extended 12 months from 8 Mar 20271st sale agreement 8 Mar 2024 | 84% |
| FLORA DWIPUNCAK SANTAIKPKT 14320-17 | Johor BahruJohor | 460 | SmoothOn schedule | 11 Mar 2028Extended 12 months from 11 Mar 20271st sale agreement 11 Mar 2024 | 75% |
Show all 53 projects not yet completed
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| WELLINGTON GARDENKPKT 14505-7 | Kuala SelangorSelangor | 605 | SmoothOn schedule | 18 Nov 20261st sale agreement 18 Nov 2023 | 98% |
| RESIDENSI BOTANI 3KPKT 19985-7 | Johor BahruJohor | 112 | SmoothOn schedule | 21 Dec 20261st sale agreement 21 Dec 2023 | 98% |
| RESIDENSI BOTANI 3KPKT 19985-8 | Johor BahruJohor | 128 | SmoothOn schedule | 21 Jan 20271st sale agreement 21 Jan 2024 | 98% |
| LAMAN INDAH 3KPKT 6443-27 | Johor BahruJohor | 280 | SmoothOn schedule | 13 Jun 20271st sale agreement 13 Jun 2025 | 80% |
| ECO HORIZON 1KPKT 19152-9 | Seberang Perai SelatanPulau Pinang | 112 | SmoothOn schedule | 20 Jul 20271st sale agreement 20 Jul 2024 | 75% |
| RESIDENSI KOMERSIAL BOTANI SAYANGKPKT 14020-5 | Johor BahruJohor | 383 | SmoothOn schedule | 10 Oct 2027Extended 12 months from 10 Oct 20261st sale agreement 10 Oct 2023 | 98% |
| EKOFLORA 4KPKT 14320-19 | Johor BahruJohor | 132 | SmoothOn schedule | 27 Nov 20271st sale agreement 27 Nov 2024 | 72% |
| PRESINT 2KPKT 14020-6 | Johor BahruJohor | 76 | SmoothOn schedule | 30 Dec 20271st sale agreement 30 Dec 2024 | 72% |
| LAMAN INDAH 3KPKT 6443-28 | Johor BahruJohor | 282 | SmoothOn schedule | 3 Mar 20281st sale agreement 3 Mar 2026 | 50% |
| EKOFLORA 4KPKT 14320-20 | Johor BahruJohor | 32 | SmoothOn schedule | 7 Mar 20281st sale agreement 7 Mar 2025 | 72% |
| FLORA SANTAIKPKT 14320-18 | Johor BahruJohor | 460 | SmoothOn schedule | 8 Mar 2028Extended 12 months from 8 Mar 20271st sale agreement 8 Mar 2024 | 84% |
| FLORA DWIPUNCAK SANTAIKPKT 14320-17 | Johor BahruJohor | 460 | SmoothOn schedule | 11 Mar 2028Extended 12 months from 11 Mar 20271st sale agreement 11 Mar 2024 | 75% |
| ECO HORIZON 3KPKT 19152-12 | Pulau Pinang | 262 | SmoothOn schedule | 20 Mar 20281st sale agreement 20 Mar 2025 | 50% |
| EKOTROPIKA 10KPKT 6443-29 | Johor BahruJohor | 425 | SmoothOn schedule | 18 Apr 20281st sale agreement 18 Apr 2025 | 65–69% |
| RESIDENSI KOMERSIAL BOTANI SAYANG 2KPKT 19985-9 | Johor BahruJohor | 509 | SmoothOn schedule | 25 May 2028Extended 12 months from 25 May 20271st sale agreement 25 May 2024 | 88% |
| BIRCHPARKKPKT 19150-17Eco Forest Birchpark · on PropertySifu | Hulu LangatSelangor | 184 | SmoothOn schedule | 1 Aug 20281st sale agreement 1 Aug 2025 | 46–59% |
| BIRCHPARKKPKT 19150-18 | Hulu LangatSelangor | 128 | SmoothOn schedule | 2 Aug 20281st sale agreement 2 Aug 2025 | 50–56% |
| NOBLEGATEKPKT 19150-16 | Hulu LangatSelangor | 266 | SmoothOn schedule | 23 Aug 20281st sale agreement 23 Aug 2025 | 37–56% |
| PRESINT BOTANI 1KPKT 31135-1 | Johor | 721 | SmoothOn schedule | 8 Sep 20281st sale agreement 8 Sep 2025 | 36% |
