BCB (BCB Berhad)
BCB Berhad is a Bursa Malaysia-listed property developer based in Kluang, Johor, with 92 housing projects in the KPKT register under seven group companies: 80 completed, 8 under construction (1 of them classed Sick), 3 not yet started and 1 whose permit was cancelled; none is classed Abandoned. Most of them are in Batu Pahat, Johor.
- 92 projects in the KPKT register
- 80 completed
- 8 under construction (of which 1 Sick)
- 3 not yet started
- 1 with the permit cancelled
Has BCB handed over on time? What the KPKT register shows
KPKT's TEDUH register (as at 27 Oct 2026) lists 92 housing projects under 7 BCB companies in 4 states: 80 completed, 8 under construction (of which 1 Sick), 3 not yet started, 1 with the permit cancelled.
Of the 80 completed projects, 59 have both a handover deadline and a completion date in the register: 13 handed over on or before the deadline (the extended deadline where KPKT approved an extension); 23 handed over or certified complete after that deadline (1 of these were under construction during the 18 Mar–31 Aug 2020 movement control period, which the law excludes from the deadline†); 23 received the completion certificate before the deadline (handover date not recorded).
1 project had the delivery period extended with KPKT approval.
Completed projects — the 12 most recent of 80
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR PUTERA INDAHKPKT 7430-29 | Batu PahatJohor | 47 | 13 Feb 20261st sale agreement 13 Feb 2024 | CCC 18 Jun 2026 Handover 19 Jun 2026 | 126 days after |
| TAMAN BUKIT PERDANA IIKPKT 4441-70 | Batu PahatJohor | 96 | 2 Nov 20261st sale agreement 2 Nov 2023 | CFO 3 Feb 2026 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-28 | Batu PahatJohor | 79 | 15 Mar 20261st sale agreement 15 Mar 2024 | CCC 30 Jan 2026 | CCC before deadline; handover not recorded |
| BROADLEAF (ALAM KEMUNING)KPKT 13053-6 | KlangSelangor | 28 | 9 Aug 20271st sale agreement 9 Aug 2024 | CCC 21 Aug 2025 Handover 21 Aug 2025 | 718 days before |
| BANDAR PUTERA INDAHKPKT 7430-27 | Batu PahatJohor | 39 | 22 Nov 20251st sale agreement 22 Nov 2023 | CCC 14 Jul 2025 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-24 | Batu PahatJohor | 74 | 30 Jun 20251st sale agreement 30 Jun 2023 | CCC 21 May 2025 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-25 | Batu PahatJohor | 48 | 29 May 20251st sale agreement 29 May 2023 | CCC 16 Jan 2025 Handover 20 Mar 2025 | 70 days before |
| BANDAR PUTERA INDAHKPKT 7430-26 | Batu PahatJohor | 120 | 23 Jun 20251st sale agreement 23 Jun 2023 | CCC 22 Jan 2025 Handover 20 Mar 2025 | 95 days before |
| BANDAR PUTERA INDAHKPKT 7430-21 | Batu PahatJohor | 75 | 18 Nov 20241st sale agreement 18 Nov 2022 | CCC 19 Aug 2024 Handover 30 Oct 2024 | 19 days before |
| BROAD LEAF(PHASE 2)KPKT 13053-5 | KlangSelangor | 42 | 3 Mar 20261st sale agreement 3 Mar 2023 | CCC 29 Aug 2024 Handover 23 Sep 2024 | 526 days before |
| BANDAR PUTERA INDAHKPKT 7430-23 | Batu PahatJohor | 24 | 12 Dec 20241st sale agreement 12 Dec 2022 | CCC 24 Jun 2024 Handover 22 Jul 2024 | 143 days before |
| TAMAN EVERGREEN HEIGTSKPKT 8528-19 | Batu PahatJohor | 55 | — | CCC 22 Jan 2024 | — |
Handed over or certified complete after the deadline — 12 most recent of 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR PUTERA INDAHKPKT 7430-29 | Batu PahatJohor | 47 | 13 Feb 20261st sale agreement 13 Feb 2024 | CCC 18 Jun 2026 Handover 19 Jun 2026 | 126 days after |
