Biz Link Group
Biz Link Group is a private Kuala Lumpur developer with five housing projects in the KPKT register under three Biz Link companies: four completed (two phases each of Prima Utama and Koi Park Residences, in Hulu Selangor) and one under construction, Residensi Alam Impian in Kota Warisan, Sepang, none classed Sick or Abandoned. It says it started in 2016.
- 5 projects in the KPKT register
- 4 completed
- 1 under construction
- None Sick or Abandoned
Has Biz Link Group handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 5 housing projects under 3 Biz Link Group companies in 1 state: 4 completed, 1 under construction. None is classed Sick (Sakit) or Abandoned (Terbengkalai).
Of the 4 completed projects, 4 have both a handover deadline and a completion date in the register: 1 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 3 handed over or certified complete after that deadline (2 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†).
2 projects had the delivery period extended with KPKT approval.
Completed projects — most recent first
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| KOI PARK RESIDENCES@ANTARA GAPIKPKT 19952-2 | Hulu SelangorSelangor | 67 | 18 Dec 20251st sale agreement 18 Dec 2023 | CCC 9 Sep 2025 Handover 9 Sep 2025 | 100 days before |
| KOI PARK RESIDENCES@ANTARA GAPIKPKT 19952-1 | Hulu SelangorSelangor | 73 | 25 Jun 2023Extended 10 months from 25 Aug 20221st sale agreement 25 Aug 2020 | CCC 9 Nov 2023 Handover 9 Nov 2023 | 137 days after † |
| PRIMA UTAMA @ RAWANG NORTHKPKT 14687-2 | Hulu SelangorSelangor | 35 | 18 Oct 2022Extended 11 months from 18 Nov 20211st sale agreement 18 Nov 2019 | CCC 23 Nov 2022 Handover 23 Nov 2022 | 36 days after † |
| PRIMA UTAMA @ RAWANG NORTHKPKT 14687-1 | Hulu SelangorSelangor | 30 | 17 Jul 20191st sale agreement 17 Jul 2017 | CCC 10 Sep 2019 | 55 days after |
Under construction
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| RESIDENSI ALAM IMPIANKPKT 30381-1Residensi Alam Impian · on PropertySifu | SepangSelangor | 96 | SmoothOn schedule | 11 Mar 20271st sale agreement 11 Mar 2024 | 94% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
Biz Link Group at a glance
| Listed | Not listed — the Biz Link developer companies are private limited companies (Sdn Bhd) |
|---|---|
| Started | 2016, when the group says it began property development[1] |
| Head office | Bandar Baru Seri Petaling, Kuala Lumpur[1] |
| Leadership | P.H. Lee — Managing Director and founder[3] |
| Companies in the KPKT register | BIZ LINK LAND SDN. BHD. KPKT 30381[2] BIZ LINK PROPERTY SDN. BHD. KPKT 19952[2] BIZ LINK DEVELOPMENT SDN. BHD. KPKT 14687[2] |
| Website | bizlinkgroup.com.my |
| Early projects (company figures) | Prima Utama Phase 1, gross development value RM17 million; Phase 2, RM28 million; Koi Park Residence Phase 1, RM40 million[1] |
| Where it builds | Batang Kali (Rawang North) and Serendah in Hulu Selangor; Kota Warisan in Sepang[2] |
| Other businesses | Property management and sales and marketing; Biz Link United Sdn Bhd, formed in 2021, provides sales and marketing services[1] |
Biz Link Group projects on sale on PropertySifu
Who is Biz Link Group? The company behind the projects
Biz Link Group says it began property development in 2016; the name joins "Biz" (business) and "Link" (connection) [1]. Its first land was in Rawang North, where it launched Prima Utama; the company puts the gross development value at RM17 million for Phase 1, RM28 million for Phase 2 and RM40 million for Koi Park Residence Phase 1 [1]. Its founder and managing director, P.H. Lee, has been in the property industry since 2011, according to the company [3]. The office is in Bandar Baru Seri Petaling, Kuala Lumpur [1]. No stock-exchange listing was found.
The group's website lists Prima Utama 1 and 2 in Batang Kali (Rawang North) and Koi Park Residences phases 1 and 2 in Antara Gapi, Serendah, as completed, and Residensi Alam Impian in Kota Warisan as ongoing [2]. In the KPKT register they sit under three companies: Biz Link Development Sdn Bhd (PRIMA UTAMA @ RAWANG NORTH, 14687-1 and 14687-2), Biz Link Property Sdn Bhd (KOI PARK RESIDENCES@ANTARA GAPI, 19952-1 and 19952-2) and Biz Link Land Sdn Bhd (RESIDENSI ALAM IMPIAN, 30381-1). The Prima Utama shop offices are commercial and are not in the KPKT housing register.
Besides development, the group has moved into property management and sales and marketing; in 2021 it formed Biz Link United Sdn Bhd to provide sales and marketing services [1].
Frequently asked questions
Is Biz Link a listed company?
No stock-exchange listing was found. Each Biz Link project is developed through its own private company; in the KPKT register, Residensi Alam Impian is under Biz Link Land Sdn Bhd, Koi Park Residences under Biz Link Property Sdn Bhd and Prima Utama under Biz Link Development Sdn Bhd. The group's website lists all three projects as its own [2].
What does KPKT show for Residensi Alam Impian?
KPKT registers it in Sepang district under Biz Link Land Sdn Bhd (30381-1): 96 units, first sale agreement 11 March 2024, handover deadline 11 March 2027, with no extension recorded. It is on schedule (Lancar), with reported progress of 93.75%.
Were Koi Park Residences and Prima Utama handed over on time?
One of the four was handed over before its deadline. Koi Park Residences phase 1 (19952-1, 73 houses): first sale agreement 25 August 2020, deadline 25 August 2022 extended with approval by 10 months to 25 June 2023; CCC and handover on 9 November 2023, 137 days after the extended deadline. Phase 2 (19952-2, 67 houses): handover on 9 September 2025, 100 days before its 18 December 2025 deadline. Prima Utama (14687-1, 30 houses): CCC on 10 September 2019, 55 days after the 17 July 2019 deadline; the handover date is not recorded. Prima Utama 2 (14687-2, 35 houses): deadline 18 November 2021 extended by 11 months to 18 October 2022; CCC and handover on 23 November 2022, 36 days after the extended deadline. Construction of 19952-1 and 14687-2 ran through 18 March–31 August 2020, a period that section 35 of the COVID-19 Act (Act 829) excludes from handover deadlines; the register does not show whether their deadlines already reflect it.
Does Biz Link have any Sick or Abandoned projects?
No. As at 27 October 2026, the KPKT register classes none of the five projects under the three Biz Link companies as Sick (Sakit), Abandoned (Terbengkalai) or Late (Lewat). Four are completed; Residensi Alam Impian is under construction and on schedule (Lancar).
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] About Biz Link Group — home page · Biz Link Group · accessed 28 Oct 2026
https://bizlinkgroup.com.my/ - [2] Our Businesses — completed, ongoing and future projects · Biz Link Group · accessed 28 Oct 2026
https://bizlinkgroup.com.my/our-businesses/ - [3] Our Company — mission, vision and managing director · Biz Link Group · accessed 28 Oct 2026
https://bizlinkgroup.com.my/our-company/
Last updated 28 Oct 2026