| TAMAN ECO SUNKPKT 19152-13 | Pulau Pinang | 264 | SmoothOn schedule | 12 Sep 20281st sale agreement 12 Sep 2025 | 17% |
| EKOFLORA 2KPKT 14320-21 | Johor BahruJohor | 28 | SmoothOn schedule | 27 Oct 20281st sale agreement 27 Oct 2025 | 46% |
| EKOTROPIKA 10KPKT 6443-32 | Johor BahruJohor | 76 | SmoothOn schedule | 8 Nov 20281st sale agreement 8 Nov 2025 | 47% |
| EKOTROPIKA 10KPKT 6443-31 | Johor BahruJohor | 83 | SmoothOn schedule | 10 Nov 20281st sale agreement 10 Nov 2025 | 51% |
| EKOFLORA 2KPKT 14320-22 | Johor BahruJohor | 24 | SmoothOn schedule | 12 Nov 20281st sale agreement 12 Nov 2025 | 52% |
| EKOTROPIKA 10KPKT 6443-30 | Johor BahruJohor | 118 | SmoothOn schedule | 17 Nov 20281st sale agreement 17 Nov 2025 | 48% |
| SE.DUDUKKPKT 30561-1 | Hulu LangatSelangor | 1,220 | SmoothOn schedule | 7 Dec 2028Extended 12 months from 7 Dec 20271st sale agreement 7 Dec 2024 | 20–24% |
| PRESINT BOTANI 2KPKT 31135-2 | Johor | 125 | SmoothOn schedule | 3 Jan 20291st sale agreement 3 Jan 2026 | 14% |
| PRESINT BOTANI 2KPKT 31135-3 | Johor | 100 | SmoothOn schedule | 3 Jan 20291st sale agreement 3 Jan 2026 | 20% |
| PRESINT BOTANI 2KPKT 31135-4 | Johor | 115 | SmoothOn schedule | 3 Jan 20291st sale agreement 3 Jan 2026 | 13% |
| PRESINT BOTANI 2KPKT 31135-5 | Johor | 182 | SmoothOn schedule | 3 Jan 20291st sale agreement 3 Jan 2026 | 22% |
| PRESINT BOTANI 2KPKT 31135-6 | Johor | 119 | SmoothOn schedule | 3 Jan 20291st sale agreement 3 Jan 2026 | 24% |
| PRESINT BOTANI 2KPKT 31135-7 | Johor | 125 | SmoothOn schedule | 3 Jan 20291st sale agreement 3 Jan 2026 | 23% |
| TAMAN ECO SUNKPKT 19152-14 | Pulau Pinang | 264 | SmoothOn schedule | 1 Mar 20291st sale agreement 1 Mar 2026 | 6% |
| PRESINT 2KPKT 14020-7 | Johor | 24 | SmoothOn schedule | 9 May 20291st sale agreement 9 May 2026 | 20% |
| PRESINT 2KPKT 14020-8 | Johor | 24 | SmoothOn schedule | 9 May 20291st sale agreement 9 May 2026 | 20% |
| PRESINT 2KPKT 14020-9 | Johor | 16 | SmoothOn schedule | 10 May 20291st sale agreement 10 May 2026 | 12% |
| PRESINT 2KPKT 14020-10 | Johor | 7 | SmoothOn schedule | 26 May 20291st sale agreement 26 May 2026 | 9% |
| PRESINT 2KPKT 14020-12 | Johor | 24 | SmoothOn schedule | 15 Jun 20291st sale agreement 15 Jun 2026 | 20% |
| PRESINT 2KPKT 14020-14 | Johor | 8 | SmoothOn schedule | 15 Jun 20291st sale agreement 15 Jun 2026 | 12% |
| PRESINT 2KPKT 14020-13 | Johor | 16 | SmoothOn schedule | 20 Jun 20291st sale agreement 20 Jun 2026 | 12% |
| PRESINT 2KPKT 14020-11 | Johor | 24 | SmoothOn schedule | 25 Jun 20291st sale agreement 25 Jun 2026 | 20% |
| SE.RUMAKPKT 14050-10 | Kuala LangatSelangor | 483 | SmoothOn schedule | 13 Jul 2029Extended 12 months from 13 Jul 20281st sale agreement 13 Jul 2025 | 24% |
| MAYAKPKT 14504-8 | PetalingSelangor | 995 | SmoothOn schedule | 18 Oct 2029Extended 12 months from 18 Oct 20281st sale agreement 18 Oct 2025 | 25% |