| BANDAR PUTERA INDAHKPKT 7430-11 | Batu PahatJohor | 63 | 12 May 20211st sale agreement 12 May 2019 | CCC 3 May 2021 Handover 25 Oct 2021 | 166 days after † |
| THE ELYSIA PARK RESIDENCEKPKT 13996-1 | Johor BahruJohor | 987 | 13 Jun 20181st sale agreement 13 Jun 2015 | CCC 28 Nov 2019 | 533 days after |
| TAMAN BUKIT PERDANA 2KPKT 4441-69 | Batu PahatJohor | 20 | 17 Aug 20191st sale agreement 17 Aug 2017 | CCC 10 Nov 2019 Handover 18 Nov 2019 | 93 days after |
| EVERGREEN HEIGHTSKPKT 8528-13 | Batu PahatJohor | 79 | 30 Jul 20181st sale agreement 30 Jul 2016 | CCC 15 Sep 2019 | 412 days after |
| EVERGREEN HEIGHTSKPKT 8528-11 | Batu PahatJohor | 76 | 23 Feb 20161st sale agreement 23 Feb 2014 | CCC 20 Aug 2019 | 1,274 days after |
| TAMAN SRI KLUANGKPKT 4441-68 | KluangJohor | 8 | 25 Feb 20181st sale agreement 25 Feb 2016 | CCC 3 Jun 2019 | 463 days after |
| BANDAR PUTERA INDAHKPKT 7430-10 | Batu PahatJohor | 85 | 25 Oct 20181st sale agreement 25 Oct 2016 | CCC 4 Apr 2019 | 161 days after |
| BANDAR PUTERA INDAHKPKT 7430-8 | Batu PahatJohor | 92 | 30 Aug 20171st sale agreement 30 Aug 2015 | CCC 31 Jan 2019 | 519 days after |
| BANDAR PUTERA INDAHKPKT 7430-12 | Batu PahatJohor | 55 | 9 Oct 20181st sale agreement 9 Oct 2016 | CCC 25 Nov 2018 | 47 days after |
| BANDAR PUTERA INDAHKPKT 7430-7 | Batu PahatJohor | 503 | 6 Jun 20141st sale agreement 6 Jun 2012 | CCC 25 Nov 2018 | 1,633 days after |
| TAMAN BUKIT PERDANA II FASA 1KPKT 4441-26 | Batu PahatJohor | 599 | 8 May 20101st sale agreement 8 May 2007 | CCC 26 Aug 2018 Handover 13 Apr 2000 / 24 Oct 2000 / 12 Jun 2009 / 14 Sep 2018 | 3,051 days after |
Show all 23
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR PUTERA INDAHKPKT 7430-29 | Batu PahatJohor | 47 | 13 Feb 20261st sale agreement 13 Feb 2024 | CCC 18 Jun 2026 Handover 19 Jun 2026 | 126 days after |
| BANDAR PUTERA INDAHKPKT 7430-11 | Batu PahatJohor | 63 | 12 May 20211st sale agreement 12 May 2019 | CCC 3 May 2021 Handover 25 Oct 2021 | 166 days after † |
| THE ELYSIA PARK RESIDENCEKPKT 13996-1 | Johor BahruJohor | 987 | 13 Jun 20181st sale agreement 13 Jun 2015 | CCC 28 Nov 2019 | 533 days after |
| TAMAN BUKIT PERDANA 2KPKT 4441-69 | Batu PahatJohor | 20 | 17 Aug 20191st sale agreement 17 Aug 2017 | CCC 10 Nov 2019 Handover 18 Nov 2019 | 93 days after |
| EVERGREEN HEIGHTSKPKT 8528-13 | Batu PahatJohor | 79 | 30 Jul 20181st sale agreement 30 Jul 2016 | CCC 15 Sep 2019 | 412 days after |
| EVERGREEN HEIGHTSKPKT 8528-11 | Batu PahatJohor | 76 | 23 Feb 20161st sale agreement 23 Feb 2014 | CCC 20 Aug 2019 | 1,274 days after |
| TAMAN SRI KLUANGKPKT 4441-68 | KluangJohor | 8 | 25 Feb 20181st sale agreement 25 Feb 2016 | CCC 3 Jun 2019 | 463 days after |
| BANDAR PUTERA INDAHKPKT 7430-10 | Batu PahatJohor | 85 | 25 Oct 20181st sale agreement 25 Oct 2016 | CCC 4 Apr 2019 | 161 days after |
| BANDAR PUTERA INDAHKPKT 7430-8 | Batu PahatJohor | 92 | 30 Aug 20171st sale agreement 30 Aug 2015 | CCC 31 Jan 2019 | 519 days after |
| BANDAR PUTERA INDAHKPKT 7430-12 | Batu PahatJohor | 55 | 9 Oct 20181st sale agreement 9 Oct 2016 | CCC 25 Nov 2018 | 47 days after |
| BANDAR PUTERA INDAHKPKT 7430-7 | Batu PahatJohor | 503 | 6 Jun 20141st sale agreement 6 Jun 2012 | CCC 25 Nov 2018 | 1,633 days after |
| TAMAN BUKIT PERDANA II FASA 1KPKT 4441-26 | Batu PahatJohor | 599 | 8 May 20101st sale agreement 8 May 2007 | CCC 26 Aug 2018 Handover 13 Apr 2000 / 24 Oct 2000 / 12 Jun 2009 / 14 Sep 2018 | 3,051 days after |