| FLORA SANTAI TIGAKPKT 14320-23 | Johor BahruJohor | 627 | SmoothOn schedule | 31 Dec 2029Extended 12 months from 31 Dec 20281st sale agreement 31 Dec 2025 | 24% |
| RESIDENSI KOMERSIAL BOTANI SAYANG 3KPKT 19985-10 | Johor BahruJohor | 1,200 | SmoothOn schedule | 31 Dec 2029Extended 12 months from 31 Dec 20281st sale agreement 31 Dec 2025 | 20% |
| PANGSAPURI PERKHIDMATAN IRAMAKPKT 19152-15 | Pulau Pinang | 500 | SmoothOn schedule | 6 Jun 2030Extended 12 months from 6 Jun 20291st sale agreement 6 Jun 2026 | 5% |
| ECO MAJESTICKPKT 13544-11 | Hulu LangatSelangor | 33 | Not startedNot started | — | 0% |
| EKOFLORA 2KPKT 14320-24 | Johor BahruJohor | 30 | Not startedNot started | — | 0% |
| EKOFLORA 2KPKT 14320-25 | Johor BahruJohor | 42 | Not startedNot started | — | 0% |
| ECO HORIZONKPKT 13968-2 | Seberang Perai SelatanPulau Pinang | 235 | Not startedNot started | — | 0% |
| KOTA MASAIKPKT 6443-10 | Johor BahruJohor | 5,284 | SmoothOn schedule | — | 2–100% |
| EKOTROPIKA 9KPKT 6443-33 | Johor BahruJohor | 216 | Not startedNot started | — | 0% |
| EKOTROPIKA 9KPKT 6443-34 | Johor BahruJohor | 177 | Not startedNot started | — | 0% |
Permit cancelled or other KPKT status (5)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| ECO BOTANIC DEVELOPMENT SDN BHDKPKT 13165-3 | Johor BahruJohor | 184 | Permit cancelledPermit cancelled | — | 0% |
| ECO HORIZONKPKT 19152-3 | Seberang Perai SelatanPulau Pinang | 241 | Permit cancelledPermit cancelled | — | 0% |
| ECO MAJESTICKPKT 13544-9 | Hulu LangatSelangor | 128 | Permit cancelledPermit cancelled | — | 0% |
| ECO SANCTUARYKPKT 14050-5 | Kuala LangatSelangor | 164 | Permit cancelledPermit cancelled | — | 5% |
| ECO SUMMER SDN BHDKPKT 14320-3 | Johor BahruJohor | 92 | Permit cancelledPermit cancelled | — | 0% |
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
EcoWorld at a glance
| Listed | Bursa Malaysia Main Market · ECOWLD (8206) · named Focal Aims Holdings Berhad until 18 December 2013[1][5][3] |
|---|---|
| Started | Registered in 1974 (company no. 197401000725); took the EcoWorld name on 18 December 2013[1][3] |
| Head office | Menara EcoWorld, Bukit Bintang City Centre, Kuala Lumpur[1] |
| Leadership | Tan Sri Dato' Sri Liew Kee Sin — Executive Chairman[1] Dato' Chang Khim Wah — Executive Director, President and Chief Executive Officer[1] |
| Companies in the KPKT register | ECO TROPICS DEVELOPMENT SDN. BHD. KPKT 6443[1] ECO SUMMER SDN. BHD. KPKT 14320[1] ECO MAJESTIC DEVELOPMENT SDN. BHD. KPKT 19150[1] ECO BOTANIC SDN. BHD. KPKT 14020[1] ECO SANCTUARY SDN. BHD. KPKT 14050[1] MELIA SPRING SDN. BHD. KPKT 19985[1] ECO BOTANIC 3 SDN. BHD. KPKT 31135[1] PARAGON PINNACLE SDN. BHD. KPKT 14505[1] ECO TERRACES SDN. BHD. KPKT 30561[1] ECO MEADOWS SDN. BHD. KPKT 14518[1] FOCAL AIMS LAND SDN. BHD. KPKT 10192[1] ECO HORIZON SDN. BHD. (60%) KPKT 19152[1] ECO ARDENCE SDN. BHD. (50%) KPKT 14504[1] BBCC DEVELOPMENT SDN. BHD. (40%) KPKT 14510[1][4] ECO MAJESTIC SDN. BHD. KPKT 13544[1][2] ECO SPRINGS DEVELOPMENT SDN. BHD. KPKT 13518[1][2] ECO SKY DEVELOPMENT SDN. BHD. KPKT 13307[1][2] ECO BOTANIC DEVELOPMENT SDN. BHD. KPKT 13165[1][2] ECO MEADOWS DEVELOPMENT SDN. BHD. KPKT 14145[1][2] ECO TERRACES DEVELOPMENT SDN. BHD. KPKT 13968[1][2] |
| Website | ecoworld.my |
| Land bank (company figure) | 11,021 acres in total, 4,365 acres of it undeveloped (financial year to 31 October 2025)[1] |
| Where it builds (company figure) | Klang Valley, Iskandar Malaysia in Johor and Penang; its first Negeri Sembilan project, Eco Business Park VII, was launched in November 2025[1] |
| Units completed in FY2025 (company figure) | 4,331 units[1] |
| Joint ventures in the KPKT table | Eco Horizon Sdn Bhd 60%, Eco Ardence Sdn Bhd 50%, BBCC Development Sdn Bhd 40% (UDA Holdings 40%, EPF 20%)[1][4] |
EcoWorld projects on sale on PropertySifu
Eco Forest Birchpark
- ECO FOREST — 0.4 km, 2023
- ECO FOREST — 0.4 km, 2023
- ECO FOREST — 0.6 km, 2023
Who is EcoWorld? The company behind the projects
EcoWorld's listed company was previously Focal Aims Holdings Berhad, a Johor developer whose flagship was Kota Masai, a 2,484-acre township in Iskandar Malaysia [3]; its registration number dates from 1974 [1]. A takeover offer by Eco World Development Holdings Sdn Bhd and Liew Tian Xiong closed on 12 November 2013 with the offerors holding about 65%, and the company took its present name on 18 December 2013 [3]. In April 2014 it announced it would buy the development rights to eight projects from subsidiaries of its major shareholder [2]. Six companies in the table above are not in the 2025 annual report's list of subsidiaries, such as Eco Majestic Sdn Bhd and Eco Sky Development Sdn Bhd; they are included because KPKT registers phases of EcoWorld projects such as Eco Majestic, Eco Sky and Eco Botanic under them.
The company says its land bank totalled 11,021 acres in the financial year to 31 October 2025, with 4,365 acres undeveloped, across the Klang Valley, Iskandar Malaysia and Penang; its first Negeri Sembilan project, Eco Business Park VII, was launched in November 2025 [1]. It reports 4,331 units completed in that year [1]. These are group-wide figures; the KPKT register covers only projects licensed as housing, so its business parks are not in the table above.
Most EcoWorld projects are developed by wholly owned subsidiaries. Three companies in the table are joint ventures: EcoWorld holds 60% of Eco Horizon Sdn Bhd (Eco Horizon and Eco Sun in Penang), 50% of Eco Ardence Sdn Bhd (Eco Ardence in Selangor) and 40% of BBCC Development Sdn Bhd (Bukit Bintang City Centre in Kuala Lumpur) [1]. In BBCC, UDA Holdings also holds 40% and the EPF 20%, and UDA remains the landowner [4]. Paragon Pinnacle Sdn Bhd, the developer of Eco Grandeur, became wholly owned on 18 February 2025, when EcoWorld bought the remaining 40% from an EPF subsidiary [1].