| TAMAN SRI KLUANG FASA 1JKPKT 4441-43 | KluangJohor | 548 | 22 Dec 20041st sale agreement 22 Dec 2002 | CFO 24 Jun 2018 | 4,932 days after |
| EVERGREEN HEIGHTSKPKT 8528-12 | Batu PahatJohor | 64 | 26 Sep 20171st sale agreement 26 Sep 2015 | CCC 16 Nov 2017 | 51 days after |
| BANDAR PUTERA INDAHKPKT 7430-9 | Batu PahatJohor | 99 | 16 Aug 20171st sale agreement 16 Aug 2015 | CCC 16 Nov 2017 | 92 days after |
| EVERGREEN HEIGHTSKPKT 8528-8 | Batu PahatJohor | 234 | 6 May 20141st sale agreement 6 May 2012 | CCC 26 Jul 2017 | 1,177 days after |
| TAMAN BUKIT PERDANA 2KPKT 7430-2 | Batu PahatJohor | 279 | 12 Jan 20081st sale agreement 12 Jan 2006 | CCC 10 Jul 2017 | 3,467 days after |
| TAMAN BUKIT PERDANA 2KPKT 7430-6 | Batu PahatJohor | 12 | 23 May 20131st sale agreement 23 May 2011 | CCC 10 Jul 2017 | 1,509 days after |
| TAMAN PULAI UTAMAKPKT 7360-2 | Johor BahruJohor | 244 | 3 Sep 20161st sale agreement 3 Sep 2014 | CCC 20 Jun 2017 | 290 days after |
| TAMAN SRI KLUANGKPKT 4441-41 | KluangJohor | 300 | 11 Nov 20011st sale agreement 11 Nov 1999 | CCC 27 Oct 2016 | 5,464 days after |
| TAMAN MEGAHKPKT 4441-67 | PontianJohor | 79 | 11 Oct 20151st sale agreement 11 Oct 2013 | CCC 1 Sep 2016 | 326 days after |
| EVERGREEN HEIGHTSKPKT 8528-7 | Batu PahatJohor | 559 | 31 Dec 20121st sale agreement 31 Dec 2010 | CCC 1 Feb 2016 | 1,127 days after |
| EVERGREEN HEIGHTS FASA 2KPKT 8528-2 | Batu PahatJohor | 78 | 15 Apr 20031st sale agreement 15 Apr 2001 | CFO 27 Nov 2006 | 1,322 days after |
Show all 80 completed projects
| Project (KPKT name) | Area | Units | Handover deadline | CCC / handover | Against deadline |
|---|---|---|---|---|---|
| BANDAR PUTERA INDAHKPKT 7430-29 | Batu PahatJohor | 47 | 13 Feb 20261st sale agreement 13 Feb 2024 | CCC 18 Jun 2026 Handover 19 Jun 2026 | 126 days after |
| TAMAN BUKIT PERDANA IIKPKT 4441-70 | Batu PahatJohor | 96 | 2 Nov 20261st sale agreement 2 Nov 2023 | CFO 3 Feb 2026 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-28 | Batu PahatJohor | 79 | 15 Mar 20261st sale agreement 15 Mar 2024 | CCC 30 Jan 2026 | CCC before deadline; handover not recorded |
| BROADLEAF (ALAM KEMUNING)KPKT 13053-6 | KlangSelangor | 28 | 9 Aug 20271st sale agreement 9 Aug 2024 | CCC 21 Aug 2025 Handover 21 Aug 2025 | 718 days before |
| BANDAR PUTERA INDAHKPKT 7430-27 | Batu PahatJohor | 39 | 22 Nov 20251st sale agreement 22 Nov 2023 | CCC 14 Jul 2025 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-24 | Batu PahatJohor | 74 | 30 Jun 20251st sale agreement 30 Jun 2023 | CCC 21 May 2025 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-25 | Batu PahatJohor | 48 | 29 May 20251st sale agreement 29 May 2023 | CCC 16 Jan 2025 Handover 20 Mar 2025 | 70 days before |
| BANDAR PUTERA INDAHKPKT 7430-26 | Batu PahatJohor | 120 | 23 Jun 20251st sale agreement 23 Jun 2023 | CCC 22 Jan 2025 Handover 20 Mar 2025 | 95 days before |
| BANDAR PUTERA INDAHKPKT 7430-21 | Batu PahatJohor | 75 | 18 Nov 20241st sale agreement 18 Nov 2022 | CCC 19 Aug 2024 Handover 30 Oct 2024 | 19 days before |
| BROAD LEAF(PHASE 2)KPKT 13053-5 | KlangSelangor | 42 | 3 Mar 20261st sale agreement 3 Mar 2023 | CCC 29 Aug 2024 Handover 23 Sep 2024 | 526 days before |
| BANDAR PUTERA INDAHKPKT 7430-23 | Batu PahatJohor | 24 | 12 Dec 20241st sale agreement 12 Dec 2022 | CCC 24 Jun 2024 Handover 22 Jul 2024 | 143 days before |
| TAMAN EVERGREEN HEIGTSKPKT 8528-19 | Batu PahatJohor | 55 | — | CCC 22 Jan 2024 | — |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-20 | Batu PahatJohor | 9 | 12 Jan 20251st sale agreement 12 Jan 2023 | CCC 22 Jan 2024 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-22 | Batu PahatJohor | 40 | 16 Nov 20241st sale agreement 16 Nov 2022 | CCC 6 Dec 2023 | CCC before deadline; handover not recorded |
| KOTA KEMUNINGKPKT 13053-4 | KlangSelangor | 66 | 28 May 20241st sale agreement 28 May 2021 | CCC 17 Aug 2023 Handover 22 Aug 2023 | 280 days before |
| BANDAR PUTERA INDAHKPKT 7430-20 | Batu PahatJohor | 36 | 26 Jul 20231st sale agreement 26 Jul 2021 | CCC 16 Feb 2023 Handover 16 Mar 2023 | 132 days before |
| BANDAR PUTERA INDAHKPKT 7430-19 | Batu PahatJohor | 65 | 5 Jul 20231st sale agreement 5 Jul 2021 | CCC 1 Jan 2023 Handover 23 Feb 2023 | 132 days before |
| TAMAN EVERGREENKPKT 8528-17 | Batu PahatJohor | 27 | 20 Feb 20231st sale agreement 20 Feb 2021 | CCC 8 Feb 2023 Handover 14 Feb 2023 | 6 days before |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-18 | Batu PahatJohor | 52 | 11 Jan 20231st sale agreement 11 Jan 2021 | CCC 4 Dec 2022 Handover 2 Jan 2023 / 3 Jan 2023 | 8 days before |
| TAMAN PUTERA INDAHKPKT 7430-18 | Batu PahatJohor | 59 | 25 Sep 20221st sale agreement 25 Sep 2020 | CCC 25 Jan 2022 | CCC before deadline; handover not recorded |
| KOTA KEMUNINGKPKT 13053-3 | KlangSelangor | 46 | 6 Apr 20241st sale agreement 6 Apr 2021 | CCC 15 Nov 2021 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-11 | Batu PahatJohor | 63 | 12 May 20211st sale agreement 12 May 2019 | CCC 3 May 2021 Handover 25 Oct 2021 | 166 days after † |
| BANDAR PUTERA INDAHKPKT 7430-17 | Batu PahatJohor | 67 | 7 Nov 20211st sale agreement 7 Nov 2019 | CCC 2 Feb 2021 | CCC before deadline; handover not recorded |
| ALAM KEMUNINGKPKT 13053-2 | KlangSelangor | 113 | 15 Dec 2021Extended 12 months from 15 Dec 20201st sale agreement 15 Dec 2017 | CCC 20 Oct 2020 | CCC before deadline; handover not recorded |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-16 | Batu PahatJohor | 50 | 19 Sep 20211st sale agreement 19 Sep 2019 | CCC 23 Aug 2020 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-16 | Batu PahatJohor | 78 | 26 Nov 20201st sale agreement 26 Nov 2018 | CCC 30 Jun 2020 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-14 | Batu PahatJohor | 27 | 6 May 20201st sale agreement 6 May 2018 | CCC 20 Apr 2020 | CCC before deadline; handover not recorded |
| THE ELYSIA PARK RESIDENCEKPKT 13996-1 | Johor BahruJohor | 987 | 13 Jun 20181st sale agreement 13 Jun 2015 | CCC 28 Nov 2019 | 533 days after |
| TAMAN BUKIT PERDANA 2KPKT 4441-69 | Batu PahatJohor | 20 | 17 Aug 20191st sale agreement 17 Aug 2017 | CCC 10 Nov 2019 Handover 18 Nov 2019 | 93 days after |
| BANDAR PUTERA INDAHKPKT 7430-15 | Batu PahatJohor | 66 | 31 Dec 20191st sale agreement 31 Dec 2017 | CCC 13 Oct 2019 | CCC before deadline; handover not recorded |
| EVERGREEN HEIGHTSKPKT 8528-13 | Batu PahatJohor | 79 | 30 Jul 20181st sale agreement 30 Jul 2016 | CCC 15 Sep 2019 | 412 days after |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-15 | Batu PahatJohor | 10 | 6 Jan 20201st sale agreement 6 Jan 2018 | CCC 15 Sep 2019 | CCC before deadline; handover not recorded |
| EVERGREEN HEIGHTSKPKT 8528-11 | Batu PahatJohor | 76 | 23 Feb 20161st sale agreement 23 Feb 2014 | CCC 20 Aug 2019 | 1,274 days after |