Eco World International Berhad, set up in 2013 to focus on projects outside Malaysia, is a separate listed company; it was renamed EWI Capital Berhad in July 2025 and is turning to the Malaysian market [5]. EcoWorld held 29% of it but has not treated it as an associate since 30 April 2025 [1], and EWI's projects are not counted on this page. Eco Forest Birchpark in Semenyih, listed on PropertySifu, is developed by the wholly owned Eco Majestic Development Sdn Bhd [1]. The executive chairman is Tan Sri Dato' Sri Liew Kee Sin, president and chief executive officer of S P Setia from 1996 to 2014, and the president and chief executive officer is Dato' Chang Khim Wah [1].
Frequently asked questions
Is EcoWorld a listed company?
How many housing projects has EcoWorld completed?
In the KPKT register, 116 of the 174 housing projects under 20 EcoWorld companies and joint ventures are completed. Of the 111 completed projects that have both a deadline and a completion date in the register, 41 were handed over on or before the deadline set by the first sale agreement (where KPKT approved an extension, the extended deadline is used), 14 were handed over or certified complete after that deadline, and 56 received the completion certificate before the deadline, with no handover date recorded. The company says it completed 4,331 units in the financial year to 31 October 2025 [1].
Does EcoWorld have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the 174 EcoWorld projects as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). The 47 projects under construction are on schedule (Lancar); 6 have not started (Belum Mula), and 5 — 13165-3, 13544-9, 14050-5, 14320-3 and 19152-3 — have the status Permit Telah Dibatalkan (permit cancelled).
Which company develops Eco Forest Birchpark, and when is its handover deadline?
Eco Majestic Development Sdn Bhd (KPKT developer code 19150), a wholly owned EcoWorld subsidiary [1]. KPKT registers the project as 19150-17: 184 two-storey terrace houses and town houses, with the first sale agreement signed on 1 August 2025 and a handover deadline of 1 August 2028; no extension is registered. It is recorded as on schedule (Lancar), with reported construction progress of 46% to 59% across its five components.
Is Eco World International part of EcoWorld?
No. Eco World International Berhad, set up in 2013 to focus on projects outside Malaysia, is a separate listed company; it was renamed EWI Capital Berhad in July 2025 and is turning to the Malaysian market [5]. EcoWorld held 29% of it, but since 30 April 2025 it no longer treats EWI as an associate, and the agreement that kept EcoWorld's overseas projects within EWI and EWI out of Malaysia has been ended [1]. None of EWI's projects are counted on this page.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] Eco World Development Group Berhad Integrated Annual Report 2025 · Eco World Development Group Berhad · 12 Feb 2026 · accessed 28 Oct 2026
https://ecoworld.my/wp-content/uploads/2026/02/Eco-World-Integrated-Annual-Report-2025.pdf - [2] #Highlight* Eco World announces major corporate exercise to immediately turn it into top property player · The Edge Malaysia · 25 Apr 2014 · accessed 28 Oct 2026
https://theedgemalaysia.com/article/highlight-eco-world-announces-major-corporate-exercise-turn-it-huge-property-player - [3] Eco World Development Group Berhad (formerly Focal Aims Holdings Berhad) Annual Report 2013 · Eco World Development Group Berhad · accessed 28 Oct 2026
https://ecoworld.my/wp-content/uploads/2021/12/ar2013.pdf - [4] UDA to receive RM1 billion development rights from BBCC project · Eco World Development Group Berhad · 5 Feb 2015 · accessed 28 Oct 2026
https://ecoworld.my/news/uda-to-receive-rm1-billion-development-rights-from-bbcc-project/ - [5] Eco World International is now EWI Capital Bhd; stock short name is EWICAP from July 7 · The Edge Malaysia · 3 Jul 2025 · accessed 28 Oct 2026
https://theedgemalaysia.com/node/761268
Last updated 28 Oct 2026