| TAMAN SRI KLUANGKPKT 4441-68 | KluangJohor | 8 | 25 Feb 20181st sale agreement 25 Feb 2016 | CCC 3 Jun 2019 | 463 days after |
| BANDAR PUTERA INDAHKPKT 7430-10 | Batu PahatJohor | 85 | 25 Oct 20181st sale agreement 25 Oct 2016 | CCC 4 Apr 2019 | 161 days after |
| BANDAR PUTERA INDAHKPKT 7430-8 | Batu PahatJohor | 92 | 30 Aug 20171st sale agreement 30 Aug 2015 | CCC 31 Jan 2019 | 519 days after |
| BANDAR PUTERA INDAHKPKT 7430-12 | Batu PahatJohor | 55 | 9 Oct 20181st sale agreement 9 Oct 2016 | CCC 25 Nov 2018 | 47 days after |
| BANDAR PUTERA INDAHKPKT 7430-13 | Batu PahatJohor | 58 | 16 Apr 20191st sale agreement 16 Apr 2017 | CCC 25 Nov 2018 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-7 | Batu PahatJohor | 503 | 6 Jun 20141st sale agreement 6 Jun 2012 | CCC 25 Nov 2018 | 1,633 days after |
| TAMAN BUKIT PERDANA II FASA 1KPKT 4441-26 | Batu PahatJohor | 599 | 8 May 20101st sale agreement 8 May 2007 | CCC 26 Aug 2018 Handover 13 Apr 2000 / 24 Oct 2000 / 12 Jun 2009 / 14 Sep 2018 | 3,051 days after |
| TAMAN SRI KLUANG FASA 1JKPKT 4441-43 | KluangJohor | 548 | 22 Dec 20041st sale agreement 22 Dec 2002 | CFO 24 Jun 2018 | 4,932 days after |
| EVERGREEN HEIGHTSKPKT 8528-12 | Batu PahatJohor | 64 | 26 Sep 20171st sale agreement 26 Sep 2015 | CCC 16 Nov 2017 | 51 days after |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-14 | Batu PahatJohor | 8 | 28 Feb 20191st sale agreement 28 Feb 2017 | CCC 16 Nov 2017 | CCC before deadline; handover not recorded |
| BANDAR PUTERA INDAHKPKT 7430-9 | Batu PahatJohor | 99 | 16 Aug 20171st sale agreement 16 Aug 2015 | CCC 16 Nov 2017 | 92 days after |
| EVERGREEN HEIGHTSKPKT 8528-8 | Batu PahatJohor | 234 | 6 May 20141st sale agreement 6 May 2012 | CCC 26 Jul 2017 | 1,177 days after |
| TAMAN BUKIT PERDANA 2KPKT 7430-2 | Batu PahatJohor | 279 | 12 Jan 20081st sale agreement 12 Jan 2006 | CCC 10 Jul 2017 | 3,467 days after |
| TAMAN BUKIT PERDANA 2KPKT 7430-6 | Batu PahatJohor | 12 | 23 May 20131st sale agreement 23 May 2011 | CCC 10 Jul 2017 | 1,509 days after |
| TAMAN PULAI UTAMAKPKT 7360-2 | Johor BahruJohor | 244 | 3 Sep 20161st sale agreement 3 Sep 2014 | CCC 20 Jun 2017 | 290 days after |
| TAMAN SRI KLUANGKPKT 4441-41 | KluangJohor | 300 | 11 Nov 20011st sale agreement 11 Nov 1999 | CCC 27 Oct 2016 | 5,464 days after |
| TAMAN MEGAHKPKT 4441-67 | PontianJohor | 79 | 11 Oct 20151st sale agreement 11 Oct 2013 | CCC 1 Sep 2016 | 326 days after |
| ALAM KEMUNINGKPKT 13053-1 | KlangSelangor | 101 | 7 Aug 20161st sale agreement 7 Aug 2013 | CCC 1 Jul 2016 | CCC before deadline; handover not recorded |
| EVERGREEN HEIGHTSKPKT 8528-7 | Batu PahatJohor | 559 | 31 Dec 20121st sale agreement 31 Dec 2010 | CCC 1 Feb 2016 | 1,127 days after |
| CONCERTO KIARAKPKT 4441-66 | Kuala LumpurWP Kuala Lumpur | 440 | —1st sale agreement 10 Aug 2012 | CCC 9 Nov 2015 | — |
| EVERGREEN HEIGHTS FASA 5KPKT 8528-5 | Batu PahatJohor | 172 | 21 May 20161st sale agreement 21 May 2014 | CCC 17 Jun 2015 | CCC before deadline; handover not recorded |
| TAMAN KLUANG BARU 2KPKT 8718-2 | KluangJohor | 74 | 1 Jan 20161st sale agreement 1 Jan 2014 | CCC 18 Nov 2014 Handover 1 Jan 2006 / 1 Feb 2008 / 1 Jun 2015 | 214 days before |
| TAMAN BUKIT PERDANA 3KPKT 8718-4 | Batu PahatJohor | 20 | 27 Aug 20151st sale agreement 27 Aug 2013 | CCC 12 Oct 2014 | CCC before deadline; handover not recorded |
| EVERGREEN HEIGHTSKPKT 8528-10 | Batu PahatJohor | 96 | 25 Mar 20151st sale agreement 25 Mar 2013 | CCC 12 Oct 2014 | CCC before deadline; handover not recorded |
| TAMAN BUKIT PERDANA 3KPKT 8718-3 | Batu PahatJohor | 34 | 14 Jan 20151st sale agreement 14 Jan 2013 | CCC 10 Oct 2014 | CCC before deadline; handover not recorded |
| EVERGREEN HEIGHTSKPKT 8528-9 | Batu PahatJohor | 20 | — | CCC 19 Apr 2013 | — |
| TAMAN BUKIT PERDANA IIKPKT 7430-3 | Batu PahatJohor | 222 | — | CFO 28 Feb 2013 | — |
| TAMAN BUKIT PERDANA IIKPKT 4441-29 | Batu PahatJohor | 19 | 18 May 20141st sale agreement 18 May 2012 | CFO 29 Jul 2011 Handover 22 Jul 2008 / 1 Aug 2012 | 655 days before |
| TAMAN BUKIT PERDANA 2KPKT 4441-65 | Batu PahatJohor | 42 | — | CCC 22 Jun 2012 | — |
| TAMAN BERLIAN BIRU 2KPKT 4441-62 | KluangJohor | 32 | — | CCC 18 Jun 2012 | — |
| PTD 18610KPKT 7430-5 | Batu PahatJohor | 268 | — | CFO 19 Dec 2011 | — |
| TAMAN SRI KLUANG FASA 1LKPKT 4441-64 | KluangJohor | 82 | — | CCC 25 Feb 2011 | — |
| TAMAN MEGAHKPKT 4441-35 | PontianJohor | 125 | — | CFO 12 Jan 2011 | — |
| TAMAN MEGAHKPKT 4441-38 | PontianJohor | 108 | — | CFO 12 Feb 2010 | — |
| MEDAN BUNGA CEMPAKA BARUKPKT 4441-61 | Batu PahatJohor | 128 | — | CFO 28 Dec 2009 | — |
| TAMAN SRI KLUANGKPKT 4441-49 | KluangJohor | 45 | — | CFO 18 Feb 2009 | — |
| TAMAN MEGAHKPKT 4441-39 | PontianJohor | 242 | — | CFO 16 Apr 2008 | — |
| TAMAN KLUANG BARU 2KPKT 8718-1 | KluangJohor | 39 | — | CFO 24 Sep 2007 | — |
| EVERGREEN HEIGHTSKPKT 8528-6 | Batu PahatJohor | 88 | — | CFO 25 May 2007 | — |
| EVERGREEN HEIGHTS FASA 4KPKT 8528-4 | Batu PahatJohor | 204 | — | CFO 22 May 2007 | — |
| TAMAN SEREMBAN JAYAKPKT 4441-23 | SerembanNegeri Sembilan | 378 | — | CFO 22 Feb 2007 | — |
| TAMAN SEREMBAN JAYAKPKT 4441-24 | SerembanNegeri Sembilan | 463 | — | CFO 5 Jan 2007 | — |
| EVERGREEN HEIGHTS FASA 2KPKT 8528-2 | Batu PahatJohor | 78 | 15 Apr 20031st sale agreement 15 Apr 2001 | CFO 27 Nov 2006 | 1,322 days after |
| EVERGREEN HEIGHTS FASA 3KPKT 8528-3 | Batu PahatJohor | 122 | — | CFO 22 Jun 2006 | — |
| TAMAN PULAI UTAMAKPKT 7360-13 | Johor BahruJohor | 423 | — | CFO 7 Feb 2006 | — |
| TAMAN SRI KLUANGKPKT 4441-21 | KluangJohor | 108 | — | CFO 19 Jan 2006 | — |
| TAMAN PULAI UTAMAKPKT 7360-10 | Johor BahruJohor | 336 | 19 Dec 20031st sale agreement 19 Dec 2000 | CCC 29 Aug 2003 | CCC before deadline; handover not recorded |
Under construction (8) and not yet started (3)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN PULAI UTAMAKPKT 7360-11 | Johor BahruJohor | 564 | Not startedNot started | 29 Jan 20041st sale agreement 29 Jan 2001 | 0–100% |
| BANDAR PUTERA INDAHKPKT 7430-30 | Batu PahatJohor | 95 | SickSick | 9 Aug 20261st sale agreement 9 Aug 2024 | 88% |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-21 | Batu PahatJohor | 47 | SmoothOn schedule | 7 Jul 20271st sale agreement 7 Jul 2025 | 80% |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-22 | Batu PahatJohor | 38 | SmoothOn schedule | 30 Jan 20281st sale agreement 30 Jan 2026 | 20–80% |
| ALAM KEMUNINGKPKT 13053-7Springwood Residences · on PropertySifuMarketed as Springwood Residences, phase 3 of HomeTree. BCB's 2025 annual report describes sub-phase 3A, launched in March 2025, as 72 two-storey link houses and 44 two-storey semi-detached houses; KPKT registers 144 units under this permit: 72 terrace and 72 semi-detached houses.[1] | KlangSelangor | 144 | SmoothOn schedule | 15 Mar 20281st sale agreement 15 Mar 2025 | 52–82% |
| TAMAN EVERGREEN HEIGHTKPKT 8528-23 | Batu PahatJohor | 60 | SmoothOn schedule | 6 Jul 20281st sale agreement 6 Jul 2026 | 8% |
| BANDAR PUTERA INDAHKPKT 7430-31 | Batu PahatJohor | 74 | SmoothOn schedule | 17 Aug 20281st sale agreement 17 Aug 2026 | 50% |
| TAMAN SRI KLUANGKPKT 4441-30 | KluangJohor | 422 | Not startedNot started | — | 0–100% |
| TAMAN BANDAR PERMAIKPKT 8718-5 | Batu PahatJohor | 33 | SmoothOn schedule | — | 5% |
| TAMAN BANDAR PERMAIKPKT 8718-6 | Batu PahatJohor | 94 | SmoothOn schedule | — | 5% |
| TAMAN EVERGREEN HEIGHTSKPKT 8528-24 | Batu PahatJohor | 58 | Not startedNot started | — | 0% |
Permit cancelled or other KPKT status (1)
| Project (KPKT name) | Area | Units | KPKT status | Handover deadline | Progress |
|---|---|---|---|---|---|
| TAMAN BUKIT PERDANA IKPKT 4441-48 | Batu PahatJohor | 18 | Permit cancelledPermit cancelled | — | 0% |
† Section 35 of the Temporary Measures for Reducing the Impact of COVID-19 Act 2020 (Act 829) excludes 18 March–31 August 2020 from the time for delivering vacant possession. The register does not show whether a deadline already reflects this.
Deadlines are counted from each project's first sale agreement, as KPKT records them; buyers who signed later have later deadlines. CCC = Certificate of Completion and Compliance; CFO = Certificate of Fitness for Occupation.
BCB at a glance
| Listed | Bursa Malaysia Main Market · BCB (6602) · listed 3 December 1996[1][2] |
|---|---|
| Started | 13 July 1988, as Kemajuan Buditama Sdn Bhd; renamed BCB Berhad on becoming a public company in 1995[2] |
| Head office | Kluang Parade, Kluang, Johor[1] |
| Leadership | Tan Sri Dato' Tan Seng Leong — Founder and Group Managing Director (on the board since 9 November 1988)[1] Dato' Ismail bin Karim — Chairman, Independent Non-Executive Director (on the board since 15 July 2022)[1] |
| Companies in the KPKT register | BCB BERHAD KPKT 4441[1] JOHBASE DEVELOPMENT SDN. BHD. KPKT 7430[1] BCB RESOURCES SDN. BHD. KPKT 8528[1] BCB LAND SDN. BHD. KPKT 8718[1] GLOBAL EARNEST SDN. BHD. (86.6%) KPKT 7360[1] BCB DEVELOPMENT SDN. BHD. (70%) KPKT 13053[1] BCB HEIGHTS SDN. BHD. (60%) KPKT 13996[1] |
| Website | bcbbhd.com.my |
| Land bank (company figure) | 825 acres, group-wide (2025 annual report, financial year ended 30 June 2025)[1] |
| Main townships | Bandar Putera Indah (370 acres) and Evergreen Heights (432 acres) in Batu Pahat, Johor; HomeTree (151 acres) in Kota Kemuning, Selangor[1] |
| Joint ventures | HomeTree with Landshine Limited (BCB holds 70% of BCB Development); Elysia Medini with United Harvest Group of Hong Kong (BCB 60%)[1] |
| Other businesses | Owns and runs Prime City Hotel in Kluang; manages the Kluang Parade and U-Mall shopping malls[2] |
BCB projects on sale on PropertySifu
Springwood Residences
- KOTA KEMUNING — 0.6 km, 2023
- KOTA KEMUNING — 0.6 km, 2021
- ALAM KEMUNING — 2.2 km, 2020
Who is BCB? The company behind the projects
BCB Berhad was incorporated on 13 July 1988 as Kemajuan Buditama Sdn Bhd and became a public company under its present name on 21 August 1995 [2]. It was listed on the main board of what is now Bursa Malaysia on 3 December 1996 [2] and trades on the Main Market under stock number 6602 [1]. Its roots and head office are in Kluang, Johor [2][1]. The founder, Tan Sri Dato' Tan Seng Leong, has been on the board since 9 November 1988 and is group managing director; the chairman is Dato' Ismail bin Karim, an independent non-executive director who joined the board on 15 July 2022 [1].
Most of BCB's housing is in Johor. The company began building in Batu Pahat about 30 years ago with Taman Bukit Perdana, and its two current townships there are Bandar Putera Indah (370 acres) and Evergreen Heights (432 acres) [1]. In Iskandar Puteri, Elysia Medini is a joint venture between BCB (60%) and United Harvest Group, a Hong Kong developer; its first phase of three towers was completed in 2019 [1]. KPKT registers that phase as The Elysia Park Residence under BCB Heights Sdn Bhd, which BCB owns 60% of [1]. BCB's 2025 annual report puts its land bank at 825 acres [1]; that is a group-wide figure, while the KPKT register counts only licensed housing projects.
BCB entered the Klang Valley in 2010 [2]. Concerto North Kiara in Kuala Lumpur was completed and handed over in 2015 [1]. HomeTree in Kota Kemuning, Shah Alam, is a 151-acre township along the Klang River, developed with Landshine Limited, an affiliate of a Xiamen developer, and launched in June 2013 [1]; BCB holds 70% of the developer, BCB Development Sdn Bhd [1]. Its first phase, Long Branch Residences (101 three-storey bungalows), was handed over in July 2016; the second, Broadleaf Residences (51 bungalows and 244 semi-detached houses), was built in six sub-phases, the last completed in 2025; and the third, Springwood Residences, opened its first sub-phase, 3A, in March 2025 [1].
Besides housing, BCB owns and runs Prime City Hotel in Kluang and manages two shopping malls, Kluang Parade in Kluang and U-Mall in Taman Pulai Utama, Skudai [2]. The KPKT register covers only projects licensed as housing, so BCB's shop offices and commercial parks, such as Lumina Commercial Park in Iskandar Puteri [1], are not in the table above. The table counts the seven companies in BCB's 2025 annual report that have KPKT housing records: BCB Berhad itself and six subsidiaries, three of them not wholly owned (Global Earnest 86.6%, BCB Development 70%, BCB Heights 60%) [1].
Frequently asked questions
Is BCB a listed company?
Which company develops Springwood Residences?
BCB Development Sdn Bhd (KPKT developer code 13053), which BCB Berhad owns 70% of; Springwood is the third phase of HomeTree in Kota Kemuning, a joint venture with Landshine Limited [1]. KPKT registers it as 13053-7: 144 two-storey houses, first sale agreement 15 March 2025, handover deadline 15 March 2028, recorded as on schedule (Lancar), with 82% reported progress for the 72 terrace houses and 52% for the 72 semi-detached houses.
Does BCB have any Sick or Abandoned projects?
One project is classed Sick (Sakit) in the KPKT register as at 27 October 2026: 7430-30 in Bandar Putera Indah, Batu Pahat, 95 single- and double-storey terrace houses under Johbase Development Sdn Bhd. Its first sale agreement was signed on 9 August 2024 and its handover deadline was 9 August 2026, with no extension registered; both components report 87.5% progress. None of BCB's 92 projects is classed Abandoned (Terbengkalai).
How many housing projects has BCB completed, and how many were handed over after the deadline?
In the KPKT register, 80 of the 92 housing projects under seven BCB companies are completed. Of the 59 completed projects with both a handover deadline and a completion date recorded, 13 were handed over on or before the deadline (the extended deadline where KPKT approved an extension); 23 were handed over or certified complete after it, 1 of them under construction during the 18 March–31 August 2020 movement control period; 23 received the completion certificate before the deadline, with no handover date recorded. The other 21 completed projects do not have both dates in the register.
Were the earlier HomeTree phases in Kota Kemuning handed over on time?
KPKT registers six completed HomeTree projects under BCB Development (13053-1 to 13053-6), and all six received their CCC before their handover deadlines. One of them, 13053-2 (113 houses), had its deadline extended with approval by 12 months to 15 December 2021 and received the CCC on 20 October 2020. The three with a handover date recorded (13053-4, 13053-5 and 13053-6) were handed over 280, 526 and 718 days before their deadlines.
Was The Elysia Park Residence in Medini handed over on time?
KPKT records the first sale agreement on 13 June 2015 and a handover deadline of 13 June 2018, with no extension registered. All three towers (13996-1, 987 units) received the CCC on 28 November 2019, 533 days after that deadline; the register does not record the handover date.
Sources and how we checked
- Housing project records: KPKT TEDUH register (teduh.kpkt.gov.my), data as at 27 Oct 2026. Sumber: TEDUH, KPKT — used under the Government Open Data Terms of Use 1.0.
- [1] BCB Berhad Annual Report 2025 · BCB Berhad · 30 Oct 2025 · accessed 28 Oct 2026
https://ir2.chartnexus.com/bcb/docs/ar/2025.pdf - [2] About Us · BCB Berhad · accessed 28 Oct 2026
http://bcbbhd.com.my/about-us.php
Last updated 28 Oct 2026